CN111893262A - Heat treatment process of rust-proof and corrosion-proof steel - Google Patents

Heat treatment process of rust-proof and corrosion-proof steel Download PDF

Info

Publication number
CN111893262A
CN111893262A CN202010870795.7A CN202010870795A CN111893262A CN 111893262 A CN111893262 A CN 111893262A CN 202010870795 A CN202010870795 A CN 202010870795A CN 111893262 A CN111893262 A CN 111893262A
Authority
CN
China
Prior art keywords
steel
rust
proof
quenching
tempering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010870795.7A
Other languages
Chinese (zh)
Inventor
王晓东
魏世忠
周玉成
张程
江涛
邹悟会
徐超
林乙丑
聂新林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Science and Technology
Original Assignee
Henan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Science and Technology filed Critical Henan University of Science and Technology
Priority to CN202010870795.7A priority Critical patent/CN111893262A/en
Publication of CN111893262A publication Critical patent/CN111893262A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D1/00General methods or devices for heat treatment, e.g. annealing, hardening, quenching or tempering
    • C21D1/18Hardening; Quenching with or without subsequent tempering
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05DPROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05D7/00Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials
    • B05D7/14Processes, other than flocking, specially adapted for applying liquids or other fluent materials to particular surfaces or for applying particular liquids or other fluent materials to metal, e.g. car bodies
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D1/00General methods or devices for heat treatment, e.g. annealing, hardening, quenching or tempering
    • C21D1/18Hardening; Quenching with or without subsequent tempering
    • C21D1/25Hardening, combined with annealing between 300 degrees Celsius and 600 degrees Celsius, i.e. heat refining ("Vergüten")
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D1/00General methods or devices for heat treatment, e.g. annealing, hardening, quenching or tempering
    • C21D1/26Methods of annealing
    • C21D1/30Stress-relieving
    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C8/00Solid state diffusion of only non-metal elements into metallic material surfaces; Chemical surface treatment of metallic material by reaction of the surface with a reactive gas, leaving reaction products of surface material in the coating, e.g. conversion coatings, passivation of metals
    • C23C8/40Solid state diffusion of only non-metal elements into metallic material surfaces; Chemical surface treatment of metallic material by reaction of the surface with a reactive gas, leaving reaction products of surface material in the coating, e.g. conversion coatings, passivation of metals using liquids, e.g. salt baths, liquid suspensions
    • C23C8/42Solid state diffusion of only non-metal elements into metallic material surfaces; Chemical surface treatment of metallic material by reaction of the surface with a reactive gas, leaving reaction products of surface material in the coating, e.g. conversion coatings, passivation of metals using liquids, e.g. salt baths, liquid suspensions only one element being applied
    • C23C8/48Nitriding
    • C23C8/50Nitriding of ferrous surfaces
    • CCHEMISTRY; METALLURGY
    • C23COATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; CHEMICAL SURFACE TREATMENT; DIFFUSION TREATMENT OF METALLIC MATERIAL; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL; INHIBITING CORROSION OF METALLIC MATERIAL OR INCRUSTATION IN GENERAL
    • C23CCOATING METALLIC MATERIAL; COATING MATERIAL WITH METALLIC MATERIAL; SURFACE TREATMENT OF METALLIC MATERIAL BY DIFFUSION INTO THE SURFACE, BY CHEMICAL CONVERSION OR SUBSTITUTION; COATING BY VACUUM EVAPORATION, BY SPUTTERING, BY ION IMPLANTATION OR BY CHEMICAL VAPOUR DEPOSITION, IN GENERAL
    • C23C8/00Solid state diffusion of only non-metal elements into metallic material surfaces; Chemical surface treatment of metallic material by reaction of the surface with a reactive gas, leaving reaction products of surface material in the coating, e.g. conversion coatings, passivation of metals
    • C23C8/60Solid state diffusion of only non-metal elements into metallic material surfaces; Chemical surface treatment of metallic material by reaction of the surface with a reactive gas, leaving reaction products of surface material in the coating, e.g. conversion coatings, passivation of metals using solids, e.g. powders, pastes

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Organic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Metallurgy (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Crystallography & Structural Chemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Health & Medical Sciences (AREA)
  • Child & Adolescent Psychology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Wood Science & Technology (AREA)
  • Heat Treatment Of Articles (AREA)

Abstract

The invention discloses a heat treatment process of rust-proof and corrosion-proof steel, which comprises the following steps: s1: selecting proper steel, cleaning the steel, and wiping the steel which is hard by rust spots by using steel wires; the steel with lower hardness should be wiped by cotton cloth; after the surface of the steel is cleaned and tightened, carrying out quenching and tempering treatment on the steel; s2: quenching the steel by a box-type resistance furnace at a proper quenching temperature of 850 ℃ for 20-25 min; the method has simple process, and can ensure that the steel has good structural stability and structural strength by carrying out normal quenching and tempering treatment on the steel; in addition, in the heat treatment process, the steel is subjected to salt bath soft nitriding treatment, vacuum zincification treatment and paint coating treatment, so that the steel has good corrosion prevention and rust prevention effects, the performance of the steel is effectively improved, and the service life of the steel is prolonged.

Description

Heat treatment process of rust-proof and corrosion-proof steel
Technical Field
The invention relates to the technical field of steel heat treatment, in particular to a heat treatment process of rust-proof and corrosion-proof steel.
Background
The heat treatment of steel is a process of putting a steel workpiece in a certain medium to be heated to a proper temperature, keeping the temperature for a certain time, cooling the steel workpiece in different media at different speeds, and controlling the performance of the steel workpiece by changing the microstructure of the surface or the interior of a metal material; the potential of steel can be fully exerted through heat treatment, the service performance of the workpiece is improved, the weight of the workpiece is reduced, materials are saved, the cost is reduced, and the service life of the workpiece can be prolonged.
In the steel heat treatment process in the prior art, when water cooling is needed to be carried out on steel in the processing process, the cooling rate of the steel is slow, so that the performance of the steel is influenced; meanwhile, in the heat treatment process of steel, the processes of corrosion prevention and rust prevention treatment of steel are poor, so that it is necessary to design a heat treatment process of rust-proof and corrosion-prevention steel.
Disclosure of Invention
The invention aims to provide a heat treatment process of rust-proof and corrosion-proof steel, which is simple in process, and can enable the steel to have good structural stability and structural strength by carrying out normal quenching and tempering treatment on the steel; in addition, in the heat treatment process, the steel is subjected to salt bath soft nitriding treatment, vacuum zincification treatment and paint coating treatment, so that the steel has good corrosion prevention and rust prevention effects, the performance of the steel is effectively improved, and the service life of the steel is prolonged.
The purpose of the invention can be realized by the following technical scheme:
a heat treatment process of rust-proof and corrosion-proof steel comprises the following steps:
s1: selecting proper steel, cleaning the steel, and wiping the steel which is hard by rust spots by using steel wires; the steel with lower hardness should be wiped by cotton cloth; after the surface of the steel is cleaned and tightened, carrying out quenching and tempering treatment on the steel;
s2: quenching the steel through a box type resistance furnace, selecting a proper quenching temperature which is 850 ℃ to quench the steel, carrying out quenching heat preservation for 20-25min, cooling the steel after quenching, transferring the steel to an electric heating nitrogen protection tempering furnace for tempering treatment after cooling, wherein the tempering temperature is 740 ℃, the tempering heat preservation is 60-65min, and carrying out cooling treatment again after finishing the tempering heat preservation;
s3: carrying out stress relief annealing treatment on the steel so as to eliminate residual stress generated in the machining process of the steel; during stress relief annealing, after the steel is slowly heated to 550 ℃, annealing and heat preservation are carried out for 2.5 hours, air cooling treatment is carried out after annealing is finished, the annealed steel is slowly cooled by air, the annealed steel is transferred into a salt bath tufftride furnace, treatment is carried out for 2-3 hours at the temperature of 550-600 ℃, so that the steel is subjected to salt bath tufftride, low-temperature tempering is required for reducing the residual stress and the brittleness of the steel, the tempering temperature is 160 ℃, heat preservation is carried out for 1.5 hours, and water cooling is carried out through water cooling equipment after heat preservation is finished;
s4: polishing the steel subjected to salt bath soft nitriding by using polishing equipment, removing a loose layer on the nitride outer layer on the surface of the steel, performing infiltration treatment on the polished steel by using a vacuum heating furnace, taking zinc powder as a raw material, and in a rotating closed container, contacting the heated steel with zinc powder under a vacuum condition, so that a zinc-iron alloy infiltration layer can be formed on the surface layer of a matrix of the steel, and an anti-rust layer is formed on the surface of the steel;
s5: performing anticorrosive coating on the steel obtained by heat treatment, selecting proper anticorrosive coating, and performing brushing treatment on the steel to sequentially form a primer layer, an intermediate paint layer and an outer paint layer on the surface of the steel; in the process of painting the paint layer, after the first painting is finished, a certain time gap is kept, after the first drying, the second painting is carried out, the painting direction of the second painting is perpendicular to the painting direction of the first painting, so that the thickness of the paint film is uniform and consistent, after the primer is painted, steel and the paint surface are dried, and after the drying, the rust-proof and corrosion-resistant steel is prepared.
As a further scheme of the invention: in the step S2, the cooling medium used in the cooling process is oil quenching during the quenching and tempering.
As a further scheme of the invention: in the step S5, the primer layer of the steel is an epoxy zinc-rich primer, the intermediate paint layer of the steel is an epoxy micaceous iron intermediate paint, and the outer paint layer of the steel is an acrylic polyurethane finish paint.
As a further scheme of the invention: the thickness of the primer layer is 50-60 μm; the thickness of the intermediate paint layer is 70-80 μm; the thickness of the outer paint surface layer is 60-70 μm;
as a further scheme of the invention: in the step S3, the water cooling equipment includes a chassis, a feed chute, a sealing cover plate, a material conveying assembly, a smoke exhaust assembly, a striker plate, a drainage assembly, a water injection pipe, a hydraulic station and a frame, the feed chute is arranged on one side of the top end surface of the chassis, the sealing cover plate is fixedly arranged on one side of the end surface of the feed chute through a hinge, the striker plate is fixedly arranged on the bottom of the inner side of the feed chute, the drainage assembly is arranged on one side of the outer portion of the striker plate, the water injection pipe is inserted and installed on the other side of the outer portion of the striker plate, the smoke exhaust assembly is arranged on the other side of the top end surface of the chassis, the hydraulic station is fixedly installed on one side of the bottom end surface of the chassis through a screw, the material;
defeated material subassembly includes pneumatic cylinder, guide holder, hydraulic stem, material platform, material frame and supporting link, pneumatic cylinder fixed mounting is in the inside at hydraulic pressure station, the top terminal surface connection of pneumatic cylinder installs the guide holder, and the guide holder is located the inside of quick-witted case, the hydraulic stem is installed in the inside grafting of pneumatic cylinder, and the one end of hydraulic stem passes the guide holder and connects and install the material platform, the top terminal surface fixed mounting of material platform has two material frames, and has the supporting link through welded fastening between the material frame.
As a further scheme of the invention: and drain holes are formed in the periphery of the end face of the material rack.
As a further scheme of the invention: the drainage component comprises a filter frame, a drain pipe, a motor shell, a driving motor and a spiral blade, wherein the filter frame is fixedly installed at one end of the material baffle plate, the drain pipe is installed on one side of the bottom of the filter frame in an inserting mode, the motor shell is fixedly installed on one side of the outside of the case through bolts, the driving motor is fixedly installed on one side of the inside of the motor shell, the spiral blade is installed on one end of the driving motor in a connecting mode, and the spiral blade is located inside the case.
As a further scheme of the invention: the exhaust assembly comprises an equipment box, an exhaust pump, a drying cylinder, an exhaust pipe and a flow guide cover, wherein the equipment box is fixedly installed at the other side of the top of the case through bolts, the exhaust pump is fixedly installed inside the equipment box, one end of the bottom of the exhaust pump is connected with the flow guide cover, the flow guide cover is located at the top of the inner side of the case, the drying cylinder is installed on the end face of the top of the exhaust pump, and the exhaust pipe is installed on the top of the drying cylinder in an inserted mode.
The invention has the beneficial effects that:
1. the method has simple process, and can ensure that the steel has good structural stability and structural strength by carrying out normal quenching and tempering treatment on the steel; in addition, in the heat treatment process, the steel is subjected to salt bath soft nitriding treatment, vacuum zincification treatment and paint surface brushing treatment, so that the steel has good corrosion prevention and rust prevention effects, the performance of the steel is effectively improved, and the service life of the steel is prolonged;
2. in the processing process, when the steel needs to be water-cooled, water cooling is carried out through water cooling equipment; the feeding and discharging are convenient and fast, and the flowing speed of cold water can be increased, so that the cooling speed of steel is increased; meanwhile, in the water cooling process, the water vapor can be dried and discharged.
Drawings
In order to facilitate understanding for those skilled in the art, the present invention will be further described with reference to the accompanying drawings.
FIG. 1 is a schematic view of the overall structure of the water cooling apparatus of the present invention;
FIG. 2 is an overall sectional view of the water cooling apparatus of the present invention;
FIG. 3 is a schematic structural diagram of a material conveying assembly of the water cooling apparatus of the present invention;
in the figure: 1. a chassis; 2. a feed chute; 3. sealing the cover plate; 4. a material conveying component; 5. a smoke evacuation assembly; 6. a striker plate; 7. a drainage assembly; 8. a water injection pipe; 9. a hydraulic station; 10. a frame; 41. a hydraulic cylinder; 42. a guide seat; 43. a hydraulic lever; 44. a material table; 45. a material rack; 46. a support link; 51. an equipment box; 52. an exhaust pump; 53. a drying cylinder; 54. an exhaust pipe; 55. a pod; 71. a filter frame; 72. a drain pipe; 73. a motor housing; 74. a drive motor; 75. helical leaves.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the following embodiments, and it should be understood that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1-3, a heat treatment process of rust-proof and corrosion-proof steel comprises the following steps:
s1: selecting proper steel, cleaning the steel, and wiping the steel which is hard by rust spots by using steel wires; the steel with lower hardness should be wiped by cotton cloth; after the surface of the steel is cleaned and tightened, carrying out quenching and tempering treatment on the steel;
s2: quenching the steel through a box type resistance furnace, selecting a proper quenching temperature which is 850 ℃ to quench the steel, carrying out quenching heat preservation for 20-25min, cooling the steel after quenching, transferring the steel to an electric heating nitrogen protection tempering furnace for tempering treatment after cooling, wherein the tempering temperature is 740 ℃, the tempering heat preservation is 60-65min, and carrying out cooling treatment again after finishing the tempering heat preservation;
wherein, during quenching and tempering, the cooling medium selected for cooling treatment is oil quenching; the oil cooling rate has ideal cooling characteristics at the fastest speed at the temperature of 500-350 ℃, so that the supercooled austenite structure of the steel has the fastest cooling rate in the most unstable area, and the maximum depth of a hardening layer can be obtained; the martensite transformation zone has the minimum cooling speed, so that the tissue stress can be reduced to the minimum, and the deformation and cracking tendency is reduced;
s3: carrying out stress relief annealing treatment on the steel so as to eliminate residual stress generated in the machining process of the steel; during stress relief annealing, after the steel is slowly heated to 550 ℃, annealing and heat preservation are carried out for 2.5 hours, air cooling treatment is carried out after annealing is finished, the annealed steel is slowly cooled by air, the annealed steel is transferred into a salt bath tufftride furnace, treatment is carried out for 2-3 hours at the temperature of 550-600 ℃, so that the steel is subjected to salt bath tufftride, low-temperature tempering is required for reducing the residual stress and the brittleness of the steel, the tempering temperature is 160 ℃, heat preservation is carried out for 1.5 hours, and water cooling is carried out through water cooling equipment after heat preservation is finished;
wherein, the water cooling device comprises a case 1, a feed chute 2, a sealing cover plate 3, a material conveying component 4, a smoke exhaust component 5, a material baffle plate 6, a water drainage component 7, a water injection pipe 8, a hydraulic station 9 and a frame 10, the feed chute 2 is arranged on one side of the top end surface of the case 1, the sealing cover plate 3 is fixedly arranged on one side of the end surface of the feed chute 2 through a hinge, the material baffle plate 6 is fixedly arranged on the bottom of the inner side of the feed chute 2, the water drainage component 7 is arranged on one side of the outer part of the material baffle plate 6, the water drainage component 7 comprises a filter frame 71, a water drainage pipe 72, a motor shell 73, a driving motor 74 and a spiral vane 75, the filter frame 71 is fixedly arranged at one end of the material baffle plate 6, the water drainage pipe 72 is inserted and installed on one side of the bottom of the filter frame 71, the motor shell 73 is fixedly arranged on, the spiral blade 75 is positioned inside the case 1, so that the water flow speed can be increased, and the water cooling speed is increased; the water injection pipe 8 is installed on the other side of the outer portion of the material baffle 6 in an inserted mode, the smoke exhaust assembly 5 is arranged on the other side of the top end face of the case 1, the smoke exhaust assembly 5 comprises an equipment box 51, an exhaust pump 52, a drying cylinder 53, an exhaust pipe 54 and a flow guide cover 55, the equipment box 51 is fixedly installed on the other side of the top of the case 1 through bolts, the exhaust pump 52 is fixedly installed inside the equipment box 51, the flow guide cover 55 is installed at one end of the bottom of the exhaust pump 52 in a connected mode, the flow guide cover 55 is located on the top of the inner side of the case 1, the drying cylinder 53 is installed on the top end face of the exhaust pump 52 in a connected mode, the exhaust pipe 54; a hydraulic station 9 is fixedly installed on one side of the end face of the bottom of the case 1 through screws, a material conveying assembly 4 is connected and installed on the top of the hydraulic station 9, the material conveying assembly 4 comprises a hydraulic cylinder 41, a guide seat 42, a hydraulic rod 43, a material table 44, material frames 45 and a support connecting rod 46, the hydraulic cylinder 41 is fixedly installed inside the hydraulic station 9, the guide seat 42 is connected and installed on the end face of the top of the hydraulic cylinder 41, the guide seat 42 is located inside the case 1, the hydraulic rod 43 is installed inside the hydraulic cylinder 41 in an inserted mode, one end of the hydraulic rod 43 penetrates through the guide seat 42 and is connected and installed with the material table 44, the two material frames 45 are fixedly installed on the end face of the top of the material table 44, the support connecting rod 46 is fixedly installed between the material frames 45 through welding, and drain holes are; the periphery of the end surface of the bottom of the case 1 is fixedly provided with a frame 10;
the machine case 1 can be supported through the machine frame 10, external cooling water is conveyed to the inside of the machine case 1 through the water injection pipe 8, steel materials needing water cooling are conveyed to the inside of the machine case 1 through the material conveying assembly 4, the steel materials are placed at the top of the material frame 45, the material frame 45 at the top position can be supported through the support connecting rod 46, a plurality of steel materials can be placed, after the steel materials are placed, the hydraulic cylinder 41 in the hydraulic station 9 works, the hydraulic cylinder 41 enables the hydraulic rod 43 to move inside the hydraulic cylinder 41, the hydraulic rod 43 moves inside the guide seat 42 in the downward moving process, the guide effect is achieved, the hydraulic rod 43 drives the material table 44 and the material frame 45 to move downwards, the material table 44 and the material frame 45 move downwards to the inside of the machine case 1 through the feed chute 2, the sealing cover plate 3 covers the upper portion of the feed chute 2, and the steel materials move downwards to the inside of the machine case 1, the contact of the steel and cold water can evaporate moisture, steam is discharged through the smoke exhaust assembly 5, the exhaust pump 52 in the equipment box 51 works, the steam is conveyed to the drying cylinder 53 through the guide cover 55 to be dried, and then the steam is discharged through the exhaust pipe 54; in the process of cooling steel, the water flow speed inside the case 1 is increased through the drainage assembly 7, the driving motor 74 inside the motor shell 73 works, the driving motor 74 drives the spiral blade 75 to rotate at a high speed, the water flow is increased, the cooling speed of the steel can be increased, the surface layer of the steel can fall off in the cooling process of the steel, partial scraps fall on the material baffle plate 6, the scraps can fall into the filter frame 71 along with the continuous flow of the water flow, the drainage pipe 72 is opened, and waste water and the scraps can be conveniently discharged; after cooling, the sealing cover plate 3 is opened, the hydraulic cylinder 41 pushes the hydraulic rod 43 to move upwards, so that the hydraulic rod 43 pushes the material platform 44 and the material rack 45, and steel is moved out of the interior of the case 1;
s4: polishing the steel subjected to salt bath soft nitriding by using polishing equipment, removing a loose layer on the nitride outer layer on the surface of the steel, performing infiltration treatment on the polished steel by using a vacuum heating furnace, taking zinc powder as a raw material, and in a rotating closed container, contacting the heated steel with zinc powder under a vacuum condition, so that a zinc-iron alloy infiltration layer can be formed on the surface layer of a matrix of the steel, and an anti-rust layer is formed on the surface of the steel;
s5: performing anticorrosive coating on the steel obtained by heat treatment, selecting proper anticorrosive coating, and performing brushing treatment on the steel to sequentially form a primer layer, an intermediate paint layer and an outer paint layer on the surface of the steel; in the process of painting the paint layer, after the first painting is finished, a certain time gap is kept, after the first drying, the second painting is carried out, the painting direction of the second painting is perpendicular to the painting direction of the first painting, so that the thickness of the paint film is uniform and consistent, after the primer is painted, the steel and the paint surface are dried, and after the drying is finished, the rust-proof and corrosion-resistant steel is prepared;
wherein, the primer layer of the steel is epoxy zinc-rich primer, the intermediate paint layer of the steel is epoxy micaceous iron intermediate paint, the outer paint layer of the steel is acrylic polyurethane finish paint, and the thickness of the primer layer is 50-60 mu m; the thickness of the intermediate paint layer is 70-80 μm; the thickness of the outer paint surface layer is 60-70 mu m, and the rust prevention and corrosion prevention effects of the steel can be improved.
The preferred embodiments of the invention disclosed above are intended to be illustrative only. The preferred embodiments are not intended to be exhaustive or to limit the invention to the precise embodiments disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and the practical application, to thereby enable others skilled in the art to best utilize the invention. The invention is limited only by the claims and their full scope and equivalents.

Claims (8)

1. The heat treatment process of the rust-proof and corrosion-proof steel is characterized by comprising the following steps of:
s1: selecting proper steel, cleaning the steel, and wiping the steel which is hard by rust spots by using steel wires; the steel with lower hardness should be wiped by cotton cloth; after the surface of the steel is cleaned and tightened, carrying out quenching and tempering treatment on the steel;
s2: quenching the steel through a box type resistance furnace, selecting a proper quenching temperature which is 850 ℃ to quench the steel, carrying out quenching heat preservation for 20-25min, cooling the steel after quenching, transferring the steel to an electric heating nitrogen protection tempering furnace for tempering treatment after cooling, wherein the tempering temperature is 740 ℃, the tempering heat preservation is 60-65min, and carrying out cooling treatment again after finishing the tempering heat preservation;
s3: carrying out stress relief annealing treatment on the steel so as to eliminate residual stress generated in the machining process of the steel; during stress relief annealing, after the steel is slowly heated to 550 ℃, annealing and heat preservation are carried out for 2.5 hours, air cooling treatment is carried out after annealing is finished, the annealed steel is slowly cooled by air, the annealed steel is transferred into a salt bath tufftride furnace, treatment is carried out for 2-3 hours at the temperature of 550-600 ℃, so that the steel is subjected to salt bath tufftride, low-temperature tempering is required for reducing the residual stress and the brittleness of the steel, the tempering temperature is 160 ℃, heat preservation is carried out for 1.5 hours, and water cooling is carried out through water cooling equipment after heat preservation is finished;
s4: polishing the steel subjected to salt bath soft nitriding by using polishing equipment, removing a loose layer on the nitride outer layer on the surface of the steel, performing infiltration treatment on the polished steel by using a vacuum heating furnace, taking zinc powder as a raw material, and in a rotating closed container, contacting the heated steel with zinc powder under a vacuum condition, so that a zinc-iron alloy infiltration layer can be formed on the surface layer of a matrix of the steel, and an anti-rust layer is formed on the surface of the steel;
s5: performing anticorrosive coating on the steel obtained by heat treatment, selecting proper anticorrosive coating, and performing brushing treatment on the steel to sequentially form a primer layer, an intermediate paint layer and an outer paint layer on the surface of the steel; in the process of painting the paint layer, after the first painting is finished, a certain time gap is kept, after the first drying, the second painting is carried out, the painting direction of the second painting is perpendicular to the painting direction of the first painting, so that the thickness of the paint film is uniform and consistent, after the primer is painted, steel and the paint surface are dried, and after the drying, the rust-proof and corrosion-resistant steel is prepared.
2. The heat treatment process of rust-proof and corrosion-resistant steel as claimed in claim 1, wherein in step S2, the cooling medium used in the cooling treatment is oil quenching during quenching and tempering.
3. The heat treatment process of rust-proof and corrosion-resistant steel as claimed in claim 1, wherein in step S5, the primer layer of the steel is epoxy zinc-rich primer, the intermediate paint layer of the steel is epoxy mica iron intermediate paint, and the outer paint layer of the steel is acrylic polyurethane finish paint.
4. The heat treatment process for rust-inhibitive and corrosion-inhibitive steel according to claim 3, wherein the thickness of said primer layer is 50 to 60 μm; the thickness of the intermediate paint layer is 70-80 μm; the thickness of the outer paint surface layer is 60-70 μm.
5. The heat treatment process of rust-proof and corrosion-resistant steel as claimed in claim 1, wherein in step S3, the water cooling equipment comprises a case (1), a feed chute (2), a sealing cover plate (3), a material conveying component (4), a smoke exhaust component (5), a striker plate (6), a drainage component (7), a water injection pipe (8), a hydraulic station (9) and a frame (10), wherein the feed chute (2) is arranged on one side of the top end surface of the case (1), the sealing cover plate (3) is fixedly arranged on one side of the end surface of the feed chute (2) through a hinge, the striker plate (6) is fixedly arranged at the bottom of the inner side of the feed chute (2), the drainage component (7) is arranged on one side of the outer part of the striker plate (6), the water injection pipe (8) is inserted and mounted on the other side of the outer part of the striker plate (6), the smoke exhaust component (5), a hydraulic station (9) is fixedly arranged on one side of the bottom end face of the case (1) through screws, the top of the hydraulic station (9) is connected with and provided with a material conveying assembly (4), and racks (10) are fixedly arranged on the periphery of the bottom end face of the case (1);
defeated material subassembly (4) include pneumatic cylinder (41), guide holder (42), hydraulic stem (43), material platform (44), material frame (45) and supporting connecting rod (46), pneumatic cylinder (41) fixed mounting is in the inside of hydraulic pressure station (9), guide holder (42) are installed in the connection of the top terminal surface of pneumatic cylinder (41), and guide holder (42) are located the inside of quick-witted case (1), hydraulic stem (43) are installed in the inside grafting of pneumatic cylinder (41), and the one end of hydraulic stem (43) passes guide holder (42) and connects and install material platform (44), the top terminal surface fixed mounting of material platform (44) has two material frames (45), and installs supporting connecting rod (46) through welded fastening between material frame (45).
6. The heat treatment process of the rust-proof and corrosion-resistant steel as claimed in claim 5, wherein the periphery of the end surface of the material frame (45) is provided with drain holes.
7. The heat treatment process of rust-proof and corrosion-resistant steel according to claim 5, wherein the drainage assembly (7) comprises a filter frame (71), a drainage pipe (72), a motor shell (73), a driving motor (74) and a spiral blade (75), the filter frame (71) is fixedly installed at one end of the baffle plate (6), the drainage pipe (72) is installed on one side of the bottom of the filter frame (71) in an inserting mode, the motor shell (73) is fixedly installed on one side of the outer portion of the case (1) through bolts, the driving motor (74) is fixedly installed on one side of the inner portion of the motor shell (73), the spiral blade (75) is installed at one end of the driving motor (74) in a connecting mode, and the spiral blade (75) is located inside the case (1).
8. The heat treatment process of rust-resistant anticorrosive steel of claim 5, characterized in that, the subassembly of discharging fume (5) includes equipment box (51), exhaust pump (52), drying cylinder (53), blast pipe (54) and kuppe (55), equipment box (51) passes through bolt fixed mounting at the top opposite side of quick-witted case (1), the inside fixed mounting of equipment box (51) has exhaust pump (52), kuppe (55) is installed in the connection of the bottom one end of exhaust pump (52), and kuppe (55) is located the inboard top of quick-witted case (1), drying cylinder (53) is installed in the connection of the top terminal surface of exhaust pump (52), and blast pipe (54) is installed in the grafting of the top of drying cylinder (53).
CN202010870795.7A 2020-08-26 2020-08-26 Heat treatment process of rust-proof and corrosion-proof steel Pending CN111893262A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010870795.7A CN111893262A (en) 2020-08-26 2020-08-26 Heat treatment process of rust-proof and corrosion-proof steel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010870795.7A CN111893262A (en) 2020-08-26 2020-08-26 Heat treatment process of rust-proof and corrosion-proof steel

Publications (1)

Publication Number Publication Date
CN111893262A true CN111893262A (en) 2020-11-06

Family

ID=73224249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010870795.7A Pending CN111893262A (en) 2020-08-26 2020-08-26 Heat treatment process of rust-proof and corrosion-proof steel

Country Status (1)

Country Link
CN (1) CN111893262A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114472119A (en) * 2021-12-24 2022-05-13 南通市国盾门业有限公司 Bottom surface anticorrosion spraying method for steel door leaf
CN118109665A (en) * 2024-04-30 2024-05-31 东宇东庵(无锡)科技有限公司 Steel surface quenching device with staged cooling function and quenching process

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4055446A (en) * 1975-04-02 1977-10-25 Deutsche Gold- Und Silber-Scheideanstalt Vormals Roessler Salt bath quenching of construction parts treated with a nitriding bath
JP2007063667A (en) * 2005-08-02 2007-03-15 Honda Motor Co Ltd LAYERED Fe-BASED ALLOY AND PROCESS FOR PRODUCTION THEREOF
CN102410225A (en) * 2011-10-17 2012-04-11 上海西工压缩机配件有限公司 Compressor blade and preparation technology thereof
CN104928445A (en) * 2014-11-17 2015-09-23 山东天瑞重工有限公司 High-wind-pressure impacter piston and thermal treating process thereof
CN105238913A (en) * 2015-11-02 2016-01-13 杭州持正科技股份有限公司 Pin shaft of engine timing chain and tufftriding process
CN105463360A (en) * 2015-12-15 2016-04-06 安徽伟宏钢结构集团股份有限公司 Anticorrosion coating construction technology of steel structural member
CN105583589A (en) * 2014-10-23 2016-05-18 无锡华冶钢铁有限公司 Machining forming and manufacturing technique for piston made of 38CrMnAl steel
CN106906340A (en) * 2017-03-31 2017-06-30 河南科技大学 A kind of fine grain heat treatment method
CN107937666A (en) * 2017-11-18 2018-04-20 蚌埠市宏大制药机械有限公司 A kind of processing method for lifting mould steel and using quality
CN208829727U (en) * 2018-10-04 2019-05-07 天津润信多新材料科技有限公司 A kind of steel plate processing hot gas cycle device

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4055446A (en) * 1975-04-02 1977-10-25 Deutsche Gold- Und Silber-Scheideanstalt Vormals Roessler Salt bath quenching of construction parts treated with a nitriding bath
JP2007063667A (en) * 2005-08-02 2007-03-15 Honda Motor Co Ltd LAYERED Fe-BASED ALLOY AND PROCESS FOR PRODUCTION THEREOF
CN102410225A (en) * 2011-10-17 2012-04-11 上海西工压缩机配件有限公司 Compressor blade and preparation technology thereof
CN105583589A (en) * 2014-10-23 2016-05-18 无锡华冶钢铁有限公司 Machining forming and manufacturing technique for piston made of 38CrMnAl steel
CN104928445A (en) * 2014-11-17 2015-09-23 山东天瑞重工有限公司 High-wind-pressure impacter piston and thermal treating process thereof
CN105238913A (en) * 2015-11-02 2016-01-13 杭州持正科技股份有限公司 Pin shaft of engine timing chain and tufftriding process
CN105463360A (en) * 2015-12-15 2016-04-06 安徽伟宏钢结构集团股份有限公司 Anticorrosion coating construction technology of steel structural member
CN106906340A (en) * 2017-03-31 2017-06-30 河南科技大学 A kind of fine grain heat treatment method
CN107937666A (en) * 2017-11-18 2018-04-20 蚌埠市宏大制药机械有限公司 A kind of processing method for lifting mould steel and using quality
CN208829727U (en) * 2018-10-04 2019-05-07 天津润信多新材料科技有限公司 A kind of steel plate processing hot gas cycle device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张黔: "《表面强化技术》", 30 November 1996, 华中理工大学出版社 *
赵一生等: "热处理对钢结硬质合金TLMW50覆层抗磨性的影响", 《粉末冶金技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114472119A (en) * 2021-12-24 2022-05-13 南通市国盾门业有限公司 Bottom surface anticorrosion spraying method for steel door leaf
CN118109665A (en) * 2024-04-30 2024-05-31 东宇东庵(无锡)科技有限公司 Steel surface quenching device with staged cooling function and quenching process

Similar Documents

Publication Publication Date Title
CN111893262A (en) Heat treatment process of rust-proof and corrosion-proof steel
CN110846612A (en) Vacuum carburizing heat treatment processing technology
EP3632577B1 (en) Plastic spraying process and apparatus for bearing retainer
CN111719041B (en) Heat treatment system and heat treatment method for universal joint cross shaft of automobile
CN102409143B (en) Heat treatment process of carbon structural steel
CN101294240B (en) Thermal treatment method for mounting frame for air conditioner motor
US3769068A (en) Method for manufacturing steel plates coated with aluminum powder
CN216473342U (en) Channel steel surface quenching device for ferrous metal smelting rolled product
CN218232511U (en) Wheel hub quenching equipment
EP2604710A1 (en) Method for hardening of a metallic workpiece
CN114410903A (en) Local quenching device is used in hot rolling medium plate production
CN1616705A (en) Salt bath tuff-triding treatment for high speed steel (W6Mo5Cr4V2) slide vane (or vane)
CN112143993B (en) Continuous hot galvanizing plating process method and equipment with post-plating dehydrogenation function
CN113481352A (en) Quenching heat treatment process for wear-resisting plate
CN220846209U (en) Quenching device for alloy steel casting machining
CN220413482U (en) Quenching device for hub bearing outer ring forging
CN220634968U (en) Rust-proof oil spraying equipment
US3912846A (en) Apparatus for manufacturing steel plates coated with aluminium powder
CN216420752U (en) Preparation facilities of high anti-corrosion hot pressing spare part
CN220432892U (en) Quenching treatment device for shell produced by rotary cylinder
CN212741504U (en) QPQ (quench-Polish-quench) treatment device for valve core and valve sleeve surface of screw drill accessory
CN217052325U (en) Special gear quenching equipment
CN219689782U (en) Metal quenching equipment for metal heat treatment
CN116727936B (en) Welding method for heat-resistant sink roll machining
CN214937660U (en) Semi-axis high-frequency quenching production line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201106

RJ01 Rejection of invention patent application after publication