CN112195938A - Treatment method for water seepage of occlusive pile - Google Patents
Treatment method for water seepage of occlusive pile Download PDFInfo
- Publication number
- CN112195938A CN112195938A CN202010923015.0A CN202010923015A CN112195938A CN 112195938 A CN112195938 A CN 112195938A CN 202010923015 A CN202010923015 A CN 202010923015A CN 112195938 A CN112195938 A CN 112195938A
- Authority
- CN
- China
- Prior art keywords
- grouting
- pile
- vertical shaft
- occlusive
- treating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/16—Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/0023—Slurry
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The invention provides a method for treating water seepage of an occlusive pile, and relates to the technical field of underground construction engineering. The method for treating the water seepage of the occlusive pile comprises the following steps: s1, forming a plurality of grouting holes in an occlusive pile element pile on the outer side of a vertical shaft well wall, wherein the grouting holes penetrate through the occlusive pile element pile to reach a foundation at the outer end; s2, inserting a grouting pipe into the inner end of the prepared grouting hole; s3, grouting outside the vertical shaft through a grouting pipe by using a grouting machine; and S4, arranging pressure-reducing and dewatering wells on the foundation outside the vertical shaft awning, wherein the arranging quantity of the pressure-reducing and dewatering wells in each direction is determined according to the water inrush degree in the well and the site construction conditions. When the method is used for construction, special equipment is not needed, the construction method is simple, the problem of water seepage of the vertical shaft secant pile can be effectively solved, the waterless operation of the vertical shaft is ensured, and meanwhile, the method has a reinforcing effect on the enclosure structure.
Description
Technical Field
The invention relates to the technical field of underground construction engineering, in particular to a method for treating water seepage of an occlusive pile.
Background
The secant pile is often used as a containment and water stop structure for shaft excavation. When the secant pile has defects or the secant pile is not tightly meshed due to insufficient vertical precision, underground water contained in the stratum flows out of the shaft along the water seepage channel on the pile body to influence the construction operation of the shaft, so that a treatment method needs to be invented to solve the water seepage problem of the secant pile.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides a method for treating water seepage of an occlusive pile, which solves the problem of water seepage of a pile body of the existing vertical shaft caused by the defects of the occlusive pile or the untight occlusion.
(II) technical scheme
In order to achieve the purpose, the invention is realized by the following technical scheme: a method for treating seepage of a secant pile comprises the following steps:
s1, forming a plurality of grouting holes in an occlusive pile element pile on the outer side of a vertical shaft well wall, wherein the grouting holes penetrate through the occlusive pile element pile to reach a foundation at the outer end;
s2, inserting a grouting pipe into the inner end of the prepared grouting hole;
s3, grouting outside the vertical shaft through a grouting pipe by using a grouting machine;
and S4, arranging pressure-reducing and dewatering wells on the foundation outside the vertical shaft awning, wherein the arranging quantity of the pressure-reducing and dewatering wells in each direction is determined according to the water inrush degree in the well and the site construction conditions.
Preferably, the grouting pipe is a welded steel pipe of phi 40, and the grouting pipe is arranged on the plain pile perpendicular to the well wall.
Preferably, the transverse distance between two adjacent hole sites of the grouting holes is 500-600mm, the vertical distance is 500mm, and the hole depth is 2 m.
Preferably, the grouting material in the grouting process is cement-water glass double-liquid slurry.
Preferably, the plane scope of slip casting is around the shaft, from the outside 2 m's of interlock stake outline scope, and vertical range does not have fixed size, guarantees to cover all infiltration points of the wall of a well.
(III) advantageous effects
The invention provides a method for treating water seepage of an occlusive pile. The method has the following beneficial effects:
the invention provides a method for treating water seepage of an occlusive pile, which is simple in construction method and can effectively solve the problem of water seepage of the occlusive pile of a vertical shaft, ensure the waterless operation of the vertical shaft and simultaneously have the function of reinforcing a building enclosure.
Drawings
FIG. 1 is a schematic plan view of the grouting range of the present invention;
FIG. 2 is a schematic cross-sectional view of a grouting range according to the present invention;
FIG. 3 is a schematic view of the grouting hole arrangement of the present invention;
FIG. 4 is a schematic plan view of the pressure-reducing dewatering well according to the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b):
as shown in fig. 1 to 4, an embodiment of the present invention provides a method for treating water seepage of a bite pile, including the following steps:
s1, arranging a plurality of grouting holes on an occlusive pile element pile on the outer side of a vertical shaft well wall, wherein the grouting holes penetrate through the occlusive pile element pile to reach a foundation at the outer end, and the transverse distance between two adjacent hole sites of the grouting holes is 500-600mm, the vertical distance is 500mm, and the hole depth is 2m, as shown in FIG. 3;
s2, inserting a grouting pipe into the inner end of the arranged grouting hole, wherein the grouting pipe is a welded steel pipe with the diameter of phi 40, and the grouting pipe is arranged on the plain pile in a manner of being vertical to the well wall;
s3, grouting outside the vertical shaft through a grouting pipe by using a grouting machine, wherein the grouting material is cement-water glass double-liquid slurry, the grouting plane range is the range of 2m outward from the outer contour line of the occlusive pile around the vertical shaft, and the vertical range has no fixed size, so that all water seepage points of the shaft wall are covered, as shown in the figures 1 and 2;
s4, arranging pressure-reducing and dewatering wells on the foundation outside the shaft awning, wherein the arranging quantity of the pressure-reducing and dewatering wells in each direction is determined according to the water gushing degree in the well and the site construction conditions, the pressure-reducing and dewatering wells can reduce the water pressure in the foundation near the shaft, and the condition of water flow permeation in the foundation near the shaft is prevented, as shown in figure 4.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. A method for treating water seepage of an occlusive pile is characterized by comprising the following steps: the method comprises the following steps:
s1, forming a plurality of grouting holes in an occlusive pile element pile on the outer side of a vertical shaft well wall, wherein the grouting holes penetrate through the occlusive pile element pile to reach a foundation at the outer end;
s2, inserting a grouting pipe into the inner end of the prepared grouting hole;
s3, grouting outside the vertical shaft through a grouting pipe by using a grouting machine;
and S4, arranging pressure-reducing and dewatering wells on the foundation outside the vertical shaft awning, wherein the arranging quantity of the pressure-reducing and dewatering wells in each direction is determined according to the water inrush degree in the well and the site construction conditions.
2. The method for treating the seepage of the occlusive pile according to claim 1, wherein the method comprises the following steps: the grouting pipe is a welded steel pipe of phi 40, and the grouting pipe is arranged on the plain pile perpendicular to the well wall.
3. The method for treating the seepage of the occlusive pile according to claim 1, wherein the method comprises the following steps: the transverse distance between two adjacent hole sites of the grouting holes is 500-600mm, the vertical distance is 500mm, and the hole depth is 2 m.
4. The method for treating the seepage of the occlusive pile according to claim 1, wherein the method comprises the following steps: the grouting material in the grouting process is cement-water glass double-liquid slurry.
5. The method for treating the seepage of the occlusive pile according to claim 1, wherein the method comprises the following steps: the plane scope of slip casting is around the shaft, from the outside 2 m's of interlock stake outline scope, and vertical scope does not have fixed size, guarantees to cover all infiltration points of the wall of a well.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010923015.0A CN112195938A (en) | 2020-09-04 | 2020-09-04 | Treatment method for water seepage of occlusive pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010923015.0A CN112195938A (en) | 2020-09-04 | 2020-09-04 | Treatment method for water seepage of occlusive pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112195938A true CN112195938A (en) | 2021-01-08 |
Family
ID=74005271
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010923015.0A Pending CN112195938A (en) | 2020-09-04 | 2020-09-04 | Treatment method for water seepage of occlusive pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112195938A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103114599A (en) * | 2013-03-04 | 2013-05-22 | 济南城建集团有限公司 | Deep foundation pit sealed precipitation device and construction method thereof |
KR101545307B1 (en) * | 2014-10-14 | 2015-08-19 | 유한회사 강남이앤씨 | Construction method of complex temporary facility with bottom grouting for weak ground |
CN204940315U (en) * | 2015-09-28 | 2016-01-06 | 北京城建道桥建设集团有限公司 | A kind of water-stopping system for the large-scale vertical shaft of region of FuShui |
CN106677787A (en) * | 2016-12-27 | 2017-05-17 | 中冶集团武汉勘察研究院有限公司 | Vertical shaft restoration and reinforcement structure and restoration and reinforcement construction method |
CN109339079A (en) * | 2018-12-05 | 2019-02-15 | 中铁科学研究院有限公司 | A kind of foundation pit water-stopping system and its construction technology close to river permeable stratum |
-
2020
- 2020-09-04 CN CN202010923015.0A patent/CN112195938A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103114599A (en) * | 2013-03-04 | 2013-05-22 | 济南城建集团有限公司 | Deep foundation pit sealed precipitation device and construction method thereof |
KR101545307B1 (en) * | 2014-10-14 | 2015-08-19 | 유한회사 강남이앤씨 | Construction method of complex temporary facility with bottom grouting for weak ground |
CN204940315U (en) * | 2015-09-28 | 2016-01-06 | 北京城建道桥建设集团有限公司 | A kind of water-stopping system for the large-scale vertical shaft of region of FuShui |
CN106677787A (en) * | 2016-12-27 | 2017-05-17 | 中冶集团武汉勘察研究院有限公司 | Vertical shaft restoration and reinforcement structure and restoration and reinforcement construction method |
CN109339079A (en) * | 2018-12-05 | 2019-02-15 | 中铁科学研究院有限公司 | A kind of foundation pit water-stopping system and its construction technology close to river permeable stratum |
Non-Patent Citations (2)
Title |
---|
周建春: "新建地铁车站下穿既有运营车站施工技术", 《湖南城市学院学报(自然科学版)》 * |
郑邦友等: "强风化板岩地基明挖地铁车站钻孔咬合桩围护结构渗漏治理技术", 《施工技术》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103993603B (en) | A kind of anchor pole churning back cover deep foundation ditch reversed construction method without dewatering operation | |
CN107246008A (en) | A kind of side slope protection from draining anchor cable system and its construction method | |
CN102454167A (en) | Construction method for large ultra-deep well | |
CN104631475A (en) | Safe and fast construction method of down-traversing river shallow depth bored tunnel | |
CN105780779A (en) | Externally arranged, compacted and grouted Larsen steel sheet pile composite retaining structure and use method thereof | |
CN106351229B (en) | Soft clay area basement support structure | |
CN109736340B (en) | Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab | |
CN102535441A (en) | Construction method of underground diaphragm wall | |
CN102433886A (en) | Construction method for adding water lowering well in water collecting well | |
CN106351312A (en) | Pipeline and construction method thereof | |
CN206408655U (en) | The top plate sidewall structure of covered back-digging construction | |
CN106013265A (en) | Emergency basement anti-floating structure and construction method thereof | |
CN111810176A (en) | Subway station end reinforcement construction method for water-rich sand layer shield construction | |
CN106759241A (en) | A kind of vacuum method basement process discharge structure | |
CN207619996U (en) | Precipitation well construction | |
CN104895093A (en) | Semi-prefabricated underground continuous wall and construction method thereof | |
CN216342131U (en) | Shield tunnel invades limit stake and handles reinforced structure | |
CN108149682A (en) | A kind of slip casting casing device and the pile foundation drilling construction method using the casing device | |
CN107956221A (en) | Downcast well pipe proof protecting device and construction method | |
CN107100206A (en) | A kind of prevention and controls of basement leakage | |
CN107245989A (en) | Bear the tunnel structure and its construction technology of external water pressure in height | |
CN212250042U (en) | Subway station end reinforcing structure for water-rich sand layer shield construction | |
CN206157860U (en) | Drainage pipeline | |
CN204456228U (en) | A kind of diaphragm wall fast plugging device | |
CN204356738U (en) | A kind of concrete face rockfill dam upstream face structure of preventing face slab dislocation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210108 |