CN112443070B - Finished suspended ceiling grade-falling installation structure and installation method - Google Patents
Finished suspended ceiling grade-falling installation structure and installation method Download PDFInfo
- Publication number
- CN112443070B CN112443070B CN202011383927.XA CN202011383927A CN112443070B CN 112443070 B CN112443070 B CN 112443070B CN 202011383927 A CN202011383927 A CN 202011383927A CN 112443070 B CN112443070 B CN 112443070B
- Authority
- CN
- China
- Prior art keywords
- plate
- suspended ceiling
- ceiling
- low
- horizontal plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009434 installation Methods 0.000 title claims abstract description 50
- 238000000034 method Methods 0.000 title claims abstract description 22
- 230000002787 reinforcement Effects 0.000 claims description 11
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- 239000002184 metal Substances 0.000 claims description 3
- 230000000472 traumatic effect Effects 0.000 claims 6
- 238000010276 construction Methods 0.000 abstract description 23
- 238000005034 decoration Methods 0.000 abstract description 8
- 238000004519 manufacturing process Methods 0.000 abstract description 5
- 238000005516 engineering process Methods 0.000 description 4
- 230000003014 reinforcing effect Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 239000000428 dust Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 238000013475 authorization Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 201000010099 disease Diseases 0.000 description 1
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 1
- 238000007688 edging Methods 0.000 description 1
- 230000002708 enhancing effect Effects 0.000 description 1
- 239000012634 fragment Substances 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000009323 psychological health Effects 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/04—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/04—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like
- E04B9/0435—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like having connection means at the edges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/18—Means for suspending the supporting construction
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/22—Connection of slabs, panels, sheets or the like to the supporting construction
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Finishing Walls (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention provides a finished suspended ceiling grade-falling installation structure and an installation method, and relates to the technical field of decoration design. The invention has the advantages of simple structure, convenient construction, no need of on-site production, assembly type installation, improved construction efficiency, more environment protection, good structural stability after installation, low construction requirement, difficult occurrence of quality problem, good connection performance and good aesthetic property.
Description
Technical Field
The invention relates to the technical field of decoration design,
In particular, the invention relates to a finished suspended ceiling falling-level installation structure and an installation method.
Background
At present, the decoration industry is developing towards the direction of industrialized modularized installation, in general, suspended ceiling decoration is a decoration method commonly adopted in indoor design, so that the layering sense of indoor space can be increased, and the effect of beautifying and decorating is achieved.
The industrial assembly technology and the assembly type decoration technology are widely applied in the decoration industry, the assembly type suspended ceiling technology is very important in practical application as an indoor decoration technology, and the suspended ceiling is frequently used for displaying the sense of space opening due to falling. Frequently, the conventional suspended ceiling is mainly provided with four-side falling stages, namely: the center of the top surface of the room is provided with a higher groove, the peripheral top surface is lower, the groove is provided with four groove walls, and the four groove walls enclose a rectangle, for example, chinese patent invention patent No. CN106013585A discloses a suspended ceiling stage-falling device and an installation method. The suspended ceiling grade-dropping device comprises a vertical frame, wherein the vertical frame comprises a plurality of vertical plates, and the vertical plates are sequentially connected end to end along the length direction to form a closed structure; the first keels extend along the length direction of the vertical plate; a first connecting groove is formed in the surface, facing away from the vertical plate, of the first keel; the first hanging piece is clamped in the first connecting groove; each edge of the top plate is overlapped with the edge of one of the vertical plates; a second keel is connected to the surface of the top plate, which is back to the vertical plate, and a second connecting groove is formed in the surface of the second keel; the second hanging piece is adjustably clamped in the second connecting groove. The installation method of the suspended ceiling grade-dropping device can be used for rapidly installing the suspended ceiling grade-dropping device. The suspended ceiling grade-falling device and the installation method provided by the invention provide a modularized integrated central unit which is fast to install, reduce construction difficulty and construction labor intensity, reduce installation and construction procedures, save installation time and reduce pollution on a construction site.
The suspended ceiling edging structure still has the following defects: 1. the drop-level suspended ceiling structure has complex modeling and multiple construction processes, not only affects the engineering progress, but also is extremely easy to generate various quality common diseases among various construction procedures; 2. when the suspended ceiling is manufactured on site, quality problems such as large deviation of flatness, cracking and the like of the suspended ceiling can occur due to uneven hand skills of constructors; 3. when the construction method is used for on-site production, problems such as noise, wood dust and dust are generated, and the physical and psychological health and the environment of constructors are seriously damaged; 4. the gap between the plate bodies is large, and the attractive appearance is poor.
Therefore, in order to solve the above problems, it is necessary to design a reasonable and efficient finished suspended ceiling stage-falling installation structure.
Disclosure of Invention
The invention aims to provide the suspended ceiling edge-folding structure which has the advantages of simple structure, convenient construction, no need of on-site manufacturing, assembly type installation, improved construction efficiency, more environment friendliness, good structural stability after installation, low construction requirement, difficult occurrence of quality problems, good connection performance and good attractiveness.
In order to achieve the above purpose, the invention is realized by adopting the following technical scheme:
The utility model provides a finished suspended ceiling falls a level mounting structure, includes high-order furred ceiling board, low-order furred ceiling board and is used for connecting the function piece of high-order furred ceiling board and low-order furred ceiling board, high-order furred ceiling board and low-order furred ceiling board all pass through the connecting piece with the function piece is connected, the function piece include with the first horizontal plate that high-order furred ceiling board is connected, with the second horizontal plate that low-order furred ceiling board is connected and be used for connecting the connecting plate of first horizontal plate and second horizontal plate, the connecting piece includes first riser, second riser and is used for connecting the joint board of first riser and second riser, first riser both ends are provided with respectively to be away from the first cardboard that the second riser direction extends, high-order roof board and low-order furred ceiling board all are connected with the fossil fragments, the square steel keel is connected with, the second jib is connected with the square steel.
Preferably, the connection part of the second horizontal plate and the connecting plate is provided with a reinforcement.
Preferably, the connection part of the first horizontal plate and the connecting plate is provided with a reinforcement.
Preferably, a lamp groove plate is arranged at one end of the second horizontal plate far away from the low-level ceiling plate.
Preferably, the connecting piece is an integrally formed metal piece.
Preferably, the thickness of the high-position ceiling tile and the low-position ceiling tile are equal to the width between the two second clamping boards.
Preferably, the thickness of the first horizontal plate and the second horizontal plate is equal to the width between the two first clamping plates.
Preferably, the first horizontal plate and the second horizontal plate are each disposed perpendicular to the connection plate.
Preferably, the number of the joint plates is at least one.
Preferably, the reinforcement is a right-angle plate.
The invention also provides an installation method of the finished suspended ceiling falling-level installation structure, which comprises the following steps:
S1: setting the mounting heights of the high-position ceiling plate and the low-position ceiling plate on the wall surface elastic line;
S2: the first suspender is installed, the connecting plate of the functional piece is connected to the lower end of the first suspender, the height of the first horizontal plate is guaranteed to be the same as that of the high-position suspended ceiling plate, and the height of the second horizontal plate is guaranteed to be the same as that of the low-position suspended ceiling plate;
S3: installing connecting pieces at the ends of the first horizontal plate and the second horizontal plate, so that the first horizontal plate and the second horizontal plate extend between two first clamping plates of the connecting pieces;
S4: installing a second suspender, square steel pieces and keels for installing the high-position suspended ceiling plate and the low-position suspended ceiling plate;
S5: installing a high-position suspended ceiling plate and a low-position suspended ceiling plate below the keels, so that the end parts of the high-position suspended ceiling plate and the low-position suspended ceiling plate extend between two second clamping plates of the connecting piece;
s6: and (2) repeatedly executing the steps S2 to S5, and sequentially installing the functional parts, the high-level suspended ceiling plate and the low-level suspended ceiling plate around the house to finish the installation of the whole drop-level suspended ceiling.
Preferably, in the step S2, a reinforcement is installed at a connection portion between the first horizontal plate or the second horizontal plate and the connection plate when the functional member is installed.
As the preference of the invention, when the step S3 is executed, the thickness of the first horizontal plate and the second horizontal plate is ensured to be equal to the width between the two first clamping plates when the connecting piece is installed, and the thickness of the high-position suspended ceiling plate and the low-position suspended ceiling plate is equal to the width between the two second clamping plates.
The invention relates to a finished suspended ceiling falling-level installation structure and an installation method, which have the beneficial effects that: simple structure, construction convenience need not the scene preparation, can assembled installation, improves the efficiency of construction, and more green, structural stability is good after the installation, is low to the construction requirement, is difficult for appearing quality problem, and linking property is good, and the aesthetic property is good.
Drawings
FIG. 1 is a schematic view of an embodiment of a finished ceiling drop mounting structure of the present invention at the completion of installation;
FIG. 2 is a schematic diagram of the functional components of one embodiment of a finished ceiling drop mounting structure of the present invention;
FIG. 3 is a schematic view of the structure of the connector in one embodiment of a finished ceiling drop mounting structure of the present invention;
FIG. 4 is a schematic diagram of an installation flow of an installation method of a finished ceiling falling installation structure according to the present invention;
In the figure: 1. the functional parts, 11, the first horizontal plates, 12, the second horizontal plates, 13, the connecting plates, 14, the first suspenders, 15, the reinforcing parts, 16, the lamp groove plates, 2, the high-position suspended ceiling plates, 3, the low-position suspended ceiling plates, 4, the connecting parts, 41, the first vertical plates, 411, the first clamping plates, 42, the second vertical plates, 421, the second clamping plates, 43, the joint plates, 51, keels, 52, the square steel parts, 53 and the second suspenders.
Detailed Description
The following are specific examples of the present invention, and the technical solutions of the present invention are further described, but the present invention is not limited to these examples.
Various exemplary embodiments of the present invention will now be described in detail with reference to the accompanying drawings. It should be noted that: the relative arrangement of the modules and steps set forth in these embodiments and the steps do not limit the scope of the present invention unless specifically stated otherwise.
Meanwhile, it should be understood that the flow in the drawings is not merely performed alone, but a plurality of steps are performed to cross each other for convenience of description.
The following description of at least one exemplary embodiment is merely exemplary in nature and is in no way intended to limit the invention, its application, or uses.
Techniques, methods, and systems known to those of ordinary skill in the relevant art may not be discussed in detail, but should be considered part of the authorization specification where appropriate.
Embodiment one: as shown in fig. 1 to 3, the finished suspended ceiling low-level installation structure comprises a high suspended ceiling 2, a low suspended ceiling 3 and a functional piece 1 for connecting the high suspended ceiling 2 and the low suspended ceiling 3, wherein the high suspended ceiling 2 and the low suspended ceiling 3 are connected with the functional piece 1 through connecting pieces 4, the functional piece 1 comprises a first horizontal plate 11 connected with the high suspended ceiling 2, a second horizontal plate 12 connected with the low suspended ceiling 3 and a connecting plate 13 for connecting the first horizontal plate 11 and the second horizontal plate 12, the connecting plate 13 is connected with a first hanging rod 14, the connecting pieces 4 comprise a first vertical plate 41, a second vertical plate 42 and a connecting slot plate 43 for connecting the first vertical plate 41 and the second vertical plate 42, two ends of the first vertical plate 41 are respectively provided with a first clamping plate 411 extending in a direction away from the second vertical plate 42, two ends of the second vertical plate 42 are respectively provided with a second vertical plate 421 extending in a direction away from the first vertical plate 41 and a second vertical plate 52, two ends of the second vertical plate 41 are respectively connected with a second hanging plate 51, and two ends of the second vertical plate 41 are connected with a second hanging plate 52 are connected with a second hanging plate 51.
In the invention, the high-level suspended ceiling plate 2 is arranged in the middle of the top of a house, the low-level suspended ceiling plate 3 is arranged around the high-level suspended ceiling plate 2, the functional piece 1 is used for connecting the high-level suspended ceiling plate 2 and the low-level suspended ceiling plate 3, the functional piece 1 is naturally hoisted to the top of the wall by using the first suspender 14, and the high-level suspended ceiling plate 2 and the low-level suspended ceiling plate 3 are hoisted to the top of the wall by the second suspender 53.
Firstly, the functional element 1 is configured, the functional element 1 comprises a first horizontal plate 11 connected with the high-level suspended ceiling plate 2, a second horizontal plate 12 connected with the low-level suspended ceiling plate 3, and a connecting plate 13 for connecting the first horizontal plate 11 and the second horizontal plate 12, wherein the first horizontal plate 11 has the same height as the high-level suspended ceiling plate 2, the second horizontal plate 12 has the same height as the low-level suspended ceiling plate 3, and the first horizontal plate 11 and the second horizontal plate 12 are perpendicular to the connecting plate 13, so that the functional element 1 forms a positive Z-shaped element (or a reverse positive Z-shaped element), and the first horizontal plate 11 and the second horizontal plate 12 are respectively connected with the high-level suspended ceiling plate 2 and the low-level suspended ceiling plate 3 to play the role of installing a drop suspended ceiling.
Then the high-level suspended ceiling plate 2 and the low-level suspended ceiling plate 3 are connected with the functional piece 1, the high-level suspended ceiling plate 2 and the low-level suspended ceiling plate 3 are connected with the functional piece 1 through a connecting piece 4, the connecting piece 4 comprises a first riser 41, a second riser 42 and a joint plate 43 for connecting the first riser 41 and the second riser 42, two ends of the first riser 41 are respectively provided with a first clamping plate 411 extending away from the second riser 42, two ends of the second riser 42 are respectively provided with a second clamping plate 421 extending away from the first riser 41,
Here, the thicknesses of the high-level ceiling tile 2 and the low-level ceiling tile 3 are equal to the width between the two second clamping boards 421, and the thicknesses of the first horizontal board 11 and the second horizontal board 12 are equal to the width between the two first clamping boards 411. When the connecting piece 4 is installed, the first horizontal plate 11 and the second horizontal plate 12 are clamped between the two first clamping plates 411, the high-position suspended ceiling plate 2 and the low-position suspended ceiling plate 3 are clamped between the two second clamping plates 421, and the assembly of the functional piece 1, the high-position suspended ceiling plate 2 and the low-position suspended ceiling plate 3 is completed.
Like this, the perfect problem of being connected of high-order furred ceiling board 2 and low-order furred ceiling board 3 and function piece 1 of having solved through connecting piece 4, and the board seam is the length of linking seam board 43, and the furred ceiling gap is controllable, has better decorative effect and aesthetic property, and connecting piece 4 can bear the weight of the tip of high-order furred ceiling board 2 and low-order furred ceiling board 3 moreover, prevents high-order furred ceiling board 2 and low-order furred ceiling board 3 tip bending deformation, shares well weight to function piece 1 and be used for hoisting the first jib 14 departments of function piece 1.
It should be noted that the functional element 1 is an integrally formed piece, and the connecting element 4 is an integrally formed metal piece. Thus, the functional piece 1 and the connecting piece 4 are integrally processed and produced in a factory, finished products are installed on site, the construction efficiency is improved, the construction period is shortened, and the method is more environment-friendly.
In addition, connecting plate 13 is connected with first jib 14 to when guaranteeing that function 1 is in forward level and placing, its focus is in connecting plate 13, connecting plate 13 is connected to first jib 14 bottom, and function 1 can not rotate like this, has not only effectually reduced the installation and has been hung the structural stability after the piece use quantity has been guaranteed simultaneously, reduces the emergence of quality common problems.
The high-level suspended ceiling plate 2 and the low-level suspended ceiling plate 3 are both connected with keels 51, the keels 51 are connected with square steel pieces 52, the square steel pieces 52 are connected with second suspenders 53, and of course, the length of the second suspenders 53 of the high-level suspended ceiling plate 2 is smaller than that of the second suspenders 53 of the low-level suspended ceiling plate 3.
The finished suspended ceiling grade-falling installation structure is simple in structure, convenient to construct, free of on-site manufacturing, capable of being installed in an assembled mode, improved in construction efficiency, environment-friendly, good in structural stability after installation, low in construction requirement, good in connection performance and attractive in appearance, and quality problems are not easy to occur.
In the second embodiment, as shown in fig. 1 to 3, which are only one embodiment of the present invention, on the basis of the first embodiment, in the final suspended ceiling stage-falling installation structure of the present invention, a reinforcement 15 is disposed at a connection position between the second horizontal plate 12 and the connection plate 13, and the reinforcement 15 is a right-angle plate. One side of the right angle plate is connected with the second horizontal plate 12, and the other side of the right angle plate is connected with the connecting plate 13, so that the stability of the connection of the second horizontal plate 12 and the connecting plate 13 is enhanced.
Or the connection part of the first horizontal plate 11 and the connecting plate 13 is provided with a reinforcement 15.
Or the connection parts of the first horizontal plate 11 and the second horizontal plate 12 and the connecting plate 13 are provided with reinforcing members 15.
Under the condition of larger space, when the bearing weight of the high-position suspended ceiling plate 2 and the low-position suspended ceiling plate 3 is larger, the weight of the high-position suspended ceiling plate 2 and the low-position suspended ceiling plate 3 is shared to the functional piece 1, and in order to prevent the connection deformation of the first horizontal plate and the second horizontal plate and the connecting plate, the reinforcing member 15 is added to strengthen the mounting strength of the finished falling-stage suspended ceiling product piece.
Also, the end of the second horizontal plate 12 away from the lower ceiling plate 3 is provided with a lamp groove plate 16. For mounting down lamps or color light bars at the troffer boards 16, enhancing aesthetics.
Finally, the number of the joint plates 43 is at least one, so that not only the connection stability of the first horizontal plate 11 and the high-level ceiling plate 2 (or the connection stability of the second horizontal plate 12 and the low-level ceiling plate 3) is higher, but also the aesthetic appearance of the joint is better.
In a third embodiment, as shown in fig. 4, the present invention further provides an installation method of the finished suspended ceiling stage-falling installation structure in all the above embodiments, including the following steps:
S1: setting the mounting heights of the high-position ceiling plate and the low-position ceiling plate on the wall surface elastic line;
S2: the first suspender is installed, the connecting plate of the functional piece is connected to the lower end of the first suspender, the height of the first horizontal plate is guaranteed to be the same as that of the high-position suspended ceiling plate, and the height of the second horizontal plate is guaranteed to be the same as that of the low-position suspended ceiling plate;
S3: installing connecting pieces at the ends of the first horizontal plate and the second horizontal plate, so that the first horizontal plate and the second horizontal plate extend between two first clamping plates of the connecting pieces;
S4: installing a second suspender, square steel pieces and keels for installing the high-position suspended ceiling plate and the low-position suspended ceiling plate;
S5: installing a high-position suspended ceiling plate and a low-position suspended ceiling plate below the keels, so that the end parts of the high-position suspended ceiling plate and the low-position suspended ceiling plate extend between two second clamping plates of the connecting piece;
s6: and (2) repeatedly executing the steps S2 to S5, and sequentially installing the functional parts, the high-level suspended ceiling plate and the low-level suspended ceiling plate around the house to finish the installation of the whole drop-level suspended ceiling.
And when the step S2 is executed, installing a reinforcement at the joint of the first horizontal plate or the second horizontal plate and the connecting plate when the functional piece is installed.
When executing step S3, when the connecting piece is installed, guarantee that the thickness of first horizontal plate and second horizontal plate all equals the width between two first cardboard, and the thickness of high-order furred ceiling board and low-order furred ceiling board all equals the width between two second cardboard.
The finished suspended ceiling grade-falling installation structure and the installation method have the advantages of simple structure, convenient construction, no need of on-site production, assembly type installation, improved construction efficiency, more environment friendliness, good structural stability after installation, low requirements on construction, difficult occurrence of quality problems, good connection performance and good attractiveness.
The present invention is not limited to the above-described specific embodiments, and various modifications and variations are possible. Any modification, equivalent replacement, improvement, etc. of the above embodiments according to the technical substance of the present invention should be included in the protection scope of the present invention.
Claims (10)
1. A finished suspended ceiling falls a level mounting structure which characterized in that: including high-order furred ceiling board (2), low-order furred ceiling board (3) and be used for connecting function piece (1) of high-order furred ceiling board (2) and low-order furred ceiling board (3), high-order furred ceiling board (2) and low-order furred ceiling board (3) all through connecting piece (4) with function piece (1) are connected, function piece (1) include with first horizontal plate (11) that high-order furred ceiling board (2) are connected, with second horizontal plate (12) that low-order furred ceiling board (3) are connected and be used for connecting plate (13) of first horizontal plate (11) and second horizontal plate (12), connecting plate (13) are connected with first jib (14), connecting piece (4) include first riser (41), second riser (42) and be used for connecting linking seam board (43) of first riser (41) and second riser (42), first riser (41) both ends are provided with respectively and keep away from second riser (2) are connected with connecting plate (12) of second riser (42) direction (41) and extension direction riser (42), the square steel piece (52) is connected with a second suspender (53).
2. The finished ceiling traumatic installation structure of claim 1, wherein: the connection part of the second horizontal plate (12) and the connecting plate (13) is provided with a reinforcement (15).
3. The finished ceiling traumatic installation structure of claim 1, wherein: the connection part of the first horizontal plate (11) and the connecting plate (13) is provided with a reinforcement (15).
4. The finished ceiling traumatic installation structure of claim 1, wherein: and one end of the second horizontal plate (12) far away from the low-position ceiling plate (3) is provided with a lamp groove plate (16).
5. The finished ceiling traumatic installation structure of claim 1, wherein: the connecting piece (4) is an integrally formed metal piece.
6. The finished ceiling traumatic installation structure of claim 1, wherein: the thicknesses of the high-position suspended ceiling plate (2) and the low-position suspended ceiling plate (3) are equal to the width between the two second clamping plates (421).
7. The finished ceiling traumatic installation structure of claim 1, wherein: the thickness of the first horizontal plate (11) and the second horizontal plate (12) is equal to the width between the two first clamping plates (411).
8. The method for installing a finished suspended ceiling stepped installation structure according to any one of claims 1 to 7, comprising the steps of:
S1: setting the mounting heights of the high-position ceiling plate and the low-position ceiling plate on the wall surface elastic line;
S2: the first suspender is installed, the connecting plate of the functional piece is connected to the lower end of the first suspender, the height of the first horizontal plate is guaranteed to be the same as that of the high-position suspended ceiling plate, and the height of the second horizontal plate is guaranteed to be the same as that of the low-position suspended ceiling plate;
S3: installing connecting pieces at the ends of the first horizontal plate and the second horizontal plate, so that the first horizontal plate and the second horizontal plate extend between two first clamping plates of the connecting pieces;
S4: installing a second suspender, square steel pieces and keels for installing the high-position suspended ceiling plate and the low-position suspended ceiling plate;
S5: installing a high-position suspended ceiling plate and a low-position suspended ceiling plate below the keels, so that the end parts of the high-position suspended ceiling plate and the low-position suspended ceiling plate extend between two second clamping plates of the connecting piece;
s6: and (2) repeatedly executing the steps S2 to S5, and sequentially installing the functional parts, the high-level suspended ceiling plate and the low-level suspended ceiling plate around the house to finish the installation of the whole drop-level suspended ceiling.
9. The method for installing a finished suspended ceiling drop mounting structure according to claim 8, wherein:
and when the step S2 is executed, installing a reinforcement at the joint of the first horizontal plate or the second horizontal plate and the connecting plate when the functional piece is installed.
10. The method for installing a finished suspended ceiling drop mounting structure according to claim 8, wherein:
when executing step S3, when the connecting piece is installed, guarantee that the thickness of first horizontal plate and second horizontal plate all equals the width between two first cardboard, and the thickness of high-order furred ceiling board and low-order furred ceiling board all equals the width between two second cardboard.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011383927.XA CN112443070B (en) | 2020-12-01 | 2020-12-01 | Finished suspended ceiling grade-falling installation structure and installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011383927.XA CN112443070B (en) | 2020-12-01 | 2020-12-01 | Finished suspended ceiling grade-falling installation structure and installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112443070A CN112443070A (en) | 2021-03-05 |
CN112443070B true CN112443070B (en) | 2024-06-21 |
Family
ID=74739174
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011383927.XA Active CN112443070B (en) | 2020-12-01 | 2020-12-01 | Finished suspended ceiling grade-falling installation structure and installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112443070B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113338523B (en) * | 2021-05-24 | 2024-06-21 | 浙江亚厦装饰股份有限公司 | Inlaid section bar splicing integrated member |
CN113293916B (en) * | 2021-06-18 | 2024-07-12 | 浙江亚厦装饰股份有限公司 | Assembled suspended ceiling edge folding structure and installation method |
CN113323230B (en) * | 2021-06-18 | 2024-07-12 | 浙江亚厦装饰股份有限公司 | Lamp slot structure of assembled suspended ceiling and mounting method |
CN113356458B (en) * | 2021-06-21 | 2023-06-13 | 北新集团建材股份有限公司 | Suspended ceiling member and method for mounting suspended ceiling plate |
CN113605592B (en) * | 2021-08-13 | 2024-06-21 | 浙江亚厦装饰股份有限公司 | Assembled type drop lamp trough suspended ceiling structure |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN214461679U (en) * | 2020-12-01 | 2021-10-22 | 浙江亚厦装饰股份有限公司 | Finished product furred ceiling falls grade mounting structure |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106013585B (en) * | 2016-06-29 | 2017-06-20 | 浙江亚厦装饰股份有限公司 | Furred ceiling falls stage arrangement and installation method |
CN205917959U (en) * | 2016-06-29 | 2017-02-01 | 浙江亚厦装饰股份有限公司 | Furred ceiling falls a grade device |
CN111139964A (en) * | 2020-01-16 | 2020-05-12 | 金螳螂精装科技(苏州)有限公司 | Mounting structure of prefabricated drop level furred ceiling of assembled |
-
2020
- 2020-12-01 CN CN202011383927.XA patent/CN112443070B/en active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN214461679U (en) * | 2020-12-01 | 2021-10-22 | 浙江亚厦装饰股份有限公司 | Finished product furred ceiling falls grade mounting structure |
Also Published As
Publication number | Publication date |
---|---|
CN112443070A (en) | 2021-03-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112443070B (en) | Finished suspended ceiling grade-falling installation structure and installation method | |
CN105569251B (en) | Device for split-level ceiling and installation method | |
CN208473207U (en) | A kind of assembled hanging plate mounts system | |
CN210177866U (en) | Wall keel | |
CN207469649U (en) | One kind can adjust, dismountable integrated wall Modularized installing structure | |
CN214461679U (en) | Finished product furred ceiling falls grade mounting structure | |
CN207160487U (en) | Can quickly and be precisely controlled wallboard installation gap assembled type bar assembly | |
CN202731198U (en) | GRG (glass reinforced gypsum) suspended ceiling board connecting structure | |
CN214614928U (en) | Assembled arc furred ceiling mounting structure | |
CN217326277U (en) | Curtain ornamental strip and have curtain of this curtain ornamental strip | |
CN214614965U (en) | Novel integral type fossil fragments of assembled furred ceiling and furred ceiling system | |
CN205617685U (en) | Outer sunshade system of decorating of glass curtain wall | |
CN205530911U (en) | Ceiling lamp groove device | |
CN204510567U (en) | A kind of panel built-in type curtain wall | |
CN102704636B (en) | Indoor antique glass fiber reinforced cement (GRC) combined column and antique colored drawing beam decoration system and construction method thereof | |
CN104929346A (en) | Novel indoor combined vertex angle line | |
CN204983286U (en) | Unsmooth glass curtain wall structure of polygon | |
CN211775294U (en) | Internal corner structure of decorative wall | |
CN213774249U (en) | Joint formula installation design structure of assembled wood veneer | |
CN215888902U (en) | Ceiling plate with embedded hanging pieces | |
CN202787621U (en) | Connecting structure for connecting decoration panel and wall | |
CN219229582U (en) | Mounting structure of assembled suspended ceiling curtain box | |
CN211396141U (en) | Novel modularization collage curved surface curtain | |
CN211949159U (en) | Suspended ceiling | |
CN210177867U (en) | Soil style of calligraphy wall fossil fragments |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |