CN111764910A - Coal mine overpass air bridge roadway tunneling construction method - Google Patents

Coal mine overpass air bridge roadway tunneling construction method Download PDF

Info

Publication number
CN111764910A
CN111764910A CN202010585761.3A CN202010585761A CN111764910A CN 111764910 A CN111764910 A CN 111764910A CN 202010585761 A CN202010585761 A CN 202010585761A CN 111764910 A CN111764910 A CN 111764910A
Authority
CN
China
Prior art keywords
lane
roadway
overpass
beams
air bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010585761.3A
Other languages
Chinese (zh)
Inventor
李存禄
秦涛
姜启彬
王龙江
张现刚
路皓然
单辉庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linyi Mining Group Heze Coal Power Co Ltd
Original Assignee
Linyi Mining Group Heze Coal Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Linyi Mining Group Heze Coal Power Co Ltd filed Critical Linyi Mining Group Heze Coal Power Co Ltd
Priority to CN202010585761.3A priority Critical patent/CN111764910A/en
Publication of CN111764910A publication Critical patent/CN111764910A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/155Laggings made of strips, slats, slabs or sheet piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention provides a coal mine overpass air bridge tunneling construction method, and relates to the technical field of mine tunneling. The method comprises the following steps: A. excavating a foundation trench in an upper roadway according to the position of the calibrated overpass measured by the mine ground; B. paving transverse I-beams at the bottom of the base groove, and paving a first warp-weft net above the I-beams; C. laying longitudinal I-beams above the longitude and latitude net, and welding and fixing the transverse I-beams and the longitudinal I-beams through anchor rods; D. laying a second graticule above the longitudinal I-shaped steel, and fixedly connecting the two graticules through iron wires and anchor rods; E. pouring concrete in the foundation trench to manufacture an upper lane false bottom, and driving a lower lane; F. after the lower lane is tunneled to pass through the interchange position, laying a steel plate above the I-shaped steel frame shed of the lower lane; G. and (4) expanding the two sides of the lower lane, building a wall, and pouring concrete to manufacture the lower lane false roof. The method simplifies the process of air bridge tunneling construction, can also effectively prevent short circuit of wind current, and is safer and more stable in roadway support.

Description

Coal mine overpass air bridge roadway tunneling construction method
Technical Field
The invention relates to the technical field of mine roadway tunneling, in particular to a coal mine overpass roadway tunneling construction method.
Background
In the ventilation structure of the coal mine, the air bridge is a ventilation structure which separates the air inlet from the air return when the air inlet lane and the air return lane in the ventilation system need to be horizontally crossed. The mine overpass is easy to leak air due to the close distance of the overpass tunnels, and the two tunnels of the vertical overpass tunnels are an air inlet tunnel and an air return tunnel respectively, which often cause the short circuit of a ventilation system when air leakage occurs. In order to avoid short circuit of the overpass, the existing construction method is to directly pour the concrete air bridge between the upper layer of overpass roadway and the lower layer of overpass roadway, the concrete air bridge has compact structure and is firmer, but the construction of the concrete air bridge is complicated, the construction amount is large, and the construction cost is high. The concrete construction of the concrete air bridge comprises the steps of firstly expanding the two sides of the tunnel at the air bridge, digging a wall foundation after expanding the sides, then setting a reinforcement anchor rod as reinforcement, erecting a model box for pouring the wall, and finally erecting a construction shed perpendicular to the direction of the tunnel. In order to ensure the stability of ventilation and diversion of the tunnel, avoid ventilation short circuit caused by air leakage, ensure the stability of tunnel support and facilitate construction, the existing method for tunneling the tunnel of the overpass needs to be further improved.
Disclosure of Invention
In order to simplify the air bridge tunneling construction procedure, effectively prevent short circuit of air current and ensure the safety and stability of roadway support, the invention provides a coal mine overpass roadway tunneling construction method, which has the following specific technical scheme:
a coal mine overpass air bridge roadway tunneling construction method is characterized by comprising the following steps:
A. excavating a base groove on a bottom plate of an upper roadway according to the interchange position calibrated by the mine ground survey data;
B. paving transverse I-beams at the bottom of the base groove, and paving a first warp-weft net above the I-beams;
C. laying longitudinal I-beams above the first warp-weft net, and welding and fixing the transverse I-beams and the longitudinal I-beams through anchor rods;
D. a second graticule is laid above the longitudinal I-steel, and the first graticule and the second graticule are fixedly connected;
E. pouring concrete in the foundation trench to manufacture an upper lane false bottom, and driving a lower lane;
F. after the lower lane is tunneled to pass through the interchange position, laying a steel plate above the I-shaped steel frame shed of the lower lane;
G. and (4) expanding the two sides of the lower lane, building a wall, and pouring concrete to manufacture the lower lane false roof.
Preferably, the size of the foundation trench is at least 100mm larger than the width of the roadway of the upper roadway.
Preferably, the first warp-weft net and the second warp-weft net are fixedly connected through iron wires and anchor rods.
Preferably, the distance between the transverse and longitudinal i-beams is greater than 800 mm.
Preferably, the step of building the wall in the step G includes excavating a wall foundation, driving a reinforced anchor rod, manufacturing a mold box, and pouring the wall.
It is further preferable that the upper lane false bottom closes a bottom plate of the upper lane space, the lower lane false top closes a top plate of the lower lane space, and an airtight shell of the overpass is formed between the upper lane false bottom and the lower lane false top.
It is further preferred that when soft rock is arranged between the upper lane false bottom and the lower lane false top, a counter-pull anchor rod is arranged, and grouting is carried out on the soft rock from the upper lane top plate.
The coal mine overpass air bridge roadway tunneling construction method provided by the invention has the beneficial effects that: the method ensures the stable ventilation in the upper lane by excavating the foundation trench in the upper lane and constructing the artificial false bottom of the upper lane, and is more convenient to construct the wall and the false top in the lower lane, thereby simplifying the construction steps, not constructing an integral concrete overpass, completing the sealing between the overpass lanes at the false bottom of the upper lane and the false top of the lower lane, and avoiding the ventilation short circuit caused by air leakage.
Drawings
FIG. 1 is a schematic diagram of a construction process of coal mine overpass air bridge tunneling;
FIG. 2 is a top view of a construction roadway;
FIG. 3 is a cross-sectional view of a portion of a construction roadway;
in the figure: 1-upper lane false bottom, 2-lower lane false top, 3-single hydraulic prop, 4-hinged top beam, 5-I-steel, 6-anchor rod and 7-steel plate.
Detailed Description
A concrete embodiment of the coal mine overpass air bridge roadway excavation construction method provided by the invention is described with reference to fig. 1 to 3.
Example 1
A coal mine overpass tunnel driving construction method is applied to the construction of the overpass tunnel at the crossing position of an air inlet tunnel and an air return tunnel under a coal mine, and the method ensures the tightness by constructing an upper tunnel false bottom and a lower tunnel false top and avoids the short circuit of a ventilation system caused by air leakage, and comprises the following steps:
A. according to the position of the interchange calibrated according to the mine ground survey data, the upper lane of the interchange air bridge position is an upper layer lane, the lower lane is a lower layer lane, the upper lane and the lower lane are respectively an air inlet lane and an air return lane, and the upper lane can cross the lower lane through an upper slope lane and a lower slope lane. And excavating a foundation trench on the bottom plate of the upper roadway, wherein the size of the foundation trench is at least 100mm larger than the width of the upper roadway, and the depth of the foundation trench is determined according to the spacing distance between the upper roadway and the lower roadway, and is generally larger than 1000 mm.
B. And paving transverse I-beams at the bottom of the base groove, and paving a first warp-weft net above the I-beams. The I-steel can be 12# I-steel, the I-steel cushion is transversely arranged at the bottom of the base groove, the transverse I-steel is arranged perpendicular to the trend of the roadway, the I-steel is fixed in the bottom plates at two sides of the base groove, and then the graticule is laid in the base groove.
C. And laying longitudinal I-beams above the first warp-weft net, arranging the longitudinal I-beams along the trend of the roadway, and fixing the transverse I-beams and the longitudinal I-beams by welding through anchor rods, wherein the distance between the transverse I-beams and the longitudinal I-beams is more than 800 mm.
D. And a second graticule is laid above the longitudinal I-shaped steel, and the first graticule and the second graticule are fixedly connected. Wherein first longitude and latitude net and second longitude and latitude net are concrete through iron wire and stock fixed connection, can also can tighten through the iron wire through welded fastening and fix in addition can set up the group portion of the fixed longitude and latitude net structure of stock and foundation ditch.
E. And (5) pouring concrete in the foundation trench to manufacture an upper roadway false bottom, and tunneling a lower roadway. Concrete is poured in the foundation trench, the foundation trench side part, the I-shaped steel and the graticule form a whole under the action of the concrete, the concrete structure can be used for preferably sealing the upper roadway bottom plate, the reinforced concrete structure also has good bearing capacity and deformation capacity, and the width of the foundation trench is greater than that of the upper roadway, so that the complete sealing of the bottom plate can be ensured. And after the concrete is solidified, tunneling a lower lane, and carrying out shed supporting on the lower lane along with the tunneling of the lower lane.
F. And after the lower lane tunnels through the interchange position, laying a steel plate above the I-shaped steel frame shed of the lower lane. The steel plates are arranged densely, so that the roadway can be better supported, and convenience is provided for the next step of concrete pouring.
G. And (4) expanding the two sides of the lower lane, building a wall, and pouring concrete to manufacture the lower lane false roof. The step of building the wall includes, excavate the wall body basis, beat the stability of arrangement of reinforcement stock assurance building the wall, the preparation diaphragm capsule is conveniently pour, pours the wall body. And after the concrete pouring wall body is solidified, manufacturing a lower lane false roof above the steel plate, and forming the stable lower lane false roof by grouting.
The upper lane false bottom closes a bottom plate of the upper lane space, the lower lane false top closes a top plate of the lower lane space, and an airtight shell of the overpass is formed between the upper lane false bottom and the lower lane false top. When soft rock exists between the upper lane false bottom and the lower lane false top, a counter-pull anchor rod can be arranged, and grouting can be performed on the soft rock from the upper lane top plate, so that cracks are sealed, and air leakage is prevented.
The existing concrete air bridge is constructed, the space between an upper roadway and a lower roadway needs to be completely excavated and then concrete is poured, the method ensures stable ventilation in the upper roadway by excavating a foundation trench in the upper roadway and constructing an artificial false bottom of the upper roadway, the construction of wall body and false roof in the lower roadway is more convenient, the construction steps are simplified, the whole concrete overpass needs not to be constructed, the airtight between the overpass roadways is completed by the artificial bottom of the upper roadway and the false roof of the lower roadway, and the ventilation short circuit caused by air leakage is avoided.
Example 2
The method will be further explained by taking the mine-808 auxiliary air intake ascending and 1314 rail down-grade crossroads, -808 and filling connection roadway crossroads as examples in combination with the embodiment 1.
-808 auxiliary air intake ascending and 1314 rail descending overpass, -808 overpass with filling connection roadway, forming an overpass air bridge when the driving roadway is communicated, in order to prevent the air flow from generating short circuit when the overpass air bridge is communicated and ensure the stability and safety of ventilation system and the stability of roadway support. During construction, a construction false roof foundation trench is calibrated at the site position in advance, and concrete is poured into the foundation trench to build an upper lane false bottom (a lower lane false roof). After the head-on completely passes through the interchange position, the method starts to expand the two sides of the tunnel at the air bridge at the lower tunnel false roof (steel plates are laid above the I-shaped steel shed beam), the wall foundation is dug after the side expansion, reinforcement arrangement anchor rods are arranged to be used for reinforcement arrangement, a model box is erected for wall body pouring, and finally the construction shed is erected in the direction perpendicular to the tunnel. The construction of the overpass is completed in advance, so that the stability of wind current and the stability of roadway support safety before two roadways are communicated are guaranteed.
The concrete construction is as follows: firstly, excavating a foundation trench on a bottom plate of an upper roadway according to a position of a interchange calibrated by mine ground survey data, wherein the upper roadway is supported by a single hydraulic prop and a hinged top beam, the width of the upper roadway is 5m, and the width of the foundation trench is 7.2 m; secondly, laying transverse I-beams at the bottom of the base groove, using 12# I-beams, and laying a first warp-weft net above the I-beams; then, laying longitudinal I-beams above the first warp-weft net, and welding and fixing the transverse I-beams and the longitudinal I-beams through anchor rods, wherein the distance between the anchor rods is 2m, and the length of each anchor rod is 1.2 m; then laying a second graticule above the longitudinal I-steel, and fixedly connecting the first graticule with the second graticule; pouring concrete in the foundation trench to manufacture an upper lane false bottom, and driving a lower lane; after the lower lane is tunneled to pass through the interchange position, laying a 10mm steel plate above the I-shaped steel frame shed of the lower lane; and finally, expanding the two sides of the lower lane and building a wall, expanding the lower lane to 6m, and pouring concrete to manufacture the lower lane false roof.
The method for constructing the overpass in advance not only ensures the stability of the wind flow of the through front roadway of the overpass, but also shortens the link of the air bridge construction in the tunneling process by pouring and hardening the air bridge surface in the process of tunneling the overpass by a tunneling team.
It is to be understood that the above description is not intended to limit the present invention, and the present invention is not limited to the above examples, and those skilled in the art may make modifications, alterations, additions or substitutions within the spirit and scope of the present invention.

Claims (7)

1. A coal mine overpass air bridge roadway tunneling construction method is characterized by comprising the following steps:
A. excavating a base groove on a bottom plate of an upper roadway according to the interchange position calibrated by the mine ground survey data;
B. paving transverse I-beams at the bottom of the base groove, and paving a first warp-weft net above the I-beams;
C. laying longitudinal I-beams above the first warp-weft net, and welding and fixing the transverse I-beams and the longitudinal I-beams through anchor rods;
D. a second graticule is laid above the longitudinal I-steel, and the first graticule and the second graticule are fixedly connected;
E. pouring concrete in the foundation trench to manufacture an upper lane false bottom, and driving a lower lane;
F. after the lower lane is tunneled to pass through the interchange position, laying a steel plate above the I-shaped steel frame shed of the lower lane;
G. and (4) expanding the two sides of the lower lane, building a wall, and pouring concrete to manufacture the lower lane false roof.
2. The coal mine overpass air bridge roadway driving construction method according to claim 1, wherein the size of the foundation trench is at least 100mm larger than the roadway width of the upper roadway.
3. The coal mine interchange air bridge roadway driving construction method according to claim 1, wherein the first longitude and latitude net and the second longitude and latitude net are fixedly connected through iron wires and anchor rods.
4. The coal mine overpass air bridge roadway driving construction method according to claim 1, wherein the distance between the transverse I-shaped steel and the longitudinal I-shaped steel is larger than 800 mm.
5. The coal mine overpass air bridge roadway driving construction method according to claim 1, wherein the step of building the wall in the step G comprises the steps of excavating a wall foundation, driving a reinforcement anchor rod, manufacturing a mold box and pouring the wall.
6. The coal mine overpass air bridge tunneling construction method according to claim 1, wherein the upper lane false bottom closes a bottom plate of an upper lane space, the lower lane false top closes a top plate of a lower lane space, and an airtight shell of the overpass is formed between the upper lane false bottom and the lower lane false top.
7. The coal mine overpass air bridge roadway driving construction method according to claim 6, wherein a counter-pulling anchor rod is arranged between the upper roadway false bottom and the lower roadway false top when soft rock exists, and grouting is performed on the soft rock from the upper roadway top plate.
CN202010585761.3A 2020-06-24 2020-06-24 Coal mine overpass air bridge roadway tunneling construction method Pending CN111764910A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010585761.3A CN111764910A (en) 2020-06-24 2020-06-24 Coal mine overpass air bridge roadway tunneling construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010585761.3A CN111764910A (en) 2020-06-24 2020-06-24 Coal mine overpass air bridge roadway tunneling construction method

Publications (1)

Publication Number Publication Date
CN111764910A true CN111764910A (en) 2020-10-13

Family

ID=72722280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010585761.3A Pending CN111764910A (en) 2020-06-24 2020-06-24 Coal mine overpass air bridge roadway tunneling construction method

Country Status (1)

Country Link
CN (1) CN111764910A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113137243A (en) * 2021-03-27 2021-07-20 山东新巨龙能源有限责任公司 Reinforcing method for corrosion-resistant interchange roadway of loose coal cylinder

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5466187A (en) * 1991-05-28 1995-11-14 Jack Kennedy Metal Products And Buildings, Inc. Mine ventilation structure
US20100017975A1 (en) * 2008-07-28 2010-01-28 Kennedy Metal Products & Buildings, Inc. Reinforced Mine Ventilation Device
CN102383820A (en) * 2011-10-06 2012-03-21 山西晋城无烟煤矿业集团有限责任公司 Coal mine underground airbridge construction method
CN103410550A (en) * 2013-08-05 2013-11-27 山西晋城无烟煤矿业集团有限责任公司 Method for constructing underground air crossing of coal mine
CN203730041U (en) * 2014-01-26 2014-07-23 平顶山天安煤业股份有限公司 Suspended air bridge
CN109209393A (en) * 2018-09-13 2019-01-15 内蒙古伊泰京粤酸刺沟矿业有限责任公司 Tunnel grade separation speedy construction method
CN208816163U (en) * 2018-06-18 2019-05-03 北京昊华能源股份有限公司 A kind of soft air crossing of return air access

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5466187A (en) * 1991-05-28 1995-11-14 Jack Kennedy Metal Products And Buildings, Inc. Mine ventilation structure
US20100017975A1 (en) * 2008-07-28 2010-01-28 Kennedy Metal Products & Buildings, Inc. Reinforced Mine Ventilation Device
CN102383820A (en) * 2011-10-06 2012-03-21 山西晋城无烟煤矿业集团有限责任公司 Coal mine underground airbridge construction method
CN103410550A (en) * 2013-08-05 2013-11-27 山西晋城无烟煤矿业集团有限责任公司 Method for constructing underground air crossing of coal mine
CN203730041U (en) * 2014-01-26 2014-07-23 平顶山天安煤业股份有限公司 Suspended air bridge
CN208816163U (en) * 2018-06-18 2019-05-03 北京昊华能源股份有限公司 A kind of soft air crossing of return air access
CN109209393A (en) * 2018-09-13 2019-01-15 内蒙古伊泰京粤酸刺沟矿业有限责任公司 Tunnel grade separation speedy construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113137243A (en) * 2021-03-27 2021-07-20 山东新巨龙能源有限责任公司 Reinforcing method for corrosion-resistant interchange roadway of loose coal cylinder

Similar Documents

Publication Publication Date Title
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN110486034A (en) Subway station and construction method based on pile foundation in four pilot tunnel of single layer and middle drift
CN112575670A (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN111485902B (en) Tunnel construction method for side-span non-filling type deep and large karst cave section
CN112681374A (en) Shallow-buried underground-excavated channel cover excavation top-down construction method under complex conditions
CN111236952A (en) Full-recovery assembly type rectangular pipe-jacking working well steel structure supporting device and construction method of working well
CN106812359B (en) A kind of assembled underground garage and its method of construction
CN111764910A (en) Coal mine overpass air bridge roadway tunneling construction method
CN110994523B (en) Method and system for protecting cable
KR100510092B1 (en) A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it
CN111706366A (en) Tunnel lining structure penetrating through large full-filling karst cave and construction method
CN111593739A (en) Cement mixing pile enclosure wall-profile steel cantilever type combined support
CN111549789A (en) Reinforcing structure for foundation pit support and construction method thereof
CN111705576A (en) Steep slope high-filling roadbed structure adopting high-density EPS filler
CN216894442U (en) Multi-guide-hole combined excavation steel frame connecting device
CN216765941U (en) Tunnel decompression load shedding structure under bias voltage state
CN114320388A (en) Underground excavation large-span station reserved tunnel underpass structure and construction method thereof
CN205857198U (en) Subway station construction main body building enclosure
CN112507424A (en) Construction method for shield tunneling of expansive soil stratum to pass through railway track downwards
CN112901213A (en) Underground roof construction method based on pipe curtain support
CN112627002A (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof
CN217176659U (en) Underground excavation large-span station reserved tunnel underpass structure
CN111218873A (en) Steep slope supporting stress type roadbed structure and construction method
CN218911435U (en) Half-cover-excavated foundation pit cover plate supporting structure suitable for non-horizontal topography condition
CN117967323B (en) Reinforcing ring structure at hydraulic tunnel fork-to-branch hole interface and roof-picking construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201013

RJ01 Rejection of invention patent application after publication