CN111962507A - Pile foundation hole forming method - Google Patents

Pile foundation hole forming method Download PDF

Info

Publication number
CN111962507A
CN111962507A CN202010843100.6A CN202010843100A CN111962507A CN 111962507 A CN111962507 A CN 111962507A CN 202010843100 A CN202010843100 A CN 202010843100A CN 111962507 A CN111962507 A CN 111962507A
Authority
CN
China
Prior art keywords
hole
drilling
pile foundation
forming method
drilling rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010843100.6A
Other languages
Chinese (zh)
Inventor
贺涛
王俊伟
谢欢
韩登伦
赵希望
袁德权
乔晓伟
周闯
王佩
程松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of Highway Engineering Bureau of CCCC
CCCC First Highway Engineering Co Ltd
Original Assignee
Third Engineering Co Ltd of Highway Engineering Bureau of CCCC
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of Highway Engineering Bureau of CCCC, CCCC First Highway Engineering Co Ltd filed Critical Third Engineering Co Ltd of Highway Engineering Bureau of CCCC
Priority to CN202010843100.6A priority Critical patent/CN111962507A/en
Publication of CN111962507A publication Critical patent/CN111962507A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B1/00Percussion drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B3/00Rotary drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a pile foundation hole forming method, which relates to the technical field of cast-in-place pile construction, and comprises the following steps: (1) drilling to the weak interlayer by adopting a rotary drilling rig; (2) rotating the hole to collapse; (3) backfilling cement soil or lime soil after the hole collapse of the soft interlayer; (4) replacing the rotary drilling rig with a percussion drilling rig, and adopting the percussion drilling rig to perform impact compaction in the collapsed hole; wherein, the drill bit of the percussion drill is a conical head; (5) replacing the impact drilling machine with a rotary drilling machine; (6) and drilling by adopting a rotary drilling rig until the hole is formed. In the construction process, the backfill impact adopts a drill bit with a pointed lower part, so that the extrusion force diffused to the collapsed hole range during impact can be greatly improved, a compact and stable retaining wall structure with the strength far higher than that of an original stratum is formed, and the cost of cement soil or lime soil is low. When the stratum has the local weak interlayer, the method can effectively treat the collapsed hole, has low treatment cost and can improve the construction efficiency.

Description

Pile foundation hole forming method
Technical Field
The invention relates to the technical field of cast-in-place pile construction, in particular to a pile foundation hole forming method.
Background
The cast-in-situ bored pile is a pile formed by forming a pile hole in foundation soil through mechanical drilling, steel pipe soil extrusion or manual excavation and the like on an engineering site, placing a reinforcement cage in the pile hole and pouring concrete into the pile hole. Common pile foundation hole forming methods comprise long auger drilling hole forming, impact drilling hole forming, rotary drilling hole forming, manual hole digging and the like, and slurry (chemical slurry) wall protection is adopted according to construction and is divided into wet operation and dry operation.
In the prior art, when the construction position is located in a water shortage area and the self-weight collapsible loess on the upper part of the pile foundation deforms and collapses when meeting water, dry operation is generally adopted. In order to reduce noise, a rotary drilling hole with less vibration is generally adopted.
However, when a local weak interlayer exists in the stratum, hole collapse can occur when the stratum is dug to the weak interlayer in a rotary mode, if the stratum is processed in time and is dug downwards, the collapse is easily transmitted from the hole collapse position to the upper stable hole wall, the whole pile hole collapses, the rotary digging bucket is buried, the processing cost is high, and the construction progress is delayed.
Disclosure of Invention
The invention aims to provide a pile foundation pore-forming method, which aims to solve the technical problems that in the prior art, when a local weak interlayer exists in a stratum, a hole collapse occurs when a rotary excavating machine rotates to the weak interlayer, and if the local weak interlayer is not processed in time and continues to dig downwards, the hole wall is easy to transfer downwards from the hole collapse position to the upper stable hole wall, so that the whole pile hole collapses, a rotary excavating bucket is buried, the processing cost is high, and the construction progress is delayed.
The invention provides a pile foundation pore-forming method, which comprises the following steps:
(1) drilling to the weak interlayer by adopting a rotary drilling rig;
(2) rotating the hole to collapse;
(3) backfilling cement soil or lime soil after the hole collapse of the soft interlayer;
(4) replacing the rotary drilling rig with a percussion drilling rig, and adopting the percussion drilling rig to perform impact compaction in the collapsed hole; wherein, the drill bit of the percussion drill is a conical head;
(5) replacing the impact drilling machine with a rotary drilling machine;
(6) and drilling by adopting a rotary drilling rig until the hole is formed.
Further, before the step (6), the following steps are included: and checking whether a drilling bucket of the rotary drilling rig penetrates through the soft interlayer or not.
Further, when the drilling bucket passes through the weak interlayer, the step (6) is carried out: and (5) when the drilling and excavating bucket does not pass through the weak interlayer, repeating the steps (2) - (5) until the drilling and excavating bucket passes through the weak interlayer, and then performing the step (6).
Further, in the step (2), the depth of each rotary digging is 1.5m-2 m.
Further, in the step (3), the cement soil is prepared by mixing cement and loess according to the mass ratio of 3: 7; the lime soil is prepared by uniformly mixing slaked lime and loess according to the mass ratio of 3: 7.
Further, the moisture content of the loess is 13% to 15%.
Further, in the step (3), the backfill height is 0.8m-1.2m higher than the upper part of the collapse hole.
Further, in the step (4), the stroke of the percussion drill is 2.5m to 3.5 m.
Further, before the step (1), the following steps are included: construction lofting; and (5) lowering the steel casing.
Further, the following steps are included after the step (6): putting down a reinforcement cage; and pouring pile foundation concrete.
According to the pile foundation pore-forming method provided by the invention, in the construction process, the backfill impact adopts the drill bit with the pointed lower part, so that the extrusion force diffused to the hole collapse range in the impact process can be greatly improved, and a compact and stable retaining wall structure with the strength far higher than that of an original stratum is formed. The rotary drilling rig is adopted for drilling, so that construction vibration can be reduced, the noise is low, and the interference to surrounding residents can be reduced. In addition, the method can also avoid the hole forming operation of slurry retaining walls, chemical slurry retaining walls or clear water retaining walls, save water resources and reduce environmental pollution. The cost of the cement soil or the lime soil is low, and the cost of hole collapse treatment is greatly reduced by backfilling the cement soil or the lime soil. In addition, when the water-rich stratum is formed, the lime soil can also play a role in sealing water.
Therefore, the pile foundation pore-forming method can effectively treat collapsed pores when a local weak interlayer exists in the stratum, the treatment cost is low, and the construction efficiency can be improved.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without creative efforts.
Fig. 1 is a block diagram illustrating steps of a pile foundation hole forming method according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram corresponding to steps (1) and (2) provided in the embodiment of the present invention;
fig. 3 is a schematic structural diagram corresponding to steps (3) and (4) provided in the embodiment of the present invention;
fig. 4 is a schematic structural diagram corresponding to steps (5) and (6) provided in the embodiment of the present invention.
Icon: 1-rotary drilling rig; 2-soft interlayer; 3-cemented soil or limestone soil; 4-a percussion drill; 5-a drill bit; 6-drilling and excavating bucket; 7-collapse of the hole; 8-steel casing; 9-stabilizing the formation.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the following embodiments, and it should be understood that the described embodiments are some, but not all, embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1 to 4, a pile foundation hole forming method provided by an embodiment of the present invention includes the following steps: (1) drilling to the soft interlayer 2 by adopting a rotary drilling rig 1; (2) rotating the hole to collapse 7; (3) backfilling cement soil or lime soil 3 after the hole collapse 7 of the soft interlayer 2; (4) replacing the rotary drilling rig 1 with an impact drilling rig 4, and adopting the impact drilling rig 4 to perform impact compaction in the collapsed hole 7; wherein, the drill bit 5 of the percussion drill 4 is a conical head; (5) replacing the impact drilling machine 4 with the rotary drilling machine 1; (6) and drilling by adopting a rotary drilling rig 1 until a hole is formed.
Further, before the step (1), the following steps are included: construction lofting; and (5) lowering the steel casing 8.
Specifically, according to the pile position coordinates and the field control network provided by the design drawing, the central position of the pile position hole is lofted by a total station or a Global Positioning System (GPS), the timber pile is nailed, the hole position is lofted accurately on the timber pile, and the cement nail is nailed. After the pile position is determined, four pile protectors are led out in a cross shape along the pile axis, and meanwhile, after the subsequent pile protectors are buried, the stay wires are pulled again to mark the edges of the pile protectors with red paint. The elevation of the pile foundation is controlled by the elevation of the top of the pile casing. And measuring the top elevation of the protective cylinder by using a leveling instrument and a leveling point arranged near the bridge, and then measuring and calculating the bottom elevation of the hole by using a measuring rope.
When the rotary drilling rig 1 is in place, whether the performance of the rotary drilling rig 1 is good or not needs to be checked firstly, and the normal work of the drilling rig is ensured. The position of the drilling machine is accurately determined through the measured pile position, the rotary drilling machine 1 is moved to the drilling position, the stability is guaranteed, after the drill rod is basically vertical through manual rough leveling, the automatic control system is used for adjusting the drill rod to keep a vertical state, and a constructor can detect the vertical degree of the drill rod through a hanging ball method. Meanwhile, the alignment accuracy of the drilling machine is rechecked again by drawing the cross wire, so that the drilling quality is ensured.
During the drilling process of the rotary drilling rig 1, the drilling bucket 6 is firstly landed during drilling, the zero clearing operation is carried out through a zero clearing button on a display, and the original position of the drilling bucket 6 is recorded. At the moment, the display displays the bar-shaped columns and the numbers of the current position of the drilling hole, and the total depth of the magnetic control can be displayed by monitoring the construction working position, the advancing position and the hole depth of the drilling hole through the display. After the drilling bucket 6 is fully extruded with the drilling slag, the drilling bucket is lifted out of the ground surface, the drilling slag is placed at a designated position, and the drilling slag is cleared and transported to a designated spoil area by using a loader and a dumper, so that water and soil loss or farmland pollution is avoided.
After the rotary drilling rig 1 drills 2-3m, the drilling bucket 6 is lifted out of the hole, an earth cutter is installed on one side of the drilling bucket 6 and extends out of the outer side of the drilling bucket 6 by 5cm, then the drilling bucket 6 is placed into the hole again to carry out rotary cutting and reaming on the hole opening 2-3m, after reaming is finished, the drilling bucket 6 is lifted out of the hole again, a steel protective cylinder 8 is placed downwards, the top of the protective cylinder is 30cm higher than the ground, earth is filled around the protective cylinder and is higher than the ground around, and meanwhile, a water prevention and drainage system is perfected. Therefore, rainwater can be prevented from flowing into the hole when raining, and the upper hole wall is deformed due to the structural damage after the self-weight collapsible loess meets water, so that the hole 7 is collapsed. And after the steel pile casings 8 are buried according to the designed pile positions, lifting the drilling and excavating bucket 6 into the hole to continue drilling until the top surface of the soft interlayer 2.
Further, the following steps are included after the step (6): putting down a reinforcement cage; and pouring pile foundation concrete.
The pile foundation hole forming method provided by the embodiment of the invention comprises the following steps: (1) drilling to the soft interlayer 2 by adopting a rotary drilling rig 1; (2) rotating the hole to collapse 7; (3) backfilling cement soil or lime soil 3 after the hole collapse 7 of the soft interlayer 2; (4) replacing the rotary drilling rig 1 with an impact drilling rig 4, and adopting the impact drilling rig 4 to perform impact compaction in the collapsed hole 7; wherein, the drill bit 5 of the percussion drill 4 is a conical head; (5) replacing the impact drilling machine 4 with the rotary drilling machine 1; (6) and drilling by adopting a rotary drilling rig 1 until a hole is formed. In the construction process, the backfill impact adopts the drill bit 5 with the pointed lower part, so that the extrusion force diffused to the collapsed hole 7 during impact can be greatly improved, and a compact and stable retaining wall structure with the strength far higher than that of an original stratum is formed. The rotary drilling rig 1 is adopted for drilling, so that construction vibration can be reduced, noise is low, and interference to surrounding residents can be reduced. In addition, the method can also avoid the hole forming operation of slurry retaining walls, chemical slurry retaining walls or clear water retaining walls, save water resources and reduce environmental pollution. The cost of the cement soil or the lime soil 3 is low, and the treatment cost of the hole collapse 7 is greatly reduced by backfilling the cement soil or the lime soil 3. In addition, when the water-rich stratum is formed, the lime soil can also play a role in sealing water.
Therefore, the pile foundation pore-forming method can effectively treat the collapsed hole 7 when the local weak interlayer 2 exists in the stratum, has low treatment cost and can improve the construction efficiency.
As shown in fig. 1-4, on the basis of the above embodiment, further, before step (6), the following steps are included: and checking whether the drilling bucket 6 of the rotary drilling rig 1 penetrates through the weak interlayer 2.
Further, when the drilling bucket 6 passes through the weak interlayer 2, the step (6) is carried out: and (5) repeating the steps (2) - (5) when the drilling and excavating bucket 6 does not penetrate through the soft interlayer 2 until the drilling and excavating bucket 6 penetrates through the soft interlayer 2, and then performing the step (6).
Further, in the step (2), the depth of each rotary digging is 1.5m-2 m.
Further, in the step (3), the backfill height is 0.8m-1.2m higher than the upper part of the collapse hole 7. With the downward falling of the drill bit 5 of the percussion drill 4, the top surface of the cement soil or the lime soil 3 in the collapsed hole 7 is lowered continuously, and the cement soil or the lime soil 3 is added into the collapsed hole 7 in time.
Further, in step (4), the stroke of the hammer drill 4 is 2.5m to 3.5 m.
Wherein, the drill bit 5 of the impact drilling machine 4 weighs about 3t to ensure that the cement soil or the lime soil 3 can be extruded into the hole collapse 7 during impact.
In the impact compaction process, the drill bit 5 is lifted, the drill bit 5 falls down by self weight to compact and compact the collapsed hole 7, the stroke is controlled to be about 3m, meanwhile, the sinking condition of the cement soil or the lime soil 3 is observed by a flashlight, the backfilling is supplemented in time, the top surface of the compacted cement soil or the lime soil 3 is always ensured to be 0.3-0.5m higher than the upper part of the collapsed hole 7, the impact is stopped until the drill bit 5 impacts the cement soil or the lime soil 3 for 50 times and the top surface of the cement soil or the lime soil 3 sinks for less than 5cm, the section of the collapsed hole 7 is filled with compact cement soil or lime soil 3, the rotary drilling rig 1 is replaced to perform repeated drilling, and after the cement soil or the lime soil 3 in the pile hole range is dug, the remaining compacted cement soil or lime soil 3 of the collapsed hole 7 forms.
Further, in the step (3), the cement soil is prepared by mixing cement and loess according to the mass ratio of 3: 7; the lime soil is prepared by uniformly mixing slaked lime and loess according to the mass ratio of 3: 7.
Further, the moisture content of the loess is 13% to 15%.
Specifically, when the rotary drilling is carried out to the weak interlayer 2, hole excavation should be stopped, the top surface depth of the weak interlayer 2 is recorded, and P.O 32.5.5 (or P.042.5) cement and the collapsible loess excavated at the upper part are uniformly mixed according to the mass ratio of 3:7 outside the hole opening by 5 m; if the water content of the soft interlayer 2 is higher, adopting hydrated lime: mixing loess 3:7 with lime soil, wherein the loess used for mixing is slightly wet, and the water content is controlled to be 13-15%.
In the embodiment, in the construction process, when the top surface of the weak interlayer 2 is rotationally dug downwards for 1.5-2 m, if the drilling bucket 6 enters the stable stratum 9, collapsed soil on the hole wall of the weak interlayer 2 is cleaned by a rotary digging machine, and cement soil or lime soil 3 is quickly backfilled, wherein the backfilling height is 0.8-1.2 m higher than the upper part of the collapsed hole 7. And after backfilling is finished, the rotary drilling rig 1 is moved away, the impact drilling rig 4 is in place for impact compaction, and the cement soil or the lime soil 3 is squeezed into the collapsed hole 7. And (3) if the weak interlayer 2 is thick, repeating the steps (2) - (5), and performing rotary drilling, hole collapse 7 and cleaning section by section, backfilling cement soil or lime soil 3, impacting and compacting from top to bottom according to each section of 1.5-2 m for multiple times, and performing rotary drilling and rotary drilling under the condition of compacting the cement soil or lime soil 3 to protect the wall until the soft interlayer 2 penetrates into the stable stratum 9.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; and the modifications or the substitutions do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention.

Claims (10)

1. A pile foundation pore-forming method is characterized by comprising the following steps:
(1) drilling to the weak interlayer by adopting a rotary drilling rig;
(2) rotating the hole to collapse;
(3) backfilling cement soil or lime soil after the hole collapse of the soft interlayer;
(4) replacing the rotary drilling rig with a percussion drilling rig, and adopting the percussion drilling rig to perform impact compaction in the collapsed hole; wherein, the drill bit of the percussion drill is a conical head;
(5) replacing the impact drilling machine with a rotary drilling machine;
(6) and drilling by adopting a rotary drilling rig until the hole is formed.
2. The pile foundation pore-forming method according to claim 1, characterized by further comprising the following steps before step (6):
and checking whether a drilling bucket of the rotary drilling rig penetrates through the soft interlayer or not.
3. The pile foundation hole forming method according to claim 2, wherein when the drilling bucket of the rotary drilling rig passes through the weak interlayer, the step (6) is carried out:
and (5) when the drilling and excavating bucket does not pass through the weak interlayer, repeating the steps (2) - (5) until the drilling and excavating bucket passes through the weak interlayer, and then performing the step (6).
4. The pile foundation pore-forming method according to any one of claims 1-3, wherein in step (2), the depth of each rotary digging is 1.5m-2 m.
5. The pile foundation pore-forming method according to the claim 1, characterized in that in the step (3), the cement soil is prepared by mixing cement and loess according to the mass ratio of 3: 7; the lime soil is prepared by uniformly mixing slaked lime and loess according to the mass ratio of 3: 7.
6. A pile foundation pore-forming method according to claim 5, characterized in that the moisture content of loess is 13% -15%.
7. The pile foundation pore-forming method according to the claim 1, characterized in that in the step (3), the backfill height is 0.8m-1.2m higher than the upper part of the collapsed pore.
8. The pile foundation pore-forming method according to the claim 7, wherein in the step (4), the stroke of the impact drilling machine is 2.5m-3.5 m.
9. The pile foundation pore-forming method according to claim 1, characterized by further comprising the following steps before step (1):
construction lofting;
and (5) lowering the steel casing.
10. The pile foundation pore-forming method according to claim 1, characterized by further comprising the following steps after the step (6):
putting down a reinforcement cage;
and pouring pile foundation concrete.
CN202010843100.6A 2020-08-20 2020-08-20 Pile foundation hole forming method Pending CN111962507A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010843100.6A CN111962507A (en) 2020-08-20 2020-08-20 Pile foundation hole forming method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010843100.6A CN111962507A (en) 2020-08-20 2020-08-20 Pile foundation hole forming method

Publications (1)

Publication Number Publication Date
CN111962507A true CN111962507A (en) 2020-11-20

Family

ID=73388734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010843100.6A Pending CN111962507A (en) 2020-08-20 2020-08-20 Pile foundation hole forming method

Country Status (1)

Country Link
CN (1) CN111962507A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112832231A (en) * 2021-01-05 2021-05-25 江西省地质工程(集团)公司 Construction method of cast-in-situ bored pile in karst cave area
CN113669003A (en) * 2021-08-05 2021-11-19 深圳宏业基岩土科技股份有限公司 Deep rockfill and sludge area breast wall hole forming construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758430A (en) * 2012-07-31 2012-10-31 中建五局第三建设有限公司 Large-diameter rotary digging pile construction process for ultra-deep throwing and filling unconsolidated soil body
CN105019431A (en) * 2015-05-28 2015-11-04 杭州江润科技有限公司 Large-diameter super-long bored pile construction method for steep dip stratified rock mass with alternative smashed parts and integral parts
CN106906823A (en) * 2017-03-29 2017-06-30 中铁上海工程局集团第五工程有限公司 A kind of drilled pile caves in and locates the processing method of active supporting
CN107090821A (en) * 2017-05-10 2017-08-25 中国十七冶集团有限公司 A kind of processing method of churning driven drilling landslide
CN206503562U (en) * 2017-01-05 2017-09-19 深圳市盛业地下工程有限公司 A kind of impact rotating extrusion sealing drill bit
CN107268608A (en) * 2017-06-06 2017-10-20 中铁十九局集团轨道交通工程有限公司 Building waste earth-boring stake forming hole method
CN210918893U (en) * 2019-12-02 2020-07-03 张云健 Drill bit for rapidly repairing wall of pile hole
CN111501783A (en) * 2020-06-04 2020-08-07 信息产业电子第十一设计研究院科技工程股份有限公司 Structure and method for solving collapse of large-diameter mechanical rotary digging pile in throwing and filling area by using ton bag

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758430A (en) * 2012-07-31 2012-10-31 中建五局第三建设有限公司 Large-diameter rotary digging pile construction process for ultra-deep throwing and filling unconsolidated soil body
CN105019431A (en) * 2015-05-28 2015-11-04 杭州江润科技有限公司 Large-diameter super-long bored pile construction method for steep dip stratified rock mass with alternative smashed parts and integral parts
CN206503562U (en) * 2017-01-05 2017-09-19 深圳市盛业地下工程有限公司 A kind of impact rotating extrusion sealing drill bit
CN106906823A (en) * 2017-03-29 2017-06-30 中铁上海工程局集团第五工程有限公司 A kind of drilled pile caves in and locates the processing method of active supporting
CN107090821A (en) * 2017-05-10 2017-08-25 中国十七冶集团有限公司 A kind of processing method of churning driven drilling landslide
CN107268608A (en) * 2017-06-06 2017-10-20 中铁十九局集团轨道交通工程有限公司 Building waste earth-boring stake forming hole method
CN210918893U (en) * 2019-12-02 2020-07-03 张云健 Drill bit for rapidly repairing wall of pile hole
CN111501783A (en) * 2020-06-04 2020-08-07 信息产业电子第十一设计研究院科技工程股份有限公司 Structure and method for solving collapse of large-diameter mechanical rotary digging pile in throwing and filling area by using ton bag

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘宪文: "《地基与基础工程300问》", 31 January 2012, 中国建材工业出版社 *
本书编委会: "《炼钢工程施工管理与施工技术》", 31 January 2017, 冶金工业出版社 *
肖昭然: "《地基处理》", 30 September 2012, 黄河水利出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112832231A (en) * 2021-01-05 2021-05-25 江西省地质工程(集团)公司 Construction method of cast-in-situ bored pile in karst cave area
CN113669003A (en) * 2021-08-05 2021-11-19 深圳宏业基岩土科技股份有限公司 Deep rockfill and sludge area breast wall hole forming construction method
CN113669003B (en) * 2021-08-05 2023-12-15 深圳宏业基岩土科技股份有限公司 Construction method for wall protection pore-forming in deep filled stone and silt region

Similar Documents

Publication Publication Date Title
CN107938676B (en) Pile foundation construction method for penetrating through full-filling karst cave
CN105714772B (en) Karst area embedded rock pile pore-forming bores concrete dado method again
CN105780763A (en) Construction method of medium-hole vibrating casing wall protection type long spiral cast-in-situ bored pile
CN106988302A (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN111042116A (en) Karst cave stratum pile foundation construction method
CN108589707A (en) A kind of full-sleeve long screw auger and churning driven combined type construction
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN112030956A (en) Karst stratum bored pile construction method
CN112392400A (en) Hole forming construction process for slope protection pile in complex geological environment
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
CN110761265A (en) Karst cave disposal method for deep foundation pit pile foundation construction in karst area
CN1265062C (en) Construction for making piles and tools
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN111962507A (en) Pile foundation hole forming method
CN106677166A (en) Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode
CN109667276A (en) A kind of karst cave treatment and tracking grouting construction method
CN206721870U (en) A kind of long auger guncreting pile steel reinforcement cage
CN112227389A (en) Rectangular-section slide-resistant pile combined mechanical pore-forming construction method
CN111608174A (en) Karst area karst cave treatment method based on punched cast-in-place pile
CN104652427A (en) Construction method of drilling pile
CN107964977A (en) The composite foundation and its construction method of a kind of karst landform
CN114059527A (en) Large-diameter mixing pile construction method suitable for high-groundwater-level hard soil layer
CN113668564A (en) Construction method for supporting and reinforcing open-cut underground passage adjacent to subway station
CN112921947A (en) Foundation construction method in house building construction
CN103806444A (en) Soft soil layer rotary excavating pile construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201120

RJ01 Rejection of invention patent application after publication