CN112459438A - Scaffold structure and erection method thereof - Google Patents

Scaffold structure and erection method thereof Download PDF

Info

Publication number
CN112459438A
CN112459438A CN202011378333.XA CN202011378333A CN112459438A CN 112459438 A CN112459438 A CN 112459438A CN 202011378333 A CN202011378333 A CN 202011378333A CN 112459438 A CN112459438 A CN 112459438A
Authority
CN
China
Prior art keywords
groove
installation
cooperation
scaffold
mounting groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011378333.XA
Other languages
Chinese (zh)
Inventor
陈红春
薛昌均
张建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Qiankun Construction Group Co ltd
Original Assignee
Sichuan Qiankun Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Qiankun Construction Group Co ltd filed Critical Sichuan Qiankun Construction Group Co ltd
Priority to CN202011378333.XA priority Critical patent/CN112459438A/en
Publication of CN112459438A publication Critical patent/CN112459438A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/02Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means
    • E04G1/04Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section
    • E04G1/06Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section comprising members with rod-like or tubular portions fitting together end to end, with or without separate connecting pieces
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/30Scaffolding bars or members with non-detachably fixed coupling elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/30Scaffolding bars or members with non-detachably fixed coupling elements
    • E04G7/301Scaffolding bars or members with non-detachably fixed coupling elements for connecting bars or members which are parallel or in end-to-end relation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model relates to a scaffold structure and a building method thereof, comprising a plurality of vertical pipes, transverse pipes and connecting components between the vertical pipes and the transverse pipes, wherein the connecting components comprise mounting parts arranged at one ends of the vertical pipes, and mounting grooves are uniformly arranged on the mounting parts along the circumferential direction of the mounting parts; the other end of riser is provided with cooperation portion, when two risers were spliced along vertical direction, the cooperation portion of a riser and the installation department butt of another riser, set up the cooperation groove that corresponds with the mounting groove in the cooperation portion, during cooperation portion and installation department butt, the mounting groove forms the fixed slot that is used for fixed violently managing with the cooperation groove, the fixed orifices has been seted up on the tip of violently managing, the cooperation inslot is provided with the fixed block that inserts to the fixed orifices, be provided with the locating part in the mounting groove, the locating part is used for the restriction to violently manage and take place to remove in. This application has the effect of the condition of being convenient for reduce the horizontal pipe position skew of taking place in the installation.

Description

Scaffold structure and erection method thereof
Technical Field
The application relates to the field of construction facilities, in particular to a scaffold structure and a building method thereof.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is smoothly carried out. The scaffold is divided into an outer scaffold and an inner scaffold according to the erected positions; the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials; the scaffold is divided into a vertical rod type scaffold, a bridge type scaffold, a door type scaffold, a suspension type scaffold, a hanging type scaffold, a lifting type scaffold and a climbing type scaffold according to the structural form.
The existing Chinese patent with application publication number CN109989572A discloses a quick-assembly type scaffold connecting structure, which comprises an upper pipe, a lower pipe and 2-4 side pipes uniformly distributed around the axis of the upper pipe, wherein the lower part of the upper pipe is provided with an upper connecting plate, the outer wall of the upper pipe is provided with an external thread, the external thread is positioned above the upper connecting plate, the external thread is provided with a nut in threaded connection, the side surface of the upper connecting plate is provided with upper slots corresponding to the side pipes one by one, and the cross section of each upper slot is semicircular; the upper part of the lower pipe is provided with a lower connecting plate, the side surface of the lower connecting plate is provided with lower slots which are in one-to-one correspondence with the upper slots, the upper slots and the lower slots can be spliced into an inserting groove with a circular cross section, and the end part of the side pipe can extend into the inserting groove; the upper connecting plate and the lower connecting plate are provided with second pin holes, pin rods penetrating through the second pin holes are arranged in the second pin holes, the upper end of each pin rod is fixed on an end plate, the center of each end plate is provided with a hole through which an upper pipe can penetrate, and the end plates are positioned between the upper connecting plate and the nuts; the section of the side pipe extending into the inserting groove is provided with a first pin hole through which the pin rod can pass.
In view of the above-mentioned related art, the inventor thinks that when installing the scaffold, after the staff places the tip of side pipe in the lower slot, still need to splice upper junction plate and lower connecting plate just can fix the side pipe, but when splicing upper junction plate and lower connecting plate, need install all side pipes in every lower slot earlier again, in actual construction, the condition that the skew appears in last side pipe position often appears in the installation of next side pipe, the side pipe of installing before this moment need be adjusted again, the adjustment is again likely to lead to other side pipe position skews, cause the inconvenience of construction, reduced the installation effectiveness of scaffold.
Disclosure of Invention
In order to reduce the situation of taking place horizontal pipe offset in the installation process for the convenience, this application provides a scaffold structure and sets up the method.
In a first aspect, the present application provides a scaffold structure, which adopts the following technical scheme:
a scaffold structure comprises a plurality of vertical pipes, transverse pipes and connecting assemblies between the vertical pipes and the transverse pipes, wherein each connecting assembly comprises an installation part arranged at one end of each vertical pipe, and installation grooves are uniformly formed in the installation parts along the circumferential direction of the installation parts; the other end of riser is provided with cooperation portion, two when the riser splices along vertical direction, one the cooperation portion of riser and the installation department butt of another riser, set up the cooperation groove that corresponds with the mounting groove in the cooperation portion, during cooperation portion and installation department butt, the mounting groove forms the fixed slot that is used for fixed violently managing with the cooperation groove, the fixed orifices has been seted up on the tip of violently managing, the cooperation inslot is provided with the fixed block that inserts to the fixed orifices, be provided with the locating part in the mounting groove, the locating part is used for the restriction to violently manage and takes place to remove in the mounting groove.
By adopting the technical scheme, when the scaffold is erected, a worker firstly installs the vertical pipe and the installation part, then installs the transverse pipe in each installation groove in the installation part, in the installation process, the worker can utilize the limiting piece to keep the transverse pipe fixed, so that the transverse pipe cannot move after being placed in the installation groove, after the transverse pipe is installed, the worker installs another vertical pipe on the vertical pipe, the matching part of the other vertical pipe is abutted against the installation part of the vertical pipe, meanwhile, when the transverse pipe is installed, the fixing block on the matching part is inserted into the fixing hole on the transverse pipe, so that the transverse pipe can be fixed between the installation part and the matching part, and when the transverse pipe is installed, the limiting piece is arranged to ensure that the position of the transverse pipe cannot deviate, so that the worker does not need to repeatedly adjust the position of the transverse pipe, and the installation efficiency of the scaffold is improved, meanwhile, the limiting piece also has a certain positioning effect, so that the fixing hole can always face to the correct position.
Optionally, the locating part is including setting up the spacing in the mounting groove, spacing sets up on the inner wall of mounting groove, spacing is provided with more than at least one, spacing sets up along the length direction of mounting groove, the spacing groove has been seted up on the tip of violently managing, spacing groove and spacing cooperation setting.
Through adopting above-mentioned technical scheme, when violently managing in the installation, remove violently the pipe towards the mounting groove in, make spacing on the mounting groove inner wall joint violently manage the spacing inslot that corresponds, utilize spacing and spacing groove alright in order to restrict the position of violently managing to make violently the pipe fix in the mounting groove.
Optionally, the locating part is including seting up the joint groove in the mounting groove, at least more than one has been seted up in the joint groove, be provided with the joint piece on the tip of violently managing, the quantity of joint piece is the same and the one-to-one with the quantity in joint groove, the joint piece sets up with the cooperation of joint groove.
Through adopting above-mentioned technical scheme, when will violently managing in installing the mounting groove, the joint piece that the messenger violently managed gets into the joint inslot that corresponds to in will violently managing and putting into the mounting groove, utilize joint piece and joint groove to make violently manage and can not remove at will, thereby realized violently the restriction of managing the position.
Optionally, one end of the vertical pipe is provided with an insertion part, the insertion part and the vertical pipe are integrally arranged, and the diameter of the insertion part is smaller than the inner diameter of the vertical pipe.
By adopting the technical scheme, the two stand pipes are spliced, the insertion part on one stand pipe is inserted into the other stand pipe, so that the two stand pipes are spliced, and the connection between the two stand pipes is tighter by utilizing the arrangement of the insertion part.
Optionally, the mounting portion and the mating portion are provided with fixing components for fixing the mounting portion and the mating portion.
Through adopting above-mentioned technical scheme, will violently manage and install the back in the mounting groove, splice the riser again to make installation department and cooperation portion butt, utilize installation department and cooperation portion will violently manage completely fixed, then recycle fixed subassembly and fix installation department and cooperation portion, thereby further improve scaffold frame structure's stability.
Optionally, the fixed subassembly is including seting up the spread groove on the installation department, just be provided with the block rubber on being located relative inner wall in the spread groove, be provided with the connecting block of plug-in connection to in the spread groove in the cooperation portion, the connecting block sets up with the spread groove cooperation.
Through adopting above-mentioned technical scheme, at fixed mounting portion and cooperation portion, make cooperation portion remove towards the installation department, make connecting block on the installation department plug-in connect to corresponding spread groove simultaneously, the connecting block can produce the extrusion to the block rubber of both sides inserting the in-process, make the block rubber warp, can produce elasticity to the connecting block after the block rubber warp, and the block rubber of both sides then can fix the connecting block in the spread groove, thereby realize the fixed of installation department and cooperation portion.
Optionally, the fixing assembly comprises a fixing screw rod arranged on the installation portion, the fixing screw rod penetrates through the matching portion along the vertical direction, and a fixing nut tightly abutted to the matching portion is connected to the fixing screw rod through threads.
Through adopting above-mentioned technical scheme, when carrying out the fixed of installation department and cooperation portion, make the clamping screw on the installation department pass cooperation portion, then on screwing clamping screw with fixation nut again, after the installation department is gone up in cooperation portion butt, screw up fixation nut again and make it tightly support on cooperation portion, so alright in fixed mounting department and cooperation portion.
Optionally, the edges of the mounting groove and the matching groove are provided with rubber strips.
Through adopting above-mentioned technical scheme, the setting of rubber strip makes violently the pipe can fix between mounting groove and cooperation groove better.
In a second aspect, the present application provides a method for setting up a scaffold, which adopts the following technical scheme:
a method for building a scaffold, which comprises the scaffold structure, comprises the following steps:
s1: a step of foundation treatment, namely, leveling and tamping the ground before the scaffold is erected, and paving a wood board on the ground;
s2: a pole erecting step, namely installing vertical pipes in sequence from inside to outside, temporarily fixing the vertical pipes, then installing the transverse pipes on the vertical pipes, and fixing the transverse pipes by using the installation parts and the matching parts on the vertical pipes in the installation process;
s3: anchoring, namely anchoring the scaffold every 4-5m in the horizontal direction to connect the scaffold and the building through anchor rods;
s4: the installation net is hung and arranged, and the installation net is hung and arranged on the outer side of the scaffold.
Through adopting above-mentioned technical scheme, at the in-process of installation riser and violently managing, the locating part that utilizes in the mounting groove of installation department can carry out temporary fixed to violently managing, and the staff need not to adjust the position of violently managing repeatedly for the effect of setting up of scaffold frame obtains improving.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the limiting pieces are arranged in the mounting grooves, and the transverse pipes mounted in the mounting grooves are preliminarily fixed by the limiting pieces, so that the situation that the mounted transverse pipes deviate when other transverse pipes are mounted can be reduced, workers do not need to repeatedly adjust the positions of the transverse pipes, and the building efficiency of the scaffold is improved;
2. come fixed mounting portion and cooperation portion through setting up fixed subassembly for connection between installation department and the fixed part is inseparabler, makes installation department and cooperation portion obtain improving to the fixed effect of violently managing, thereby has improved the holistic stability of scaffold frame.
Drawings
FIG. 1 is a schematic overall structure diagram of a first embodiment of the present application;
FIG. 2 is a schematic diagram of a partial explosion after explosion of two risers in FIG. 1 according to an embodiment of the present application;
FIG. 3 is an enlarged partial schematic view of portion A of FIG. 2;
FIG. 4 is a schematic structural diagram of a mating portion of an embodiment of the present application;
FIG. 5 is a schematic diagram of a partial explosion structure of two risers after explosion according to the second embodiment of the present application;
FIG. 6 is an enlarged partial schematic view of portion B of FIG. 5;
fig. 7 is a schematic overall structure diagram of a third embodiment of the present application.
Description of reference numerals: 1. a riser; 11. a plug-in part; 2. a transverse tube; 21. a fixing hole; 22. a limiting groove; 23. a clamping block; 3. a connecting assembly; 31. an installation part; 311. mounting grooves; 312. a limiting strip; 313. a clamping groove; 314. connecting grooves; 315. a rubber block; 316. fixing the screw rod; 317. fixing a nut; 32. a fitting portion; 321. a mating groove; 322. connecting blocks; 323. a through hole; 4. a rubber strip.
Detailed Description
The present application is described in further detail below with reference to figures 1-7.
The embodiment of the application discloses scaffold structure.
Example one
Referring to fig. 1 and 2, a scaffold structure includes a plurality of risers 1, cross pipes 2, and connection assemblies 3 (only partial structure is shown) between the risers 1 and the cross pipes 2, wherein the connection assemblies 3 include mounting portions 31 and fitting portions 32, the mounting portions 31 are welded to one ends of the risers 1, the fitting portions 32 are welded to the other ends of the fitting pipes, and when two risers 1 are spliced in a vertical direction, the fitting portions 32 of one riser 1 abut against the mounting portions 31 of the other riser 1; evenly seted up mounting groove 311 along the circumference of mounting portion 31 on the mounting portion 31, the quantity of mounting groove 311 is generally four, also can be one, two or three, the cross sectional shape of mounting groove 311 sets up to semi-circular, the diameter size of mounting groove 311 and the external diameter size looks adaptation of violently managing 2, set up the cooperation groove 321 that corresponds with mounting groove 311 quantity and position homogeneous phase on the cooperation portion 32, the cross sectional shape of cooperation groove 321 is semi-circular equally, and when cooperation portion 32 and mounting portion 31 butt, mounting groove 311 and cooperation groove 321 form the fixed slot that is used for fixed violently managing 2.
Referring to fig. 2 and 3, a fixing hole 21 is formed in an end portion of the horizontal tube 2 located in the mounting groove 311, a fixing block is welded in the fitting groove 321, and after the fitting portion 32 abuts against the mounting portion 31, the fixing block is also inserted into the fixing hole 21, so that the horizontal tube 2 is fixed in the fixing groove; a limiting member is arranged in the mounting groove 311, and the limiting member can limit the horizontal tube 2 from moving in the mounting groove 311.
When setting up the scaffold frame, at first finish the installation of first layer riser 1, the installation of violently managing 2 is carried out afterwards, the tip that will violently manage 2 during the installation is arranged in riser 1 in installation groove 311 of installation department 31, utilize the locating part to carry out preliminary fixed to violently managing 2, make the position of violently managing 2 can not produce the skew, will violently manage 2 installation back, the installation of second layer riser 1 is carried out again, splice first layer riser 1 on second layer riser 1, and make cooperation portion 32 on the second riser 1 and the 31 butts of installation department of first layer riser 1, make the fixed block in the cooperation groove 321 insert in violently managing the fixed orifices 21 on 2, thereby violently realize violently managing 2 complete fixed, utilize the locating part to the restriction of violently managing 2 positions, make the staff need not to go repeatedly to adjust violently pipe 2, the efficiency of setting up of scaffold frame has been improved.
Referring to fig. 2 and 3, the limiting member includes two limiting bars 312 welded on the inner wall of the mounting groove 311, the two limiting bars 312 are symmetrically disposed, and the limiting bars 312 extend along the length direction of the mounting groove 311, in other embodiments, the number of the limiting bars 312 may also be one, three or more, the end of the transverse tube 2 is provided with the limiting groove 22, and the number of the limiting grooves 22 is the same as that of the limiting bars 312, and the positions of the limiting grooves 22 and the positions of the limiting bars 312 correspond; when violently managing 2 in the installation, at first make violently pipe 2 tip support in the position of mounting groove 311, then remove violently pipe 2 towards the mounting groove 311 in, spacing 312 in the in-process mounting groove 311 just can the joint violently manage the spacing groove 22 on 2 in, utilize spacing 312 and spacing groove 22 alright prevent violently pipe 2 position emergence skew.
Referring to fig. 3 and 4, be provided with fixed subassembly on installation department 31 and the cooperation portion 32, fixed subassembly can fix installation department 31 and cooperation portion 32, fixed subassembly is including seting up a plurality of spread grooves 314 on installation department 31, the position between two adjacent mounting grooves 311 is seted up to spread grooves 314, it has rubber block 315 to paste in the spread grooves 314 and on being located relative inner wall, rubber block 315 is whole to be the hemisphere, the sphere of two rubber blocks 315 sets up relatively, and the welding has connecting block 322 on the cooperation portion 32, connecting block 322 and spread grooves 314 looks adaptation.
In-process at cooperation portion 32 and installation department 31 butt, connecting block 322 can get into in the connecting groove 314 that corresponds, connecting block 322 produces the extrusion to rubber block 315 at the entering in-process, rubber block 315 is produced elasticity after being extruded, produce elasticity to connecting block 322, the elasticity that the rubber block 315 of both sides produced alright fix connecting block 322 in connecting groove 314, thereby realized the fixed between cooperation portion 32 and the installation department 31, and when dismantling, only need make hard cooperation portion 32 and installation department 31 separate can, it is very convenient.
Referring to fig. 4, an inserting portion 11 is integrally formed at one end where the matching portion 32 of the vertical pipe 1 is located, the diameter of the inserting portion 11 is smaller than the inner diameter of the vertical pipe 1, when two vertical pipes 1 are spliced, the inserting portion 11 on one vertical pipe 1 is inserted into the other vertical pipe 1, and the two vertical pipes 1 are connected more tightly by using the inserting portion 11.
Referring to fig. 3, in order to improve the fixing effect to the horizontal tube 2, a rubber strip 4 is attached to the edges of the mounting groove 311 and the fitting groove 321.
The implementation principle of the first embodiment is as follows: after the first layer of vertical pipes 1 are installed, the horizontal pipes 2 are sequentially installed in the installation grooves 311 of the installation parts 31 on the vertical pipes 1, in the installation process, the limiting strips 312 in the mounting grooves 311 are clamped with the limiting grooves 22 on the transverse pipes 2 to realize the primary fixation of the transverse pipes 2, then the second layer of vertical pipes 1 are mounted, the insertion parts 11 of the second layer of vertical pipes 1 are inserted into the first layer of vertical pipes 1, and the matching part 32 is abutted against the mounting part 31, in the process, the fixing block can be inserted into the fixing hole 21 to fix the transverse pipe 2, the connecting block 322 can be inserted into the connecting groove 314 to fix the mounting part 31 and the matching part 32, thus, the fixing between the two vertical pipes 1 is realized, and the position of the transverse pipe 2 is limited by the limiting strip 312 and the limiting groove 22, in the installation process of the transverse pipe 2, the transverse pipe 2 cannot deviate, and the setting efficiency of the scaffold is improved.
Example two
Referring to fig. 5 and 6, the present embodiment is different from the first embodiment in that: the limiting part comprises clamping grooves 313 formed in the inner wall of the mounting groove 311, the clamping grooves 313 are four in number, the four clamping grooves 313 are formed in the vertical direction, in other embodiments, the clamping grooves 313 can be one, two, three or more, the end portion of the transverse pipe 2 is welded with a plurality of clamping blocks 23, the number and the positions of the clamping grooves 313 are the same as those of the clamping grooves 313, the clamping blocks 23 correspond to the clamping grooves 313 one by one, and meanwhile the clamping blocks 23 are matched with the clamping grooves 313.
The implementation principle of the second embodiment is as follows: when violently managing 2 in the installation, make on violently managing 2 joint piece 23 insert the mounting groove 311 in the joint groove 313 that corresponds to violently managing 2 and arranging violently managing in mounting groove 311, utilize joint piece 23 and joint groove 313 alright with the removal of restricting violently managing 2, can also realize the effect of location simultaneously, make the fixed orifices 21 of violently managing 2 all the time towards correct position.
EXAMPLE III
Referring to fig. 7, the present embodiment is different from the first embodiment in that: the fixing assembly comprises four fixing screws 316 welded on the installation part 31, the four fixing screws 316 are located at four corners of the installation part 31, the four fixing screws 316 extend along the vertical direction, a through hole 323 is formed in the matching part 32, the fixing screws 316 penetrate through the through hole 323 to be arranged in the matching part 32, and the fixing screws 316 are connected with fixing nuts 317 tightly abutted to the matching part 32 through threads.
The implementation principle of the third embodiment is as follows: after the horizontal tube 2 is installed, the two vertical tubes 1 are spliced, the matching portion 32 is abutted to the installation portion 31, in the process, the fixing screw 316 penetrates through the corresponding through hole 323 in the matching portion 32, and then after the matching portion 32 is abutted to the installation portion 31, the fixing nut 317 is screwed to enable the fixing nut 317 to be abutted to the matching portion 32, so that the matching portion 32 is fixed to the installation portion 31.
The embodiment of the application also discloses a method for erecting the scaffold, which comprises the following steps:
s1: a step of foundation treatment, namely, leveling and tamping the ground before the scaffold is erected, and paving a wood board on the ground;
s2: a pole setting step, namely installing the vertical pipe 1 in the sequence from inside to outside, temporarily fixing the vertical pipe, then installing the transverse pipe 2 on the vertical pipe 1, fixing the transverse pipe 2 by using an installation part 31 and a matching part 32 on the vertical pipe 1 in the installation process, and limiting the transverse pipe 2 by using a limiting part in an installation groove 311 on the installation part 31;
s3: anchoring, namely anchoring the scaffold every 4-5m in the horizontal direction to connect the scaffold and the building through anchor rods;
s4: the installation net is hung and arranged, and the installation net is hung and arranged on the outer side of the scaffold.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (9)

1. The utility model provides a scaffold structure, includes a plurality of risers (1), violently manages (2) and riser (1) and violently manage coupling assembling (3) between (2), its characterized in that: the connecting assembly (3) comprises an installation part (31) arranged at one end of the stand pipe (1), and installation grooves (311) are uniformly formed in the installation part (31) along the circumferential direction of the installation part (31); the other end of riser (1) is provided with cooperation portion (32), two when riser (1) splices along vertical direction, one cooperation portion (32) of riser (1) and installation department (31) butt of another riser (1), cooperation portion (32) are gone up and are seted up cooperation groove (321) that correspond with mounting groove (311), during cooperation portion (32) and installation department (31) butt, mounting groove (311) and cooperation groove (321) form the fixed slot that is used for fixed violently pipe (2), fixed orifices (21) have been seted up on the tip of violently pipe (2), be provided with the fixed block that inserts in fixed orifices (21) in cooperation groove (321), be provided with the locating part in mounting groove (311), the locating part is used for restricting violently pipe (2) and takes place to remove in mounting groove (311).
2. The scaffolding structure as claimed in claim 1, wherein: the locating part is including setting up spacing (312) in mounting groove (311), spacing (312) set up on the inner wall of mounting groove (311), spacing (312) are provided with more than at least one, spacing (312) set up along the length direction of mounting groove (311), spacing groove (22) have been seted up on the tip of violently managing (2), spacing groove (22) set up with spacing (312) cooperation.
3. The scaffolding structure as claimed in claim 1, wherein: the locating part is including offering joint groove (313) in mounting groove (311), joint groove (313) have been seted up more than at least one, be provided with joint piece (23) on the tip of violently managing (2), the quantity of joint piece (23) is the same and the one-to-one with the quantity in joint groove (313), joint piece (23) set up with joint groove (313) cooperation.
4. The scaffolding structure as claimed in claim 1, wherein: one end of the vertical pipe (1) is provided with an inserting part (11), the inserting part (11) and the vertical pipe (1) are integrally arranged, and the diameter of the inserting part (11) is smaller than the inner diameter of the vertical pipe (1).
5. The scaffolding structure as claimed in claim 1, wherein: and fixing components for fixing the mounting part (31) and the matching part (32) are arranged on the mounting part (31) and the matching part (32).
6. The scaffolding structure as claimed in claim 5, wherein: fixed subassembly is including offering spread groove (314) on installation department (31), be provided with rubber block (315) in spread groove (314) and on being located relative inner wall, be provided with on cooperation portion (32) and insert to connecting block (322) in spread groove (314), connecting block (322) and spread groove (314) cooperation setting.
7. The scaffolding structure as claimed in claim 5, wherein: the fixing assembly comprises a fixing screw rod (316) arranged on the installation portion (31), the fixing screw rod (316) penetrates through the matching portion (32) along the vertical direction, and a fixing nut (317) abutting against the matching portion (32) is connected to the fixing screw rod (316) through threads.
8. The scaffolding structure as claimed in claim 1, wherein: the edge of the mounting groove (311) and the edge of the matching groove (321) are provided with rubber strips (4).
9. A method of erecting a scaffold comprising the scaffold structure of any one of claims 1 to 8, comprising the steps of:
s1: a step of foundation treatment, namely, leveling and tamping the ground before the scaffold is erected, and paving a wood board on the ground;
s2: a pole erecting step, namely installing vertical pipes (1) in sequence from inside to outside, temporarily fixing the vertical pipes, then installing transverse pipes (2) on the vertical pipes (1), and fixing the transverse pipes (2) by utilizing an installation part (31) and a matching part (32) on the vertical pipes (1) in the installation process;
s3: anchoring, namely anchoring the scaffold every 4-5m in the horizontal direction to connect the scaffold and the building through anchor rods;
s4: the installation net is hung and arranged, and the installation net is hung and arranged on the outer side of the scaffold.
CN202011378333.XA 2020-11-30 2020-11-30 Scaffold structure and erection method thereof Pending CN112459438A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011378333.XA CN112459438A (en) 2020-11-30 2020-11-30 Scaffold structure and erection method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011378333.XA CN112459438A (en) 2020-11-30 2020-11-30 Scaffold structure and erection method thereof

Publications (1)

Publication Number Publication Date
CN112459438A true CN112459438A (en) 2021-03-09

Family

ID=74806339

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011378333.XA Pending CN112459438A (en) 2020-11-30 2020-11-30 Scaffold structure and erection method thereof

Country Status (1)

Country Link
CN (1) CN112459438A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2622312Y (en) * 2003-05-29 2004-06-30 上海大学 Thin rod, plane board and rope joining member
US20150152654A1 (en) * 2012-11-23 2015-06-04 Yukio Yamane Support steel pipe and bracket for scaffolding or falsework, and scaffolding or falsework
CN207377078U (en) * 2017-10-17 2018-05-18 安徽建诚国际经济技术合作有限公司 A kind of construction scaffold of reusable edible
CN208184183U (en) * 2018-03-30 2018-12-04 北京城建一建设发展有限公司 A kind of new type scaffold
CN109989572A (en) * 2017-12-29 2019-07-09 天津市莎烽科技有限公司 Quick-mounting scaffold connection structure
CN210888033U (en) * 2019-09-20 2020-06-30 严晓安 Quick non-right-angle multipurpose square tube, round tube, flat rectangular tube scaffold sleeve
CN211817923U (en) * 2020-03-20 2020-10-30 杭州佳恒建筑科技有限公司 Scaffold for building construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2622312Y (en) * 2003-05-29 2004-06-30 上海大学 Thin rod, plane board and rope joining member
US20150152654A1 (en) * 2012-11-23 2015-06-04 Yukio Yamane Support steel pipe and bracket for scaffolding or falsework, and scaffolding or falsework
CN207377078U (en) * 2017-10-17 2018-05-18 安徽建诚国际经济技术合作有限公司 A kind of construction scaffold of reusable edible
CN109989572A (en) * 2017-12-29 2019-07-09 天津市莎烽科技有限公司 Quick-mounting scaffold connection structure
CN208184183U (en) * 2018-03-30 2018-12-04 北京城建一建设发展有限公司 A kind of new type scaffold
CN210888033U (en) * 2019-09-20 2020-06-30 严晓安 Quick non-right-angle multipurpose square tube, round tube, flat rectangular tube scaffold sleeve
CN211817923U (en) * 2020-03-20 2020-10-30 杭州佳恒建筑科技有限公司 Scaffold for building construction

Similar Documents

Publication Publication Date Title
US8632056B1 (en) Safety rail system
CN110670867A (en) Construction method of scaffold for improving outer vertical surface of existing building
CN105696802B (en) Edge protection column and its installation method in constructing applied to large area floor template
CN112459438A (en) Scaffold structure and erection method thereof
CN110735525B (en) Prefabricated assembled self-supporting steel pipe scaffold system
CN212743282U (en) Supporting and fixing frame for building construction
CN210342875U (en) Outdoor tent support structure
CN211777140U (en) Be applicable to protector for water plant civil engineering
CN111877724A (en) Splicing combined type high-stability cantilever frame convenient to adjust
CN219241416U (en) Safety protection structure
CN213980234U (en) Building guardrail for civil engineering
KR200392074Y1 (en) Trussed supporting post for easily constructing concrete structures
CN215669565U (en) Foundation ditch side slope concrete shotcrete anchor supporting construction
CN216105700U (en) Tower crane that easily sets up attaches operation platform for wall
CN211396523U (en) Assembled supports construction platform
CN216641637U (en) A protection network for construction
CN211058273U (en) Building scaffold structure of encorbelmenting
CN219411911U (en) Adjustable net frame assembling support jig frame
CN221143817U (en) Be applied to steel construction stair protection railing in construction field
CN211974234U (en) Civil engineering construction support
CN211369448U (en) Prefabricated assembled self-supporting steel pipe scaffold foundation
CN212428035U (en) Scaffold frame installation fixing device for construction
CN218563273U (en) Plug-in type limb surrounding rod device
CN211498517U (en) Stable supporting device for bridge formwork
CN220247695U (en) A face limit operation protector for construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210309

RJ01 Rejection of invention patent application after publication