CN112502277A - Construction method of mirror concrete of wood plastic-coated flat template - Google Patents

Construction method of mirror concrete of wood plastic-coated flat template Download PDF

Info

Publication number
CN112502277A
CN112502277A CN202011327154.3A CN202011327154A CN112502277A CN 112502277 A CN112502277 A CN 112502277A CN 202011327154 A CN202011327154 A CN 202011327154A CN 112502277 A CN112502277 A CN 112502277A
Authority
CN
China
Prior art keywords
concrete
mirror
cement
construction method
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011327154.3A
Other languages
Chinese (zh)
Inventor
郭相武
汤建和
刘佳银
陈晓红
王智勇
周晓林
王志
龚斯昆
赵代强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CN202011327154.3A priority Critical patent/CN112502277A/en
Publication of CN112502277A publication Critical patent/CN112502277A/en
Priority to ZA2021/09490A priority patent/ZA202109490B/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/02Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for rooms as a whole by which walls and floors are cast simultaneously, whole storeys, or whole buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention relates to the technical field of concrete construction, in particular to a construction method of mirror concrete of a wood plastic-coated flat template. According to the construction method disclosed by the invention, the appearance impression quality of the beam and column concrete members is improved through the splicing design of the beam and column templates, the design of the concrete proportion and the improvement of the construction technology; the material is saved, the self weight of the building is reduced, and the natural and beautiful effect is added to the building; not only the construction period is shortened, but also the construction cost is reduced; the working procedures of decoration plastering, spraying and the like are saved, a large amount of construction waste is reduced, and the environment protection is facilitated.

Description

Construction method of mirror concrete of wood plastic-coated flat template
Technical Field
The invention relates to the technical field of concrete construction, in particular to a construction method of mirror concrete of a wood plastic-coated flat template.
Background
The finished mirror-finished concrete member has the mirror-finished effect of marble, granite and other block materials on the surface, and is applied and implemented in industrial buildings such as power plants, coal mines, industrial plants and the like in China in recent years. The mirror surface concrete has the following characteristics:
1. the mirror surface concrete can achieve the mirror surface decoration effect of marble, granite and other bulk materials without secondary decoration, and the decoration materials such as paint, veneer plates and the like are omitted.
2. The mirror concrete structure is not plastered or sprayed, thereby reducing a large amount of construction waste and being beneficial to environmental protection.
3. The mirror concrete avoids the hidden quality troubles of plastering cracking, hollowing and even dropping, and eliminates a plurality of common quality problems.
However, the existing mirror concrete construction technology is uneven, so that the engineering effect after actual construction cannot reach or even cannot reach the effect. Therefore, a more reasonable technical scheme needs to be provided to solve the technical problems in the prior art.
Disclosure of Invention
In order to overcome the defects of the prior art mentioned in the content, the invention provides a construction method of the mirror concrete of the wood plastic-coated flat template, aiming at improving the quality effect of the mirror concrete construction by an improved construction process.
In order to achieve the purpose, the invention specifically adopts the technical scheme that:
a construction method of mirror concrete of a wood plastic-coated flat template comprises the following steps:
arranging templates, assembling and manufacturing a wall template, a top template, a frame column template and a beam template by using wood plastic-coated flat templates, and respectively placing and fixing along an installation standard;
pouring concrete, namely performing layered pouring and vibrating in layers, or performing one-time pouring;
curing the concrete, namely covering the concrete by using a film after the concrete is poured and the surface is calendered, and keeping the original blended water in the concrete from evaporating to form natural vacuum curing;
concrete repair, namely performing construction repair on the defective part on the surface of the concrete finished product so as to achieve the surface effect consistent with that of mirror concrete;
and (4) removing the templates, and removing the templates from the lower layer upwards in sequence.
According to the construction method disclosed by the invention, after the smooth formwork is arranged, concrete is selected and blended, and pouring, maintenance and repair are carried out, so that the construction of the mirror concrete is finally realized, and the set requirements on strength and surface degree are met.
Furthermore, in the construction process, if high-grade cement is used for preparing low-grade concrete, the cement consumption is too small, the W/C is increased, and the surface of the concrete cannot achieve the mirror effect due to sand generation in the use process; if the high-grade concrete is prepared by using the low-grade cement, the cement consumption is increased, the shrinkage deformation of the concrete is increased, and the micro-cracks on the surface of the concrete are directly generated. Therefore, the concrete is optimized when being prepared, and the following specific feasible schemes are listed: the concrete is prepared by adopting Portland cement with 0.4-0.5 percent of alkali content, coarse aggregate with the maximum grain diameter not more than 40mm and fine aggregate with the grain diameter less than 0.15mm accounting for 6-8 percent of the total weight of the aggregate.
When the concrete surface treatment agent is arranged, the cement consumption can be saved due to the arrangement of the coarse aggregate, the concrete can be more compact due to the arrangement of the fine aggregate, capillary holes on the surface of the concrete can be blocked, and the surface degree of the concrete is improved.
Still further, as a preferable mode, the selection of the coarse aggregate is not uniquely determined, and the following specifically possible modes are exemplified here: the coarse aggregate is crushed stone with a continuous gradation of 5-31.5 mm in particle size.
Furthermore, the amount of the fly ash added into the concrete can save the cement consumption, but the excessive addition of the fly ash can cause the shortage of the cement content and the separation of the fly ash and the cement in the concrete vibrating process, the fly ash is suspended on the upper part of the concrete, so that the upper part of the concrete member is matt, and the mirror effect is directly influenced, therefore, the addition amount of the fly ash is strictly controlled. Therefore, the following embodiments are specifically possible: and replacing part of cement with fly ash, wherein the cement replaced with fly ash accounts for 5-8% of the weight of the cement.
Furthermore, under the condition that the cement consumption is not changed, the water consumption is increased, and the bubble holes on the surface of the formed concrete member are increased, so that on the premise of ensuring the concrete strength, the workability and the flowability of the concrete must be solved if the unit water consumption is reduced, and the two problems are solved by the following steps: adding a certain amount of high-efficiency water reducing agent into the concrete and increasing the sand rate to increase the slump of the concrete.
The theoretical basis for solving the workability of concrete is as follows: the cement dosage must be adjusted when the sand rate is increased; and adding a water reducing agent to ensure that the water-cement ratio is unchanged.
The theoretical basis for solving the fluidity of concrete is as follows: the water consumption is increased or a water reducing agent is added to increase the slump of the concrete. The water consumption is increased, and the cement consumption is required to be adjusted to ensure that the water-cement ratio is not changed, but the water-cement ratio is not economical; and adding a water reducing agent, and keeping the water-cement ratio unchanged.
Therefore, a specific feasible technical scheme is proposed here: in the process of preparing concrete, a water reducing agent with the air content less than 4% is added to solve a series of problems of slow setting, slump loss prevention, reinforcement and the like.
Furthermore, in the concrete pouring process, when the concrete is poured in layers, the laying thickness of each layer of concrete is less than or equal to 40cm, and after one layer of concrete is laid, a transition layer with the thickness of 5-10 cm is filled on the joint surface of the layer of concrete and the subsequent concrete pouring.
And further, after the concrete pouring is finished, the upper openings of the outer formworks are aligned, so that the joint lines of the concrete are smooth and straight, and the concrete on the outer side is higher than the concrete on the inner side.
And further, the concrete curing time is more than or equal to seven days.
Further, the concrete repairing method comprises the following steps:
chiseling the defect part to be repaired, cleaning and brushing cement paste, wherein the mass ratio of 1: 2, repairing and drying cement mortar;
washing the deep surface for 3-5 mm and cleaning the surface, wherein Portland cement with alkali content of 0.4-0.5% and white cement are adopted according to the weight ratio of 1: 1.5, adding a building glue solution to prepare a cement paste to construct the surface of the defect part, flattening, scraping, and naturally drying;
carrying out dry grinding and rough flattening on the surface, winding and maintaining by using a film, and carrying out surface finish grinding after the preset strength requirement is met; and (4) fully brushing 1-2 times of water glass after the requirement of the set flatness is met, and performing fine grinding after 24 hours.
Furthermore, in the whole construction process, the thickness of the wood plastic-coated flat template is not less than 15 mm. In the later construction period, the concrete must reach enough strength when the form is removed, and the lower-layer member formwork is removed after the upper-layer member concrete is poured to prevent the lower-layer member from being polluted.
Compared with the prior art, the invention has the beneficial effects that:
according to the construction method disclosed by the invention, the appearance impression quality of the beam and column concrete members is improved through the splicing design of the beam and column templates, the design of the concrete proportion and the improvement of the construction technology; the material is saved, the self weight of the building is reduced, and the natural and beautiful effect is added to the building; not only the construction period is shortened, but also the construction cost is reduced; the working procedures of decoration plastering, spraying and the like are saved, a large amount of construction waste is reduced, and the environment protection is facilitated.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings needed to be used in the embodiments will be briefly described below, it should be understood that the following drawings only show some embodiments of the present invention, and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
FIG. 1 is a process diagram of the construction method.
Detailed Description
The invention is further explained below with reference to the drawings and the specific embodiments.
It should be noted that the description of the embodiments is provided to help understanding of the present invention, but the present invention is not limited thereto. Specific structural and functional details disclosed herein are merely illustrative of example embodiments of the invention. This invention may, however, be embodied in many alternate forms and should not be construed as limited to the embodiments set forth herein.
Examples
Aiming at the current situations of long construction period, complex process and high cost of the existing mirror concrete, the embodiment provides a construction method, aiming at shortening the construction period of the mirror concrete, optimizing the construction process, reducing the construction cost and simultaneously ensuring the construction quality. Specifically, the scheme adopted in this embodiment is as follows:
as shown in fig. 1, a method for constructing wood-coated plastic flat formwork mirror concrete comprises the following steps:
s01: the method comprises the steps of arranging templates, assembling and manufacturing a wall template, a top template, a frame column template and a beam template by using a wood plastic-coated flat template, and respectively placing and fixing along an installation benchmark.
Preferably, when the template is arranged, the seam of the template is adhered by using 20mm wide adhesive tape.
S02: and (3) pouring concrete, namely pouring in layers and vibrating in layers, or pouring and vibrating at one time.
S03: and (3) curing the concrete, namely covering the concrete by using a film after the concrete is poured and the surface is calendered, and keeping the original mixed water in the concrete from evaporating to form natural vacuum curing.
S04: and (3) concrete repair, namely constructing and repairing the defective part on the surface of the concrete finished product to achieve the surface effect consistent with that of mirror concrete.
S05: and (4) removing the templates, and removing the templates from the lower layer upwards in sequence.
According to the construction method disclosed by the invention, after the smooth formwork is arranged, concrete is selected and blended, and pouring, maintenance and repair are carried out, so that the construction of the mirror concrete is finally realized, and the set requirements on strength and surface degree are met.
In the construction process, if high-grade cement is used for preparing low-grade concrete, the cement consumption is too small, the W/C is increased, and the surface of the concrete cannot achieve the mirror effect due to sand generation in the use process; if the high-grade concrete is prepared by using the low-grade cement, the cement consumption is increased, the shrinkage deformation of the concrete is increased, and the micro-cracks on the surface of the concrete are directly generated. Therefore, the concrete is optimized when being prepared, and the following specific feasible schemes are listed: the concrete is prepared by adopting Portland cement with 0.47 percent of alkali content, coarse aggregate with the maximum grain diameter not more than 40mm and fine aggregate with the grain diameter less than 0.15mm accounting for 6 to 8 percent of the total weight of the aggregate.
When the concrete surface treatment agent is arranged, the cement consumption can be saved due to the arrangement of the coarse aggregate, the concrete can be more compact due to the arrangement of the fine aggregate, capillary holes on the surface of the concrete can be blocked, and the surface degree of the concrete is improved.
The selection of the coarse aggregate is not limited to a preferred embodiment, and the following embodiments are specifically possible: the coarse aggregate is crushed stone with a continuous gradation of 5-31.5 mm in particle size.
The use amount of cement can be saved by doping a certain amount of fly ash into concrete, but the excessive doping of fly ash can cause the shortage of the cement and the separation of fly ash and cement in the concrete vibrating process, the fly ash is suspended on the upper part of the concrete, so that the upper part of a concrete member is matt, the mirror effect is directly influenced, and therefore, the doping amount of fly ash is strictly controlled. Therefore, the following embodiments are specifically possible: and replacing part of cement with fly ash, wherein the cement replaced with fly ash accounts for 5-8% of the weight of the cement.
Under the unchangeable condition of cement quantity, the water consumption increases, and the concrete member surface bubble hole after the shaping will increase, consequently, under the prerequisite of guaranteeing the concrete strength, want to reduce the unit water consumption, just must solve the concrete "workability" and "mobility", and the way of solving these two problems is: adding a certain amount of high-efficiency water reducing agent into the concrete and increasing the sand rate to increase the slump of the concrete.
The theoretical basis for solving the workability of concrete is as follows: the cement dosage must be adjusted when the sand rate is increased; and adding a water reducing agent to ensure that the water-cement ratio is unchanged.
The theoretical basis for solving the fluidity of concrete is as follows: the water consumption is increased or a water reducing agent is added to increase the slump of the concrete. The water consumption is increased, and the cement consumption is required to be adjusted to ensure that the water-cement ratio is not changed, but the water-cement ratio is not economical; and adding a water reducing agent, and keeping the water-cement ratio unchanged.
Therefore, a specific feasible technical scheme is proposed here: in the process of preparing concrete, a water reducing agent with the air content less than 4% is added to solve a series of problems of slow setting, slump loss prevention, reinforcement and the like.
In the concrete pouring procedure, when the concrete is poured in layers, the laying thickness of each layer of concrete is less than or equal to 40cm, and after one layer of concrete is laid, a transition layer with the thickness of 5-10 cm is filled on the joint surface of the concrete and the subsequent concrete pouring.
After the concrete is poured, the upper openings of the outer formworks are aligned, so that the joint lines of the concrete are smooth and straight, and the concrete on the outer side is higher than the concrete on the inner side.
In this example, the concrete curing time was not less than seven days.
In this embodiment, repairing the concrete includes the following steps:
s041: chiseling the defect part to be repaired, cleaning and brushing cement paste, wherein the mass ratio of 1: 2, repairing and drying cement mortar;
s042: washing the deep surface for 3-5 mm and cleaning the surface, wherein Portland cement with alkali content of 0.4-0.5% and white cement are adopted according to the weight ratio of 1: 1.5, adding a building glue solution to prepare a cement paste to construct the surface of the defect part, flattening, scraping, and naturally drying;
s043: carrying out dry grinding and rough flattening on the surface, winding and maintaining by using a film, and carrying out surface finish grinding after the preset strength requirement is met; and (4) fully brushing 1-2 times of water glass after the requirement of the set flatness is met, and performing fine grinding after 24 hours.
Preferably, the rough grinding is performed by using sand paper, and the finish grinding is performed by using water-grinding sand paper.
In the whole construction process, the thickness of the wood plastic-coated flat template is not less than 15 mm. In the later construction period, the concrete must reach enough strength when the form is removed, and the lower-layer member formwork is removed after the upper-layer member concrete is poured to prevent the lower-layer member from being polluted.
According to the construction method, the embodiment exemplifies an actual construction case, and the construction content is a visiting channel. The method comprises the following specific steps:
the side wall of the visiting passage adopts a 1220 multiplied by 2440 multiplied by 18mm wooden plastic film (PP) flat template, and a certain number of keels are additionally arranged on the compound surface of the side wall template.
The side wall adopts 1220 multiplied by 2440 multiplied by 18mm wood plastic-coated film plane waves, the long edges are assembled along the horizontal direction, and a release agent is cleaned and brushed before use. The template is vertically reinforced by using square timbers of 5 multiplied by 10cm, the square timbers are spaced by 20cm, the steel pipes are transversely added with phi 48, the steel pipes are spaced by 60cm, the water stop pull rods are horizontally used at the outer sides of the vertical square timbers and the steel pipes, the phi 16 and the distance of 60 multiplied by 60cm are adopted for the water stop pull rods, the middle of the water stop pull rods is welded with a steel sheet water stop sheet of 50 multiplied by 50, full welding is needed, and rubber pads are added at two ends of.
The top plate adopts the built full-hall type socket-and-spigot type support, the transverse distance between the supports is 1.2m, the longitudinal distance between the supports is 1.2m, the step pitch is 1.5m, the bottom support is arranged below the upright stanchion, the top support is arranged above the upright stanchion, 10I-steel is paved on the top support, 10 multiplied by 10cm square timber is paved on the I-steel at the distance of 30cm, and the wood is paved on the plastic film-coated flat template.
A square plate formed by 50mm multiplied by 100mm square wooden nails is fixed at the bottom of the column template, and the net size in the square plate is the peripheral size of the template back edge and is used for accurately positioning the template. The template is temporarily positioned according to the number, corrected according to the elastic template line and then reinforced by double rows of steel pipe column hoops with the diameter of 48 mm. The distance between the column hoops is @300 mm-600 m (the distance of the central line), the channel steel is oppositely pulled by phi 14-phi 16 bolts, and the double nuts can change from loose to dense from bottom to top according to the change of the lateral pressure of the concrete.
The beam bottom die and the side die are longitudinally spliced by adopting 2440mm long-sized multi-layer boards, the back surfaces of the multi-layer boards are longitudinally reinforced by 50 multiplied by 100mm square timbers, and the distance between the square timbers and the side dies is 200 mm. And steel pipe cross rods are laid under the back edges of the beam bottom die at intervals of 200 mm. The outer sides of the back edges of the beam side forms are reinforced by short steel pipe vertical rods with the interval of 400mm, and then the back edges of the beam side forms are tightly propped against the short steel pipes and are firmly connected with an external integral frame.
The arching method of the frame beam is as follows: the beam bottoms at the two ends of the beam are reduced by 1cm, the beam bottom in the middle of the beam is arched by 1cm, and the middle part of the beam with the span of more than 10m is lifted by 1.5 cm.
In order to ensure that the beam side mold and the plate bottom template are tightly assembled, when the beam side mold is manufactured, the arching factor of the beam bottom is considered, the lower part of the beam side mold is manufactured into an inclined plane, and the upper opening of the beam side mold is ensured to be straight; the method of adding a wood batten at the bottom of the beam bottom die can also be adopted to ensure that the beam side die is flat and consistent.
And after concrete is poured, repairing the clear water mirror surface concrete.
The parts with a small amount of pitted surfaces, rotten roots, slurry leakage, sand flooding and other defects are treated by mixing colors, polishing and grinding by adopting materials such as ordinary cement, white cement, 107 building glue solution, water glass and the like: chiseling a pitted surface and a slurry leakage part, brushing plain cement slurry after cleaning, and performing treatment by using a method comprising the following steps of 1: 2, repairing cement mortar, and rubbing the surface to be flat. And (3) after the cement mortar is slightly dried (about 2 hours), wringing out the cement mortar by using sponge block soaking water, washing the deep surface for 3-5 mm, and removing surface sand grains (floating sand can be removed due to defects such as sand flooding). After 24 hours, the cement and the white cement which are used in the concrete raw ratio are mixed according to the weight ratio of 1: mixing at a ratio of 1.5, stirring (repeatedly trial-preparing according to specific repaired part, and adjusting ratio to control color difference), adding 107 construction glue solution, stirring to obtain pasty cement slurry, spreading on the surface of the component defect, repeatedly flattening, and scraping. And after the natural air drying is carried out for about 8 hours, dry grinding is carried out once by using abrasive paper, the rough and flat degree is achieved, wrapping and maintaining are carried out by using a plastic film, the intensity is achieved, then fine grinding is carried out by using the abrasive paper, after the flatness is qualified, 1-2 times of full brushing are carried out by using the abrasive paper, and after 24 hours, fine grinding is carried out by using the abrasive paper. The surface of the member treated by the method can basically achieve the surface effect consistent with that of the fair-faced mirror concrete, and can effectively prevent the surface from cracking during repairing.
By applying the construction method, the construction period of the construction is shortened, the construction cost is reduced, and certain economic benefit is obtained.
During the construction of the main body, the construction cost increased by each square meter of the clear water mirror surface concrete is about 20 yuan/m2
During decoration construction, the construction cost saved by each square meter of clear water mirror surface concrete is about 35 yuan/m2
In construction, the total construction period is shortened by 7 days due to the application of the method, and lease fees and mechanical fees can be saved by about 3 ten thousand yuan.
The obtained economic benefits are as follows:
30000 + (35M 2-20M 2) x 3520m2 ═ 82800M
Therefore, the mode disclosed by the embodiment is suitable for popularization and application.
The present invention is not limited to the above-described alternative embodiments, and various other embodiments can be obtained by those skilled in the art from the above-described embodiments in any combination, and any other embodiments can be obtained in various forms while still being within the spirit of the present invention. The above detailed description should not be taken as limiting the scope of the invention, which is defined in the claims, and which the description is intended to be interpreted accordingly.

Claims (10)

1. A construction method for mirror concrete of a wood plastic-coated flat template is characterized by comprising the following steps:
arranging templates, assembling and manufacturing a wall template, a top template, a frame column template and a beam template by using wood plastic-coated flat templates, and respectively placing and fixing along an installation standard;
pouring concrete, namely performing layered pouring and vibrating in layers, or performing one-time pouring;
curing the concrete, namely covering the concrete by using a film after the concrete is poured and the surface is calendered, and keeping the original blended water in the concrete from evaporating to form natural vacuum curing;
concrete repair, namely performing construction repair on the defective part on the surface of the concrete finished product so as to achieve the surface effect consistent with that of mirror concrete;
and (4) removing the templates, and removing the templates from the lower layer upwards in sequence.
2. The construction method of the wood plastic-coated flat formwork mirror concrete according to claim 1, characterized in that:
the concrete is prepared by adopting Portland cement with 0.4-0.5 percent of alkali content, coarse aggregate with the maximum grain diameter not more than 40mm and fine aggregate with the grain diameter less than 0.15mm accounting for 6-8 percent of the total weight of the aggregate.
3. The construction method of the wood-coated plastic flat formwork mirror concrete according to claim 2, characterized in that: the coarse aggregate is crushed stone with a continuous gradation of 5-31.5 mm in particle size.
4. The construction method of the wood-coated plastic flat formwork mirror concrete according to claim 2, characterized in that:
and replacing part of cement with fly ash, wherein the cement replaced with fly ash accounts for 5-8% of the weight of the cement.
5. The construction method of the wood-coated plastic flat formwork mirror concrete according to claim 2, characterized in that:
in the process of preparing concrete, a water reducing agent with the gas content less than 4 percent is added.
6. The construction method of the wood-coated plastic flat formwork mirror concrete according to claim 2, characterized in that:
when the layered concrete pouring is adopted, the laying thickness of each layer of concrete is less than or equal to 40cm, and after one layer of concrete is laid, a transition layer with the thickness of 5-10 cm is filled on a joint surface of the concrete and the subsequent concrete pouring.
7. The construction method of the wood plastic-coated flat formwork mirror concrete according to claim 1, characterized in that:
after the concrete is poured, the upper openings of the outer formworks are aligned, so that the joint lines of the concrete are smooth and straight, and the concrete on the outer side is higher than the concrete on the inner side.
8. The construction method of the wood plastic-coated flat formwork mirror concrete according to claim 1, characterized in that:
the concrete curing time is more than or equal to seven days.
9. The method for constructing the mirror concrete of the wood-coated plastic flat template according to claim 1, wherein the step of repairing the concrete comprises the following steps:
chiseling the defect part to be repaired, cleaning and brushing cement paste, wherein the mass ratio of 1: 2, repairing and drying cement mortar;
washing the deep surface for 3-5 mm and cleaning the surface, wherein Portland cement with alkali content of 0.4-0.5% and white cement are adopted according to the weight ratio of 1: 1.5, adding a building glue solution to prepare a cement paste to construct the surface of the defect part, flattening, scraping, and naturally drying;
carrying out dry grinding and rough flattening on the surface, winding and maintaining by using a film, and carrying out surface finish grinding after the preset strength requirement is met; and (4) fully brushing 1-2 times of water glass after the requirement of the set flatness is met, and performing fine grinding after 24 hours.
10. The construction method of the wood plastic-coated flat formwork mirror concrete according to claim 1, characterized in that:
the thickness of the wood plastic-coated flat template is not less than 15 mm.
CN202011327154.3A 2020-11-24 2020-11-24 Construction method of mirror concrete of wood plastic-coated flat template Pending CN112502277A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202011327154.3A CN112502277A (en) 2020-11-24 2020-11-24 Construction method of mirror concrete of wood plastic-coated flat template
ZA2021/09490A ZA202109490B (en) 2020-11-24 2021-11-24 Construction method for mirror concrete with wooden polypropylene-coated flat formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011327154.3A CN112502277A (en) 2020-11-24 2020-11-24 Construction method of mirror concrete of wood plastic-coated flat template

Publications (1)

Publication Number Publication Date
CN112502277A true CN112502277A (en) 2021-03-16

Family

ID=74959676

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011327154.3A Pending CN112502277A (en) 2020-11-24 2020-11-24 Construction method of mirror concrete of wood plastic-coated flat template

Country Status (2)

Country Link
CN (1) CN112502277A (en)
ZA (1) ZA202109490B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1530499A (en) * 2003-03-11 2004-09-22 李保法 Mirror concrete construction plan
US20080098934A1 (en) * 2004-05-19 2008-05-01 Sang-Woon Kwak Cement Mortar Composition and Concrete Composition
CN109537893A (en) * 2017-09-22 2019-03-29 上海宝冶集团有限公司 Pouring construction method without facing layer concrete

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1530499A (en) * 2003-03-11 2004-09-22 李保法 Mirror concrete construction plan
US20080098934A1 (en) * 2004-05-19 2008-05-01 Sang-Woon Kwak Cement Mortar Composition and Concrete Composition
CN109537893A (en) * 2017-09-22 2019-03-29 上海宝冶集团有限公司 Pouring construction method without facing layer concrete

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
朱林: "清水镜面混凝土技术的研究与应用", 《施工技术》 *
杨良等: "镜面混凝土施工技术", 《建筑技术开发》 *
韩全卫: "《混凝土脱模剂和相关工程材料的应用》", 30 September 2008, 东南大学出版社 *

Also Published As

Publication number Publication date
ZA202109490B (en) 2022-03-30

Similar Documents

Publication Publication Date Title
CN106801517B (en) External reinforcing and reinforcing method for school shed with prefabricated porous plate brick mixed structure
CN105484391A (en) Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks
CN104358341A (en) Building brickwork and masonry construction method of building brickwork
CN101886457B (en) Method for constructing wear-resistant and crack-resistant hardened ground
CN110107089A (en) Municipal works clear-water concrete casting construction method
CN113931384B (en) Construction method for steel structure pressure relief roof
CN107313531A (en) A kind of assembled integral shear wall connecting node and its system and its construction technology
CN112780009A (en) Plastering-free concealed pipe slotting-free secondary structure wall and construction method thereof
CN102116092A (en) Method for constructing reinforcing band for compensating contraction of concrete and preventing cracks
CN112282294A (en) Construction method of steel fiber wear-resistant terrace
CN102806592A (en) Manufacturing method for demolition-free textile fiber web reinforced concrete formwork
CN211306754U (en) Prestressed decorative concrete plank road plate
CN210597982U (en) Composite copper plate structure with back bolt on floor
CN108824810B (en) Laying construction process for steel skeleton composite building top plate
CN112502277A (en) Construction method of mirror concrete of wood plastic-coated flat template
CN113914530B (en) Inclined roof fish scale type concrete structure and construction method
CN102767284B (en) Semi-prefabricating construction process for concrete thin-wall lower return eave
CN114809603A (en) Construction method for fair-faced concrete of special-shaped structure canopy veneer of high-speed rail station house
CN113513202A (en) Construction method for pouring clear water concrete of garbage pool
CN1264775A (en) High-speed building technology by permanent pattern plates, predecoration, self solidification and silkworm-like advance
CN106639089A (en) Novel assembled I-shaped prefabricated composite floor supporting plate and preparing method thereof
CN110924691A (en) Environment-friendly building construction method
CN105297950A (en) Infilled wall and horizontal load-bearing structure gap wall surface crack-controlling construction method
CN211200914U (en) Anti-cracking cement artificial stone structure
CN220790185U (en) ALC wallboard and prefabricated reinforced concrete shear wall construction node of assembled

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210316