CN112360468A - Excavation supporting method for vertical shaft slag sliding well - Google Patents

Excavation supporting method for vertical shaft slag sliding well Download PDF

Info

Publication number
CN112360468A
CN112360468A CN202011345813.6A CN202011345813A CN112360468A CN 112360468 A CN112360468 A CN 112360468A CN 202011345813 A CN202011345813 A CN 202011345813A CN 112360468 A CN112360468 A CN 112360468A
Authority
CN
China
Prior art keywords
tunnel
shaft
hole
slag
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011345813.6A
Other languages
Chinese (zh)
Other versions
CN112360468B (en
Inventor
许小路
程万强
易神州
薛守中
倪卫达
廖卓
郭如杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang East China Geotechnical Survey And Design Institute Co ltd
Original Assignee
Zhejiang Huadong Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Huadong Construction Engineering Co Ltd filed Critical Zhejiang Huadong Construction Engineering Co Ltd
Priority to CN202011345813.6A priority Critical patent/CN112360468B/en
Publication of CN112360468A publication Critical patent/CN112360468A/en
Application granted granted Critical
Publication of CN112360468B publication Critical patent/CN112360468B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D7/00Shaft equipment, e.g. timbering within the shaft

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The invention relates to a vertical shaft slag chute excavation supporting method. The invention aims to provide a vertical shaft slag sliding well excavation supporting method, which aims to solve the problem of collapse of the wall of a slag sliding hole during reverse shaft excavation, reduce construction risks and improve construction efficiency. The technical scheme of the invention is as follows: a vertical shaft slag sliding well excavation supporting method is characterized in that: s01, completing excavation and supporting of the top space of the top of the tunnel at the upper end of the shaft to be excavated; completing excavation support of a construction branch hole at the lower part of the vertical shaft to be excavated, wherein the construction branch hole is excavated to the inside of the vertical shaft to be excavated; finishing the excavation of a tailrace tunnel at the bottom of the shaft to be excavated, wherein the position of the tailrace tunnel is lower than the construction branch tunnel; s02, constructing a pilot hole I from the top space of the tunnel along the axial line of the shaft to be excavated until the pilot hole I is communicated with the construction branch tunnel below the pilot hole; and S03, performing reverse broaching and reaming by matching the pilot hole I with the large-diameter reverse broaching and reaming bit to form a slag chute hole I extending from the construction branch hole to the top space of the hole. The invention is suitable for the field of ultra-deep and ultra-large shaft engineering.

Description

Excavation supporting method for vertical shaft slag sliding well
Technical Field
The invention relates to a vertical shaft slag chute excavation supporting method. The method is suitable for the field of ultra-deep and ultra-large shaft engineering.
Background
The reverse well construction method is that a reverse well drilling machine is used for drilling, then an enlarged cutter head is used for reverse drawing from bottom to top to form a slag chute channel with the diameter of about 1.4-2.0 m, then the slag chute channel is excavated from top to bottom, and slag materials slide to the bottom through the slag chute by means of self weight to discharge slag. The construction method is widely applied to various gangue sliding holes, mining area wind holes, coal sliding holes, safety rescue holes and the like of a coal system; various guide wells, surge shafts, ventilation shafts and the like of the hydroelectric system are widely used.
Compared with other construction methods, the well reversing method has the characteristics of safe construction, high working efficiency, good engineering quality and the like. When the raise boring machine is constructed, workers do not need to enter a working face, are all on the upper portion with better environment and safety conditions and are not damaged by falling rocks and drenching water, and the occurrence of all accidents is avoided. Meanwhile, the construction of the raise boring machine is mechanical continuous operation, and the raise boring machine adopts a hob cutter to mechanically break rock, so that the damage to surrounding rock is small, and the raise boring machine is favorable for expanding and digging slag, ventilating and draining water.
However, in a modern volcanic rock area or a strong structural development area with high geological structure development and poor rock quality, the rock ballast impacts the hole wall for multiple times to easily cause collapse of the hole wall of the slag sliding hole, particularly, the middle and lower parts of the slag sliding hole bear large impact energy and are subjected to multiple times, the hole wall is more easily collapsed and unstable, great safety risks are brought to supply construction, and the construction progress is also influenced.
At present, a scheme for advanced support of a hole of a slag sliding hole is mature, but reinforcing support of a deep area of a surge shaft or a whole shaft section is less, so that a scheme for integrally reinforcing the slag sliding hole under a complex geological condition is necessary to be researched.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: aiming at the existing problems, the method for excavating and supporting the vertical shaft slag sliding well is provided, so that the problem of collapse of the wall of the slag sliding hole during the excavation of the raise shaft is solved, the construction risk is reduced, and the construction efficiency is improved.
The technical scheme adopted by the invention is as follows: a vertical shaft slag sliding well excavation supporting method is characterized in that:
s01, completing excavation and supporting of the top space of the top of the tunnel at the upper end of the shaft to be excavated; completing excavation support of a construction branch hole at the lower part of the vertical shaft to be excavated, wherein the construction branch hole is excavated to the inside of the vertical shaft to be excavated; finishing the excavation of a tailrace tunnel at the bottom of the shaft to be excavated, wherein the position of the tailrace tunnel is lower than the construction branch tunnel;
s02, constructing a pilot hole I from the top space of the tunnel along the axial line of the shaft to be excavated until the pilot hole I is communicated with the construction branch tunnel below the pilot hole;
s03, performing reverse broaching and reaming by matching the pilot hole I with a large-diameter reverse broaching and reaming bit to form a slag chute hole I extending from the construction branch hole to the top space of the hole;
s04, plugging the construction branch holes to enable the construction branch holes in the range of the vertical shaft and the slag sliding holes I to form a chamber to be backfilled, wherein the opening is formed in the upper end of the slag sliding holes I, and concrete is backfilled into the chamber to be backfilled;
s05, constructing a pilot hole II downwards along the axial line of the shaft to be excavated from the top space of the tunnel, penetrating through the construction branch tunnel until the pilot hole II is communicated with the tailrace tunnel below;
s06, performing reverse broaching and reaming by matching the pilot hole II with a small-diameter reverse broaching and reaming bit to form a slag chute II extending from the tailwater tunnel to the top space of the tunnel;
and a concrete support layer is formed on the side wall of the slag chute II above the construction branch tunnel, and a concrete gravity pier for bearing the upper concrete support layer is formed in the construction branch tunnel.
The diameter of the large-diameter reverse broaching bit is 160-180 cm; the diameter of the small-diameter reverse broaching bit is 140 cm.
The concrete is steel fiber concrete.
The strength grade of the concrete is at least over B30, and the mixing amount of the concrete and the steel fiber is not less than 35kg/m 3.
The height difference between the construction branch tunnel and the tailrace tunnel is 10-15 m.
The invention has the beneficial effects that: the invention adopts the reverse broaching and reaming drill bits with different diameters to carry out reverse broaching and backfills concrete after the first reverse broaching and reaming, so that the second reverse broaching and reaming is carried out to form a concrete support layer with a certain thickness (10-20cm) on the wall of the slag sliding hole II, and the concrete is backfilled at the construction branch hole part at the lower part of the well body to form a gravity pier for bearing the concrete support layer at the upper part, thereby playing a role of supporting and protecting and increasing the safety coefficient of the structure. By the construction method, the shaft chute slag well is increased, the stability of the shaft wall of the shaft is improved, the collapse of the shaft wall is prevented, the stone slag collision resistance is enhanced, and the chute slag is smooth, so that the purposes of accelerating the construction progress, improving the construction efficiency and ensuring the construction safety are achieved.
Drawings
FIG. 1 is a three-dimensional schematic diagram of an engineering arrangement of an embodiment.
Fig. 2 is a schematic diagram of the first counter-pulling broaching in the example.
FIG. 3 is a schematic diagram of the construction of backfilled concrete in the embodiment.
Fig. 4 is a sectional view a-a of fig. 3.
Fig. 5 is a schematic diagram of the second counter-pulling broaching in the example.
1. A ceiling space; 2. a traffic hole; 3. a shaft; 4. constructing branch holes; 5. a tailwater tunnel; 6. a shaft vent hole; 7. a pilot hole I; 8. a large-diameter reverse-broaching reamer bit; 9. a rig floor; 10. a slag sliding hole I; 11. slag returning; 12. grouting vehicle; 13. a pulp conveying pipe; 14. backfilling concrete; 15. a raise boring machine; 16. a small-diameter reverse-broaching reamer bit; 17. concrete gravity piers; 18. a concrete supporting layer; 19. a loading vehicle; 20. a slag discharging vehicle; 21. a pilot hole II; 22. and a slag sliding hole II.
Detailed Description
The embodiment is a shaft slag sliding well excavation supporting method, which is mainly used for reinforcing a shaft slag sliding hole, and solves the problems that the wall of the deep-buried surge shaft slag sliding hole is unstable under complex geological conditions, and further, the collapse of one part of a shaft body section of a large-diameter shaft is possibly caused, so that the construction risk is increased, and the efficiency is reduced.
In this embodiment, a pumped storage power station is taken as an example for explanation, and the power station is composed of an upper water reservoir, a lower water reservoir, a diversion tunnel, a high-pressure shaft, an underground plant, a main transformer room, a tail water surge shaft, a tail water tunnel and other buildings, a general installation machine 314MW, two units and a power generation head 440 m. The tail water pressure regulating well upper chamber is shaped like a near-urban portal, the diameter of a tunnel body section is 16.9m, and the burial depth is about 250-350 m. The tunnel section rock mass is basalt and volcanic debris, interbedded development and joint development, and has a structure development such as an extrusion deformation zone and a fault, the rock mass quality is poor, the surrounding rock category is mainly IV, the local V type is adopted, and the excavation mode is reverse shaft method slag sliding excavation.
The specific construction method of the embodiment comprises the following steps:
and S01, preparing a construction space. After excavation and support are carried out in the top space of the upper end of the surge shaft (the shaft to be excavated), the elevation-176.70 site is leveled to form a drilling rig platform, a portal crane is installed, and facilities such as a wind, water, electricity and slurry circulating pool are installed, so that the construction conditions of the raise-reversing method are met.
And after the field leveling is finished and the wind, water and electricity are prepared, hoisting the BMC300 raise boring machine by using a gantry crane, and installing the raise boring machine and supporting facilities thereof. The BMC300 raise boring machine comprises: the system comprises a host system, a drilling tool system, a hydraulic and electric control system, an auxiliary system, an operating system, a slurry system, a cooling system and the like. According to the actual situation of the site, a host, a pump station, an operation platform, a starting box and the like are respectively placed at corresponding positions. The drilling center and the drilling angle are determined to be accurate through measurement and calibration, the drilling machine is normally debugged, and the drilling operation can be carried out if the water supply and the power supply are normal.
During the process of the top space of the tunnel, after the traffic tunnel is finished, construction branch tunnel excavation can be carried out, the designed section is a city gate tunnel type with the height of 4m multiplied by the width of 4m and the diameter of the top of the tunnel of 4m, the tunnel is excavated from the entrance of the traffic tunnel to the lower part of the shaft to be excavated and is excavated to the shaft to be excavated, and the tunnel penetrates through the shaft axis for a certain distance. The construction branch hole mainly serves as a slag discharging channel and provides installation space for the inverted drill bit. Due to poor geological conditions, mainly IV and partial V, the cavern needs to be supported in time to ensure the stability of the cavern.
The tail water tunnel excavation of the bottom of the shaft to be excavated is a slag discharging channel of surge shaft slag, and the excavation needs to be finished before the excavation of the pilot hole II in the step S05. The tailrace tunnel is lower than the construction branch tunnel, and the height difference between the construction branch tunnel and the tailrace tunnel is 10-15 m.
S02, conducting pilot hole I drilling work from the top by using a pilot hole drill bit with the diameter phi of 241 mm. The drilling speed is 10-20r/min, the drilling pressure is 450-550KN, and the torque is 20-30 kg/m. For rock slag generated by drilling of the pilot hole I, the rock slag is flushed to a grit chamber through hole flushing water and is cleaned in time, a large amount of silt is prevented from entering a water pumping tank, rock debris in holes must be completely discharged after drilling of each drill rod is completed, the drill rods can be connected and disconnected by stopping pumping after circulating water becomes clear, the guide hole is matched with the perforated drill rod through the perforated centralizer when drilling, the slag is discharged from the guide hole in a positive circulation mode, and the rock slag is flushed after drilling of each drill rod. The guide hole drills from-176.7 m to the top elevation of the construction branch hole of-265 m, and the top space of the hole is communicated with the construction branch hole.
And S03, performing reverse broaching and reaming by matching the pilot hole I with the large-diameter reverse broaching and reaming bit to form a slag chute hole I extending from the construction branch hole to the top space of the tunnel. Before reaming, good communication between the upper and lower cavities should be established to facilitate the removal and installation of the pilot bit and reamer bit. And a sufficient space is ensured for installing the expanding drill bit in the construction branch hole, and the diameter of the drill bit is 160cm-180 cm. After the reaming bit is installed, the drilling tool is lifted at a low speed until the hob of the drilling bit starts to contact with the rock, then the drilling tool stops lifting, rotates at the lowest rotating speed, slowly feeds the drilling bit and ensures that the hob of the drilling bit is not damaged by overlarge impact, a specially-assigned person is arranged at the position of a construction branch hole for observation, the condition is timely notified to an operator, and normal reaming and drilling can be carried out only when the drilling bit is completely and uniformly contacted with the rock. The drilling speed is 5-11r/min, the drilling pressure is 1000-1250KN, and the torque is 50-60 kg/m. The broken slag that gets off of reaming in time of the reaming drilling in order to clear up prevents that the end opening from blockking up. The reaming process is also a process of detaching the drill rod, and the detached drill rod needs to be cleaned, smeared with screw thread oil and provided with a protective cap. When the drill bit drills to a position 3m away from the foundation, the drill bit needs to drill at a low speed, whether abnormal phenomena exist around the foundation or not needs to be carefully observed, and if the abnormal phenomena exist, measures need to be taken timely.
And S04, plugging the construction branch holes through the templates to enable the construction branch holes and the slag sliding holes I in the range of the vertical shaft to form a chamber to be backfilled, wherein the opening is formed in the upper end of the slag sliding hole I, and backfilling concrete into the chamber to be backfilled through a grouting vehicle and a slurry conveying pipe.
In order to ensure the strength of concrete and increase the stability of the wall of the slag chute, steel fiber concrete is adopted. The strength grade of the concrete is at least over B30, and the mixing amount of the concrete and the steel fiber is not less than 35kg/m 3. During the self-weight concrete grouting backfilling, after concrete pouring of each truck is finished, the height of the liquid level of the concrete is measured by using the measuring ropes from time to time so as to calculate the difference between the actual backfilling square amount and the designed backfilling square amount.
And S05, after concrete backfilling is completed, constructing a pilot hole II downwards along the axis of the shaft to be excavated from the space at the top of the tunnel, penetrating through the construction branch tunnel until the tail water tunnel below is communicated, wherein the construction method of the pilot hole II is the same as that of the pilot hole I in the S02.
And S06, performing reverse broaching and reaming by matching the pilot hole II with a small-diameter reverse broaching and reaming bit to form a slag chute II extending from the tailwater tunnel to the top space of the tunnel. It should be noted that the raise boring is installed and drilled according to the original position, and the raise boring is drilled to the top of the tail water tunnel, and the small-diameter back-pull reamer bit (diameter 140cm) is replaced to perform back-pull from bottom to top, so that the formed back slag falls to the bottom plate of the tail water tunnel by self weight and is transported out by a loading vehicle and a slag discharging vehicle. The bottom of the tail water tunnel also becomes a slag discharging channel of the tail water surge shaft.
After the reverse broaching and hole expanding are finished, the aperture of the slag sliding hole I is larger than that of the slag sliding hole II, a concrete supporting layer with the thickness of 10-20cm is formed on the side wall of the slag sliding hole II above the construction branch hole, and a concrete gravity pier for bearing the upper concrete supporting layer is formed in the construction branch hole. The concrete supporting layer ensures the stability of the slag sliding hole and leaves a stable channel for further excavation construction.

Claims (5)

1. A vertical shaft slag sliding well excavation supporting method is characterized in that:
s01, completing excavation and supporting of the top space of the top of the tunnel at the upper end of the shaft to be excavated; completing excavation support of a construction branch hole at the lower part of the vertical shaft to be excavated, wherein the construction branch hole is excavated to the inside of the vertical shaft to be excavated; finishing the excavation of a tailrace tunnel at the bottom of the shaft to be excavated, wherein the position of the tailrace tunnel is lower than the construction branch tunnel;
s02, constructing a pilot hole I from the top space of the tunnel along the axial line of the shaft to be excavated until the pilot hole I is communicated with the construction branch tunnel below the pilot hole;
s03, performing reverse broaching and reaming by matching the pilot hole I with a large-diameter reverse broaching and reaming bit to form a slag chute hole I extending from the construction branch hole to the top space of the hole;
s04, plugging the construction branch holes to enable the construction branch holes in the range of the vertical shaft and the slag sliding holes I to form a chamber to be backfilled, wherein the opening is formed in the upper end of the slag sliding holes I, and concrete is backfilled into the chamber to be backfilled;
s05, constructing a pilot hole II downwards along the axial line of the shaft to be excavated from the top space of the tunnel, penetrating through the construction branch tunnel until the pilot hole II is communicated with the tailrace tunnel below;
s06, performing reverse broaching and reaming by matching the pilot hole II with a small-diameter reverse broaching and reaming bit to form a slag chute II extending from the tailwater tunnel to the top space of the tunnel;
and a concrete support layer is formed on the side wall of the slag chute II above the construction branch tunnel, and a concrete gravity pier for bearing the upper concrete support layer is formed in the construction branch tunnel.
2. The method for excavating and supporting the shaft slag well according to claim 1, which is characterized in that: the diameter of the large-diameter reverse broaching bit is 160-180 cm; the diameter of the small-diameter reverse broaching bit is 140 cm.
3. The method for excavating and supporting the shaft ore pass according to claim 1 or 2, which is characterized in that: the concrete is steel fiber concrete.
4. The shaft slag shaft excavation supporting method according to claim 3, characterized in that: the strength grade of the concrete is at least over B30, and the mixing amount of the concrete and the steel fiber is not less than 35kg/m 3.
5. The method for excavating and supporting the shaft slag well according to claim 1, which is characterized in that: the height difference between the construction branch tunnel and the tailrace tunnel is 10-15 m.
CN202011345813.6A 2020-11-25 2020-11-25 Excavation supporting method for vertical shaft slag sliding well Active CN112360468B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011345813.6A CN112360468B (en) 2020-11-25 2020-11-25 Excavation supporting method for vertical shaft slag sliding well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011345813.6A CN112360468B (en) 2020-11-25 2020-11-25 Excavation supporting method for vertical shaft slag sliding well

Publications (2)

Publication Number Publication Date
CN112360468A true CN112360468A (en) 2021-02-12
CN112360468B CN112360468B (en) 2022-04-12

Family

ID=74532982

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011345813.6A Active CN112360468B (en) 2020-11-25 2020-11-25 Excavation supporting method for vertical shaft slag sliding well

Country Status (1)

Country Link
CN (1) CN112360468B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863243A (en) * 2021-10-23 2021-12-31 中电建十一局工程有限公司 Construction method for quickly excavating underground powerhouse of hydropower station
CN118065906A (en) * 2024-04-24 2024-05-24 北京中煤矿山工程有限公司 Vertical shaft back-drilling stepping type while-drilling supporting equipment

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010031544A (en) * 2008-07-29 2010-02-12 East Japan Railway Co Hole wall protecting method of cast in place pile
CN102305075A (en) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 Vertical shaft construction method under unfavorable geological condition
CN102493809A (en) * 2011-12-12 2012-06-13 北京中煤矿山工程有限公司 Comprehensive shaft sinking method of positive and raising boring for vertical shaft
CN103850684A (en) * 2013-11-22 2014-06-11 北京中煤矿山工程有限公司 Sinking technology for expanding pilot well drilled by raise-boring machine, by using vertical well heading machine
CN105298499A (en) * 2015-11-12 2016-02-03 中国水利水电第七工程局有限公司 Excavation deviation processing method of raise-boring machine for deep vertical shaft
CN110952986A (en) * 2019-12-18 2020-04-03 中国水利水电第五工程局有限公司 Secondary shaft expanding and digging method and steel platform
CN111894596A (en) * 2020-07-27 2020-11-06 广西路桥工程集团有限公司 Vertical shaft raise construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010031544A (en) * 2008-07-29 2010-02-12 East Japan Railway Co Hole wall protecting method of cast in place pile
CN102305075A (en) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 Vertical shaft construction method under unfavorable geological condition
CN102493809A (en) * 2011-12-12 2012-06-13 北京中煤矿山工程有限公司 Comprehensive shaft sinking method of positive and raising boring for vertical shaft
CN103850684A (en) * 2013-11-22 2014-06-11 北京中煤矿山工程有限公司 Sinking technology for expanding pilot well drilled by raise-boring machine, by using vertical well heading machine
CN105298499A (en) * 2015-11-12 2016-02-03 中国水利水电第七工程局有限公司 Excavation deviation processing method of raise-boring machine for deep vertical shaft
CN110952986A (en) * 2019-12-18 2020-04-03 中国水利水电第五工程局有限公司 Secondary shaft expanding and digging method and steel platform
CN111894596A (en) * 2020-07-27 2020-11-06 广西路桥工程集团有限公司 Vertical shaft raise construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863243A (en) * 2021-10-23 2021-12-31 中电建十一局工程有限公司 Construction method for quickly excavating underground powerhouse of hydropower station
CN118065906A (en) * 2024-04-24 2024-05-24 北京中煤矿山工程有限公司 Vertical shaft back-drilling stepping type while-drilling supporting equipment
CN118065906B (en) * 2024-04-24 2024-06-18 北京中煤矿山工程有限公司 Vertical shaft back-drilling stepping type while-drilling supporting equipment

Also Published As

Publication number Publication date
CN112360468B (en) 2022-04-12

Similar Documents

Publication Publication Date Title
CN105888551B (en) Anti- well method is once drilled to long inclined shaft sinking shaft technique
CN103835661B (en) A kind of local excavation pre support mine shaft rising boring technique
CN113445498A (en) Construction process of karst hole pile foundation in complex geology
CN112360468B (en) Excavation supporting method for vertical shaft slag sliding well
CN104047542B (en) Embedding rock taper pile impacts drilling pipe hammer system and embedding rock taper pile impacts construction method
CN101818644A (en) Well digging process of mining vertical shaft by adopting one-drilling well completion and well drilling method
CN104947690A (en) Grooving construction method for embedding underground continuous wall into rock
CN103046931A (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN105697018A (en) Shaft excavation construction technology
CN116220546A (en) Construction method for combining super-thick hard rock condition large-diameter long piles into holes
CN104929514B (en) Raise-boring machine construction method
CN112411530A (en) Construction method for controlling verticality of sea-filling stratum casing secant pile
CN111042820B (en) Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method
CN112196494B (en) Construction process and construction equipment for geological pipeline jointed between rock and soil layer
CN114045854A (en) Bridge pile foundation composite construction method under complex geological condition
CN103147435A (en) Method for treating construction engineering foundation in gob
CN208396651U (en) Rectangle pile foundation drilling construction equipment
CN113266283B (en) Well-guiding type shaft heading machine starting process
CN205100226U (en) Underground continuous wall goes into rock grooving construction equipment
CN107143335A (en) The guide hole construction method of ultra-deep shaft
CN210105867U (en) Shield tunnel end frozen soil wall and ground are wall jointly reinforced structure
CN115492583A (en) Construction process of outlet shaft under rock mass crushing condition
CN214832833U (en) Open caisson mechanical construction device penetrating rock stratum
CN112502615B (en) Construction method of deep large-diameter gas extraction well
CN114991818B (en) Advanced grouting construction method for tunnel penetrating fault

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No. 997 Gudun Road, Sandun Town, Xihu District, Hangzhou City, Zhejiang Province, 310023

Patentee after: Zhejiang East China Geotechnical Survey and Design Institute Co.,Ltd.

Address before: No. 997, gudun Road, Sandun Town, Hangzhou City, Zhejiang Province, 310030

Patentee before: ZHEJIANG HUADONG CONSTRUCTION ENGINEERING Co.,Ltd.