CN111926942A - Prepackage type building module - Google Patents

Prepackage type building module Download PDF

Info

Publication number
CN111926942A
CN111926942A CN202010810541.6A CN202010810541A CN111926942A CN 111926942 A CN111926942 A CN 111926942A CN 202010810541 A CN202010810541 A CN 202010810541A CN 111926942 A CN111926942 A CN 111926942A
Authority
CN
China
Prior art keywords
groove
block
wall body
placing plate
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010810541.6A
Other languages
Chinese (zh)
Other versions
CN111926942B (en
Inventor
周增强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Construction Engineering Management Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010810541.6A priority Critical patent/CN111926942B/en
Publication of CN111926942A publication Critical patent/CN111926942A/en
Application granted granted Critical
Publication of CN111926942B publication Critical patent/CN111926942B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/26Strutting means for wall parts; Supports or the like, e.g. for holding in position prefabricated walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Building Environments (AREA)

Abstract

The invention relates to a preassembled building module which comprises a supporting component, a placing plate, a wall body and a first limiting component, wherein the supporting component is arranged on the placing plate; the supporting assembly comprises a buffering device, the buffering device comprises a hinged frame, the wall body is installed on a placing plate, the placing plate is installed on the hinged frame, the first limiting assembly comprises a guiding block and a limiting column, the guiding block comprises a first block part and a second block part which are perpendicular to each other and are connected together at the end parts, the first block part is vertically arranged, and the second block part is arranged at the lower end of the first block part; the limiting column is arranged at the upper end of the first block part, and the limiting column and the second block part are positioned at the same side of the first block part; the first block is hinged in the notch around the horizontal axis extending from left to right, the second block is positioned at the lower side of the placing plate, and the limiting column is inserted into the positioning groove of the wall body in the process that the wall body rotates downwards and rightwards along with the placing plate.

Description

Prepackage type building module
Technical Field
The invention relates to the field of building modules, in particular to a preassembled building module.
Background
With the improvement of living standard of people and the rapid development of society, various buildings with different functions are emerging continuously. At present, most buildings built in China are concrete structures or concrete structures based on steel bar structures, the wall body made of the materials often consumes a large amount of manpower and material resources in installation, the wall body is positioned in an auxiliary mode through steel nails after being installed, when the wall body is subjected to external force, looseness easily occurs, collapse occurs, and great threat is caused to life health of people. And the installation and the spacing of wall body need consume a large amount of manpower and materials, and the installation is complicated inconvenient.
Disclosure of Invention
It is an object of the present invention to provide a pre-assembled building module that solves at least one of the above problems.
The invention discloses a preassembled building module, which adopts the following technical scheme:
a pre-installed building module comprises a pre-buried foundation, a foundation base, a supporting assembly, a placing plate, a wall body and a first limiting assembly;
the foundation base is provided with a groove, the opening of the groove is upward, and the front side wall and the rear side wall of the groove are provided with a plurality of notches;
the supporting component comprises a buffer device, and the buffer device comprises a hinge frame, a guide post, a first hinge block, a buffer post, a spring, an extension bar and a second hinge block; the first hinge block and the second hinge block are sequentially arranged on the bottom surface of the second groove at intervals along the left-right direction; the upper end of the guide post is rotatably arranged at the left end of the hinge frame, and the lower end of the guide post is rotatably arranged on the first hinge block; the upper end of the extension bar is rotatably arranged at the right end of the hinge frame, the bottom end of the buffer column is rotatably arranged on the second hinge block, a sliding cavity with an upward opening is arranged in the buffer column, and the extension bar is slidably arranged in the sliding groove; the spring is arranged in the sliding cavity, the lower end of the spring is in contact with and abutted against the bottom surface of the sliding cavity, and the upper end of the spring is in contact with and abutted against the lower end surface of the extension bar; the extension bar slides into the sliding groove and compresses the spring in the process that the guide post rotates rightwards and downwards;
the placing plate is a horizontal plate and extends along the left and right directions;
the front side wall and the rear side wall of the bottom of the wall body are both provided with positioning grooves, and the positioning grooves extend from the right lower end to the left upper end of the positioning grooves; the wall body is arranged on the placing plate, and the placing plate is arranged on the upper surface of the hinge frame, so that the wall body and the placing plate rotate rightwards and downwards along with the hinge frame;
the first limiting assemblies comprise a plurality of guiding blocks and limiting columns; the guide block comprises a first block part and a second block part which are perpendicular to each other and the ends of which are connected together, the first block part is vertically arranged, and the second block part is arranged at the lower end of the first block part; the limiting column is arranged at the upper end of the first block part, and the limiting column and the second block part are positioned at the same side of the first block part; first piece portion articulates in the breach around the horizontal axis that extends about, and the second piece position is in the downside of placing the board to make the wall body along with placing the board and drive first piece portion rotation through second piece portion in the downward and right pivoted in-process, thereby make spacing post rotate and insert in the constant head tank of wall body, and remove along the constant head tank.
Furthermore, the prefabricated building module also comprises a second limiting assembly, wherein the second limiting assembly comprises end positioning blocks, four horizontal bottom plates and two vertical side plates; the end positioning blocks are arranged at the left end and the right end of the upper surface of the placing plate, and the wall body is arranged on the placing plate and is positioned between the two end positioning blocks;
the four horizontal bottom plates are divided into two groups and are arranged on the front side and the rear side of the placing plate at intervals along the left and right directions respectively, the four vertical side plates are connected to the four horizontal bottom plates respectively and are located on the upper sides of the horizontal bottom plates, and the wall body is installed on the placing plate and located between the vertical side plates.
Furthermore, the middle part of the lower surface of the placing plate is provided with a limit groove; the supporting component further comprises a supporting block, the supporting block is installed in the center of the bottom surface of the groove, and after the extension bar and the guide post move to the position, on the same horizontal line, of the extension bar and the guide post, the supporting block is inserted into the limiting groove.
Furthermore, the preassembled building module also comprises a reinforcing component, wherein the reinforcing component comprises a positioning bolt, a sealing plate and a convex thorn;
the limiting column is provided with a through hole extending along the front-back direction;
the positioning bolt comprises a disc seat, a cylinder and a cone, the axis of the disc seat extends along the horizontal direction, the disc seat and the cone are respectively positioned at the outer end and the inner end of the cylinder, and the cylinder is inserted into the through hole;
the cylinder body is internally provided with an airflow channel, an air cavity and a convex thorn hole, the airflow channel extends along the front and back direction, the outer end of the airflow channel penetrates through the disc seat, the inner end of the airflow channel is communicated with the air cavity, the convex thorn hole is communicated with the air cavity, and the convex thorn hole penetrates through the peripheral wall of the cylinder body;
the sealing plate is installed in the outside of air cavity, and protruding thorn is installed on the sealing plate and is inserted protruding thorn downthehole, and the air current flows in the air cavity through airflow channel, promotes the sealing plate, and then drives protruding thorn and insert the wall body.
Furthermore, two buffering devices are arranged on the left side and the right side of the supporting block.
Furthermore, the number of foundation bases and the number of wall bodies are four; each wall body is arranged on the foundation base through a supporting component, a placing plate and a first limiting component; the foundation bases are connected end to form a rectangle; the prefabricated building module further comprises four wall positioning frames, and each wall positioning frame is arranged at the joint of the two walls.
Furthermore, the grooves comprise a first groove and a second groove, the opening of the first groove faces upwards, and the first groove extends along the left-right direction; a plurality of gaps are arranged on the side wall of the first groove, the second groove is arranged on the bottom surface of the first groove, the length of the bottom surface of the first groove is larger than that of the bottom surface of the second groove, and the right end of the placing plate is in contact with the right end of the first groove.
The invention has the beneficial effects that: the wall positioning device has the advantages that the wall can be positioned by matching the limiting columns with the arc-shaped positioning grooves, the wall is prevented from shaking up and down to be loosened under the influence of external force, the wall is horizontally limited and fixed on the placing plate through the end positioning blocks, the horizontal bottom plate and the side plates, and the wall is connected with the wall through the wall positioning frame. On the other hand, in the middle of the downward and rightward motion process of board along with placing at the wall body, place the board and act on articulated frame, further articulated frame promotes extension bar, extension bar extrusion spring to compression, and buffer plays the cushioning effect to whole board and wall body of placing, has protected the part. And finally, the reinforcing component is reused to reinforce the wall body, so that the connection between the wall body and the placing plate is more stable.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic front view of the construction of an embodiment of a pre-assembled building module according to the invention;
FIG. 2 is a schematic view of a foundation base structure in the embodiment of the pre-assembled building module of FIG. 1;
FIG. 3 is a schematic side view of a wall structure in an embodiment of the pre-assembled building module of FIG. 1;
FIG. 4 is an enlarged view of the arcuate positioning slot configuration of the embodiment of the pre-assembled building module of FIG. 1;
FIG. 5 is a subjective view of the foundation base structure of the embodiment of the pre-assembled building module of FIG. 1;
FIG. 6 is a schematic view of the internal structure of the foundation base in the embodiment of the pre-assembled building module of FIG. 1;
FIG. 7 is a schematic view of the structural attachment of the support blocks in the embodiment of the pre-assembled building module of FIG. 1;
FIG. 8 is a schematic view of a placement board in the embodiment of the pre-assembled building module of FIG. 1;
FIG. 9 is a schematic view of the internal structure of the cushioning mechanism in the embodiment of the pre-assembled building module of FIG. 1;
FIG. 10 is a front view of a positioning bolt arrangement in an embodiment of the pre-assembled building module of FIG. 1;
fig. 11 is an enlarged view of the structure at B in fig. 10.
1. Pre-burying a foundation; 2. a foundation base; 3. a wall body; 4. a guide block; 5. a limiting column; 6. positioning a groove; 7. placing the plate; 8. an end positioning block; 9. a horizontal floor; 10. a side plate; 11. a limiting groove; 12. a support block; 13. a hinged frame; 14. a guide post; 15. a first hinge block; 16. a buffer column; 17. lengthening a rod; 18. a second hinge block; 19. a spring; 20. positioning the bolt; 21. an air cavity; 22. a sealing plate; 23. convex thorns; 24. wall locating rack.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention relates to the field of buildings and has strong practicability, and the embodiment of a preassembled building module is shown in figures 1-11 and comprises a pre-buried foundation 1, a foundation base 2, a supporting component, a placing plate 7, a wall body 3, a first limiting component and a second limiting component.
The foundation base 2 has a first groove and a second groove, the opening of the first groove faces upward, and the first groove extends in the left-right direction. A plurality of notches are formed in the side wall of the first groove. The second recess is seted up on the bottom surface of first recess, and the length of the bottom surface of first recess is greater than the length of the bottom surface of second recess, can establish the basis for the support and the spacing of wall body.
The support assembly includes a cushioning device comprising a hinged frame 13, a guide post 14, a first hinged block 15, a cushioning post 16, a spring 19, an extension bar 17 and a second hinged block 18. The first hinging block 15 and the second hinging block 18 are sequentially arranged on the bottom surface of the second groove at intervals along the left-right direction. The upper end of the guide post 14 is rotatably mounted to the left end of the hinge bracket 13, and the lower end of the guide post 14 is rotatably mounted to the first hinge block 15. The upper end of extension bar 17 is rotationally installed in the right-hand member of articulated frame 13, and the bottom of bumping post 16 is rotationally installed in second articulated piece 18, is provided with the smooth chamber that the opening is up in the bumping post 16, and extension bar 17 slidable installs in the spout.
The spring 19 is arranged in the sliding cavity, the lower end of the spring 19 is contacted and abutted with the bottom surface of the sliding cavity, and the upper end of the spring 19 is contacted and abutted with the lower end surface of the extension bar 17. The extension bar 17 slides into the sliding groove and compresses the spring 19 in the process of turning the guide post 14 to the right and downward, finally moving the extension bar 17 and the guide post 14 to the position where the extension bar 17 and the guide post 14 are on the same horizontal line.
The placement plate 7 is a horizontal plate extending in the left-right direction. The constant head tank has all been seted up on the lateral wall around the wall body 3 bottom, and constant head tank 6 extends to its upper left end from its right lower extreme, and preferably constant head tank 6 becomes dark and narrows down gradually to its upper left end from its right lower extreme. The wall body 3 is installed on the placing plate 7, and the placing plate 7 is installed on the upper surfaces of the two hinge brackets 13, so that the wall body 3 and the placing plate 7 are rotated rightward and downward along with the hinge brackets 13.
The first limiting assembly comprises a plurality of guiding blocks 4 and limiting columns 5.
The guide block 4 comprises a first block part and a second block part which are perpendicular to each other and are connected through end parts, the first block part is vertically arranged, and the second block part is arranged at the lower end of the first block part. Spacing post 5 is installed in the upper end of first block portion, and spacing post 5 and second block portion are in the same one side of first block portion.
First piece portion articulates in the breach around the horizontal axis that extends about, and the second piece position is in the downside of placing board 7 to make wall body 3 along with place board 7 and drive first piece portion rotation through second piece portion in the downward and right pivoted in-process, thereby make spacing post 5 rotate and insert 6 in the constant head tank of wall body, and move along constant head tank 6.
Place on placing board 7 when wall body 3, the spacing subassembly of accessible second carries on spacingly, further promote wall body 3, in wall body 3 along with place board 7 in the middle of the downward and rightward motion process, place board 7 and act on articulated frame 13, further articulated frame 13 promotes extension bar 17, extension bar 17 extrusion spring 19 to compression, buffer converts the state of shrink into from the state of extension, and then to whole board 7 and the wall body 3 of placing play the cushioning effect, wall body 3 has been protected, place board 7 and ground base 2, the service life of the device is prolonged.
At wall body 3's decline in-process, place board 7 extrusion and lead a piece 4 for lead a piece 4 rotation, drive spacing post 5 and insert the inside of constant head tank 6, can prevent like this that wall body 3 is not hard up from top to bottom, carry out spacing fixed to wall body 3. When an earthquake happens suddenly, the ground always vibrates, the traditional wall body 3 always collapses, but the stability of the wall body 3 is greatly improved due to the action of the limiting columns 5 and the positioning grooves 6 in the structure, and the life safety of people is guaranteed.
The second limiting assembly comprises end positioning blocks 8, horizontal bottom plates 9 and vertical side plates 10, the number of the horizontal bottom plates 9 and the number of the vertical side plates 10 are four, and the number of the end positioning blocks 8 is two. The end positioning blocks 8 are disposed at the left and right ends of the upper surface of the placing plate 7, and the end positioning blocks 8 can limit the wall 3 from sliding left and right after the wall 3 is mounted on the placing plate 7.
Four horizontal base plate 9 divide into two sets ofly, follow left right direction interval respectively and set up on placing board 7 two sides around, and four vertical curb plates 10 are connected respectively in four horizontal base plate 9, and are in the upside of horizontal base plate 9, along with wall body 3 installs in placing board 7 back, and the bottom surface of wall body 3 is installed on horizontal base plate 9, and vertical curb plate 10 has restricted wall body 3 and has slided around in both sides around wall body 3 respectively. This allows the wall 3 to be more securely mounted to the resting plate 7.
The middle part of the lower surface of the placing plate 7 is provided with a limiting groove 11. The supporting block 12 is installed at the center of the bottom surface of the second groove such that the supporting block 12 is inserted into the limiting groove 11 after the extension bar 17 and the guide post 14 move to a position where the extension bar 17 and the guide post 14 are on the same horizontal line. Buffer is two, and two buffer set up in the left and right sides of supporting shoe 12 to the board 7 is being placed in the messenger and the board 7 is being placed and carrying out better support to placing board 7 and wall body 3 after the completion of obtaining better buffering and placing in the motion process downwards and right. The right end of the placing plate 7 is in contact with the right end of the first groove. Can make like this to place the board and reach static firm support, increase the supporting effect.
The pre-assembled building module further comprises a reinforcement assembly comprising a positioning bolt 20, a sealing plate 22, and a spur 23.
The limiting column 5 is provided with a through hole extending in the front-back direction, the positioning bolt 20 comprises a disc seat, a cylinder and a cone head, the axis of the disc seat extends in the horizontal direction, the disc seat and the cone head are respectively positioned at the outer end and the inner end of the cylinder, and the cylinder is inserted into the through hole. An air flow channel, an air cavity 21 and a convex thorn hole are arranged in the cylinder body, the air flow channel extends along the front-back direction, the outer end of the air flow channel penetrates through the disc seat, the inner end of the air flow channel is communicated with the air cavity 21, the convex thorn hole is communicated with the air cavity, and the convex thorn hole penetrates through the peripheral wall of the cylinder body. The sealing plate 22 is arranged on the outer side of the air cavity, the convex thorns 23 are arranged on the sealing plate and inserted into the convex thorns, and the air flow enters the air cavity 21 through the air flow channel, pushes the sealing plate 22 and further drives the convex thorns 23 to be inserted into the wall body. The wall body is more stable and can not be toppled. Specifically, the inlet of the air flow channel can be communicated with a high-pressure air pump.
The foundation bases 2 and the walls 3 are four. Each wall body 3 is installed in foundation bed 2 through supporting component, placing board 7 and first spacing subassembly. 2 end to end of foundation base constitute the rectangle, and this prepackage type building module still includes four wall locating rack 24, and every wall locating rack 24 sets up in the junction of two wall bodies 3, and wall locating rack 24 can realize being connected between wall body 3 and the wall body 3.
The working process of the preassembled building module comprises the following steps: at first place wall body 3 on placing board 7, tip locating piece 8 and lateral part locating plate 10 will insert the screens inslot that wall body 3 both ends and both sides were reserved respectively simultaneously, fix wall body 3, then promote wall body 3, wall body 3 will drive and place board 7 and rotate along with guide post 14, still can drive extension bar 17 extrusion spring 19 simultaneously, spring 19 compression produces elasticity, and supporting shoe 12 will insert the inside of spacing groove 11 simultaneously, and wall body 3 still can extrude guide block 4 at the in-process that the slope descends, makes guide block 4 rotatory, drives spacing post 5 and inserts the inside of constant head tank 6.
After the wall body 3 is installed, the positioning bolts 20 are driven into the wall body 3, the air flow flows into the air cavity 21 through the air flow channel by the high-pressure air pump, then the air flow pushes the sealing plate 22, the convex thorns 23 are driven to be inserted into the wall body 3, the effect of reinforcing the wall body 3 is achieved, and the wall body 3 is fixedly connected with the wall body 3 through the wall body positioning frame.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (7)

1. A pre-installed building module comprises a pre-embedded foundation, and is characterized by further comprising a foundation base, a supporting assembly, a placing plate, a wall body and a first limiting assembly;
the foundation base is provided with a groove, the opening of the groove is upward, and the front side wall and the rear side wall of the groove are provided with a plurality of notches;
the supporting component comprises a buffer device, and the buffer device comprises a hinge frame, a guide post, a first hinge block, a buffer post, a spring, an extension bar and a second hinge block; the first hinge block and the second hinge block are sequentially arranged on the bottom surface of the second groove at intervals along the left-right direction; the upper end of the guide post is rotatably arranged at the left end of the hinge frame, and the lower end of the guide post is rotatably arranged on the first hinge block; the upper end of the extension bar is rotatably arranged at the right end of the hinge frame, the bottom end of the buffer column is rotatably arranged on the second hinge block, a sliding cavity with an upward opening is arranged in the buffer column, and the extension bar is slidably arranged in the sliding groove; the spring is arranged in the sliding cavity, the lower end of the spring is in contact with and abutted against the bottom surface of the sliding cavity, and the upper end of the spring is in contact with and abutted against the lower end surface of the extension bar; the extension bar slides into the sliding groove and compresses the spring in the process that the guide post rotates rightwards and downwards;
the placing plate is a horizontal plate and extends along the left and right directions;
the front side wall and the rear side wall of the bottom of the wall body are both provided with positioning grooves, and the positioning grooves extend from the right lower end to the left upper end of the positioning grooves; the wall body is arranged on the placing plate, and the placing plate is arranged on the upper surface of the hinge frame, so that the wall body and the placing plate rotate rightwards and downwards along with the hinge frame;
the first limiting assemblies comprise a plurality of guiding blocks and limiting columns; the guide block comprises a first block part and a second block part which are perpendicular to each other and the ends of which are connected together, the first block part is vertically arranged, and the second block part is arranged at the lower end of the first block part; the limiting column is arranged at the upper end of the first block part, and the limiting column and the second block part are positioned at the same side of the first block part; first piece portion articulates in the breach around the horizontal axis that extends about, and the second piece position is in the downside of placing the board to make the wall body along with placing the board and drive first piece portion rotation through second piece portion in the downward and right pivoted in-process, thereby make spacing post rotate and insert in the constant head tank of wall body, and remove along the constant head tank.
2. A pre-assembled building module according to claim 1, further comprising a second stop assembly,
the second limiting assembly comprises end positioning blocks, four horizontal bottom plates and two vertical side plates; the end positioning blocks are arranged at the left end and the right end of the upper surface of the placing plate, and the wall body is arranged on the placing plate and is positioned between the two end positioning blocks;
the four horizontal bottom plates are divided into two groups and are arranged on the front side and the rear side of the placing plate at intervals along the left and right directions respectively, the four vertical side plates are connected to the four horizontal bottom plates respectively and are located on the upper sides of the horizontal bottom plates, and the wall body is installed on the placing plate and located between the vertical side plates.
3. A pre-assembled building module according to claim 1, wherein: the middle part of the lower surface of the placing plate is provided with a limiting groove; the supporting component further comprises a supporting block, the supporting block is installed in the center of the bottom surface of the groove, and after the extension bar and the guide post move to the position, on the same horizontal line, of the extension bar and the guide post, the supporting block is inserted into the limiting groove.
4. A pre-assembled building module according to claim 1, wherein: also comprises a reinforcing component which is arranged on the outer wall of the shell,
the reinforcing component comprises a positioning bolt, a sealing plate and a convex thorn;
the limiting column is provided with a through hole extending along the front-back direction;
the positioning bolt comprises a disc seat, a cylinder and a cone, the axis of the disc seat extends along the horizontal direction, the disc seat and the cone are respectively positioned at the outer end and the inner end of the cylinder, and the cylinder is inserted into the through hole;
the cylinder body is internally provided with an airflow channel, an air cavity and a convex thorn hole, the airflow channel extends along the front and back direction, the outer end of the airflow channel penetrates through the disc seat, the inner end of the airflow channel is communicated with the air cavity, the convex thorn hole is communicated with the air cavity, and the convex thorn hole penetrates through the peripheral wall of the cylinder body;
the sealing plate is installed in the outside of air cavity, and protruding thorn is installed on the sealing plate and is inserted protruding thorn downthehole, and the air current flows in the air cavity through airflow channel, promotes the sealing plate, and then drives protruding thorn and insert the wall body.
5. A pre-assembled building module according to claim 3, wherein: the two buffering devices are arranged on the left side and the right side of the supporting block.
6. A pre-assembled building module according to claim 1, wherein: the number of foundation bases and the number of wall bodies are four; each wall body is arranged on the foundation base through a supporting component, a placing plate and a first limiting component; the foundation bases are connected end to form a rectangle; the prefabricated building module further comprises four wall positioning frames, and each wall positioning frame is arranged at the joint of the two walls.
7. A pre-assembled building module according to claim 1, wherein: the grooves comprise a first groove and a second groove, the opening of the first groove faces upwards, and the first groove extends along the left-right direction; a plurality of gaps are arranged on the side wall of the first groove, the second groove is arranged on the bottom surface of the first groove, the length of the bottom surface of the first groove is larger than that of the bottom surface of the second groove, and the right end of the placing plate is in contact with the right end of the first groove.
CN202010810541.6A 2020-08-13 2020-08-13 Prepackage type building module Expired - Fee Related CN111926942B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010810541.6A CN111926942B (en) 2020-08-13 2020-08-13 Prepackage type building module

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010810541.6A CN111926942B (en) 2020-08-13 2020-08-13 Prepackage type building module

Publications (2)

Publication Number Publication Date
CN111926942A true CN111926942A (en) 2020-11-13
CN111926942B CN111926942B (en) 2021-12-17

Family

ID=73310541

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010810541.6A Expired - Fee Related CN111926942B (en) 2020-08-13 2020-08-13 Prepackage type building module

Country Status (1)

Country Link
CN (1) CN111926942B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113653213A (en) * 2021-08-25 2021-11-16 肖如刚 Assembly type green building and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180171627A1 (en) * 2009-01-20 2018-06-21 Skidmore Owings & Merrill Llp Precast wall panels and method of erecting a high-rise building using the panels
CN108797856A (en) * 2018-06-09 2018-11-13 重庆铝途新型材料有限公司 A kind of aluminum curtain walls being easily installed dismounting
CN109972727A (en) * 2019-03-22 2019-07-05 许世忠 A kind of assembled steel Reinforced Concrete Buildings
CN110306682A (en) * 2019-07-05 2019-10-08 江苏博拓新型建筑材料有限公司 A kind of assembled architecture anti-seismic structure using cement prefabricated component
CN110670752A (en) * 2019-09-26 2020-01-10 沛县宝业建筑工业化有限公司 Assembled building shock-absorbing structure
CN210421388U (en) * 2019-07-03 2020-04-28 福建同坤建设有限公司 Shock attenuation formula building house

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180171627A1 (en) * 2009-01-20 2018-06-21 Skidmore Owings & Merrill Llp Precast wall panels and method of erecting a high-rise building using the panels
CN108797856A (en) * 2018-06-09 2018-11-13 重庆铝途新型材料有限公司 A kind of aluminum curtain walls being easily installed dismounting
CN109972727A (en) * 2019-03-22 2019-07-05 许世忠 A kind of assembled steel Reinforced Concrete Buildings
CN210421388U (en) * 2019-07-03 2020-04-28 福建同坤建设有限公司 Shock attenuation formula building house
CN110306682A (en) * 2019-07-05 2019-10-08 江苏博拓新型建筑材料有限公司 A kind of assembled architecture anti-seismic structure using cement prefabricated component
CN110670752A (en) * 2019-09-26 2020-01-10 沛县宝业建筑工业化有限公司 Assembled building shock-absorbing structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113653213A (en) * 2021-08-25 2021-11-16 肖如刚 Assembly type green building and construction method thereof

Also Published As

Publication number Publication date
CN111926942B (en) 2021-12-17

Similar Documents

Publication Publication Date Title
CN111962683B (en) Prefabricated house and construction method thereof
CN108049704B (en) Municipal works rail that can height-adjusting
CN111926942B (en) Prepackage type building module
CN213233491U (en) Supporting construction convenient to operation installation
CN113089845A (en) High-stability assembly type building fixing base
CN112031245A (en) Building roof truss, building roof and supporting structure of building
KR100886343B1 (en) The ascent and descent where the assembly dissolution is possible just the infrastructure
CN111306411B (en) Embedded household appliance fixing device
KR101001650B1 (en) Concrete form
CN211396533U (en) Adjustable support frame for constructional engineering
KR102270455B1 (en) Carstopper installation apparatus
KR101279775B1 (en) Pagora
CN219711024U (en) Steel construction platform convenient to installation
CN214328886U (en) Building foundation construction supporting template
CN216276153U (en) Node of post-beam post construction
CN216043495U (en) Assembled staircase structure for interior decoration
CN213999369U (en) Liftable beam support structure
CN215112973U (en) Vibration/noise reduction air conditioner support
CN210946595U (en) Road gate
CN218373562U (en) Highway anticollision buffer
CN220746996U (en) Construction elevator foundation structure on backfill soil
CN211818593U (en) Quick mounting structure of cement fence encryption net
CN219909313U (en) Prefabricated connection structure of assembled building
CN217557606U (en) Climb frame with attaching dustproof apron of wall support
CN215926276U (en) Assembled steel construction building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20211201

Address after: 350000 floor 6, block B, Yuefeng industry and trade building, No. 126, Fuxin Middle Road, Jin'an District, Fuzhou City, Fujian Province

Applicant after: Fuzhou Construction Engineering Management Co.,Ltd.

Address before: 451450 Da Meng Xiang, Zhongmou County, Zhengzhou City, Henan Province

Applicant before: Zhou Zengqiang

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211217