CN112431208A - Construction method for deep foundation pit supporting by adopting component type force transmission belt - Google Patents

Construction method for deep foundation pit supporting by adopting component type force transmission belt Download PDF

Info

Publication number
CN112431208A
CN112431208A CN202011297717.9A CN202011297717A CN112431208A CN 112431208 A CN112431208 A CN 112431208A CN 202011297717 A CN202011297717 A CN 202011297717A CN 112431208 A CN112431208 A CN 112431208A
Authority
CN
China
Prior art keywords
transmission belt
force transmission
bracket
construction
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011297717.9A
Other languages
Chinese (zh)
Inventor
宋文智
王祖庚
洪陈超
徐秀珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN202011297717.9A priority Critical patent/CN112431208A/en
Publication of CN112431208A publication Critical patent/CN112431208A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a construction method of a component type force transmission belt for deep foundation pit supporting, which comprises the steps of firstly determining a hanging rib connecting part on a supporting pile, chiseling concrete at the part to expose a longitudinal main rib of the supporting pile, and welding the top end of the hanging rib to the longitudinal main rib; arranging a first bracket at the lower part of the support pile through an expansion bolt; the steel purlin is placed on the first bracket, and the hanging ribs are connected with the steel purlin to stably hang the steel purlin; an embedded part is reserved at the joint of the structural shear wall and the beam, and a second bracket support is welded on the embedded part; and a steel pipe is arranged between the steel purlin and the second bracket to form a component force transmission belt. The method overcomes the defects of the traditional cast-in-place concrete force transmission belt construction, effectively reduces the construction period of the force transmission belt, improves the construction efficiency, can recycle and reuse components without burying soil, does not cause pollution to the environment, and saves the construction cost.

Description

Construction method for deep foundation pit supporting by adopting component type force transmission belt
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a construction method of a component type force transmission belt for deep foundation pit supporting.
Background
In deep foundation pit engineering with basements, support design is generally carried out by arranging supports according to the number of the basement layers (single-layer or multi-layer basements), and the number of the support layers is consistent with the number of the basement layers. In the construction process, when each layer of support is dismantled from bottom to top, the support is replaced to ensure the stability and safety of the deep foundation pit. The traditional support replacement adopts a cast-in-place concrete force transmission belt for construction, and the process flow is as follows:
after the construction of the basic raft is finished, a cast-in-place concrete force transmission belt is arranged between the raft foundation and the support piles for replacing the support, the upper support can be detached after the concrete of the force transmission belt reaches the design strength, and then the construction of the upper structure is carried out. In the upper basement structure, once one floor is constructed, the supports must be replaced and then removed, and finally the structure is constructed. When the support is replaced, the construction must be carried out according to the following procedures:
1. after the basement concrete shear wall reaches a certain strength, removing the template, clearing and processing the split bolts;
2. waterproof construction is carried out on the basement shear wall, and the waterproof layer is well protected;
3. performing backfill construction on the position between the shear wall and the supporting pile;
4. pouring concrete on the backfill soil to ensure that the concrete is tightly connected with the shear wall and the support pile to form a cast-in-place concrete force transmission belt;
5. after the on-site concrete force transmission belt reaches the design strength, the support replacement is completed;
6. and (5) dismantling the upper supporting structure and carrying out upper structure construction.
The defects of the traditional on-site concrete force transmission belt construction are as follows: before the shear wall template is dismantled, the concrete strength can be met only when the concrete strength meets the design requirement, and the concrete strength usually needs 7 days; 5 days are needed for waterproof construction and waterproof layer protection construction of the shear wall; the backfill construction needs 5 days; the construction and the strength of the cast-in-place concrete force transmission belt meet the design requirements and need 10 days; after the concrete is poured on site, the concrete is buried in soil, so that the environment is polluted, and the cost loss is large. According to the defects, the traditional cast-in-place concrete force transmission belt is long in construction time consumption, high in cost, not environment-friendly, inconvenient in cast-in-place concrete construction and high in labor intensity, and is particularly not beneficial to winter construction.
Disclosure of Invention
The invention aims to solve the technical problem of providing a construction method for supporting a deep foundation pit by using a component type force transmission belt, which overcomes the defects of the construction of the traditional cast-in-place concrete force transmission belt, effectively reduces the construction period of the force transmission belt, improves the construction efficiency, can recycle components, is not required to be buried in soil, does not pollute the environment and saves the construction cost.
In order to solve the technical problem, the construction method of the deep foundation pit support by adopting the component type force transmission belt comprises the following steps:
firstly, determining a hanging bar connecting part at the upper part of a support pile, and marking the part;
chiseling supporting pile concrete at the mark position of the supporting pile to expose the longitudinal main rib of the supporting pile, and welding the top end of the hanging rib to the longitudinal main rib by adopting double-sided lap joint;
step three, installing an expansion bolt at the lower part of the support pile, and arranging a first bracket support through the expansion bolt;
manufacturing a steel enclosing purlin, placing the bottom surface of the steel enclosing purlin on the first bracket, welding the bottom end of the hanging rib to the top surface of the steel enclosing purlin, and stably hanging the steel enclosing purlin;
step five, during construction of the basement structure, reserving an embedded part at the joint of the structural shear wall and the beam, and welding a second bracket support on the embedded part;
and step six, arranging a steel pipe between the steel enclosing purlin and the second bracket, fixing one end of the steel pipe on the steel enclosing purlin, welding the other end of the steel pipe on the second bracket, and forming a component force transmission belt through the steel enclosing purlin, the steel pipe and the second bracket.
Furthermore, the specification of the hanging steel bar is HRB400-25 steel bars.
Further, the diameter of the steel pipe is 600 mm.
The construction method of the invention adopts the technical scheme that the construction method of the component type force transmission belt for supporting the deep foundation pit adopts the technical scheme that firstly, the method determines the connection part of the hanging rib on the supporting pile, chisels off the concrete at the part to expose the longitudinal main rib of the supporting pile, and welds the top end of the hanging rib on the longitudinal main rib; arranging a first bracket at the lower part of the support pile through an expansion bolt; the steel purlin is placed on the first bracket, and the hanging ribs are connected with the steel purlin to stably hang the steel purlin; an embedded part is reserved at the joint of the structural shear wall and the beam, and a second bracket support is welded on the embedded part; and a steel pipe is arranged between the steel purlin and the second bracket to form a component force transmission belt. The method overcomes the defects of the traditional cast-in-place concrete force transmission belt construction, effectively reduces the construction period of the force transmission belt, improves the construction efficiency, can recycle and reuse components without burying soil, does not cause pollution to the environment, and saves the construction cost.
Drawings
The invention is described in further detail below with reference to the following figures and embodiments:
FIG. 1 is a schematic view of a construction method of a component type force transmission belt for deep foundation pit support of the invention.
Detailed Description
The embodiment is shown in figure 1, and the construction method of the deep foundation pit support adopting the component type force transmission belt comprises the following steps:
firstly, determining a connection part of a lifting rib 2 at the upper part of a support pile 1, and marking the connection part;
chiseling concrete of the support pile 1 at the marked position of the support pile 1 to expose the longitudinal main rib 11 of the support pile, and welding the top end of the hanging rib 2 to the longitudinal main rib 11 by adopting double-sided lap joint;
step three, installing an expansion bolt at the lower part of the support pile 1, and arranging a first bracket support 3 through the expansion bolt;
fourthly, manufacturing a steel surrounding purlin 4, placing the bottom surface of the steel surrounding purlin 4 on the first bracket support 3, welding the bottom end of the hanging rib 2 to the top surface of the steel surrounding purlin 4, and stably hanging the steel surrounding purlin 4;
step five, during the construction of the basement structure, reserving an embedded part 5 at the joint of the structural shear wall and the beam, and welding a second bracket support 6 on the embedded part 5;
and step six, arranging a steel pipe 7 between the steel enclosing purlin 4 and the second bracket 6, fixing one end of the steel pipe 7 on the steel enclosing purlin 4, welding the other end of the steel pipe 7 with the second bracket 6, and forming a component force transmission belt through the steel enclosing purlin 4, the steel pipe 7 and the second bracket 6.
Preferably, the hanging bar 2 is HRB400-25 steel bar.
Preferably, the diameter of the steel pipe 7 is 600 mm.
According to the method, in the construction of the basement of the deep foundation pit, the shear wall template does not need to be removed in advance and the outer wall does not need to be waterproof in advance before the upper support is removed, earthwork backfilling does not need to be carried out in advance, the concrete curing time of the traditional cast-in-place concrete force transmission belt is also not needed, and the construction period can be about 30 days in advance. For the construction of the deep foundation pit, the shorter the construction period is, the smaller the support risk is, and the construction period is advanced by 30 days, so that the construction risk of the deep foundation pit is greatly reduced. Meanwhile, the traditional cast-in-place concrete force transmission belt can only be buried in a soil body and cannot be recycled; the component type force transmission belt in the method can be disassembled and recycled after the construction of the basement structure is finished, so that the construction cost is greatly saved. In the concrete construction process, because the basement is under construction, strong noise is caused by vibration during the construction of the traditional cast-in-place concrete force transmission belt, the traditional cast-in-place concrete force transmission belt has serious noise and dirty beams, and the component type force transmission belt does not pollute the environment, does not have strong noise during the construction process, and meets the requirement of green construction. The cast-in-place concrete force transmission belt for basement construction has high construction labor intensity and inconvenient construction operation; the component type force transmission belt is adopted to replace the traditional concrete force transmission belt, the construction process is simple, the operation is convenient, and manpower and material resources are saved.

Claims (3)

1. A construction method for supporting a deep foundation pit by adopting a component type force transmission belt is characterized by comprising the following steps:
firstly, determining a hanging bar connecting part at the upper part of a support pile, and marking the part;
chiseling supporting pile concrete at the mark position of the supporting pile to expose the longitudinal main rib of the supporting pile, and welding the top end of the hanging rib to the longitudinal main rib by adopting double-sided lap joint;
step three, installing an expansion bolt at the lower part of the support pile, and arranging a first bracket support through the expansion bolt;
manufacturing a steel enclosing purlin, placing the bottom surface of the steel enclosing purlin on the first bracket, welding the bottom end of the hanging rib to the top surface of the steel enclosing purlin, and stably hanging the steel enclosing purlin;
step five, during construction of the basement structure, reserving an embedded part at the joint of the structural shear wall and the beam, and welding a second bracket support on the embedded part;
and step six, arranging a steel pipe between the steel enclosing purlin and the second bracket, fixing one end of the steel pipe on the steel enclosing purlin, welding the other end of the steel pipe on the second bracket, and forming a component force transmission belt through the steel enclosing purlin, the steel pipe and the second bracket.
2. The construction method of the component type force transmission belt for the deep foundation pit support according to claim 1, characterized in that: the specification of the hanging bar is HRB400-25 steel bars.
3. The construction method of the component type force transmission belt for the deep foundation pit support according to claim 1 or 2, characterized in that: the diameter of the steel pipe is 600 mm.
CN202011297717.9A 2020-11-18 2020-11-18 Construction method for deep foundation pit supporting by adopting component type force transmission belt Pending CN112431208A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011297717.9A CN112431208A (en) 2020-11-18 2020-11-18 Construction method for deep foundation pit supporting by adopting component type force transmission belt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011297717.9A CN112431208A (en) 2020-11-18 2020-11-18 Construction method for deep foundation pit supporting by adopting component type force transmission belt

Publications (1)

Publication Number Publication Date
CN112431208A true CN112431208A (en) 2021-03-02

Family

ID=74694239

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011297717.9A Pending CN112431208A (en) 2020-11-18 2020-11-18 Construction method for deep foundation pit supporting by adopting component type force transmission belt

Country Status (1)

Country Link
CN (1) CN112431208A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114032965A (en) * 2021-11-25 2022-02-11 中国建筑第八工程局有限公司 Force transmission belt structure of blocking wall of subway station and construction method thereof
CN114704309A (en) * 2022-03-07 2022-07-05 中铁第一勘察设计院集团有限公司 Temporary supporting structure for solving conflict between medium plate shield hole boundary beam and shield in subway station

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN208201880U (en) * 2018-01-12 2018-12-07 浙江中成建工集团有限公司 A kind of interior steel pipe underpinning device for replacing traditional support replacement mode of deep basal pit

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN208201880U (en) * 2018-01-12 2018-12-07 浙江中成建工集团有限公司 A kind of interior steel pipe underpinning device for replacing traditional support replacement mode of deep basal pit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘飞: ""浅析船坞坞口深基坑开挖中支护体系的应用"", 《江西建材》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114032965A (en) * 2021-11-25 2022-02-11 中国建筑第八工程局有限公司 Force transmission belt structure of blocking wall of subway station and construction method thereof
CN114704309A (en) * 2022-03-07 2022-07-05 中铁第一勘察设计院集团有限公司 Temporary supporting structure for solving conflict between medium plate shield hole boundary beam and shield in subway station

Similar Documents

Publication Publication Date Title
JP2018024982A (en) Reinforcement method and reinforcement structure of existing pile foundation
CN102619152A (en) Split mounting type prefabricated reinforced concrete construction temporary road
CN112431208A (en) Construction method for deep foundation pit supporting by adopting component type force transmission belt
CN109537579B (en) Construction method of cast-in-situ bored pile
CN213836667U (en) Foundation pit engineering precast concrete non-primary support system
CN112177012A (en) Precast concrete non-primary support system with lattice columns for foundation pit engineering and construction method
CN111877330B (en) U-shaped round steel pipe template system of hole digging annular foundation pile and construction method
CN111622268B (en) Protection construction method based on large rigid box culvert penetrating under power pipe gallery
CN113529763A (en) Method for constructing sea area shoal cushion cap by utilizing reinforced concrete combined steel cofferdam
CN112096419A (en) Supporting structure and method for repairing tunnel secondary lining damage
CN113957887B (en) Pile-wall integrated construction method of core barrel
CN111042213A (en) Construction method for replacing raft split heads with anti-floating anchor rods for supporting
CN112813969A (en) Steel pipe pile foundation and construction method thereof
CN112081118A (en) Pile-anchor supporting foundation pit deepening reinforcing and supporting structure and construction method thereof
CN111424679A (en) Deep foundation pit assembled reinforced concrete support and rapid installation and rapid removal construction method thereof
CN108221954B (en) Easy-to-detach prefabricated underground diaphragm wall, lifting appliance and construction method
CN213836666U (en) Precast concrete non-primary support system with lattice columns for foundation pit engineering
CN212506305U (en) Combined supporting structure of inclined wedge-shaped pile and vertical wedge-shaped pile
KR100394780B1 (en) A Repair ethod and Repair tructure of Bridge Pier Mould Construction
CN212506306U (en) Combined supporting structure of inclined wedge-shaped pile and vertical tubular pile
CN211547797U (en) Tower crane foundation structure suitable for basement raft foundation
CN210507464U (en) Annular supporting plate for basement structure floor slab
CN113090066A (en) Construction method for newly added entrances and exits of existing buildings and elevator shaft
CN111962522A (en) Combined supporting structure of inclined wedge-shaped pile and vertical pipe pile and construction method thereof
CN216130156U (en) Building basement bottom plate water-collecting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210302