CN111828956A - Method for acquiring circulating multiplying power of CFB boiler material and separation efficiency of separator - Google Patents

Method for acquiring circulating multiplying power of CFB boiler material and separation efficiency of separator Download PDF

Info

Publication number
CN111828956A
CN111828956A CN202010767268.3A CN202010767268A CN111828956A CN 111828956 A CN111828956 A CN 111828956A CN 202010767268 A CN202010767268 A CN 202010767268A CN 111828956 A CN111828956 A CN 111828956A
Authority
CN
China
Prior art keywords
height
material circulation
cfb boiler
acquiring
pressure testing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010767268.3A
Other languages
Chinese (zh)
Inventor
时勇
李瑞波
王如超
聂志钢
刘化才
李海泉
于长深
商桂新
赵凤涛
黄秀平
王金霞
孙云国
高华
闫蕾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Trier Technology Co.,Ltd.
Original Assignee
Qingdao Clear Environmental Protection Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Clear Environmental Protection Group Co ltd filed Critical Qingdao Clear Environmental Protection Group Co ltd
Priority to CN202010767268.3A priority Critical patent/CN111828956A/en
Publication of CN111828956A publication Critical patent/CN111828956A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23CMETHODS OR APPARATUS FOR COMBUSTION USING FLUID FUEL OR SOLID FUEL SUSPENDED IN  A CARRIER GAS OR AIR 
    • F23C10/00Fluidised bed combustion apparatus
    • F23C10/02Fluidised bed combustion apparatus with means specially adapted for achieving or promoting a circulating movement of particles within the bed or for a recirculation of particles entrained from the bed
    • F23C10/04Fluidised bed combustion apparatus with means specially adapted for achieving or promoting a circulating movement of particles within the bed or for a recirculation of particles entrained from the bed the particles being circulated to a section, e.g. a heat-exchange section or a return duct, at least partially shielded from the combustion zone, before being reintroduced into the combustion zone
    • F23C10/08Fluidised bed combustion apparatus with means specially adapted for achieving or promoting a circulating movement of particles within the bed or for a recirculation of particles entrained from the bed the particles being circulated to a section, e.g. a heat-exchange section or a return duct, at least partially shielded from the combustion zone, before being reintroduced into the combustion zone characterised by the arrangement of separation apparatus, e.g. cyclones, for separating particles from the flue gases
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23CMETHODS OR APPARATUS FOR COMBUSTION USING FLUID FUEL OR SOLID FUEL SUSPENDED IN  A CARRIER GAS OR AIR 
    • F23C10/00Fluidised bed combustion apparatus
    • F23C10/02Fluidised bed combustion apparatus with means specially adapted for achieving or promoting a circulating movement of particles within the bed or for a recirculation of particles entrained from the bed
    • F23C10/12Fluidised bed combustion apparatus with means specially adapted for achieving or promoting a circulating movement of particles within the bed or for a recirculation of particles entrained from the bed the particles being circulated exclusively within the combustion zone
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23CMETHODS OR APPARATUS FOR COMBUSTION USING FLUID FUEL OR SOLID FUEL SUSPENDED IN  A CARRIER GAS OR AIR 
    • F23C10/00Fluidised bed combustion apparatus
    • F23C10/18Details; Accessories
    • F23C10/20Inlets for fluidisation air, e.g. grids; Bottoms
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23CMETHODS OR APPARATUS FOR COMBUSTION USING FLUID FUEL OR SOLID FUEL SUSPENDED IN  A CARRIER GAS OR AIR 
    • F23C10/00Fluidised bed combustion apparatus
    • F23C10/18Details; Accessories
    • F23C10/28Control devices specially adapted for fluidised bed, combustion apparatus

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Abstract

The invention discloses a method for acquiring material circulation multiplying power of a CFB (circulating fluid bed) boiler, which comprises the steps of acquiring the hearth pressure at a first height, acquiring the hearth pressure at a second height, and enabling the first height and the second height to be separated by a distance H, wherein the designed fluidizing air speed value of the hearth of the CFB boiler is V, and H is V multiplied by 1 s; calculating the difference value delta P between the furnace pressure at the first height and the furnace pressure at the second height; obtaining an actual fluidization wind speed value V in the hearth1And by the formula K ═ V1V, obtaining a correction coefficient K; obtaining the amount G of coal fed into the furnace in unit timesAccording to formula GcCalculating to obtain the material circulation amount G in unit timec(ii) a From materialsFormula of cyclic multiplying power R ═ Gc/GsAnd calculating to obtain the material circulation ratio R. The method can more accurately calculate the material circulation rate of the boiler; the invention also discloses a method for acquiring the separation efficiency of the CFB boiler separator.

Description

Method for acquiring circulating multiplying power of CFB boiler material and separation efficiency of separator
Technical Field
The invention relates to the technical field of boiler design and production, in particular to a method for acquiring material circulation multiplying power of a CFB boiler and separation efficiency of a separator.
Background
The CFB boiler is called a circulating fluidized bed boiler in English, and is called a circulating fluidized bed boiler in Chinese, and the circulating fluidized bed boiler has the advantages of wide coal variety adaptation, cleanness, environmental protection and the like, so the circulating fluidized bed boiler combustion technology becomes a clean coal combustion technology with good application prospect in the world.
The material circulation rate is an important parameter for the design and operation of the circulating fluidized bed, and has direct influence on the flow characteristic, combustion characteristic, heat transfer characteristic, variable working condition characteristic and the like of the material in the boiler, when the circulating fluidized bed boiler operates normally, the material entering the boiler and the material circulating in the boiler reach dynamic balance, the boiler has the material entering amount and the material circulating amount corresponding to the material entering amount and the material circulating amount at each working condition point, in order to express the material circulation rate quantitatively, the concept of circulation rate is introduced during the design of the boiler, and in the circulating fluidized bed boiler, the material circulation rate is the ratio of the material circulation rate to the coal entering amount in unit time.
The material circulation rate is an important technical index for the design and operation of the circulating fluidized bed boiler, and has important guiding significance for the selection and calculation of key parameters (such as combustion efficiency, separator separation efficiency, desulfurization efficiency, denitrification efficiency, fluidized air speed, bed temperature and the like) of the boiler. When the material circulation rate is increased, the heat transfer quantity of fine particles in the circulating material to a heating surface and the heat taken away from the dense-phase region are increased, so that the heat balance of the dense-phase region is facilitated, the bed temperature is effectively inhibited, and meanwhile, the low-nitrogen combustion atmosphere is created; when the material circulation rate is too small, the concentration of suspended fine particles on the upper part of the hearth is too small, the material quantity in the dense-phase region is increased, and the released heat is too much, so that the dense-phase region is over-heated and the load of the boiler is difficult to increase.
The problem that the measurement and calculation of the circulation multiplying power of the existing circulating fluidized bed boiler are not accurate enough is solved, and the selection and calculation of key parameters of the boiler are seriously influenced, so that how to accurately obtain the circulation multiplying power of the boiler material is a technical problem which needs to be solved urgently by technical personnel in the field at present.
Disclosure of Invention
In view of the above, an object of the present invention is to provide a method for acquiring a material circulation ratio of a CFB boiler, so as to accurately measure the material circulation ratio of the circulating fluidized bed boiler during actual operation, and provide reference and guidance data for efficient and stable operation of the circulating fluidized bed boiler.
Another object of the present invention is to provide a method for obtaining separation efficiency of a separator of a CFB boiler.
In order to achieve the purpose, the invention provides the following technical scheme:
a method for acquiring material circulation rate of a CFB boiler comprises the following steps:
acquiring the furnace pressure at a first height and the furnace pressure at a second height, wherein the height of the center of a furnace outlet is the first height; the height which is lower than the center of the hearth outlet and has a vertical distance H from the center of the hearth outlet is a second height, the designed fluidizing air speed value of the hearth of the CFB boiler is V, and H is V multiplied by 1 m;
calculating the difference value delta P between the furnace pressure at the first height and the furnace pressure at the second height;
obtaining an actual fluidization wind speed value V between a first height and a second height in the hearth1And by the formula K ═ V1V, obtaining a correction coefficient K;
obtaining the amount G of coal fed into the furnace in unit timesAccording to formula GcCalculating to obtain the material circulation amount G in unit timecWherein F is the cross-sectional area of the hearth, and g is the gravity acceleration; the formula of material circulation multiplying power R is Gc/GsAnd calculating to obtain the material circulation ratio R.
Preferably, the designed fluidization wind speed value V is 4.5 m/s-6 m/s.
Preferably, the design fluidization wind velocity value V is 5 m/s.
Preferably, more than two first pressure testing devices are arranged on the first height, and the average value of the pressures detected by all the first pressure testing devices is the furnace pressure at the first height;
and more than two second pressure testing devices are arranged on the second height, and the average value of the pressures detected by all the second pressure testing devices is the furnace pressure at the second height.
Preferably, the first pressure testing device and the second pressure testing device are arranged on a left wall and/or a right wall of the CFB boiler if the furnace outlet is located on a front wall and/or a rear wall of the CFB boiler; the first pressure testing device and the second pressure testing device are arranged on a front wall and/or a rear wall of the CFB boiler if the furnace outlet is located on the left wall and/or the right wall of the CFB boiler.
Preferably, the first pressure testing device and the second pressure testing device are arranged in a one-to-one correspondence in the vertical direction.
Preferably, if the capacity of the CFB boiler is not more than 240t/h, the number of the first pressure testing devices and the number of the second pressure testing devices are both 4-6; and if the capacity of the CFB boiler is more than 240t/h, the number of the first pressure testing devices and the number of the second pressure testing devices are both 6-8.
Preferably, from the formula cpThe concentration c of the recycled material is obtained from K.DELTA.P/Hgp
Preferably, the actual value of the fluidization wind speed V between the first height and the second height in the furnace1Measured by a wind speed sensor, or according to formula V1=VDsjCalculated as/D, wherein DsjThe actual load of the boiler and the rated load of the boiler are D.
The invention discloses a method for acquiring the separation efficiency of a CFB boiler separator, which comprises the following steps:
acquiring a material circulation multiplying power R by adopting any one of the CFB boiler material circulation multiplying power acquisition methods;
obtaining the part a of fly ashfhObtaining the carbon content C of the fly ashfhObtaining the received basal ash Aar
According to the formula eta ═ R/(R + a)fh×Aar/100(100-Cfh) ) the separation efficiency η is calculated.
In the method for acquiring the material circulation multiplying power of the CFB boiler, the hearth pressures at a first height and a second height are measured, then the difference value of the hearth pressures at the first height and the second height is calculated, the actual fluidization wind speed value between the first height and the second height is acquired, the ratio of the actual fluidization wind speed value to the designed fluidization wind speed value is a correction coefficient, and the material circulation multiplying power is calculated by combining a formula with the correction coefficient;
the method for acquiring the material circulation multiplying power only needs to measure the furnace pressure values at the first height and the second height and the actual fluidization air speed values at the first height and the second height, the required measurement amount is small, the position of the first height is actually close to the center of the inlet of the separator, the measured pressure at the position can reflect the flue gas concentration value of the outlet of the furnace, and the material circulation multiplying power calculated by adopting the pressure value at the position is closer to the actual value, so the measurement precision of the actual circulation multiplying power of the circulating fluidized bed boiler is easy to guarantee; and the distance between the first height and the second height is the distance of flue gas running at the designed fluidization wind speed value in unit time under the rated working condition, the distance is about 5m generally, and compared with the measurement of the hearth pressure difference in the prior art, the measurement distance is greatly reduced, so that the accuracy of the pressure difference is improved, the calculated material circulation rate is closer to the true value, and the actual circulation rate of the circulating fluidized bed boiler can be reflected more truly.
The method for obtaining the separation efficiency adopts the material circulation multiplying power obtained by the method, and then the separation efficiency is obtained by calculation according to a formula.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic flow chart illustrating a method for obtaining material circulation rate of a CFB boiler disclosed in an embodiment of the present invention;
FIG. 2 is a schematic structural diagram of a CFB boiler disclosed in an embodiment of the present invention.
The drawings are numbered as follows:
1 is a hearth, 2 is a cyclone separator, 3 is a tail flue, 4 is a first height, and 5 is a second height.
Detailed Description
One of the cores of the invention is to provide a method for acquiring the material circulation rate of the CFB boiler, so that the material circulation rate of the circulating fluidized bed boiler in actual operation can be accurately measured, and reference and guidance data are provided for the efficient and stable operation of the circulating fluidized bed boiler.
Another core of the invention is to provide a method for obtaining the separation efficiency of the CFB boiler separator.
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Please refer to fig. 1 and fig. 2, the method for obtaining the material circulation rate of the CFB boiler disclosed in the present embodiment includes:
acquiring furnace pressure at a first height and a second height, wherein in the embodiment, the height of a furnace outlet center is a first height, the height which is lower than the furnace outlet center and is vertically away from the furnace outlet center by H (in m) is a second height, if a design fluidizing air speed value of a furnace of the CFB boiler is V (in m/s), H is V × 1s, and H represents the distance that flue gas in the furnace flows according to the design fluidizing air speed in (1s) per unit time under a rated load working condition;
calculating the difference value delta P (in Pa) between the furnace pressure at the first height and the furnace pressure at the second height;
obtaining an actual fluidization wind speed value V between a first height and a second height in a hearth1(in m/s) and is represented by the formula K ═ V1V, obtaining a correction coefficient K;
obtaining the amount G of coal fed into the furnace in unit times(in kg/s) according to formula GcCalculating to obtain the material circulation amount G in unit timec(in kg/s), wherein F is the cross-sectional area of the furnace (in m)2) G is the acceleration of gravity; the formula of material circulation multiplying power R is Gc/GsAnd calculating to obtain the material circulation ratio R.
According to the embodiment, in the method for acquiring the material circulation multiplying power of the CFB boiler, the hearth pressure at the first height and the hearth pressure at the second height are measured firstly, then the difference value of the hearth pressure at the first height and the hearth pressure at the second height is calculated, the actual fluidization wind speed value between the first height and the second height is acquired, the ratio of the actual fluidization wind speed value to the designed fluidization wind speed value is the correction coefficient, and the material circulation multiplying power is calculated by combining the formula with the correction coefficient;
the method for acquiring the material circulation multiplying power only needs to measure the furnace pressure values at the first height and the second height and the actual fluidization air speed values at the first height and the second height, the required measurement amount is small, the position of the first height is actually close to the center of the inlet of the separator, the measured pressure at the position can reflect the flue gas concentration value of the outlet of the furnace, and the material circulation multiplying power calculated by adopting the pressure value at the position is closer to the actual value, so the measurement precision of the actual circulation multiplying power of the circulating fluidized bed boiler is easy to guarantee; and the distance between the first height and the second height is the distance of flue gas running at the designed fluidization wind speed value in unit time under the rated working condition, the distance is about 5m generally, and compared with the measurement of the hearth pressure difference in the prior art, the measurement distance is greatly reduced, so that the accuracy of the pressure difference is improved, the calculated material circulation rate is closer to the true value, and the actual circulation rate of the circulating fluidized bed boiler can be reflected more truly.
It will be appreciated by those skilled in the art that the design fluidization wind velocity values for CFB boilers will vary depending on the capacity, and typically the design fluidization wind velocity value V will be in the range of 4.5m/s to 6m/s, preferably 5m/s (i.e. the average fluidization wind velocity at the upper part of the furnace at rated load), where H is 5 m.
In consideration of the accuracy of pressure value measurement, when a furnace outlet (flue gas outlet) is positioned on a front wall and/or a rear wall of the CFB boiler, the first pressure testing device and the second pressure testing device are arranged on a left wall and/or a right wall of the CFB boiler; the first pressure testing device and the second pressure testing device are arranged on the front wall and/or the rear wall of the CFB boiler if the furnace outlet is located on the left wall and/or the right wall of the CFB boiler.
The number of the first pressure testing devices and the second pressure testing devices is not limited, but it should be understood by those skilled in the art that if a plurality of first pressure testing devices and a plurality of second pressure testing devices are arranged and then the average value is taken, the average value is more accurate, so in this embodiment, the first pressure testing devices and the second pressure testing devices are arranged in one-to-one correspondence in the vertical direction, more than two first pressure testing devices are arranged at the first height, and the average value of data of all the first pressure testing devices is taken as the furnace pressure at the first height; and more than two second pressure testing devices are arranged on the second height, and the average value of the pressures detected by all the second pressure testing devices is the furnace pressure at the second height.
The cross-sectional areas of boilers with different capacities are different, so that the number of first pressure testing devices and the number of second pressure testing devices which need to be arranged are different, in the method for acquiring the material circulation multiplying power of the CFB boiler disclosed by the embodiment of the invention, if the capacity of the CFB boiler is not more than 240t/h, the number of the first pressure testing devices and the number of the second pressure testing devices are both 4-6; and if the capacity of the CFB boiler is more than 240t/h, the number of the first pressure testing devices and the number of the second pressure testing devices are both 6-8.
Concentration of circulating material cpActually, the method is also an important parameter that needs to be monitored during the operation of the boiler, and in this embodiment, the method for obtaining the material circulation rate further includes the following steps:
from the formula cpThe concentration c of the recycled material is obtained from K.DELTA.P/Hgp
In an embodiment of the invention, the actual value of the fluidization wind speed V between the first level and the second level1May be measured by a wind speed sensor arranged between the first level and the second level, and may also be according to formula V1=VDsjCalculated as/D, wherein DsjThe actual load of the boiler and the rated load of the boiler are D.
In addition, the invention also discloses a method for acquiring the separation efficiency of the CFB boiler separator, which comprises the following steps:
the method for acquiring the circulating multiplying power of the CFB boiler material disclosed in any one of the embodiments is adopted to acquire the circulating multiplying power R of the material, and the base ash A can be acquired through the analysis data of the coal as fired and the ash residuear(in percent), carbon content of fly ash Cfh(in percent) and the fly ash fraction afh(in percent) and then R/(R + a) according to the formula η ═ Rfh×Aar/100(100-Cfh) ) the separation efficiency η is calculated.
According to the method for obtaining the separation efficiency, the method disclosed in the embodiment is adopted to obtain the material circulation multiplying power R, so that the separation efficiency of the separator obtained by calculating the material circulation multiplying power is more accurate and reliable.
The invention is further explained in detail by two practical operation examples:
practical working example 1
The CFB boiler with the capacity of 75t/h has the furnace sectional area F of 20m2The fly ash share a can be obtained according to the weighing of ash slag in the running process of the boilerfh50 percent, the fly ash carbon content C can be obtained from ash sampling and testing datafhThe content was 10%.
Table 1 actual operation example 1 part of the parameters
Figure BDA0002615168680000081
The boiler operates under the load working condition of 75t/h, the difference value delta P of the furnace pressure at the first height and the second height is 90Pa, and the actual fluidization wind speed value V1Setting the fluidizing wind speed value V as 5m/s in rated load condition, and calculating the fluidizing wind speed value V according to the formula GcThe material circulation amount G per unit time can be obtained by K × F × Δ P/Gc183.67kg/s, and is formed by a cyclic multiplying power formula R ═ Gc/GsCalculating to obtain the material circulation multiplying power R of 48.34;
According to the formula eta ═ R/(R + a)fh×Aar/100(100-Cfh) Calculating to obtain the separation efficiency of the separator to be 99.44%;
changing the operation condition, reducing the load of the boiler to 72t/h, setting the difference value delta P of the furnace pressure at the first height and the second height to 70Pa, and setting the actual fluidizing air speed value V14.8m/s, according to formula GcThe material circulation amount G per unit time can be obtained by K × F × Δ P/Gc137.14kg/s, and is formed by a cyclic multiplying power formula R ═ Gc/GsCalculating to obtain a material circulation multiplying power R of 36.09;
according to the formula eta ═ R/(R + a)fh×Aar/100(100-Cfh) Calculated to give a separation efficiency of 99.25% for the separator.
Practical operation example 2
The CFB boiler with the capacity of 240t/h has the furnace sectional area F of 54m2The fly ash share a can be obtained according to the weighing of ash slag in the running process of the boilerfh70 percent, the fly ash carbon content C can be obtained from ash sampling and testing datafhThe content was 5%.
Table 2 actual operation example 2 part of the parameters
Figure BDA0002615168680000091
The boiler operates under the load working condition of 240t/h, the difference value delta P of the furnace pressure at the first height and the second height is 95Pa, and the actual fluidization wind speed value V15m/s, and the fluidizing wind speed value V is 5m/s according to the formula G under the designed rated load working conditioncThe material circulation amount G per unit time can be obtained by K × F × Δ P/Gc523.47kg/s, and is formed by a cyclic multiplying power formula R ═ Gc/GsCalculating to obtain a material circulation multiplying power R of 36.53;
according to the formula eta ═ R/(R + a)fh×Aar/100(100-Cfh) Calculating to obtain the separation efficiency of the separator to be 99.45%;
changing the operation condition, reducing the boiler load to 230t/h, ensuring that the difference value delta P of the furnace pressure at the first height and the second height is 80Pa, and actually fluidizingValue of wind velocity V14.8m/s, according to formula GcThe material circulation amount G per unit time can be obtained by K × F × Δ P/Gc422.45kg/s, and is formed by a cyclic multiplying power formula R ═ Gc/GsCalculating to obtain a material circulation ratio R of 29.48;
according to the formula eta ═ R/(R + a)fh×Aar/100(100-Cfh) Calculated to give a separation efficiency of the separator of 99.30%.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (10)

1. A method for acquiring material circulation multiplying power of a CFB boiler is characterized by comprising the following steps:
acquiring the furnace pressure at a first height and the furnace pressure at a second height, wherein the height of the center of a furnace outlet is the first height; the height which is lower than the center of the hearth outlet and is at a vertical distance H from the center of the hearth outlet is a second height, the designed fluidizing air speed value of the hearth of the CFB boiler is V, and H is V multiplied by 1 s;
calculating the difference value delta P between the furnace pressure at the first height and the furnace pressure at the second height;
obtaining an actual fluidization wind speed value V between a first height and a second height in the hearth1And by the formula K ═ V1V, obtaining a correction coefficient K;
obtaining the amount G of coal fed into the furnace in unit timesAccording to formula GcCalculating to obtain the material circulation amount G in unit timecWherein F is the cross-sectional area of the hearth, and g is the gravity acceleration; the formula of material circulation multiplying power R is Gc/GsAnd calculating to obtain the material circulation ratio R.
2. The method for acquiring the material circulation rate of the CFB boiler according to claim 1, wherein the designed fluidization wind speed value V is 4.5-6 m/s.
3. The method for acquiring the material circulation rate of the CFB boiler according to claim 2, wherein the design fluidization wind speed value V is 5 m/s.
4. The method for acquiring material circulation rate of CFB boiler in accordance with claim 1,
more than two first pressure testing devices are arranged at the first height, and the average value of the pressures detected by all the first pressure testing devices is the furnace pressure at the first height;
and more than two second pressure testing devices are arranged on the second height, and the average value of the pressures detected by all the second pressure testing devices is the furnace pressure at the second height.
5. The method for acquiring material circulation rate of a CFB boiler according to claim 4, wherein if the furnace outlet is located on a front wall and/or a rear wall of the CFB boiler, the first pressure testing device and the second pressure testing device are arranged on a left wall and/or a right wall of the CFB boiler; the first pressure testing device and the second pressure testing device are arranged on a front wall and/or a rear wall of the CFB boiler if the furnace outlet is located on the left wall and/or the right wall of the CFB boiler.
6. The method for acquiring the material circulation rate of the CFB boiler according to claim 4, wherein the first pressure testing device and the second pressure testing device are arranged in a one-to-one correspondence manner in a vertical direction.
7. The method for acquiring the material circulation rate of the CFB boiler according to claim 6, wherein if the CFB boiler capacity is not more than 240t/h, the number of the first pressure testing devices and the number of the second pressure testing devices are both 4-6; and if the capacity of the CFB boiler is more than 240t/h, the number of the first pressure testing devices and the number of the second pressure testing devices are both 6-8.
8. The method for acquiring the material circulation rate of the CFB boiler according to claim 1, further comprising: from the formula cpThe concentration c of the recycled material is obtained from K.DELTA.P/Hgp
9. The method for acquiring the material circulation rate of the CFB boiler according to any one of claims 1 to 8, wherein an actual value V of the fluidization wind speed between a first height and a second height in the hearth1Measured by a wind speed sensor, or according to formula V1=VDsjCalculated as/D, wherein DsjThe actual load of the boiler and the rated load of the boiler are D.
10. A method for obtaining the separation efficiency of a CFB boiler separator is characterized by comprising the following steps:
the method for acquiring the material circulation multiplying power R of the CFB boiler according to any one of claims 1-9 is adopted to acquire the material circulation multiplying power R;
obtaining the part a of fly ashfhObtaining the carbon content C of the fly ashfhObtaining the received basal ash Aar
According to the formula eta ═ R/(R + a)fh×Aar/100(100-Cfh) ) the separation efficiency η is calculated.
CN202010767268.3A 2020-08-03 2020-08-03 Method for acquiring circulating multiplying power of CFB boiler material and separation efficiency of separator Pending CN111828956A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010767268.3A CN111828956A (en) 2020-08-03 2020-08-03 Method for acquiring circulating multiplying power of CFB boiler material and separation efficiency of separator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010767268.3A CN111828956A (en) 2020-08-03 2020-08-03 Method for acquiring circulating multiplying power of CFB boiler material and separation efficiency of separator

Publications (1)

Publication Number Publication Date
CN111828956A true CN111828956A (en) 2020-10-27

Family

ID=72919392

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010767268.3A Pending CN111828956A (en) 2020-08-03 2020-08-03 Method for acquiring circulating multiplying power of CFB boiler material and separation efficiency of separator

Country Status (1)

Country Link
CN (1) CN111828956A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112884789A (en) * 2021-02-05 2021-06-01 浙江大学 Method and system for calculating internal circulation multiplying power of circulating fluidized bed
CN113155217A (en) * 2021-01-27 2021-07-23 清华大学 Method and system for measuring solid circulation flow rate of thermal state circulating fluidized bed

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6979358B2 (en) * 2000-11-07 2005-12-27 Shell Oil Company Vertical cyclone separator
CN101655236A (en) * 2009-09-28 2010-02-24 西安热工研究院有限公司 Method for calculating height and storage quantity of material bed in hearth box of circulating fluidized bed boiler in real time
CN101666717A (en) * 2009-09-28 2010-03-10 西安热工研究院有限公司 Method for real-time online calculation and measurement of separation efficiency of separator
CN107389971A (en) * 2017-07-20 2017-11-24 清华大学 A kind of on-line measurement device of On Solids Recirculating Flowrate of Circulating Fluidized Bed
CN108679603A (en) * 2018-08-31 2018-10-19 刘学冰 A kind of circulating fluidized bed boiler circulating ratio and grey balance regulator control system and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6979358B2 (en) * 2000-11-07 2005-12-27 Shell Oil Company Vertical cyclone separator
CN101655236A (en) * 2009-09-28 2010-02-24 西安热工研究院有限公司 Method for calculating height and storage quantity of material bed in hearth box of circulating fluidized bed boiler in real time
CN101666717A (en) * 2009-09-28 2010-03-10 西安热工研究院有限公司 Method for real-time online calculation and measurement of separation efficiency of separator
CN107389971A (en) * 2017-07-20 2017-11-24 清华大学 A kind of on-line measurement device of On Solids Recirculating Flowrate of Circulating Fluidized Bed
CN108679603A (en) * 2018-08-31 2018-10-19 刘学冰 A kind of circulating fluidized bed boiler circulating ratio and grey balance regulator control system and method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
《工业自动化仪表手册》编辑委员会: "《工业自动化仪表手册》", 31 October 1988 *
岑可法,倪明江主编: "《气固分离理论及技术》", 31 March 1999, 浙江大学出版社 *
王智微等: "《分宜100MW循环流化床锅炉旋风分离器分离效率的计算》", 《锅炉制造》 *
王淑波,蒋红梅主编: "《化工原理》", 31 January 2019 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113155217A (en) * 2021-01-27 2021-07-23 清华大学 Method and system for measuring solid circulation flow rate of thermal state circulating fluidized bed
CN113155217B (en) * 2021-01-27 2023-03-24 清华大学 Method and system for measuring solid circulation flow rate of thermal state circulating fluidized bed
CN112884789A (en) * 2021-02-05 2021-06-01 浙江大学 Method and system for calculating internal circulation multiplying power of circulating fluidized bed
CN112884789B (en) * 2021-02-05 2022-09-13 浙江大学 Method and system for calculating internal circulation multiplying power of circulating fluidized bed

Similar Documents

Publication Publication Date Title
CN111828956A (en) Method for acquiring circulating multiplying power of CFB boiler material and separation efficiency of separator
Zhang et al. Fluid-dynamic boundary layers in CFB boilers
US4969408A (en) System for optimizing total air flow in coal-fired boilers
Moon et al. Thermal-fluid characteristics on near wall of gas-solid fluidized bed reactor
CN103760191B (en) Based on the full working scope boiler heating surface pollution monitoring method and apparatus of dynamic compensation
CN109668625A (en) Method is monitored and controlled in boiler slag based on dry bottom hopper vibration signal
CN213178312U (en) CFB boiler running state monitoring system
CN108460508B (en) On-line energy-saving monitoring method based on working characteristics of circulating fluidized bed boiler
CN109556749A (en) A kind of high-temperature flue gas contact type temperature measuring device and its measurement method
JP2021172882A (en) Test method of leak air rate of iron ore sintering machine system
CN108875165B (en) Boiler characteristic calibration method based on operation data
CN103343978B (en) A kind of pulverized coal flame stability prediction and diagnostic method
Peng et al. Reverse‐flow centrifugal separators in parallel: Performance and flow pattern
CN101666717A (en) Method for real-time online calculation and measurement of separation efficiency of separator
CN106021916B (en) One kind being suitable for ultra-supercritical boiler NOxThe computational methods of discharge capacity analysis
CN103699790A (en) Method for detecting average temperature of hearth outlet smoke of coal-fired power plant in real time
CN112131526A (en) On-line calculation method for fly ash concentration and fly ash flow of coal-fired boiler
Ryabov et al. Substantiating the techniques for calculating the furnace circuit of circulating fluidized bed boilers
Jones et al. An experimental investigation of gas flow in a scale model of a fluidized-bed combustor
CN103439132B (en) Wear measuring method and system in biomass recirculating fluidized bed boiler stove
Ryabov et al. Results of theoretical and experimental studies of hydrodynamics of circulation loops in circulating fluidized bed reactors and systems with interconnected reactors
CN117313428B (en) Pollutant concentration online monitoring and correcting method for thermal power plant
CN103439081B (en) Biomass recirculating fluidized bed boiler flow behavior measurement method and system
KR100376524B1 (en) Method for predicting shape of dead man in shaft type reduction furnace
CN116858308B (en) Energy-saving and environment-friendly detection system for boiler, boiler system and detection method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210603

Address after: 266073 room 402, Block E, 67 and 69 Yinchuan West Road, Shinan District, Qingdao City, Shandong Province

Applicant after: Qingdao Trier Technology Co.,Ltd.

Address before: 266071 e402, 403, No. 67, 69, Yinchuan West Road, Shinan District, Qingdao City, Shandong Province

Applicant before: QINGDAO CLEAR ENVIRONMENTAL PROTECTION GROUP Co.,Ltd.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210616

Address after: 266073 room 402, Block E, 67 and 69 Yinchuan West Road, Shinan District, Qingdao City, Shandong Province

Applicant after: Qingdao Trier Technology Co.,Ltd.

Address before: Room 402403, Block E, No. 67 and 69, Yinchuan West Road, Shinan District, Qingdao City, Shandong Province 266073

Applicant before: QINGDAO CLEAR ENVIRONMENTAL PROTECTION GROUP Co.,Ltd.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201027