CN111667224A - APP for dynamically managing engineering construction based on project division at multiple terminals - Google Patents

APP for dynamically managing engineering construction based on project division at multiple terminals Download PDF

Info

Publication number
CN111667224A
CN111667224A CN201910161976.XA CN201910161976A CN111667224A CN 111667224 A CN111667224 A CN 111667224A CN 201910161976 A CN201910161976 A CN 201910161976A CN 111667224 A CN111667224 A CN 111667224A
Authority
CN
China
Prior art keywords
terminal
construction
project
app
safety
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910161976.XA
Other languages
Chinese (zh)
Inventor
王民峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910161976.XA priority Critical patent/CN111667224A/en
Publication of CN111667224A publication Critical patent/CN111667224A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

An APP with multiple terminals for dynamically managing engineering construction based on project division is characterized in that engineering projects are divided into management bases; the terminal management window of each necessary post personnel of the construction unit and the terminal management windows of other participating units are provided, and each terminal management window is provided with a plurality of working command buttons. The management window of the multiple terminals is set according to the actual work content of the 'people' corresponding to each terminal in the engineering construction management; the dynamic management process is a technical dynamic management process which is established by each terminal according to the actual work process of a 'person' corresponding to the terminal in engineering management in the aspects of engineering construction progress, quality and safety. And each terminal can check the information of the engineering construction progress, quality and safety. Each terminal control window is provided with a 'standard, standard and regulation retrieval' search column; after the APP is used, an engineering construction statistical table can be derived.

Description

APP for dynamically managing engineering construction based on project division at multiple terminals
Technical Field
The invention relates to engineering management APP, in particular to engineering construction dynamic management. And a plurality of terminal management windows are provided for each post of the project, so as to dynamically manage the progress, quality, safety and other aspects of the project construction based on project division.
Background
Currently, a project management related system usually manages projects based on BIM, that is, a BIM database, such as chinese patent publication No. 109064133a, must be established first. Although the BIM system makes the construction of the project datamation, three-dimensional and visualized, the BIM technology is not fully applied, the BIM database is not a data model which is required to be established for each project, and the establishment of the BIM requires professional personnel, a certain amount of time and a lot of cost, so that the professional personnel and the organization engaged in the BIM are rare at present.
In addition, there is a method of electronically processing a project construction management process file in a conventional project management system, for example, chinese patent publication No. 108647311 a. The method has the advantages that the project files are only electronically stored and checked, and the management control of the project is not realized.
In addition, the existing project management APP sets relevant information, task management, correction and fine, materials, progress plans, equipment management, labor roll calling, incoming and outgoing documents, standard drawing query, audio and video materials and construction logs of a project, such as an intelligent construction site APP which can be searched on a network. The APP relates to various information of engineering construction, but the APP only has the functions of electronic storage and viewing, is static data collection management and has no function of dynamic management.
Disclosure of Invention
In order to overcome the incomplete popularity of the BIM based on the BIM engineering construction management system in the engineering industry and the static management of only electronic storage and check of a common engineering management system, the invention provides an engineering construction management APP which divides all engineering projects into a management basis and takes the actual work content and work flow of each post personnel in engineering construction as a dynamic management flow.
The technical scheme adopted by the invention for solving the technical problems is as follows: a multi-terminal APP for dynamically managing engineering construction based on project division is provided, wherein the multi-terminal APP is as follows: construction unit- "project manager terminal", "project chief worker terminal", "data member terminal", "constructor terminal", "quality inspector terminal", "measurer terminal", "tester terminal", "safety member terminal", "measurer terminal", "construction team leader terminal", and "supervision unit terminal", "construction unit terminal", "safety supervision agency terminal", "quality supervision agency terminal". The management window content of each terminal is different and is set according to the actual work content of the 'people' corresponding to the terminal in engineering management. The management process of each terminal in the aspects of project construction progress, quality and safety is that different technical dynamic management process schemes are established according to the actual work process of a 'person' corresponding to the terminal in project management.
The above-mentioned many terminals carry out the APP of dynamic management to engineering construction based on project division, each terminal correspond "people", mean: a project manager registered in a construction unit of the APP project manager terminal, a data worker registered in a construction unit of the APP data worker terminal, a constructor registered in a construction unit of the APP constructor terminal, a quality inspector registered in a construction unit of the APP quality inspector terminal, a measurer registered in a construction unit of the APP measurer terminal, a tester registered in a construction unit of the APP tester terminal, a security worker registered in a construction unit of the APP security worker terminal, a measurer registered in a construction unit of the APP metering worker terminal, a construction team length registered in a construction unit of the APP construction team leader terminal, a supervisor engineer or manager registered in a supervisor unit of the APP supervisor terminal, The construction site representatives of the construction units logged in the APP 'construction unit terminal', the safety supervision institution supervisors logged in the APP 'safety supervision institution terminal' and the quality supervision institution supervisors logged in the safety supervision institution 'quality supervision institution terminal'.
Foretell many terminals carry out the APP of dynamic management to the engineering construction based on the project division, the management window at each terminal set up multiple work order button, have: the work buttons include < upload >, < application >, < release >, < modification >, < issue >, < reminder >, < review completed >, < review >, < check >, < measurement completed >.
The above-mentioned APP that carries out dynamic management to engineering construction based on project division of many terminals, the division based on project be based on engineering project divides the management basis, and refer to: 1. the APP is led into the engineering project division in an excle format at the beginning of application, and then in a working module window for managing the engineering construction progress, quality and safety in the APP application, the engineering project division corresponding to the APP must be selected; 2. after the APP is used, an engineering construction statistical table which corresponds to engineering project division and contains data of 'progress planning date', 'construction date', 'whether measurement is performed', 'whether test is performed', 'whether background is handed over', 'material test condition', 'concrete test block result', 'construction engineering quantity', 'settlement engineering quantity' and 'acceptance' can be derived.
Foretell many terminals carry out the APP of dynamic management to the engineering construction based on the project division, each terminal in the work module that engineering construction progress, quality, safety set up, have: the progress aspect is as follows: the working modules of construction progress plan, material plan, tomorrow plan, week plan, concrete pouring plan and construction log; in the quality aspect: the working modules of construction flow, image progress, technical intersection, construction measurement, material entrance, material distribution, project acceptance and construction project amount; and (4) safety aspects: the safety inspection module comprises a safety technology intersection working module, a safety inspection working module, a safety civilization display working module, a safety hazard working module and a safety article registration working module.
The above-mentioned many terminals carry out APP of dynamic management to the engineering construction based on project division, the technical dynamic management flow scheme of establishing in the aspect of the engineering construction progress have: 1. dynamic management process of "construction progress plan": the 'data man terminal' uploads the project construction progress plan, the annual progress plan and the monthly progress plan which are managed and approved, and then the project manager terminal or the project master terminal < approval > is followed by < issue >. The uploading work of the construction progress plan mainly comprises two steps: the first step is to select the project part in the project division, and the second step is to add the planning time. 2. Dynamic management process of "material planning": according to the construction progress plan and the engineering quantity, the 'constructor terminal' uploads the material plan of the month and the next month, and then the 'project manager terminal' or the 'project chief worker terminal' signs the material plan after the 'modification'. The uploading work of the material plan mainly comprises three steps: the method comprises the steps of firstly, selecting engineering parts in engineering division, secondly, adding the types, specification models and quantity of materials, and thirdly, adding planned service time. 3. Dynamic management process of "tomorrow plan": the construction plan of the next day is uploaded by the 'constructor terminal' according to the actual construction situation of the site, and then is issued after passing through the 'project manager terminal' or the 'project chief worker terminal' < correction >. The uploading work of the tomorrow plan mainly comprises three steps: selecting time in the first step, selecting engineering positions in engineering division in the second step, checking measurement completion conditions, test completion conditions, technical background completion conditions and safety background completion conditions in the third step, and if the measurement completion conditions, the test completion conditions, the technical background completion conditions and the safety background completion conditions are not completed, selecting a reminding button and informing relevant post persons. 4. Dynamic management process of "weekly plan": the construction plan of the next week is uploaded by the 'constructor terminal' according to the actual construction situation of the site, and then is issued after passing through the 'project manager terminal' or the 'project chief worker terminal' < correction >. The uploading work of the week plan mainly comprises three steps: selecting time in the first step, selecting engineering parts in engineering division in the second step, checking measurement completion conditions, test completion conditions, technical background completion conditions and safety background completion conditions in the third step, and if the measurement completion conditions, the test completion conditions, the technical background completion conditions and the safety background completion conditions are not completed, selecting a reminding state and informing a terminal of a related post person. 5. Dynamic management process of concrete pouring plan: according to the actual construction situation of the site, the 'constructor terminal' uploads the plan of the concrete pouring in the 'tomorrow plan' and the 'week plan', then the plan is issued after passing through the 'project manager terminal' or the 'project master terminal' < correction >, and then < reminding > is sent to the 'tester terminal'. The uploading work of the concrete pouring plan mainly comprises three steps: the method comprises the steps of firstly selecting the time of planned pouring, secondly selecting the project parts in project division, and thirdly filling the project amount of concrete for planned pouring. 6. Dynamic management process of the construction log: the construction content completed on the day is collected < uploaded > by a 'constructor terminal' and a 'quality inspector terminal' according to the actual construction situation on the spot, and then < signing > is carried out after the 'project manager terminal' or the 'project master terminal' < correction >. The reporting work of the concrete pouring plan mainly comprises three steps: the method comprises the steps of firstly selecting the time of planned pouring, secondly selecting the project parts in project division, and thirdly filling the project amount of concrete for planned pouring.
The above-mentioned many terminals carry out APP of dynamic management to engineering construction based on project division, the technical dynamic management flow scheme of establishing in the aspect of engineering construction quality have: 1. dynamic management process of "construction process": the construction process is edited by the ' constructor terminal ' according to the construction scheme, construction settlement and construction drawing, then the construction process is uploaded, and then the construction team leader terminal ' is issued after the project master terminal ' revises '. The uploading work of the 'construction process' mainly comprises two steps: the first step is to select the engineering position, and the second step is to edit or paste the construction process. 2. Dynamic management process of 'image progress': the 'constructor terminal' carries out construction picture < uploading > on the intermediate construction process, the completed construction process, the concealed project, the unit project (project division), the subsection project and the unit project according to the actual construction situation of the site, and then the 'project master terminal' < release >. The uploading work of the image progress mainly comprises three steps: selecting time in the first step, selecting engineering parts in engineering division in the second step, and uploading construction pictures in the third step. 3. The dynamic management process of 'technical background of disclosure': the ' constructor terminal ' completes the technical background by ' uploading ' after completing the technical background according to the actual construction condition, the construction scheme and the construction flow editing technology on site, then ' issuing ' after ' project master terminal ' < modification >, then ' reminding ', ' construction captain terminal ' and ' construction captain terminal ' click ' after looking up, and then completes the technical background completing. The uploading work of 'technical background of disclosure' mainly comprises two steps: the first step is to edit or paste the technical background content, and the second step is to select the technical background time. 4. Dynamic management process of "construction survey": the "surveyor terminal" selects which measurement is (measurement is divided into original topography measurement, pre-construction measurement, post-construction measurement, completion measurement) first, and selects < measurement completion > and then < prompt > "constructor terminal" after the completion of the measurement. The uploading window of the 'construction measurement' mainly comprises two steps: the first step selects time, and the second step selects engineering parts in engineering division. 5. Dynamic management process of "material approach": the 'material staff terminal' edits the post < upload > according to the approach situation of the material, passes through the 'project manager terminal' < issue >, and then < remind > on the 'tester terminal'. The uploading work of the material approach mainly comprises three steps: the method comprises the steps of firstly selecting a material using part, secondly adding the type, specification and quantity of materials, and thirdly adding the material approach time. 6. Dynamic management process of "material dispensing": the 'material person terminal' edits < upload > according to the material distribution condition, and then passes through the 'project manager terminal' < issue >. The uploading of "material dispensing" essentially comprises three steps: the first step is to select the material using position, the second step is to select the advanced material, and the third step is to add the material sending time. 7. Dynamic management process of "engineering acceptance": the project acceptance comprises hidden project acceptance, subsection project acceptance, unit project acceptance, completion acceptance and completion acceptance, a quality inspector terminal carries out uploading on project parts planned to be accepted according to the project completion condition, signing and issuing are carried out after a project manager terminal or a project master terminal < modification >, then reminding is carried out at a constructor terminal and a supervision unit terminal, and after the acceptance is finished, a picture is taken by the quality inspector terminal and uploaded. The uploading work of the project acceptance mainly comprises four steps: selecting a part of a project to be checked and accepted, selecting the time to be checked and accepted, adding the time to be checked and accepted, and uploading a checking and accepting picture. 8. Dynamic management process of "construction work volume": the construction team leader terminal confirms the construction workload according to the actual construction workload < upload > of the unit project (project), and the construction workload is checked by the constructor terminal. The uploading work of the construction work amount mainly comprises three steps: the first step is to select the project part, the second step is to select the construction time, and the third step is to fill the construction project amount.
The above-mentioned many terminals carry out APP of dynamic management to engineering construction based on project partition, the technical dynamic management flow scheme of establishing in engineering construction safety aspect have: 1. the dynamic management process of the 'safety technology background' is as follows: the safety staff terminal edits safety technology according to actual construction conditions, construction schemes and construction flows on site and then sends the safety technology to the terminal < upload >, the safety staff terminal < amend > and then sends the safety technology to the terminal < remind > "construction captain", and the terminal < complete check-up > is clicked after the safety staff terminal looks up, so that the safety technology is finished. The uploading work of the safety technology cross bottom mainly comprises two steps: the first step is to edit or paste the contents of the secure technology background, and the second step is to select the time of the secure technology background. 2. Dynamic management flow of "security check": the safety inspection is carried out by a 'safety staff terminal' < uploading >, and then a 'project manager terminal' or a 'project chief staff terminal' < issuing >, a 'constructor terminal' and a 'construction team leader terminal' are carried out, and finally, after the safety inspection is finished, the 'safety staff terminal' < uploading > inspection pictures are carried out. The uploading work of the safety check mainly comprises three steps: the method comprises the steps of selecting inspection time, editing inspection content and uploading inspection pictures. 3. The dynamic management process of the safety civilization display comprises the following steps: and the 'security officer terminal' < uploading > security civilized construction management pictures. The uploading work of the safety civilization display mainly comprises three steps: selecting time in the first step, selecting parts in the second step, and uploading pictures in the third step. 4. The dynamic management process of the potential safety hazard comprises the following steps: the safety modification is completed by a safety personnel terminal < uploading > potential safety hazard, a project manager terminal < signing off >, a constructor terminal, a quality inspector terminal and a construction captain terminal, and finally a safety modification is completed, and the safety personnel terminal < uploading > modified picture is obtained. The uploading work of the safety hidden trouble mainly comprises five steps: selecting time, selecting potential safety hazard parts, editing potential safety hazard contents, selecting an adjustment and modification date and uploading an adjusted and modified picture. 5. Dynamic management process of "security articles registration": security supplies purchase and issue records are < uploaded > by the "security officer terminal". The uploading of the safety supplies registration is mainly to fill in a safety supplies registration form, and the form has the following contents: the method comprises the steps of purchasing time, name and specification models of the safety supplies, purchasing quantity, issuing date, name and specification models of the issued safety supplies, issuing quantity, purchasing unit price and project parts to be used.
The APP for dynamically managing the engineering construction based on project division by the multiple terminals has a search column of 'standard, standard and regulation retrieval' in each terminal management window. Inputting in a search bar: when any one of "material", "product", "behavior", "concept", "method", "object of task", "technical content", "quality requirement", and "form" is used, the contents of the corresponding item in "standard", "specification", and "procedure" of each industry and each department appear in the window, and the contents include the names, chapters, paragraph numbers, and paragraph contents of "standard", "specification", and "procedure".
The APP dynamically managing the engineering construction by the multiple terminals based on the project division has the advantages that the APP dynamically managing the engineering construction by the project division adopts the management foundation divided by the engineering project, provides the terminal management window of each necessary post personnel of a construction unit and the terminal management windows and the work command buttons of other participating units, sets different terminal management windows according to the actual work content of each terminal corresponding to people, and takes the actual construction management flow as the process of the APP dynamic management. And each terminal can check the information of the engineering construction progress, quality and safety. And finally, the exported engineering construction statistical form can be developed according to the engineering part, all data in the aspects of progress, quality and safety can be checked, and the arrangement is clear.
Drawings
The invention is further illustrated with reference to the following figures and examples.
FIG. 1 is a schematic diagram of the first page of APP in the present invention;
FIG. 2 is a schematic diagram of a project manager terminal management window of the APP in the present invention;
FIG. 3 is a schematic diagram of a project headquarters terminal management window of the APP in the present invention;
FIG. 4 is a schematic diagram of a constructor terminal management window of the APP of the invention;
FIG. 5 is a schematic diagram of a management window of an APP quality inspector terminal of the present invention;
FIG. 6 is a schematic diagram of a terminal management window of an APP security officer according to the present invention;
FIG. 7 is a schematic diagram of a materials manager terminal management window of the APP of the present invention;
FIG. 8 is a schematic diagram of a tester terminal management window of the APP in the present invention;
FIG. 9 is a schematic diagram of a terminal management window of a measurer of the APP in the present invention;
FIG. 10 is a schematic diagram of a terminal management window of a metering staff of the APP in the invention;
FIG. 11 is a diagram of a data administrator terminal management window of the APP of the present invention;
FIG. 12 is a schematic diagram of a construction captain terminal management window of the APP in the invention;
FIG. 13 is a schematic diagram of a terminal management window of an APP supervisor and a construction unit;
FIG. 14 is a schematic diagram of a terminal management window of a quality supervision unit APP in the present invention;
FIG. 15 is a schematic diagram of a terminal management window of an APP;
FIG. 16 is a statistical representation of engineering construction of the APP of the present invention;
FIG. 17 is a security article registration intent for the APP of the present invention;
Detailed Description
[ example 1 ]
The APP that the multi-terminal carries out dynamic management to the engineering construction based on project division, the technical dynamic management flow scheme in the aspect of the engineering construction progress is: 1. dynamic management process of "construction progress plan": the 'data man terminal' uploads the project construction progress plan, the annual progress plan and the monthly progress plan which are managed and approved, and then the project manager terminal or the project master terminal < approval > is followed by < issue >. The uploading work of the construction progress plan mainly comprises two steps: the first step is to select the project part in the project division, and the second step is to add the planning time. 2. Dynamic management process of "material planning": according to the construction progress plan and the engineering quantity, the 'constructor terminal' uploads the material plan of the month and the next month, and then the 'project manager terminal' or the 'project chief worker terminal' signs the material plan after the 'modification'. The uploading work of the material plan mainly comprises three steps: the method comprises the steps of firstly, selecting engineering parts in engineering division, secondly, adding the types, specification models and quantity of materials, and thirdly, adding planned service time. 3. Dynamic management process of "tomorrow plan": the construction plan of the next day is uploaded by the 'constructor terminal' according to the actual construction situation of the site, and then is issued after passing through the 'project manager terminal' or the 'project chief worker terminal' < correction >. The uploading work of the tomorrow plan mainly comprises three steps: selecting time in the first step, selecting engineering positions in engineering division in the second step, checking measurement completion conditions, test completion conditions, technical background completion conditions and safety background completion conditions in the third step, and if the measurement completion conditions, the test completion conditions, the technical background completion conditions and the safety background completion conditions are not completed, selecting a reminding button and informing relevant post persons. 4. Dynamic management process of "weekly plan": the construction plan of the next week is uploaded by the 'constructor terminal' according to the actual construction situation of the site, and then is issued after passing through the 'project manager terminal' or the 'project chief worker terminal' < correction >. The uploading work of the week plan mainly comprises three steps: selecting time in the first step, selecting engineering parts in engineering division in the second step, checking measurement completion conditions, test completion conditions, technical background completion conditions and safety background completion conditions in the third step, and if the measurement completion conditions, the test completion conditions, the technical background completion conditions and the safety background completion conditions are not completed, selecting a reminding state and informing a terminal of a related post person. 5. Dynamic management process of concrete pouring plan: according to the actual construction situation of the site, the 'constructor terminal' uploads the plan of the concrete pouring in the 'tomorrow plan' and the 'week plan', then the plan is issued after passing through the 'project manager terminal' or the 'project master terminal' < correction >, and then < reminding > is sent to the 'tester terminal'. The uploading work of the concrete pouring plan mainly comprises three steps: the method comprises the steps of firstly selecting the time of planned pouring, secondly selecting the project parts in project division, and thirdly filling the project amount of concrete for planned pouring. 6. Dynamic management process of the construction log: the construction content completed on the day is collected < uploaded > by a 'constructor terminal' and a 'quality inspector terminal' according to the actual construction situation on the spot, and then < signing > is carried out after the 'project manager terminal' or the 'project master terminal' < correction >. The reporting work of the concrete pouring plan mainly comprises three steps: the method comprises the steps of firstly selecting the time of planned pouring, secondly selecting the project parts in project division, and thirdly filling the project amount of concrete for planned pouring.
[ example 2 ]
The APP that carries out dynamic management to engineering construction based on project division is carried out to many terminals, and the technical dynamic management flow scheme in the aspect of engineering construction quality is: 1. dynamic management process of "construction process": the construction process is edited by the ' constructor terminal ' according to the construction scheme, construction settlement and construction drawing, then the construction process is uploaded, and then the construction team leader terminal ' is issued after the project master terminal ' revises '. The uploading work of the 'construction process' mainly comprises two steps: the first step is to select the engineering position, and the second step is to edit or paste the construction process. 2. Dynamic management process of 'image progress': the 'constructor terminal' carries out construction picture < uploading > on the intermediate construction process, the completed construction process, the concealed project, the unit project (project division), the subsection project and the unit project according to the actual construction situation of the site, and then the 'project master terminal' < release >. The uploading work of the image progress mainly comprises three steps: selecting time in the first step, selecting engineering parts in engineering division in the second step, and uploading construction pictures in the third step. 3. The dynamic management process of 'technical background of disclosure': the ' constructor terminal ' completes the technical background by ' uploading ' after completing the technical background according to the actual construction condition, the construction scheme and the construction flow editing technology on site, then ' issuing ' after ' project master terminal ' < modification >, then ' reminding ', ' construction captain terminal ' and ' construction captain terminal ' click ' after looking up, and then completes the technical background completing. The uploading work of 'technical background of disclosure' mainly comprises two steps: the first step is to edit or paste the technical background content, and the second step is to select the technical background time. 4. Dynamic management process of "construction survey": the "surveyor terminal" selects which measurement is (measurement is divided into original topography measurement, pre-construction measurement, post-construction measurement, completion measurement) first, and selects < measurement completion > and then < prompt > "constructor terminal" after the completion of the measurement. The uploading window of the 'construction measurement' mainly comprises two steps: the first step selects time, and the second step selects engineering parts in engineering division. 5. Dynamic management process of "material approach": the 'material staff terminal' edits the post < upload > according to the approach situation of the material, passes through the 'project manager terminal' < issue >, and then < remind > on the 'tester terminal'. The uploading work of the material approach mainly comprises three steps: the method comprises the steps of firstly selecting a material using part, secondly adding the type, specification and quantity of materials, and thirdly adding the material approach time. 6. Dynamic management process of "material dispensing": the 'material person terminal' edits < upload > according to the material distribution condition, and then passes through the 'project manager terminal' < issue >. The uploading of "material dispensing" essentially comprises three steps: the first step is to select the material using position, the second step is to select the advanced material, and the third step is to add the material sending time. 7. Dynamic management process of "engineering acceptance": the project acceptance comprises hidden project acceptance, subsection project acceptance, unit project acceptance, completion acceptance and completion acceptance, a quality inspector terminal carries out uploading on project parts planned to be accepted according to the project completion condition, signing and issuing are carried out after a project manager terminal or a project master terminal < modification >, then reminding is carried out at a constructor terminal and a supervision unit terminal, and after the acceptance is finished, a picture is taken by the quality inspector terminal and uploaded. The uploading work of the project acceptance mainly comprises four steps: selecting a part of a project to be checked and accepted, selecting the time to be checked and accepted, adding the time to be checked and accepted, and uploading a checking and accepting picture. 8. Dynamic management process of "construction work volume": the construction team leader terminal confirms the construction workload according to the actual construction workload < upload > of the unit project (project), and the construction workload is checked by the constructor terminal. The uploading work of the construction work amount mainly comprises three steps: the first step is to select the project part, the second step is to select the construction time, and the third step is to fill the construction project amount.
[ example 3 ]
Many terminals carry out the APP of dynamic management to engineering construction based on project division, and the technical dynamic management flow scheme in the aspect of engineering construction safety does: 1. the dynamic management process of the 'safety technology background' is as follows: the safety staff terminal edits safety technology according to actual construction conditions, construction schemes and construction flows on site and then sends the safety technology to the terminal < upload >, the safety staff terminal < amend > and then sends the safety technology to the terminal < remind > "construction captain", and the terminal < complete check-up > is clicked after the safety staff terminal looks up, so that the safety technology is finished. The uploading work of the safety technology cross bottom mainly comprises two steps: the first step is to edit or paste the contents of the secure technology background, and the second step is to select the time of the secure technology background. 2. Dynamic management flow of "security check": the safety inspection is carried out by a 'safety staff terminal' < uploading >, and then a 'project manager terminal' or a 'project chief staff terminal' < issuing >, a 'constructor terminal' and a 'construction team leader terminal' are carried out, and finally, after the safety inspection is finished, the 'safety staff terminal' < uploading > inspection pictures are carried out. The uploading work of the safety check mainly comprises three steps: the method comprises the steps of selecting inspection time, editing inspection content and uploading inspection pictures. 3. The dynamic management process of the safety civilization display comprises the following steps: and the 'security officer terminal' < uploading > security civilized construction management pictures. The uploading work of the safety civilization display mainly comprises three steps: selecting time in the first step, selecting parts in the second step, and uploading pictures in the third step. 4. The dynamic management process of the potential safety hazard comprises the following steps: the safety modification is completed by a safety personnel terminal < uploading > potential safety hazard, a project manager terminal < signing off >, a constructor terminal, a quality inspector terminal and a construction captain terminal, and finally a safety modification is completed, and the safety personnel terminal < uploading > modified picture is obtained. The uploading work of the safety hidden trouble mainly comprises five steps: selecting time, selecting potential safety hazard parts, editing potential safety hazard contents, selecting an adjustment and modification date and uploading an adjusted and modified picture. 5. Dynamic management process of "security articles registration": security supplies purchase and issue records are < uploaded > by the "security officer terminal". The uploading of the safety supplies registration is mainly to fill in a safety supplies registration form, and the form has the following contents: the method comprises the steps of purchasing time, name and specification models of the safety supplies, purchasing quantity, issuing date, name and specification models of the issued safety supplies, issuing quantity, purchasing unit price and project parts to be used.
[ example 4 ]
The APP for dynamically managing the engineering construction based on project division by the multiple terminals has a 'standard, standard and regulation retrieval' search column in each terminal management window. Inputting in a search bar: when any one of "material", "product", "behavior", "concept", "method", "object of task", "technical content", "quality requirement", and "form" is used, the contents of the corresponding item in "standard", "specification", and "procedure" of each industry and each department appear in the window, and the contents include the names, chapters, paragraph numbers, and paragraph contents of "standard", "specification", and "procedure".
[ example 5 ]
After the APP dynamically managing the project construction based on project division is used, the APP with the multiple terminals can derive a project construction statistical table which corresponds to the project part of the project division and contains data such as 'progress planning date', 'construction date', 'whether measurement', 'whether test', 'whether delivery is made', 'material test condition', 'concrete test block result', 'construction project amount', 'settlement project amount' and 'acceptance condition'.

Claims (8)

1. An APP with multiple terminals for dynamically managing engineering construction based on project division is characterized in that engineering projects are divided into management bases; providing a multi-terminal management window, and setting various working command buttons for each terminal management window; the management window of the multiple terminals is set according to the actual work content of the 'people' corresponding to each terminal in the engineering construction management; the dynamic management flow is a technical dynamic management flow which is formed by working modules of all terminals in the aspects of project construction progress, quality and safety and is established according to the actual work flow of a 'person' corresponding to the terminal in project management; each terminal can check information of the construction progress, quality and safety of the project; each terminal control window is provided with a 'standard, standard and regulation retrieval' search column; after the APP is used, an engineering construction statistical table can be derived.
2. The multi-terminal APP for dynamically managing engineering construction based on project partitioning as claimed in claim 1, wherein said multi-terminal APP comprises: construction unit- "project manager terminal", "project chief worker terminal", "data member terminal", "constructor terminal", "quality inspector terminal", "measurer terminal", "tester terminal", "safety member terminal", "measurer terminal", "construction team leader terminal", and "supervision unit terminal", "construction unit terminal", "safety supervision agency terminal", "quality supervision agency terminal".
3. The APP for dynamically managing engineering construction based on project division by multiple terminals according to claim 1, wherein the multiple terminal management window is provided with multiple working command buttons, including: the work buttons include < upload >, < application >, < release >, < modification >, < issue >, < reminder >, < review completed >, < review >, < check >, < measurement completed >.
4. The APP of claim 1, wherein the project division based APP for dynamically managing project construction comprises: 1. the APP is led into the engineering project division in an excle format at the beginning of application, and then in a working module window for managing the engineering construction progress, quality and safety in the APP application, the engineering project division corresponding to the APP must be selected; 2. after the APP is used, an engineering construction statistical table with engineering parts corresponding to engineering project division can be derived.
5. The APP for dynamically managing engineering construction based on project division by multiple terminals according to claim 1, wherein the working modules of the terminals, which are set in terms of engineering construction progress, quality and safety, comprise: the progress aspect is as follows: the working modules of construction progress plan, material plan, tomorrow plan, week plan, concrete pouring plan and construction log; construction quality: the working modules of construction flow, image progress, technical intersection, construction measurement, material entrance, material distribution, project acceptance and construction project amount; and (4) safety aspects: the working modules of 'safety technology background', 'safety inspection', 'safety civilization display', 'potential safety hazard' and 'safety article registration'.
6. The APP for dynamically managing engineering construction based on project division by multiple terminals according to claim 1, wherein each terminal corresponds to a "person", which means that: a project manager registered in a construction unit of the APP project manager terminal, a data worker registered in a construction unit of the APP data worker terminal, a constructor registered in a construction unit of the APP constructor terminal, a quality inspector registered in a construction unit of the APP quality inspector terminal, a measurer registered in a construction unit of the APP measurer terminal, a tester registered in a construction unit of the APP tester terminal, a safety budget registered in a construction unit of the APP safety worker terminal, a supervisor registered in a construction unit of the APP budget manager terminal, a construction team length registered in a construction unit of the APP construction team leader terminal, a supervisor engineer or manager registered in a supervisor unit of the APP supervisor terminal, a safety manager registered in a supervisor terminal, a supervisor of the APP supervisor terminal, a supervisor of the supervisor terminal, a computer program, a computer, the construction site representatives of the construction units logged in the APP 'construction unit terminal', the safety supervision institution supervisors logged in the APP 'safety supervision institution terminal' and the quality supervision institution supervisors logged in the safety supervision institution 'quality supervision institution terminal'.
7. The APP for dynamically managing engineering construction based on project division by multiple terminals according to claim 1, wherein the search bar for "standard, normative, and rule search" in each terminal management and control window is input in the search bar: when any one of "material", "product", "behavior", "concept", "method", "object of task", "technical content", "quality requirement", and "form" is used, the contents of the corresponding item in "standard", "specification", and "procedure" of each industry and each department appear in the window, and the contents include the names, chapters, paragraph numbers, and paragraph contents of "standard", "specification", and "procedure".
8. The APP for dynamically managing project construction based on project division according to claim 1, wherein the derivable project construction statistics table is the project construction statistics table containing data of "schedule date", "construction date", "whether to measure", "whether to test", "whether to give up", "material test condition", "concrete test block result", "construction project amount", "settlement project amount", and "acceptance condition".
CN201910161976.XA 2019-03-05 2019-03-05 APP for dynamically managing engineering construction based on project division at multiple terminals Pending CN111667224A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910161976.XA CN111667224A (en) 2019-03-05 2019-03-05 APP for dynamically managing engineering construction based on project division at multiple terminals

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910161976.XA CN111667224A (en) 2019-03-05 2019-03-05 APP for dynamically managing engineering construction based on project division at multiple terminals

Publications (1)

Publication Number Publication Date
CN111667224A true CN111667224A (en) 2020-09-15

Family

ID=72381195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910161976.XA Pending CN111667224A (en) 2019-03-05 2019-03-05 APP for dynamically managing engineering construction based on project division at multiple terminals

Country Status (1)

Country Link
CN (1) CN111667224A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009134685A (en) * 2007-09-03 2009-06-18 Tauchi Sekkei:Kk Construction management system of building
CN106572000A (en) * 2016-10-29 2017-04-19 中国十七冶集团有限公司 WeChat official account platform-based construction site quality and safety management method
CN107368967A (en) * 2017-07-20 2017-11-21 北京建工土木工程有限公司 Engineering safety quality inspection intelligent management based on internet
CN107705020A (en) * 2017-10-12 2018-02-16 山东联诚工程建设监理有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN108320127A (en) * 2017-12-20 2018-07-24 国网山东省电力公司聊城供电公司 A kind of power engineering term computer management system
CN108876190A (en) * 2018-07-09 2018-11-23 杭州溯影信息技术有限公司 A kind of engineering witness management method, system, device and medium
CN109034736A (en) * 2018-07-10 2018-12-18 李磊 Project management system and operating platform based on BIM

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009134685A (en) * 2007-09-03 2009-06-18 Tauchi Sekkei:Kk Construction management system of building
CN106572000A (en) * 2016-10-29 2017-04-19 中国十七冶集团有限公司 WeChat official account platform-based construction site quality and safety management method
CN107368967A (en) * 2017-07-20 2017-11-21 北京建工土木工程有限公司 Engineering safety quality inspection intelligent management based on internet
CN107705020A (en) * 2017-10-12 2018-02-16 山东联诚工程建设监理有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN108320127A (en) * 2017-12-20 2018-07-24 国网山东省电力公司聊城供电公司 A kind of power engineering term computer management system
CN108876190A (en) * 2018-07-09 2018-11-23 杭州溯影信息技术有限公司 A kind of engineering witness management method, system, device and medium
CN109034736A (en) * 2018-07-10 2018-12-18 李磊 Project management system and operating platform based on BIM

Similar Documents

Publication Publication Date Title
CN111598379B (en) Project management method, platform, device, computer equipment and storage medium
KR102209809B1 (en) Construction management system for real-time construction inspection and evaluation
CN112232761B (en) Infrastructure application system and method
CN106096905A (en) A kind of project management method and system
CN203165006U (en) Engineering project management system
CN111814240B (en) Highway engineering farmer management system based on BIM technology
CN110796570A (en) Intelligent text travel system
CN115375146B (en) Digital construction integrated platform
JP5905146B2 (en) Project progress management system and computer program
CN113626914A (en) Engineering project management method, device and system based on digital twins
WO2002041221A1 (en) Product development process
CN117391640A (en) Engineering construction project construction period management method and system based on BIM and GIS
CN113592680A (en) Service platform based on regional education big data
CN110555676A (en) Dynamic supervision platform system implementation method
CN108846645A (en) A kind of enterprise&#39;s flattened management method and system
CN114186955A (en) Standardized management system for safety production
CN114677117A (en) Building engineering management system and device
CN113449957A (en) Intelligent working system based on PAGEOFFLICE control
CN107609735A (en) The source of houses asset management system
CN111667224A (en) APP for dynamically managing engineering construction based on project division at multiple terminals
KR20090002218A (en) On-line construction management method
TWI263910B (en) A measuring device management system and method
CN112766818A (en) Safety target management control examination system
CN112070453A (en) Frame construction mark informatization pricing platform
CN112330170B (en) Power transmission and transformation engineering quality common fault prevention and control platform based on AR technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200915