CN112281829A - Composite pile foundation structure and construction method thereof - Google Patents

Composite pile foundation structure and construction method thereof Download PDF

Info

Publication number
CN112281829A
CN112281829A CN202011235753.2A CN202011235753A CN112281829A CN 112281829 A CN112281829 A CN 112281829A CN 202011235753 A CN202011235753 A CN 202011235753A CN 112281829 A CN112281829 A CN 112281829A
Authority
CN
China
Prior art keywords
pile
hole
precast
precast tubular
foundation structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011235753.2A
Other languages
Chinese (zh)
Inventor
徐建
李大浪
刘皓
邹明立
袁昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nerin Engineering Co Ltd
Original Assignee
China Nerin Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nerin Engineering Co Ltd filed Critical China Nerin Engineering Co Ltd
Priority to CN202011235753.2A priority Critical patent/CN112281829A/en
Publication of CN112281829A publication Critical patent/CN112281829A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/72Pile shoes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • E02D7/06Power-driven drivers

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a composite pile foundation structure and a construction method thereof, wherein the composite pile foundation structure comprises a bearing platform, a precast tubular pile and a cement layer wrapped outside the precast tubular pile in a cast-in-place mode, the bearing platform is arranged at the top of the precast tubular pile, the cement layer and the precast tubular pile are coaxially arranged, and the diameter of the cement layer is 200 mm larger than that of the precast tubular pile and 400mm larger than that of the cement layer. The composite pile foundation structure effectively combines the concrete pipe pile with the traditional cast-in-place pile by adopting the rotary drilling hole guiding, grouting and pile pressing construction methods for cast-in-place. The advantages of high strength of the precast pile and the rotary drilling and leading of the cast-in-place pile are fully utilized, and the difficulties that the cast-in-place pile is long, the bearing capacity is low and the precast pile cannot enter the rock are solved. Has obvious advantages in construction quality, construction period and engineering investment compared with single cast-in-place pile and precast pile.

Description

Composite pile foundation structure and construction method thereof
Technical Field
The invention relates to a composite pile foundation, in particular to a cast-in-place and prefabrication combined composite pile foundation structure and a construction method thereof.
Background
The precast pile is basically processed in a factory and then transported to the site for piling, and the construction speed is high. But the precast pile has limited cross-sectional area (generally 500-600 mm) and limited pile length, so that the bearing capacity is not very high. The cast-in-place pile generally has a small pile diameter (larger than 800 mm), a long pile body and a much larger bearing capacity than the precast pile. The manufacturing time of the pile body reinforcement cage is removed, and the excavator needs a relatively long time to process the pile body reinforcement cage, drill the procedures of a bearing stratum, protect the wall by mud and control the sediment at the bottom of a hole. During construction, the precast pile is difficult to enter weathered rocks, too much time is needed to be spent by using the cast-in-place pile, the best effect cannot be achieved by using the precast pile and the cast-in-place pile, and great convenience is brought to engineering construction if a pile foundation with a short pile body and high bearing capacity can be developed.
Disclosure of Invention
The invention aims to provide a composite pile foundation structure and a construction method thereof, which can improve the bearing capacity of a single pile and shorten the length of the pile by effectively combining a precast pile and a cast-in-place pile.
In order to achieve the purpose, the invention is realized by the following technical scheme:
the utility model provides a composite pile foundation structure, its characterized in that includes cushion cap, precast tubular pile and wraps up the cement layer outside precast tubular pile through cast-in-place mode, the cushion cap sets up at precast tubular pile top, cement layer and the coaxial setting of precast tubular pile, cement layer diameter ratio precast tubular pile diameter 200 increase one's worth 400 mm.
Furthermore, the bottom pile end of the precast tubular pile adopts a closed cross-shaped pile tip.
Further, the precast tubular pile is a high-strength prestressed tubular pile.
The construction method of the composite pile foundation structure is characterized by comprising the following steps of:
(1) point location lofting: adopting a high-strength prestressed precast tubular pile, planning red line control points according to a plan view of the precast tubular pile, carrying out paying-off positioning by combining the dimensions in the plan view by using a total station, filling in measurement paying-off records carefully, and rechecking important parts;
(2) hole guiding: when the rotary drilling rig is accurately in place, drilling can be started, the verticality deviation of the lead hole is ensured not to be more than 0.5%, and the protective cylinder is built while hole digging is carried out;
(3) hole cleaning: cleaning holes by using a bottom cleaning drill, cleaning sediments at the bottom of the holes to ensure that the thickness of the sediments is not more than 5cm, and measuring the depth of the holes after cleaning the holes;
(4) pouring filling materials: lowering the guide pipe to pour cement soil into the hole while drawing out the drill bit from the final hole;
(5) hoisting the tubular pile in place: vertically aligning the prefabricated pipe pile to the center of the guide hole, slowly putting down the prefabricated pipe pile and inserting the prefabricated pipe pile into the guide hole, adjusting the verticality of a pile body by using a total station after the pipe pile is put down to 0.5m or 1.0m of filler, and adjusting the verticality of the pile body in a two-way mode, wherein the verticality deviation when the prefabricated pipe pile is inserted into the ground is less than or equal to 0.5 percent, and the pile tip alignment deviation is less than or equal to 20;
(6) piling: the pile pipe at the earlier stage sinks into the hole by the aid of the dead weight, the pile machine is started to hammer and pile after the pile pipe is close to the bottom of the hole, firstly, the prestressed pipe pile is guaranteed to be deep into the bottom of the hole, the pile end falls on the supporting layer, and secondly, filling materials in the hole are extruded from the pile bottom to a gap between the outer wall of the pipe pile and the hole wall and filled by means of impact force;
(7) pile feeding: the pile feeding termination condition is that elevation control is adopted, and the final 10-degree of penetration in the pile driving process is used as a reference.
Further, the interval time between the hole guiding operation and the piling operation is not longer than 3 hours, and the tubular pile construction operation must be completed before the initial setting of the concrete.
Further, the poured cement soil is in an amount of 0.24Lm and L is the effective pile length.
The composite pile foundation is a pile foundation formed by utilizing a precast pilepaThe value is large, the end resistance of a pile foundation is increased, and meanwhile, the problems that the precast pile cannot enter the weathered shale and the pile body of the precast pile is small in diameter and small in side resistance are solved by the rotary drilling hole guiding process. Compared with a single cast-in-place pile, the bearing layer can be lifted upwards, and the pile length is largeThe amplitude decreases. Compared with a single precast pile, the precast pile has the advantages that the problem that the precast pile enters weathered rocks is solved, and the bearing capacity is greatly improved. The pile body strength can be basically controlled, and the economical efficiency is good.
This composite pile foundation is with the design and the effectual combination of construction of prestressing force high strength concrete pipe pile and traditional bored concrete pile. The advantages of high strength of the precast pile and the rotary drilling and leading of the cast-in-place pile are fully utilized, and the difficulties that the cast-in-place pile is long, the bearing capacity is low and the precast pile cannot enter the rock are solved. Has obvious advantages in construction quality, construction period and engineering investment compared with single cast-in-place pile and precast pile.
Drawings
FIG. 1 is a diagram of a composite pile foundation according to the present invention;
FIG. 2 is a cross-sectional view taken along line A-A of FIG. 1;
FIG. 3 is a flow chart of the construction process of the composite pile foundation structure of the present invention;
in the figure: 1. bearing platform, 2 prefabricated tubular pile, 3, cement layer, 4, pile tip.
Detailed Description
The invention will be further described with reference to the following examples and embodiments in conjunction with the accompanying figures 1-3:
a composite pile foundation structure is shown in figures 1-2 and comprises a bearing platform 1, a precast tubular pile 2 and a cement layer 3 wrapped outside the precast tubular pile in a cast-in-place mode, wherein the bearing platform 1 is arranged at the top of the precast tubular pile 2, the cement layer 3 and the precast tubular pile are coaxially arranged, and the diameter of the cement layer 3 is 200 mm larger than that of the precast tubular pile 2 and 400mm larger than that of the cement layer 2. The bottom pile end of the precast tubular pile 2 adopts a closed cross-shaped pile tip 4. The precast tubular pile 2 is a high-strength prestress precast tubular pile.
The construction method of the composite pile foundation structure is shown in fig. 3, and comprises the following steps:
(1) point location lofting: adopting a high-strength prestressed precast tubular pile, planning red line control points according to a plan view of the precast tubular pile, carrying out paying-off positioning by combining the dimensions in the plan view by using a total station, filling in measurement paying-off records carefully, and rechecking important parts;
(2) hole guiding: when the rotary drilling rig is accurately in place, drilling a rotary drilling hole can be started, the verticality deviation of a pilot hole is ensured not to be larger than 0.5%, and a protective cylinder is built while drilling the hole;
(3) hole cleaning: cleaning the hole by using a bottom cleaning drill after the hole is dug, cleaning sediments at the bottom of the hole to ensure that the thickness of the sediments is not more than 5cm, and measuring the depth of the hole after the hole is cleaned;
(4) pouring filling materials: and (3) lowering the guide pipe to pour cement soil into the hole while drawing the drill bit out of the final hole, wherein the pouring amount of the cement soil is 0.24Lm, and L is the effective pile length.
(5) Hoisting the tubular pile in place: vertically aligning the prefabricated pipe pile to the center of the guide hole, slowly putting down the prefabricated pipe pile and inserting the prefabricated pipe pile into the guide hole, adjusting the verticality of a pile body by using a total station after the pipe pile is put down to 0.5m or 1.0m of filler, and adjusting the verticality of the pile body in a two-way mode, wherein the verticality deviation when the prefabricated pipe pile is inserted into the ground is less than or equal to 0.5 percent, and the pile tip alignment deviation is less than or equal to 20;
(6) piling: the pile pipe at the earlier stage sinks into the hole by the aid of the dead weight, the pile machine is started to hammer and pile after the pile pipe is close to the bottom of the hole, firstly, the prestressed pipe pile is guaranteed to be deep into the bottom of the hole, the pile end falls on the supporting layer, and secondly, filling materials in the hole are extruded from the pile bottom to a gap between the outer wall of the pipe pile and the hole wall and filled by means of impact force; the interval time between the hole guiding operation and the piling operation is not longer than 3 hours, and the tubular pile construction operation must be completed before the initial setting of the concrete.
(7) Pile feeding: the pile feeding termination condition is that elevation control is adopted, and the final 10-degree of penetration in the pile driving process is used as a reference.
Example 1:
the design parameters of a certain engineering pile foundation are shown in table 1:
Figure 144299DEST_PATH_IMAGE001
the engineering construction exploration condition, the geotechnical geological stratification table is shown in table 2:
Figure DEST_PATH_IMAGE003
according to the design parameters and the construction and exploration conditions of the pile foundation, if impact hole-forming cast-in-place piles, rotary-excavation hole-forming cast-in-place piles or full casing pipe soil (rock) hole-forming cast-in-place piles are adopted, the lengths of ZH-1, ZH-2 and ZH-3 piles are 21m, 30m and 41m, and the problems of over-irrigation and sediment can be caused.
The composite pile foundation structure adopting the technical scheme is constructed in the following way:
1) selecting a high-strength prestressed precast tubular pile, and adopting a rotary drilling pile machine or a down-the-hole hammer to drill a hole, wherein the diameter of the hole is 200-400mm larger than that of the tubular pile;
2) placing the guide pipe downwards and pouring cement mortar with the thickness of 0.24Lm (L is the effective pile length) or cement soil with certain strength into the hole;
3) and after the precast tubular pile is conveyed to be close to the bottom of the hole, starting a hammering pile driver or a static pressure machine, and extruding cement mortar which is pre-poured into the hole to fill the gap between the pipe wall and the hole wall so as to enlarge the diameter of the pile foundation, stabilize the pile body and solve the problem of sediment.
The composite pile foundation structure not only improves the bearing capacity of the pile foundation, but also solves the problem of sediment in the construction process. The length, construction quality and construction period of the pile foundation are optimized and guaranteed. According to the geological conditions, the bearing capacity of a single pile of the composite pile foundation bearing layer adopting tetra-1 strongly weathered shale as the bearing layer can be more than or equal to the bearing capacity of a single pile of the traditional cast-in-place pile adopting fifth layer weathered limestone as the bearing layer, the pile length can be well optimized, the pile length of ZH-1, ZH-2 and ZH-3 can be 21m, 30m and 41m according to the traditional cast-in-place pile, and the composite pile foundation only needs 11m, 12m and 12 m; the cost of the pile foundation and the construction period are greatly saved and optimized.
The foregoing is a more detailed description of the present method in connection with specific embodiments thereof, and it is not intended that the practice of the present method be limited to these descriptions. For a person skilled in the art to which the method pertains, several equivalent alternatives or obvious modifications, which have the same properties or uses, without departing from the concept of the method, should be considered as falling within the scope of protection determined by the claims submitted to the method.

Claims (6)

1. The utility model provides a composite pile foundation structure, its characterized in that includes cushion cap, precast tubular pile and wraps up the cement layer outside precast tubular pile through cast-in-place mode, the cushion cap sets up at precast tubular pile top, cement layer and the coaxial setting of precast tubular pile, cement layer diameter ratio precast tubular pile diameter 200 increase one's worth 400 mm.
2. A composite pile foundation structure according to claim 1, wherein the precast tubular pile bottom pile tip is a closed cross-shaped pile tip.
3. A composite pile foundation structure according to claim 1, wherein said precast tubular pile is a high strength prestressed tubular pile.
4. A method of constructing a composite pile foundation structure according to any one of claims 1 to 3, including the steps of:
(1) point location lofting: adopting a high-strength prestressed precast tubular pile, planning red line control points according to a plan view of the precast tubular pile, carrying out paying-off positioning by combining the dimensions in the plan view by using a total station, filling in measurement paying-off records carefully, and rechecking important parts;
(2) hole guiding: when the rotary drilling rig is accurately in place, drilling can be started, the verticality deviation of the lead hole is ensured not to be more than 0.5%, and the protective cylinder is built while hole digging is carried out;
(3) hole cleaning: cleaning holes by using a bottom cleaning drill, cleaning sediments at the bottom of the holes to ensure that the thickness of the sediments is not more than 5cm, and measuring the depth of the holes after cleaning the holes;
(4) pouring filling materials: lowering the guide pipe to pour cement soil into the hole while drawing out the drill bit from the final hole;
(5) hoisting the tubular pile in place: vertically aligning the prefabricated pipe pile to the center of the guide hole, slowly putting down the prefabricated pipe pile and inserting the prefabricated pipe pile into the guide hole, adjusting the verticality of a pile body by using a total station after the pipe pile is put down to 0.5m or 1.0m of filler, and adjusting the verticality of the pile body in a two-way mode, wherein the verticality deviation when the prefabricated pipe pile is inserted into the ground is less than or equal to 0.5 percent, and the pile tip alignment deviation is less than or equal to 20;
(6) piling: the pile pipe at the earlier stage sinks into the hole by the aid of the dead weight, the pile machine is started to hammer and pile after the pile pipe is close to the bottom of the hole, firstly, the prestressed pipe pile is guaranteed to be deep into the bottom of the hole, the pile end falls on the supporting layer, and secondly, filling materials in the hole are extruded from the pile bottom to a gap between the outer wall of the pipe pile and the hole wall and filled by means of impact force;
(7) pile feeding: the pile feeding termination condition is that elevation control is adopted, and the final 10-degree of penetration in the pile driving process is used as a reference.
5. A method of constructing a composite pile foundation structure according to claim 3, wherein the time between the hole-guiding operation and the pile-driving operation is not longer than 3 hours and the pipe pile construction operation must be completed before the concrete is initially set.
6. A method of constructing a composite pile foundation structure according to claim 3, wherein the amount of cemented soil poured is 0.24Lm for effective pile length.
CN202011235753.2A 2020-11-09 2020-11-09 Composite pile foundation structure and construction method thereof Pending CN112281829A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011235753.2A CN112281829A (en) 2020-11-09 2020-11-09 Composite pile foundation structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011235753.2A CN112281829A (en) 2020-11-09 2020-11-09 Composite pile foundation structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN112281829A true CN112281829A (en) 2021-01-29

Family

ID=74350786

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011235753.2A Pending CN112281829A (en) 2020-11-09 2020-11-09 Composite pile foundation structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN112281829A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942341A (en) * 2021-02-06 2021-06-11 中建四局建设发展有限公司 Construction method for implanting prefabricated pipe pile into complex geology
CN113152450A (en) * 2021-04-22 2021-07-23 广东际安工程管理有限公司 Application of prestressed concrete pipe pile planting technology in complex foundation
CN113774906A (en) * 2021-07-29 2021-12-10 安徽省交通规划设计研究总院股份有限公司 Construction process for implanting composite-section hollow pile by filling mortar into expanded lead hole
CN114482013A (en) * 2022-02-14 2022-05-13 安徽省交通规划设计研究总院股份有限公司 Suspended rock-socketed composite pile structure for hole-expanding precast pile and construction method of suspended rock-socketed composite pile structure
CN114517473A (en) * 2022-02-10 2022-05-20 江苏开放大学(江苏城市职业学院) Prefabricated pipe pile suitable for soft soil stratum and capable of effectively enhancing bearing capacity and construction method of prefabricated pipe pile

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942341A (en) * 2021-02-06 2021-06-11 中建四局建设发展有限公司 Construction method for implanting prefabricated pipe pile into complex geology
CN113152450A (en) * 2021-04-22 2021-07-23 广东际安工程管理有限公司 Application of prestressed concrete pipe pile planting technology in complex foundation
CN113774906A (en) * 2021-07-29 2021-12-10 安徽省交通规划设计研究总院股份有限公司 Construction process for implanting composite-section hollow pile by filling mortar into expanded lead hole
CN114517473A (en) * 2022-02-10 2022-05-20 江苏开放大学(江苏城市职业学院) Prefabricated pipe pile suitable for soft soil stratum and capable of effectively enhancing bearing capacity and construction method of prefabricated pipe pile
CN114482013A (en) * 2022-02-14 2022-05-13 安徽省交通规划设计研究总院股份有限公司 Suspended rock-socketed composite pile structure for hole-expanding precast pile and construction method of suspended rock-socketed composite pile structure

Similar Documents

Publication Publication Date Title
CN112281829A (en) Composite pile foundation structure and construction method thereof
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN112392400B (en) Hole forming construction process for slope protection pile in complex geological environment
CN104895055A (en) Building grouting pile foundation construction method
CN112323777A (en) Hollow precast pile for rock embedding and rock embedding construction method using precast pile
CN101812843A (en) Centre grouted poured post-grouting pile construction methods, and grouter and grout injector used thereby
CN104329020B (en) A kind of reinforced long spire embedding rock construction equipment and technique thereof
CN108221972B (en) Combined pile, construction method thereof and single pile vertical bearing capacity calculation method
CN111206575A (en) Construction method of long spiral pressure-grouting pile
CN108643214A (en) It is a kind of to backfill miscellaneous native composite foundation structure and its construction method
CN113323584A (en) Drilling method of large vibrating long spiral drilling machine
CN106149745A (en) A kind of truss type steel tube grouting pile basis and construction method thereof
CN104404956A (en) Construction method for pedestal piles
CN209958343U (en) Connecting joint for connecting reinforced concrete cast-in-place piles
CN113502817B (en) Method for automatically constructing prestressed pile
CN113863706A (en) Construction method and application device of low-clearance lower jet grouting static pressure composite pile of existing building
CN105064332A (en) Construction method for bearing base piles of square pile bodies
CN107687167A (en) A kind of I-steel mini pile pile making method
CN112144514A (en) Simple method for forming hole and pile in sand and pebble stratum easy to collapse during rotary drilling machine
CN214005658U (en) Composite pile foundation structure
CN114908741B (en) Construction device and slope soft soil foundation treatment method
CN207004431U (en) Soft soil foundation exciting drilling device
CN105040699A (en) Drilling pile planting method
CN112343051B (en) Method for rotary digging implantation pile sinking in high backfill region
CN113914304A (en) CFG pile long spiral drill hole core pipe pumping mixture pouring pile-forming construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination