CN111795215A CN202010652485.8A CN202010652485A CN111795215A CN 111795215 A CN111795215 A CN 111795215A CN 202010652485 A CN202010652485 A CN 202010652485A CN 111795215 A CN111795215 A CN 111795215A
Authority
CN
China
Prior art keywords
shaped
main body
extrusion
arc
supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010652485.8A
Other languages
Chinese (zh)
Other versions
CN111795215B (en
Inventor
庞金超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningxia Zhonghong Construction Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010652485.8A priority Critical patent/CN111795215B/en
Publication of CN111795215A publication Critical patent/CN111795215A/en
Application granted granted Critical
Publication of CN111795215B publication Critical patent/CN111795215B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L9/00Rigid pipes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L57/00Protection of pipes or objects of similar shape against external or internal damage or wear
    • F16L57/02Protection of pipes or objects of similar shape against external or internal damage or wear against cracking or buckling

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Supports For Pipes And Cables (AREA)

Abstract

The invention discloses a water conservancy pipeline construction filling support structure, which comprises a conveying pipe, a protective pipe, a support framework main body and a strengthening support mechanism, wherein the support framework main body has a good support effect on the protective pipe outside the conveying pipe and also has a good protection function on the conveying pipe.

Description

Supporting structure is filled in water conservancy pipeline construction
Technical Field
The invention relates to the technical field of construction engineering equipment, in particular to a water conservancy pipeline construction filling support structure.
Background
At present, among the building site construction process, construction drainage or water delivery system are indispensable, when establishing drainage and water delivery system, need use more pipeline, can be used for carrying and delivery water to the water supply pipe, be equivalent to a switching mouth, be responsible for being connected beginning and terminal, the water supply pipe that glass steel made has anticorrosive, easily washs, longe-lived, high strength, the quality is light, characteristics such as simple to operate, water conservancy pipeline is very important to the transport and the distribution of water resource.
In the construction process of a water conservancy pipeline in the prior art, a protective pipe is usually arranged on the outer side of a conveying water pipe, materials such as heat preservation and corrosion prevention are filled between the conveying water pipe and the protective pipe, the water conveying pipe is well protected, the materials filled between the protective pipe and the conveying pipe have certain supporting effect on the pipeline, and the pipeline is placed to deform after being used for a long time.
Disclosure of Invention
The invention aims to provide a water conservancy pipeline construction filling support structure to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a water conservancy pipeline construction filling support structure comprises a conveying pipe, a protective pipe, a support framework main body and a strengthening support mechanism;
the supporting framework main body is sleeved on the outer side wall of the conveying pipe, the outer side wall of the supporting framework main body is sleeved with the protective pipe, arc-shaped filling grooves are formed in the supporting framework main body at equal intervals, arc-shaped filling assemblies are arranged in the arc-shaped filling grooves, and supporting rings are arranged on the supporting framework main body at equal intervals;
a reinforced support mechanism is arranged in the support framework main body;
a second locking thread groove is symmetrically formed in the other side of the supporting framework main body, a second locking thread column is arranged in the second locking thread groove, a rotating groove is formed in the end face of one end of the second locking thread column, and a second movable rod is movably connected in the second locking thread groove of the supporting framework main body;
one end of the second movable rod is connected with a second connecting spring, a second pushing rack is arranged at the same end of the second connecting spring of the second movable rod, and a rotating round block is arranged at the side position of the second movable rod of the support frame main body;
one side of the rotating round block is equidistantly provided with a toothed block, the other side of the rotating round block is provided with an arc extrusion chute, a second T-shaped movable extrusion block is movably connected in the arc extrusion chute, and the second T-shaped movable extrusion block is movably inserted into the supporting framework main body.
Preferably, the reinforced support mechanism comprises a first locking threaded column, a clamping groove, a first locking threaded groove, a first movable rod, a first extrusion chute, a transmission rack, a transmission gear set, a first pushing rack, an L-shaped push rod, a first T-shaped movable extrusion block, a second extrusion chute and an arc auxiliary support plate, wherein the first locking threaded column is arranged in the first locking threaded groove, the first locking threaded groove is symmetrically arranged at one end of the support frame main body, the clamping groove is equidistantly arranged at the side of the first locking threaded column, the first movable rod is movably arranged in the support frame main body, a first connecting spring is arranged at one end of the support frame main body, the first extrusion chute is equidistantly arranged in the first movable rod, the transmission rack is movably arranged in the support ring, and the transmission rack is meshed and connected with one side of the transmission gear set, the opposite side meshing of drive gear group is connected and is provided with first promotion rack, the one end symmetry of first promotion rack is provided with L type push rod, the avris activity of L type push rod one end is provided with first T type activity and extrudes the piece, the symmetry is provided with reset spring on the first T type activity extrudes the piece to the one end of first T type activity extrusion piece is provided with slope, the other end setting is in second extrusion chute, second extrusion chute symmetry sets up the avris at arc auxiliary support plate, arc auxiliary support plate activity sets up in the support ring.
Preferably, the thickness of the second T-shaped movable extrusion block is equal to the width of the cross section of the notch of the arc-shaped extrusion chute.
Preferably, the transmission rack corresponds to the first extrusion chute and the support ring in arrangement position and is arranged in the same number.
Preferably, the second extrusion chute and the first T-shaped movable extrusion block are arranged at positions corresponding to each other and have the same number of groups, and four groups are symmetrically arranged on two sides of the arc-shaped auxiliary support plate.
Preferably, the first pushing rack is the same as the transmission gear set, the transmission rack in tooth form angle and modulus.
Compared with the prior art, the invention has the beneficial effects that:
1. the supporting framework main body has a good supporting effect on the protective pipe outside the conveying pipe, and also has a good protection function on the conveying pipe, and moreover, the supporting strength of the protective pipe can be strengthened through the strengthening supporting mechanism arranged in the supporting framework main body, so that the protective pipe is not easy to deform and damage due to extrusion in the use process, the service life of the protective pipe is prolonged, and the supporting protection effect is improved;
2. the avris through first locking screw post is provided with second T type activity extrusion piece in strengthening the supporting mechanism, through the second movable rod, the second promotes the rack, the rotation circle piece, the profile modeling piece, the linkage effect of arc extrusion chute, make second T type activity extrusion piece can the card of first locking screw post die, and then make strengthening the supporting mechanism more firm and stable to the supporting role that supports the framework main part, and then more lasting and stable to the support of protection pipeline, improve its construction engineering quality, guarantee work economic benefits.
Drawings
FIG. 1 is a right side schematic view of a structural connection according to the present invention;
FIG. 2 is a schematic left side view of the structural connection of the present invention;
FIG. 3 is an exploded view of the structural attachment of the support frame body to the arcuate packing assembly of the present invention;
FIG. 4 is a right side view of a partial cross-sectional view of a structural joint according to the present invention;
FIG. 5 is a partially enlarged view of the connection structure of the reinforcing support mechanism of FIG. 4 according to the present invention;
FIG. 6 is an enlarged view of the first locking threaded post locking connection of FIG. 4 according to the present invention;
FIG. 7 is a left side schematic view of a structural joint in partial cross-section of the present invention;
fig. 8 is a partially enlarged view illustrating the connection structure of fig. 7 according to the present invention.
In the figure: the device comprises a conveying pipe 1, a protective pipe 2, a supporting framework main body 3, an arc-shaped filling groove 4, an arc-shaped filling assembly 5, a supporting ring 6, a strengthening supporting mechanism 7, a first locking threaded column 701, a clamping groove 702, a first locking threaded groove 703, a first movable rod 704, a first extrusion chute 705, a transmission rack 706, a transmission gear set 707, a first pushing rack 708, an L-shaped push rod 709, a first T-shaped movable extrusion block 710, a second extrusion chute 711, an arc-shaped auxiliary supporting plate 712, a second locking threaded groove 8, a second locking threaded column 9, a rotating groove 10, a second movable rod 11, a second pushing rack 12, a rotating circular block 13, a toothed block 14, an arc-shaped extrusion chute 15 and a second T-shaped movable extrusion block 16.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below. The embodiments of the present invention, and all other embodiments obtained by a person of ordinary skill in the art without any inventive work, belong to the scope of protection of the present invention.
Referring to fig. 1 to 8, the present invention provides a technical solution: a water conservancy pipeline construction filling support structure comprises a conveying pipe 1, a protective pipe 2, a support framework main body 3 and a strengthening support mechanism 7;
the supporting framework main body 3 is sleeved on the outer side wall of the conveying pipe 1, the outer side wall of the supporting framework main body 3 is sleeved with the protective pipe 2, the supporting framework main body 3 is equidistantly provided with an arc filling groove 4, an arc filling assembly 5 is arranged in the arc filling groove 4, and the supporting framework main body 3 is equidistantly provided with supporting rings 6;
a reinforced support mechanism 7 is arranged in the support frame main body 3;
a second locking thread groove 8 is symmetrically formed in the other side of the supporting framework main body 3, a second locking thread column 9 is arranged in the second locking thread groove 8, a rotating groove 10 is formed in the end face of one end of the second locking thread column 9, and a second movable rod 11 is movably connected in the second locking thread groove 8 of the supporting framework main body 3;
one end of the second movable rod 11 is connected with a second connecting spring, the second movable rod 11 is provided with a second pushing rack 12 at the same end of the second connecting spring, and the support frame main body 3 is provided with a rotating round block 13 at the side position of the second movable rod 11;
one side of the rotating round block 13 is equidistantly provided with a tooth-shaped block 14, the other side is provided with an arc extrusion chute 15, a second T-shaped movable extrusion block 16 is movably connected in the arc extrusion chute 15, and the second T-shaped movable extrusion block 16 is movably inserted in the supporting framework main body 3.
Further, the strengthening support mechanism 7 comprises a first locking threaded column 701, a clamping groove 702, a first locking threaded groove 703, a first movable rod 704, a first extrusion chute 705, a transmission rack 706, a transmission gear set 707, a first pushing rack 708, an L-shaped push rod 709, a first T-shaped movable extrusion block 710, a second extrusion chute 711, and an arc auxiliary support plate 712, wherein the first locking threaded column 701 is disposed in the first locking threaded groove 703, the first locking threaded groove 703 is symmetrically disposed at one end of the support frame body 3, the clamping grooves 702 are equidistantly disposed at the lateral sides of the first locking threaded column 701, the first movable rod 704 is movably disposed in the support frame body 3, one end of the support frame body 3 is provided with a first connecting spring, the first extrusion chute 705 is equidistantly disposed in the first movable rod 704, the transmission chute 705 is provided with a rack 706, the rack 706 is movably disposed in the support ring 6, the transmission rack 706 is arranged on one side of the transmission gear group 707 in a meshing connection mode, the first pushing rack 708 is arranged on the other side of the transmission gear group 707 in a meshing connection mode, an L-shaped push rod 709 is symmetrically arranged at one end of the first pushing rack 708, a first T-shaped movable extrusion block 710 is movably arranged on the side of one end of the L-shaped push rod 709, return springs are symmetrically arranged on the first T-shaped movable extrusion block 710, a slope is arranged at one end of the first T-shaped movable extrusion block 710, the other end of the first T-shaped movable extrusion block is arranged in a second extrusion chute 711, the second extrusion chute 711 is symmetrically arranged on the side of the arc-shaped auxiliary support plate 712, and the arc-shaped auxiliary support plate.
Further, the thickness of the second T-shaped movable extrusion block 16 is equal to the width of the cross section of the notch of the arc-shaped extrusion chute 15.
Furthermore, the driving rack 706 corresponds to the first extrusion chute 705 and the support ring 6 in the same number of sets.
Further, the second extrusion chutes 711 correspond to the first T-shaped movable extrusion blocks 710 in arrangement positions and are arranged in the same number of groups, and four groups are symmetrically arranged on two sides of the arc auxiliary support plate 712.
Further, the first push rack 708 has the same tooth form angle and module as the transmission gear set 707 and the transmission rack 706.
The working principle is as follows: when the invention is used for supporting construction work, firstly, the arc-shaped filling assembly 5 is placed in the arc-shaped filling groove 4 in the supporting framework main body 3, then the arc-shaped filling assembly 5 in the arc-shaped filling groove 4 is filled and sealed, then the conveying pipe 1 is inserted into the supporting framework main body 3, then the supporting framework main body 3 is inserted into the protective pipe 2, then the first locking threaded column 701 is rotated, the first locking threaded column 701 extrudes the first movable rod 704 along with the rotation of the first locking threaded column 701, further the first extrusion chute 705 on the first movable rod 704 extrudes the transmission rack 706, so as to drive the transmission gear set 707 to transmit, the transmission gear set 707 drives the first pushing rack 708 on the other side, the first pushing rack 708 further pushes the L-shaped push rod 709 to extrude the first T-shaped movable extrusion block 710, the first T-shaped movable extrusion block 710 further extrudes the second extrusion chute 711, so that the arc auxiliary supporting plate 712 is extruded outwards, and further the supporting strength of the supporting frame main body 3 to the protection pipe 2 is improved, when all the first locking threaded columns 701 are screwed, the second locking threaded column 9 arranged at the other end of the supporting frame main body 3 is screwed through the rotating groove 10, along with the rotation of the second locking threaded column 9, the second locking threaded column 9 extrudes the second movable rod 11, and further under the linkage action of the second pushing rack 12, the rotating round block 13 and the toothed block 14, the arc extrusion chute 15 extrudes and clamps the second T-shaped movable extrusion block 16 in the clamping groove 702 at the side of the first locking threaded column 701, so as to realize the locking and fixing of the position of the first locking threaded column 701, and the supporting construction work can be completed, therefore, for the invention, the supporting strength of the protection pipe can be strengthened, and the protection pipe can be ensured in the use process, the extrusion deformation damage is not easy to occur, the service life of the pipeline is prolonged, the supporting effect is improved, the supporting effect of the reinforced supporting mechanism 7 on the supporting frame main body 3 is firmer and more stable, the supporting effect on the protecting pipeline is more durable and more stable, the construction engineering quality of the pipeline is improved, and the economic benefit of the operation is guaranteed.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a bearing structure is filled in water conservancy pipeline construction which characterized in that: comprises a conveying pipe (1), a protective pipe (2), a supporting framework main body (3) and a strengthening supporting mechanism (7);
the supporting framework main body (3) is sleeved on the outer side wall of the conveying pipe (1), the outer side wall of the supporting framework main body (3) is sleeved with the protective pipe (2), the supporting framework main body (3) is provided with arc-shaped filling grooves (4) at equal intervals, arc-shaped filling assemblies (5) are arranged in the arc-shaped filling grooves (4), and the supporting framework main body (3) is provided with supporting rings (6) at equal intervals;
a reinforced support mechanism (7) is arranged in the support framework main body (3);
a second locking thread groove (8) is symmetrically formed in the other side of the supporting framework main body (3), a second locking thread column (9) is arranged in the second locking thread groove (8), a rotating groove (10) is formed in the end face of one end of the second locking thread column (9), and a second movable rod (11) is movably connected in the second locking thread groove (8) of the supporting framework main body (3);
one end of the second movable rod (11) is connected with a second connecting spring, a second pushing rack (12) is arranged at the same end of the second connecting spring of the second movable rod (11), and a rotating round block (13) is arranged at the side position of the second movable rod (11) of the support frame main body (3);
one side of the rotating round block (13) is equidistantly provided with a tooth-shaped block (14), the other side of the rotating round block is provided with an arc extrusion chute (15), a second T-shaped movable extrusion block (16) is movably connected in the arc extrusion chute (15), and the second T-shaped movable extrusion block (16) is movably inserted in the supporting framework main body (3).
2. The water conservancy pipeline construction filling support structure of claim 1, characterized in that: the reinforced support mechanism (7) comprises a first locking threaded column (701), a clamping groove (702), a first locking threaded groove (703), a first movable rod (704), a first extrusion chute (705), a transmission rack (706), a transmission gear group (707), a first pushing rack (708), an L-shaped push rod (709), a first T-shaped movable extrusion block (710), a second extrusion chute (711) and an arc auxiliary support plate (712), wherein the first locking threaded column (701) is arranged in the first locking threaded groove (703), the first locking threaded groove (703) is symmetrically arranged at one end of the support frame main body (3), the clamping groove (702) is arranged at the equidistant side of the first locking threaded column (701), the first movable rod (704) is movably arranged in the support frame main body (3), and a first connecting spring is arranged at one end of the support frame main body (3), a first extrusion chute (705) is arranged in the first movable rod (704) at a middle distance, a transmission rack (706) is arranged in the first extrusion chute (705), the transmission rack (706) is movably arranged in the support ring (6), the transmission rack (706) is arranged on one side of the transmission gear set (707) in a meshing connection mode, a first pushing rack (708) is arranged on the other side of the transmission gear set (707) in a meshing connection mode, an L-shaped push rod (709) is symmetrically arranged at one end of the first pushing rack (708), a first T-shaped movable extrusion block (710) is movably arranged on the side of one end of the L-shaped push rod (709), return springs are symmetrically arranged on the first T-shaped movable extrusion block (710), one end of the first T-shaped movable extrusion block (710) is provided with a slope, the other end of the first T-shaped movable extrusion block is arranged in a second extrusion chute (711), and the second extrusion chute (711) is symmetrically arranged on the side of the arc-shaped auxiliary support plate, the arc auxiliary supporting plate (712) is movably arranged in the supporting ring (6).
3. The water conservancy pipeline construction filling support structure of claim 1, characterized in that: the thickness of the second T-shaped movable extrusion block (16) is equal to the width of the section of the notch of the arc-shaped extrusion chute (15).
4. The water conservancy pipeline construction filling support structure of claim 2, characterized in that: the transmission rack (706) corresponds to the first extrusion chute (705) and the support ring (6) in arrangement position and has the same arrangement number.
5. The water conservancy pipeline construction filling support structure of claim 2, characterized in that: the second extrusion chutes (711) correspond to the first T-shaped movable extrusion blocks (710) in arrangement position and are arranged in the same number, and four groups are symmetrically arranged on two sides of the arc-shaped auxiliary support plate (712).
6. The water conservancy pipeline construction filling support structure of claim 2, characterized in that: the first push rack (708) is the same as the transmission gear set (707) and the transmission rack (706) in tooth form angle and modulus.
CN202010652485.8A 2020-07-08 2020-07-08 Supporting structure is filled in water conservancy pipeline construction Active CN111795215B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010652485.8A CN111795215B (en) 2020-07-08 2020-07-08 Supporting structure is filled in water conservancy pipeline construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010652485.8A CN111795215B (en) 2020-07-08 2020-07-08 Supporting structure is filled in water conservancy pipeline construction

Publications (2)

Publication Number Publication Date
CN111795215A true CN111795215A (en) 2020-10-20
CN111795215B CN111795215B (en) 2021-11-12

Family

ID=72810764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010652485.8A Active CN111795215B (en) 2020-07-08 2020-07-08 Supporting structure is filled in water conservancy pipeline construction

Country Status (1)

Country Link
CN (1) CN111795215B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112954993A (en) * 2021-02-01 2021-06-11 北海翰博士科技有限公司 Electromagnetic waveguide electric metal film with EMI resistance

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090026842A (en) * 2007-09-11 2009-03-16 주식회사 엠티마스타 Steel pipe repair and reinforcement work method
CN207205378U (en) * 2017-09-27 2018-04-10 洛阳长峰电子科技有限公司 A kind of milling machine of airborne vehicle hanger lock device housing
CN208651959U (en) * 2018-05-21 2019-03-26 杨毅 A kind of water pipeline for hydraulic engineering
CN209214482U (en) * 2018-10-24 2019-08-06 杭州师范大学 Water plant stem length observation device
CN110375125A (en) * 2019-06-05 2019-10-25 安徽管益生新材料科技有限公司 A kind of environmentally protective PE tubing
RU195865U1 (en) * 2019-04-16 2020-02-07 Общество С Ограниченной Ответственностью "Бт Свап" PIPE WITH CABLE CHANNELS

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090026842A (en) * 2007-09-11 2009-03-16 주식회사 엠티마스타 Steel pipe repair and reinforcement work method
CN207205378U (en) * 2017-09-27 2018-04-10 洛阳长峰电子科技有限公司 A kind of milling machine of airborne vehicle hanger lock device housing
CN208651959U (en) * 2018-05-21 2019-03-26 杨毅 A kind of water pipeline for hydraulic engineering
CN209214482U (en) * 2018-10-24 2019-08-06 杭州师范大学 Water plant stem length observation device
RU195865U1 (en) * 2019-04-16 2020-02-07 Общество С Ограниченной Ответственностью "Бт Свап" PIPE WITH CABLE CHANNELS
CN110375125A (en) * 2019-06-05 2019-10-25 安徽管益生新材料科技有限公司 A kind of environmentally protective PE tubing

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112954993A (en) * 2021-02-01 2021-06-11 北海翰博士科技有限公司 Electromagnetic waveguide electric metal film with EMI resistance

Also Published As

Publication number Publication date
CN111795215B (en) 2021-11-12

Similar Documents

Publication Publication Date Title
CN111795215B (en) Supporting structure is filled in water conservancy pipeline construction
CN111456770A (en) Movable tunnel segment supporting device for subway construction
CN111910779A (en) Connection mounting structure for steel frame building
CN210088169U (en) Soft foundation reinforcing structure for pipeline laying
CN215906996U (en) Steel construction building connecting piece
CN211990683U (en) Reinforcing bar bending device for housing construction
CN209814720U (en) Protective device for tubular column
CN213332945U (en) Stainless steel pipe that leakproofness is good
CN103967197A (en) Steel tube bundle combination structure provided with X-shaped web plates
CN210741099U (en) Pipeline heat cleaning furnace door
CN211498474U (en) Wet curing device for bridge anti-collision guardrail
CN214169876U (en) Scaffold reinforcing apparatus for construction
CN214273046U (en) Assembled steel structure engineering support
CN217234868U (en) Non-excavation repair structure suitable for large-diameter drainage pipeline
CN211081073U (en) Steel constructs construction and uses steel pipe support frame
CN218263399U (en) Road and bridge crack reinforced structure
CN215331193U (en) Fireproof material calcium sulfate base movable floor
CN211762271U (en) Core control device for producing gypsum fireproof door core plate
CN217324901U (en) Traffic engineering highway crack patching device
CN221221678U (en) Regional delivery pipe construction protection architecture
CN213477895U (en) Building engineering is with guardrail that has protective structure
CN210508631U (en) Steel pipe supporting rod structure for electric tower
CN220035702U (en) Steel member convenient to splice
CN216428581U (en) Steel beam connecting piece structure
CN215042834U (en) High stability building materials reinforcing bar conveyer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20211014

Address after: 314500 No.308, Hangfu Road, Chongfu Town, Tongxiang City, Jiaxing City, Zhejiang Province

Applicant after: Jiaxing Dingshan Information Technology Co.,Ltd.

Address before: 621000 No.59, middle section of Qinglong Avenue, Qingyi Town, Fucheng District, Mianyang City, Sichuan Province

Applicant before: Pang Jinchao

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20211021

Address after: 750409 room 18-1, 2 / F, building 9, Zhongkai central square, Ningdong energy and chemical base, Yinchuan City, Ningxia Hui Autonomous Region

Applicant after: Ningxia Zhonghong Construction Engineering Co.,Ltd.

Address before: 314500 No.308, Hangfu Road, Chongfu Town, Tongxiang City, Jiaxing City, Zhejiang Province

Applicant before: Jiaxing Dingshan Information Technology Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant