CN111810235A - Separated tunnel drainage system and construction method thereof - Google Patents

Separated tunnel drainage system and construction method thereof Download PDF

Info

Publication number
CN111810235A
CN111810235A CN202010711099.1A CN202010711099A CN111810235A CN 111810235 A CN111810235 A CN 111810235A CN 202010711099 A CN202010711099 A CN 202010711099A CN 111810235 A CN111810235 A CN 111810235A
Authority
CN
China
Prior art keywords
drainage
tunnel
hole
drainage system
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010711099.1A
Other languages
Chinese (zh)
Inventor
袁松
李�杰
黎良仆
郑国强
周科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Communication Surveying and Design Institute Co Ltd
Original Assignee
Sichuan Communication Surveying and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Communication Surveying and Design Institute Co Ltd filed Critical Sichuan Communication Surveying and Design Institute Co Ltd
Priority to CN202010711099.1A priority Critical patent/CN111810235A/en
Publication of CN111810235A publication Critical patent/CN111810235A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a separated tunnel drainage system and a construction method thereof, and the separated tunnel drainage system comprises a tunnel main hole, a primary support, wall back circumferential drainage pipes and a secondary lining, wherein the secondary lining, a waterproof layer and the primary support are sequentially arranged in the circumferential direction of the periphery of the tunnel main hole, a plurality of wall back circumferential drainage pipes are arranged at intervals in the circumferential direction of the periphery of the primary support, the separated tunnel drainage system also comprises a drainage hole and a water collecting well belt water pump, the drainage hole is arranged below the tunnel main hole, and the water collecting well is arranged at the opening of the drainage hole. The invention has the advantages that: the main holes are mainly used for prevention, the drainage holes are mainly used for drainage, and the prevention and drainage are separated and do not interfere with each other; all the underground water flows into the drainage hole through the annular drainage pipe and finally is collected in the water collecting well at the hole opening for residents, irrigation and water storage; the drainage hole can be used as a leading pilot hole to detect geological conditions.

Description

Separated tunnel drainage system and construction method thereof
Technical Field
The invention relates to the field of tunnel engineering water-proof and drainage systems, in particular to a separated tunnel drainage system and a construction method thereof.
Background
The traditional highway tunnel water-proof and drainage mainly adopts the guideline of 'combination of prevention, interception, drainage and blockage, adaptation according to local conditions and comprehensive treatment' and the principle of 'mainly blocking and limited drainage'. However, due to the limitation of the construction process, the annular drainage pipe, the longitudinal drainage pipe, the transverse drainage pipe and the waterproof plate in the tunnel are crossed too much, the waterproof plate is not tightly wrapped or the quality of the waterproof plate is not in place in the wrapping process, and the ten-tunnel nine-leakage is caused. For water-rich areas, full-section deep hole pre-grouting and peripheral grouting after excavation are commonly adopted in design and construction to plug surrounding rock cracks, so that the aim of water prevention is fulfilled. But the grouting engineering is often invisible without bottom holes, which causes great difficulty for design work. Therefore, a separate tunnel drainage system and a construction method thereof need to be designed, and the defects that the water is prevented and drained from being separated and interfered with each other, the main tunnel cannot be fully closed, and underground water cannot be collected and utilized in the prior art are overcome.
Disclosure of Invention
The invention aims to solve the technical problems that in the prior art, the prevention and the discharge are not separated and mutually interfered, the main tunnel cannot be fully sealed, and underground water cannot be collected and utilized.
The invention is realized by the following technical scheme:
the utility model provides a disconnect-type tunnel drainage system, includes tunnel owner hole, preliminary bracing, wall back of the body hoop drain pipe, secondary lining, the peripheral hoop in tunnel owner hole sets gradually secondary lining, waterproof layer and preliminary bracing, the peripheral hoop interval in preliminary bracing sets up a plurality of wall backs of the body hoop drain pipes, still includes drainage hole, sump pit area water pump, drainage hole sets up in tunnel owner hole below, the sump pit sets up the hole department at drainage hole.
Compared with the prior art, the invention changes the tunnel water-proof and drainage into the principle that the main hole is mainly protected, the drainage hole is mainly arranged, the protection and drainage are separated and do not interfere with each other, thus the main hole tunnel adopts the waterproof board to be completely wrapped in a whole ring, the longitudinal drainage pipe, the tunnel bottom transverse drainage pipe and the central drainage ditch are cancelled, the wall back ring is connected with the drainage hole by the drainage pipe, and the longitudinal slope of the drainage hole is consistent with that of the main hole. Therefore, the surrounding rock underground water is completely isolated from the main hole, all the underground water flows into the drainage hole through the annular drainage pipe and finally is collected in the water collecting well at the hole opening for residents, irrigation and water storage.
In conclusion, the separated tunnel drainage system and the construction method thereof are suitable for highway tunnels, and the main tunnel is truly fully closed by arranging the drainage hole which is arranged below the main tunnel of the tunnel and is relatively independent on the principle that the main tunnel is mainly used for prevention, the drainage hole is mainly used for drainage, the prevention and drainage are separated and do not interfere with each other, so that water is completely isolated outside the tunnel, and the current situation of 'ten tunnels and nine leaks' is changed; the hole is provided with a water collecting well for collecting and storing underground water for effective utilization.
Furthermore, the circumferential drain pipe on the wall back is a single-wall nonporous corrugated pipe with the diameter of 50 mm;
the method is as follows.
Furthermore, a plurality of wall backs are annularly arranged at intervals towards the drain pipe, and two adjacent walls are spaced by 5 m;
the wall back is arranged towards the drain pipe in order to better collect the surrounding rock crack water and the underground water.
Further, the drainage hole is arranged 5-10m below the main tunnel hole;
the drainage holes are arranged 5-10m below the main tunnel, and the two tunnels are changed into small clear distance due to too close distance, so that excavation and supporting between the two tunnels are influenced.
Further, the diameter of the drainage hole is 3 meters;
the diameter of the drainage hole is 3 meters, people can enter the drainage hole, and an operation space is reserved.
Furthermore, the longitudinal slope of the drainage hole is consistent with that of the main tunnel hole, and the vertical slope between the drainage hole and the main tunnel hole is consistent with that of the main tunnel hole
The radial distance is 5 m;
the longitudinal slopes are kept consistent, the vertical distance between the drainage hole and the main tunnel of the tunnel is 5m, the surrounding rock underground water is completely isolated from the main tunnel, all the underground water flows into the drainage hole through the annular drainage pipes, and finally the underground water is collected in the water collecting well at the hole opening for residents, irrigation and water storage.
Further, a water pump is arranged in the water collecting well;
the water pump is arranged in the water collecting well, so that underground water can be collected well and effectively utilized.
The construction method for realizing the separated tunnel drainage system comprises the following steps:
s1, firstly, excavating a drainage tunnel as an advanced pilot tunnel of the tunnel to find out the geological condition of the tunnel and provide a basis for dynamic design;
s2, lining and supporting the drainage tunnel;
s3, excavating a main tunnel, and timely constructing a primary support and a wall back circumferential drainage pipe;
s4, constructing a vertical drainage pipe;
and S5, constructing a main tunnel secondary lining.
Compared with the prior art, the invention has the following advantages and beneficial effects:
1. the invention relates to a separated tunnel drainage system and a construction method thereof.A main hole is mainly used for prevention, a drainage hole is mainly used for drainage, and the prevention and drainage are separated and do not interfere with each other;
2. the invention relates to a separated tunnel drainage system and a construction method thereof
The holes are finally collected in the water collecting well at the hole opening for residents, irrigation and water storage;
3. according to the separated tunnel drainage system and the construction method thereof, the drainage hole can be used as a leading pilot hole to detect geological conditions.
Drawings
The accompanying drawings, which are included to provide a further understanding of the embodiments of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the principles of the invention.
In the drawings:
fig. 1 is a schematic view of a tunnel drainage system.
Fig. 2 is a schematic view of a sump well.
Reference numbers and corresponding part names in the drawings:
1-main tunnel hole, 2-preliminary bracing, 3-circumferential wall back drainage pipe, 4-secondary lining, 5-drainage hole, 6-water collecting well and 7-waterproof layer.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail below with reference to examples and accompanying drawings, and the exemplary embodiments and descriptions thereof are only used for explaining the present invention and are not meant to limit the present invention.
Example 1:
the invention discloses a separated tunnel drainage system, which comprises a tunnel main hole 1, a primary support 2, wall back circumferential drainage pipes 3 and a secondary lining 4, wherein the secondary lining 4, a waterproof layer 7 and the primary support 2 are sequentially arranged in the circumferential direction of the periphery of the tunnel main hole 1, the wall back circumferential drainage pipes 3 are arranged in the circumferential direction of the periphery of the primary support 2 at intervals, the separated tunnel drainage system further comprises a drainage hole 5 and a water collecting well belt water pump 6, the drainage hole 5 is arranged below the tunnel main hole 1, and the water collecting well 6 is arranged at the opening of the drainage hole 5.
The working process is as follows: firstly, a drainage tunnel is excavated, the geological condition of the tunnel can be found as an advanced pilot tunnel of the tunnel, a basis is provided for dynamic design, lining support is carried out on the drainage tunnel, a main tunnel is excavated, primary support and wall back circumferential drainage pipes are constructed in time, vertical drainage pipes are constructed, and secondary lining of the main tunnel is constructed.
Example 2:
as shown in fig. 1 and fig. 2, this embodiment is based on embodiment 1, and the back wall circumferential drain pipe 3 is a single-wall non-porous corrugated pipe with a diameter of 50 mm; the plurality of wall backs are annularly arranged towards the drain pipe 3 at intervals, and every two adjacent walls are spaced by 5 m; the drainage hole 5 is arranged 5-10m below the main tunnel hole 1; the diameter of the drainage hole 5 is 3 meters; the longitudinal slope of the drainage hole 5 is consistent with that of the main tunnel hole 1, and the vertical distance between the drainage hole 5 and the main tunnel hole 1 is 5 m; and a water pump is arranged in the water collecting well 6.
Example 3:
as shown in fig. 1 and 2, the construction method for implementing the separated tunnel drainage system includes the following steps:
s1, firstly, excavating a drainage tunnel 5 as an advanced pilot tunnel of the tunnel to find out the geological condition of the tunnel and provide a basis for dynamic design;
s2, lining and supporting the drainage tunnel 5;
s3, excavating a main tunnel 1, taking the main tunnel at the buried depth of 25m, and constructing a primary support 2 and a wall back annular drainage pipe 3 in time;
s4, constructing a vertical water drainage pipe, wherein the vertical distance between the water drainage tunnel and the main tunnel 1 is 5m, and the radius of the water drainage tunnel is 3 m;
and S5, constructing the main tunnel secondary lining 4.
After construction, testing the main tunnel lining related maximum and the drainage tunnel lining related maximum, wherein the test data table 1 and the test data table 2 are as follows:
TABLE 1
Main hole result peak Numerical value Position of
Axial force 1192.02kN Arch foot
Bending moment 832.55kN·m Arch foot
Shear force 748.15kN Arch foot
Vertical displacement 11.10mm Vault
Vertical stress 960.57kPa Arch foot
TABLE 2
Peak value of drainage hole result Numerical value Position of
Axial force 1287.66kN Arch foot
Bending moment 101.36kN·m Arch foot
Shear force 85.88kN Arch foot
Vertical displacement 7.706mm Arch bottom (uplift)
Vertical stress 1186kPa Arched waist
The test data in tables 1 and 2 prove that the mutual influence of the two tunnels is small under the conditions of timely support and proper construction.
The above-mentioned embodiments are intended to illustrate the objects, technical solutions and advantages of the present invention in further detail, and it should be understood that the above-mentioned embodiments are merely exemplary embodiments of the present invention, and are not intended to limit the scope of the present invention, and any modifications, equivalent substitutions, improvements and the like made within the spirit and principle of the present invention should be included in the scope of the present invention.

Claims (8)

1. The utility model provides a disconnect-type tunnel drainage system, includes tunnel owner hole (1), preliminary bracing (2), wall back hoop drain pipe (3), secondary lining (4), tunnel owner hole (1) peripheral hoop sets gradually secondary lining (4), waterproof layer (7) and preliminary bracing (2), preliminary bracing (2) peripheral hoop interval sets up a plurality of wall backs hoop drain pipe (3), its characterized in that still includes drainage hole (5), sump pit area water pump (6), drainage hole (5) set up in tunnel owner hole (1) below, sump pit (6) set up the entrance to a cave department in drainage hole (5).
2. A split tunnel drainage system according to claim 1, wherein the back wall circumferential drainage pipe (3) is a single wall imperforate corrugated pipe each 50mm in diameter.
3. The separated tunnel drainage system according to claim 2, wherein a plurality of wall backs are arranged at intervals in the circumferential direction towards the drainage pipes (3), and the interval between two adjacent wall backs towards the drainage pipes (3) is 5 m.
4. A split tunnel drainage system according to claim 1, wherein the drainage hole (5) is arranged 5-10m below the main tunnel hole (1).
5. A split tunnel drainage system according to claim 1, wherein the drainage hole (5) is 3 meters in diameter.
6. A split tunnel drainage system according to claim 1, wherein the longitudinal slope of the drainage hole (5) is identical to the longitudinal slope of the main tunnel hole (1), and the vertical distance between the drainage hole (5) and the main tunnel hole (1) is 5 m.
7. A split tunnel drainage system according to claim 1, wherein a water pump is provided in the sump (6).
8. A construction method of the divided tunnel drainage system according to any one of claims 1 to 7, comprising the steps of:
s1, firstly, excavating a drainage tunnel (5) as an advanced pilot tunnel of the tunnel to find out the geological condition of the tunnel and provide a basis for dynamic design;
s2, lining and supporting the drainage hole (5);
s3, excavating a main tunnel, and constructing a primary support and a wall back circumferential drainage pipe (3) in time;
s4, constructing a vertical drainage pipe;
and S5, constructing the secondary lining (4) of the main tunnel.
CN202010711099.1A 2020-07-22 2020-07-22 Separated tunnel drainage system and construction method thereof Pending CN111810235A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010711099.1A CN111810235A (en) 2020-07-22 2020-07-22 Separated tunnel drainage system and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010711099.1A CN111810235A (en) 2020-07-22 2020-07-22 Separated tunnel drainage system and construction method thereof

Publications (1)

Publication Number Publication Date
CN111810235A true CN111810235A (en) 2020-10-23

Family

ID=72861902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010711099.1A Pending CN111810235A (en) 2020-07-22 2020-07-22 Separated tunnel drainage system and construction method thereof

Country Status (1)

Country Link
CN (1) CN111810235A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102678174A (en) * 2012-05-28 2012-09-19 中交第一公路勘察设计研究院有限公司 Tunnel drainage system passing through permafrost region and non-frozen ground region and arrangement method thereof
CN103032097A (en) * 2012-12-26 2013-04-10 湖南省交通规划勘察设计院 Tunnel drainage structure applicable to water-rich strata under unsymmetrical pressure and construction method thereof
KR20130114904A (en) * 2012-04-10 2013-10-21 한국도로공사 Drainage structure in tunnel and method constructing thereof
CN106761918A (en) * 2016-12-30 2017-05-31 中铁二院工程集团有限责任公司 A kind of tunnel solution cavity and Groundwater Comprehensive administer construction and construction method
CN107178393A (en) * 2017-07-07 2017-09-19 中铁第四勘察设计院集团有限公司 A kind of Tunnel Second Lining water pressure control structure
CN206647135U (en) * 2017-04-06 2017-11-17 周国海 Dredge discharge structure in a kind of tunnel
CN209604084U (en) * 2019-01-29 2019-11-08 中国建筑一局(集团)有限公司 Karst area fault broken zone tunnel gushes water and administers structure
CN111271118A (en) * 2020-03-30 2020-06-12 中铁二院工程集团有限责任公司 Drainage structure suitable for reconstruction of tunnel bottom structure of karst tunnel and construction method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20130114904A (en) * 2012-04-10 2013-10-21 한국도로공사 Drainage structure in tunnel and method constructing thereof
CN102678174A (en) * 2012-05-28 2012-09-19 中交第一公路勘察设计研究院有限公司 Tunnel drainage system passing through permafrost region and non-frozen ground region and arrangement method thereof
CN103032097A (en) * 2012-12-26 2013-04-10 湖南省交通规划勘察设计院 Tunnel drainage structure applicable to water-rich strata under unsymmetrical pressure and construction method thereof
CN106761918A (en) * 2016-12-30 2017-05-31 中铁二院工程集团有限责任公司 A kind of tunnel solution cavity and Groundwater Comprehensive administer construction and construction method
CN206647135U (en) * 2017-04-06 2017-11-17 周国海 Dredge discharge structure in a kind of tunnel
CN107178393A (en) * 2017-07-07 2017-09-19 中铁第四勘察设计院集团有限公司 A kind of Tunnel Second Lining water pressure control structure
CN209604084U (en) * 2019-01-29 2019-11-08 中国建筑一局(集团)有限公司 Karst area fault broken zone tunnel gushes water and administers structure
CN111271118A (en) * 2020-03-30 2020-06-12 中铁二院工程集团有限责任公司 Drainage structure suitable for reconstruction of tunnel bottom structure of karst tunnel and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郭磊: "官地水电站竹子坝料场边坡划破分析及支护设计", 《吉林水利》 *

Similar Documents

Publication Publication Date Title
CN206386134U (en) A kind of Underground Subway Station guarded drainage construction
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN105484773A (en) System plugging and draining structure for tunnel leakage treatment
CN104652461A (en) Underground plant shaft water-drainage-preventing structure and construction method thereof
CN114109437A (en) Rolling hinged joint anchor beam supporting method suitable for soft rock large-deformation tunnel
CN111810235A (en) Separated tunnel drainage system and construction method thereof
CN209892228U (en) Underground comprehensive pipe gallery structure constructed by adopting underground excavation method
CN112228151A (en) Tunnel open cut tunnel water drainage system
CN109024645B (en) Integrated waterproof curtain, sponge urban water circulation system and method
CN113565172B (en) Construction method of pumping and water injecting well of underground reservoir of strip mine waste dump
CN215804714U (en) Drainage depressurization system at bottom of rich water section tunnel
CN210857228U (en) Anti-freezing protection device
CN212003260U (en) Water delivery pipeline fixing device
CN211472544U (en) Dewatering well structure
CN210288158U (en) Corrugated plate arch culvert for culvert
CN216240800U (en) Mountain tunnel drainage system easy to manage and dredge
CN214328884U (en) Open precipitation of river bank construction area combines foundation ditch excavation structure of earthwork excavation
CN216865215U (en) Dredging well structure and dredging well shut-in system
CN216920436U (en) Single-port single-control same-range horizontal connecting pipe for underground garage of shallow soil source heat pump
CN208763075U (en) Underground workshop outlet vertical shaft leakage preventing structure
CN221399055U (en) Foundation pit water-stopping precipitation system
CN218542320U (en) Multi-arch tunnel mid-partition comprehensive drainage structure
CN221236072U (en) Concealed active precipitation system
CN114109494B (en) Implementation method of two-single-extra-long tunnel partition drainage system in expanded rock area
CN220746977U (en) Foundation pit plugging water-stopping precipitation system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201023

RJ01 Rejection of invention patent application after publication