CN111599013B - Method for quickly constructing three-dimensional scene of transformer substation and related device - Google Patents

Method for quickly constructing three-dimensional scene of transformer substation and related device Download PDF

Info

Publication number
CN111599013B
CN111599013B CN202010454286.6A CN202010454286A CN111599013B CN 111599013 B CN111599013 B CN 111599013B CN 202010454286 A CN202010454286 A CN 202010454286A CN 111599013 B CN111599013 B CN 111599013B
Authority
CN
China
Prior art keywords
equipment
transformer substation
model
substation
scene
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010454286.6A
Other languages
Chinese (zh)
Other versions
CN111599013A (en
Inventor
郭建龙
冯伟夏
薛江
李军锋
苏锐师
熊山
王鹏
郝腾飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Training and Evaluation Center of Guangdong Power Grid Co Ltd
Original Assignee
Training and Evaluation Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Training and Evaluation Center of Guangdong Power Grid Co Ltd filed Critical Training and Evaluation Center of Guangdong Power Grid Co Ltd
Priority to CN202010454286.6A priority Critical patent/CN111599013B/en
Publication of CN111599013A publication Critical patent/CN111599013A/en
Application granted granted Critical
Publication of CN111599013B publication Critical patent/CN111599013B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/10Constructive solid geometry [CSG] using solid primitives, e.g. cylinders, cubes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Engineering & Computer Science (AREA)
  • Computer Graphics (AREA)
  • Software Systems (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The application discloses a method and a related device for quickly constructing a three-dimensional scene of a transformer substation.

Description

Method for quickly constructing three-dimensional scene of transformer substation and related device
Technical Field
The application relates to the technical field of three-dimensional modeling of transformer substations, in particular to a method for quickly constructing a three-dimensional scene of a transformer substation and a related device.
Background
At present, 3Dmax modeling software is adopted for a three-dimensional scene of a transformer substation, single equipment modeling is firstly carried out according to scanned point cloud files or plane drawings, the equipment modeling is placed in corresponding positions one by one, then the placed equipment is connected through conducting wires, the equipment is renamed to be field real equipment name and ID, and finally, FBX files are exported for application of three-dimensional visualization software. However, the existing method is poor in model reusability due to repeated modeling of the same-model equipment, and errors are easily generated on the large-quantity same-type equipment by manually associating the equipment model with the field real equipment, so that final application is influenced. Therefore, it is necessary to optimize the existing substation three-dimensional scene modeling method.
Disclosure of Invention
The application provides a method and a related device for quickly constructing a three-dimensional scene of a transformer substation, which are used for solving the technical problems that the existing method for modeling the three-dimensional scene of the transformer substation is poor in model reusability and errors are easily caused when an equipment model is manually associated with real equipment.
In view of this, a first aspect of the present application provides a method for quickly constructing a three-dimensional scene of a substation, including:
creating a blank scene according to the size of the target scene and the central point of the plane coordinate;
importing a transformer substation equipment plane drawing in the blank scene, and enabling the equipment position size in the transformer substation equipment plane drawing to be consistent with the equipment position size of a real transformer substation;
importing a basic information ledger table of the equipment of the real transformer substation, wherein the basic information ledger table comprises equipment type information, manufacturer information and equipment model information;
retrieving all equipment models in a substation equipment model library according to the basic information ledger table;
placing each equipment model to a corresponding installation position in the transformer substation equipment plane drawing;
and conducting wire connection is carried out on each equipment model, and the construction of the three-dimensional scene of the transformer substation is completed.
Optionally, after retrieving all the device models from the substation device model library according to the basic information ledger sheet, before placing each of the device models at the installation position corresponding to the substation device plan drawing, the method further includes:
generating an equipment label for each equipment model respectively;
correspondingly, the placing each equipment model to the installation position corresponding to the substation equipment plane drawing comprises:
placing the equipment label at a mounting position corresponding to the transformer substation equipment plane drawing;
and loading the equipment model corresponding to the equipment label to the installation position.
Optionally, after the placing of each of the device models to the installation position corresponding to the substation device plane drawing, the conducting wire connection of each of the device models is performed, and before the building of the three-dimensional scene of the substation is completed, the method further includes:
and adjusting the coordinates of the equipment model to enable the coordinate position of the equipment model to be matched with the equipment position corresponding to the real transformer substation.
Optionally, before retrieving all the device models from the substation device model library according to the basic information ledger sheet, the method further includes:
constructing an equipment model of each transformer substation equipment;
and marking the type, the manufacturer and the model of the equipment to which each equipment model belongs, and constructing the substation equipment model library.
The application second aspect provides a device is found fast to three-dimensional scene of transformer substation, includes:
the blank scene construction unit is used for creating a blank scene according to the size of the target scene and the central point of the plane coordinate;
the drawing importing unit is used for importing a transformer substation equipment plane drawing in the blank scene and enabling the equipment position size in the transformer substation equipment plane drawing to be consistent with the equipment position size of a real transformer substation;
the transformer substation basic information platform account table importing unit is used for importing a basic information platform account table of the equipment of the real transformer substation, and the basic information platform account table comprises equipment type information, manufacturer information and equipment model information;
the model retrieval unit is used for retrieving all equipment models in a transformer substation equipment model library according to the basic information ledger sheet;
the configuration unit is used for placing each equipment model to an installation position corresponding to the transformer substation equipment plane drawing;
and the wire connecting unit is used for performing wire connection on each equipment model to complete the construction of the three-dimensional scene of the transformer substation.
Optionally, the method further comprises:
a label unit for generating an equipment label for each of the equipment models, respectively;
correspondingly, the configuration unit is specifically configured to:
placing the equipment label at an installation position corresponding to the substation equipment plane drawing;
and loading the equipment model corresponding to the equipment label to the installation position.
Optionally, the method further comprises:
and the coordinate adjusting unit is used for adjusting the coordinates of the equipment model so that the coordinate position of the equipment model is matched with the equipment position corresponding to the real transformer substation.
Optionally, the system further comprises a model library construction unit;
the model base construction unit is used for:
constructing an equipment model of each transformer substation equipment;
and marking the type, the manufacturer and the model of the equipment to which each equipment model belongs, and constructing the substation equipment model library.
The third aspect of the present application provides a device for rapidly constructing a three-dimensional scene of a transformer substation, where the device includes a processor and a memory:
the memory is used for storing program codes and transmitting the program codes to the processor;
the processor is configured to execute the method for rapidly constructing a three-dimensional scene of a substation according to any one of the first aspect according to instructions in the program code.
A fourth aspect of the present application provides a computer-readable storage medium, where the computer-readable storage medium is configured to store program codes, and the program codes are configured to execute the method for rapidly building a three-dimensional scene of a substation according to any one of the first aspects.
According to the technical scheme, the embodiment of the application has the following advantages:
the application provides a method for quickly constructing a three-dimensional scene of a transformer substation, which comprises the following steps: creating a blank scene according to the size of the target scene and the central point of the plane coordinate; importing a transformer substation equipment plane drawing in a blank scene, and enabling the equipment position size in the transformer substation equipment plane drawing to be consistent with the equipment position size of a real transformer substation; importing a basic information ledger table of equipment of a real transformer substation, wherein the basic information ledger table comprises equipment type information, manufacturer information and equipment model information; retrieving all equipment models in a substation equipment model library according to the basic information ledger table; placing each equipment model at a corresponding installation position in a transformer substation equipment plane drawing; and conducting wire connection on each equipment model to complete the construction of the three-dimensional scene of the transformer substation. According to the method for quickly constructing the three-dimensional scene of the transformer substation, the basic information ledger sheet of the transformer substation equipment is introduced, the matched equipment model is automatically searched in the transformer substation equipment model base according to the equipment type, the equipment manufacturer and the equipment model in the basic information ledger sheet, the reuse rate of the same-type equipment model is improved, meanwhile, errors caused by manual association of the equipment model and real equipment are avoided, and the technical problems that the existing method for modeling the three-dimensional scene of the transformer substation is poor in model reusability and the manual association of the equipment model and the real equipment are prone to errors are solved.
Drawings
Fig. 1 is a schematic flow chart of a method for rapidly constructing a three-dimensional scene of a substation provided in an embodiment of the present application;
fig. 2 is another schematic flow chart of a method for rapidly constructing a three-dimensional scene of a transformer substation provided in an embodiment of the present application;
fig. 3 is a schematic structural diagram of a device for quickly constructing a three-dimensional scene of a transformer substation provided in an embodiment of the present application.
Detailed Description
In order to make those skilled in the art better understand the technical solutions of the present application, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only a part of the embodiments of the present application, and not all the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
For convenience of understanding, referring to fig. 1, the present application provides an embodiment of a method for quickly constructing a three-dimensional scene of a substation, including:
step 101, creating a blank scene according to the size of the target scene and the central point of the plane coordinate.
It should be noted that, in the embodiment of the present application, an empty scene terrain file is first created in three-dimensional modeling software, a size of a target scene is input, a position of a plane coordinate center point is specified, and the empty scene is created, where the size of the target scene may be determined according to a size of a real substation.
And 102, importing a transformer substation equipment plane drawing in a blank scene, and enabling the equipment position size in the transformer substation equipment plane drawing to be consistent with the equipment position size of a real transformer substation.
It should be noted that after a blank scene is created, the substation equipment plane drawing is led into the blank scene, then the scaling is adjusted, and the equipment position size in the substation equipment plane drawing is adjusted to be consistent with the equipment position of the real substation.
Step 103, importing a basic information ledger table of equipment of the real transformer substation, wherein the basic information ledger table comprises equipment type information, manufacturer information and equipment model information.
It should be noted that each device of the real substation has a device type, a manufacturer, and a device model to which the device belongs, and therefore, the basic information ledger table of the device of the real substation includes device type information, manufacturer information, and device model information corresponding to the device, and the information is imported into the three-dimensional modeling software.
And step 104, retrieving all equipment models in the substation equipment model library according to the basic information ledger sheet.
It should be noted that the device models of the substation devices may be pre-constructed, and information such as the types, the manufacturers, the models and the like of the devices to which the models belong may be marked on each device model, so that the models corresponding to the various types of substation devices are stored in the substation device model library, and each model has corresponding attributes, that is, the types, the manufacturers, the models and the like of the devices to which the models belong, so that the device model corresponding to the information of the basic information ledger table may be retrieved from the substation device model library according to the basic information ledger table.
And 105, placing each equipment model to a corresponding installation position in the transformer substation equipment plane drawing.
And 106, conducting wire connection is carried out on the equipment models, and the construction of the three-dimensional scene of the transformer substation is completed.
It should be noted that after the device model is retrieved, the device model is placed at a corresponding installation position in a transformer substation device plane drawing, then the device model is connected through a wire, and the construction of a transformer substation three-dimensional scene is completed after the wire connection is completed. The wire connection of the equipment model can directly edit the generated wire by using which wire connection tool, and the workload of manufacturing the wire by using modeling software is reduced.
According to the method for quickly constructing the three-dimensional scene of the transformer substation, the basic information ledger table of the transformer substation equipment is introduced, the matched equipment model is automatically retrieved from the transformer substation equipment model base according to the equipment type, the equipment manufacturer and the equipment model in the basic information ledger table, the reuse rate of the same-type equipment model is improved, errors caused by manual association of the equipment model and real equipment are avoided, and the technical problems that the existing method for modeling the three-dimensional scene of the transformer substation is poor in model reusability and the manual association of the equipment model and the real equipment are prone to errors are solved.
For convenience of understanding, referring to fig. 2, another embodiment of a method for rapidly constructing a three-dimensional scene of a substation is provided in the present application, including:
step 201, creating a blank scene according to the size of the target scene and the central point of the plane coordinate.
It should be noted that step 201 in the embodiment of the present application is the same as step 101 in the previous embodiment, and is not described herein again.
Step 202, importing a transformer substation equipment plane drawing in a blank scene, and enabling the equipment position size in the transformer substation equipment plane drawing to be consistent with the equipment position size of a real transformer substation.
It should be noted that step 202 in the embodiment of the present application is the same as step 102 in the previous embodiment, and is not repeated herein.
Step 203, importing a basic information ledger table of equipment of the real substation, wherein the basic information ledger table comprises equipment type information, manufacturer information and equipment model information.
It should be noted that step 203 in this embodiment is the same as step 103 in the previous embodiment, and is not described herein again.
And step 204, retrieving all equipment models in the substation equipment model library according to the basic information ledger sheet.
It should be noted that step 204 in the present embodiment is the same as step 104 in the previous embodiment, and is not described herein again.
Step 205, generate device labels for each device model.
It should be noted that, the device labels are generated according to the device information in the basic information ledger table of the substation device, the names and the numbers of the device labels and the real devices should be completely consistent, and the device labels can be automatically classified and sorted according to the device types and the numbers.
And step 206, placing the equipment label at the installation position corresponding to the transformer substation equipment plane drawing.
And step 207, loading the equipment model corresponding to the equipment label to the installation position.
It should be noted that, by determining the installation position of the device tag and then loading the device model corresponding to the device tag at the installation position, the problem of blocking caused by adding the device models one by one in the splicing process of the conventional scene making method can be avoided.
And 208, adjusting the coordinates of the equipment model to enable the coordinate position of the equipment model to be matched with the equipment position corresponding to the real transformer substation.
It should be noted that, in the embodiment of the present application, the coordinates of the device model may be adjusted using an alignment tool, a distribution tool, and a parameter input field, so that the coordinate position of the device model is accurately matched with the device position corresponding to the real substation device.
And 209, conducting wire connection is carried out on each equipment model, and the construction of the three-dimensional scene of the transformer substation is completed.
For convenience of understanding, please refer to fig. 3, the present application provides a three-dimensional scene constructing apparatus for a transformer substation, including:
and the blank scene construction unit is used for creating a blank scene according to the size of the target scene and the central point of the plane coordinate.
And the drawing leading-in unit is used for leading in the substation equipment plane drawing in the blank scene and enabling the equipment position size in the substation equipment plane drawing to be consistent with the equipment position size of the real substation.
And the standing book table importing unit is used for importing a basic information standing book table of the equipment of the real transformer substation, and the basic information standing book table comprises equipment type information, manufacturer information and equipment model information.
And the model retrieval unit is used for retrieving all equipment models in the substation equipment model base according to the basic information ledger sheet.
And the configuration unit is used for placing each equipment model to the corresponding installation position in the transformer substation equipment plane drawing.
And the wire connecting unit is used for performing wire connection on each equipment model to complete the construction of the three-dimensional scene of the transformer substation.
Further, still include:
the label unit is used for respectively generating equipment labels for the equipment models;
correspondingly, the configuration unit is specifically configured to:
placing the equipment label at a mounting position corresponding to the transformer substation equipment plane drawing;
and loading the equipment model corresponding to the equipment label to the installation position.
Further, the method also comprises the following steps:
and the coordinate adjusting unit is used for adjusting the coordinates of the equipment model so that the coordinate position of the equipment model is matched with the equipment position corresponding to the real transformer substation.
Further, the system also comprises a model library construction unit;
a model library construction unit for:
constructing an equipment model of each transformer substation equipment;
and marking the type, the manufacturer and the model of the equipment to which each equipment model belongs, and constructing a substation equipment model library.
The application provides an embodiment of a three-dimensional scene rapid construction device of a transformer substation, and the device comprises a processor and a memory:
the memory is used for storing the program codes and transmitting the program codes to the processor;
the processor is used for executing any one of the transformer substation three-dimensional scene rapid construction method embodiments according to instructions in the program codes.
Embodiments of a computer-readable storage medium for storing program codes for executing any one of the foregoing transformer substation three-dimensional scene rapid construction method embodiments are provided in the present application.
In the several embodiments provided in the present application, it should be understood that the disclosed system and method may be implemented in other ways. For example, the above-described system embodiments are merely illustrative, and for example, the division of the units is only one type of logical functional division, and other divisions may be realized in practice, for example, multiple units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, devices or units, and may be in an electrical, mechanical or other form.
The units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of the embodiment.
In addition, functional units in the embodiments of the present application may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The integrated unit can be realized in a form of hardware, and can also be realized in a form of a software functional unit.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solutions of the present application, which are essential or part of the technical solutions contributing to the prior art, or all or part of the technical solutions, may be embodied in the form of a software product stored in a storage medium, and including several instructions for causing a computer system (which may be a personal computer, a server, or a network system, etc.) to execute all or part of the steps of the methods described in the embodiments of the present application. And the aforementioned storage medium includes: various media capable of storing program codes, such as a usb disk, a removable hard disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a magnetic disk, or an optical disk.
The above embodiments are only used for illustrating the technical solutions of the present application, and not for limiting the same; although the present application has been described in detail with reference to the foregoing embodiments, it should be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions in the embodiments of the present application.

Claims (6)

1. A method for quickly constructing a three-dimensional scene of a transformer substation is characterized by comprising the following steps:
creating a blank scene according to the size of the target scene and the central point of the plane coordinate;
importing a transformer substation equipment plane drawing in the blank scene, and enabling the equipment position size in the transformer substation equipment plane drawing to be consistent with the equipment position size of a real transformer substation;
importing a basic information ledger table of the equipment of the real transformer substation, wherein the basic information ledger table comprises equipment type information, manufacturer information and equipment model information;
retrieving all equipment models in a transformer substation equipment model library according to the basic information ledger sheet;
placing each equipment model to a corresponding installation position in the transformer substation equipment plane drawing;
conducting wire connection on each equipment model to complete construction of a three-dimensional scene of the transformer substation;
after all the equipment models are retrieved from the substation equipment model library according to the basic information ledger sheet and before each equipment model is placed at the installation position corresponding to the substation equipment plane drawing, the method further comprises the following steps:
generating an equipment label for each equipment model respectively;
correspondingly, the placing each equipment model to the installation position corresponding to the substation equipment plane drawing comprises:
placing the equipment label at an installation position corresponding to the substation equipment plane drawing;
loading the equipment model corresponding to the equipment label to the installation position;
after the device models are placed at the installation positions corresponding to the transformer substation device plane drawings, conducting wire connection is carried out on the device models, and before construction of a transformer substation three-dimensional scene is completed, the method further comprises the following steps:
and adjusting the coordinates of the equipment model to enable the coordinate position of the equipment model to be matched with the equipment position corresponding to the real transformer substation.
2. The method for rapidly constructing a three-dimensional scene of a substation according to claim 1, wherein before retrieving all device models from a substation device model library according to the basic information ledger sheet, the method further comprises:
constructing an equipment model of each transformer substation equipment;
and marking the type, the manufacturer and the model of the equipment to which each equipment model belongs, and constructing the substation equipment model library.
3. The utility model provides a three-dimensional scene of transformer substation constructs device fast which characterized in that includes:
the blank scene construction unit is used for creating a blank scene according to the size of the target scene and the central point of the plane coordinate;
the drawing importing unit is used for importing a transformer substation equipment plane drawing in the blank scene and enabling the equipment position size in the transformer substation equipment plane drawing to be consistent with the equipment position size of a real transformer substation;
the transformer substation basic information platform account table importing unit is used for importing a basic information platform account table of the equipment of the real transformer substation, and the basic information platform account table comprises equipment type information, manufacturer information and equipment model information;
the model retrieval unit is used for retrieving all equipment models in a substation equipment model library according to the basic information ledger sheet;
the configuration unit is used for placing each equipment model to an installation position corresponding to the transformer substation equipment plane drawing;
the wire connecting unit is used for conducting wire connection on the equipment models to complete construction of a three-dimensional scene of the transformer substation;
further comprising:
a label unit, configured to generate an equipment label for each of the equipment models;
correspondingly, the configuration unit is specifically configured to:
placing the equipment label at a mounting position corresponding to the transformer substation equipment plane drawing;
loading the equipment model corresponding to the equipment label to the installation position;
further comprising:
and the coordinate adjusting unit is used for adjusting the coordinates of the equipment model so that the coordinate position of the equipment model is matched with the equipment position corresponding to the real transformer substation.
4. The transformer substation three-dimensional scene rapid construction device according to claim 3, characterized by further comprising a model library construction unit;
the model base construction unit is used for:
constructing an equipment model of each transformer substation equipment;
and marking the type, the manufacturer and the model of the equipment to which each equipment model belongs, and constructing the substation equipment model library.
5. The three-dimensional scene rapid construction equipment of the transformer substation is characterized by comprising a processor and a memory:
the memory is used for storing program codes and transmitting the program codes to the processor;
the processor is used for executing the substation three-dimensional scene rapid construction method according to any one of claims 1-2 according to instructions in the program code.
6. A computer-readable storage medium for storing program code for executing the substation three-dimensional scene rapid construction method according to any one of claims 1-2.
CN202010454286.6A 2020-05-26 2020-05-26 Method for quickly constructing three-dimensional scene of transformer substation and related device Active CN111599013B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010454286.6A CN111599013B (en) 2020-05-26 2020-05-26 Method for quickly constructing three-dimensional scene of transformer substation and related device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010454286.6A CN111599013B (en) 2020-05-26 2020-05-26 Method for quickly constructing three-dimensional scene of transformer substation and related device

Publications (2)

Publication Number Publication Date
CN111599013A CN111599013A (en) 2020-08-28
CN111599013B true CN111599013B (en) 2023-03-14

Family

ID=72187738

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010454286.6A Active CN111599013B (en) 2020-05-26 2020-05-26 Method for quickly constructing three-dimensional scene of transformer substation and related device

Country Status (1)

Country Link
CN (1) CN111599013B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112581617A (en) * 2020-10-23 2021-03-30 维坤智能科技(上海)有限公司 Three-dimensional scene equipment model of transformer substation and electrical data connection method
CN112906225A (en) * 2021-02-23 2021-06-04 国网山东省电力公司宁阳县供电公司 Virtual live-action simulation training system for transformer substation
CN112967376B (en) * 2021-02-26 2022-08-09 南京南瑞信息通信科技有限公司 Data-driven transformer substation three-dimensional model establishing method and device
CN114820944B (en) * 2022-05-07 2023-04-25 数字太空(北京)科技股份公司 Three-dimensional scene construction method and device, electronic equipment and storage medium

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279331A (en) * 2015-10-23 2016-01-27 国家电网公司 Substation site monitoring camera constructing, deploying and modeling method
CN105574777A (en) * 2015-12-31 2016-05-11 中国南方电网有限责任公司 Three-dimensional intelligent construction method of substation
CN107679281A (en) * 2017-09-05 2018-02-09 国家电网公司 Intelligent station three-dimensional scenic analogue system and implementation method based on Unity dynamic generations
CN107909644A (en) * 2017-11-09 2018-04-13 广东电网有限责任公司教育培训评价中心 A kind of substation equipment 3 d model library method for building up
CN109165330A (en) * 2018-08-10 2019-01-08 南方电网科学研究院有限责任公司 Modeling method, device, equipment and storage medium for transformer substation
CN110765528A (en) * 2019-10-22 2020-02-07 江苏瑞中数据股份有限公司 Three-dimensional reconstruction transformer substation implementation method based on virtual simulation technology
CN111091609A (en) * 2019-12-11 2020-05-01 云南电网有限责任公司保山供电局 Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102831307B (en) * 2012-05-31 2013-11-13 山东电力集团公司青岛供电公司 Three-dimensional GIS (Geographic Information System) technology based power grid visualization system and method
US10643368B2 (en) * 2017-06-27 2020-05-05 The Boeing Company Generative image synthesis for training deep learning machines

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279331A (en) * 2015-10-23 2016-01-27 国家电网公司 Substation site monitoring camera constructing, deploying and modeling method
CN105574777A (en) * 2015-12-31 2016-05-11 中国南方电网有限责任公司 Three-dimensional intelligent construction method of substation
CN107679281A (en) * 2017-09-05 2018-02-09 国家电网公司 Intelligent station three-dimensional scenic analogue system and implementation method based on Unity dynamic generations
CN107909644A (en) * 2017-11-09 2018-04-13 广东电网有限责任公司教育培训评价中心 A kind of substation equipment 3 d model library method for building up
CN109165330A (en) * 2018-08-10 2019-01-08 南方电网科学研究院有限责任公司 Modeling method, device, equipment and storage medium for transformer substation
CN110765528A (en) * 2019-10-22 2020-02-07 江苏瑞中数据股份有限公司 Three-dimensional reconstruction transformer substation implementation method based on virtual simulation technology
CN111091609A (en) * 2019-12-11 2020-05-01 云南电网有限责任公司保山供电局 Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
变电站智能三维运检平台开发与应用;刘平等;《低碳世界》;20171125(第33期);全文 *
基于点云数据的变电站三维仿真模型的实现及展望;田小壮等;《四川电力技术》;20180820(第04期);全文 *

Also Published As

Publication number Publication date
CN111599013A (en) 2020-08-28

Similar Documents

Publication Publication Date Title
CN111599013B (en) Method for quickly constructing three-dimensional scene of transformer substation and related device
CN110795809B (en) Method, system and medium for automatically picking up connection relation of electric secondary circuit of transformer substation based on CAD (computer aided design) drawing
CN112132961B (en) Panoramic template-based digital virtual exhibition hall generation method and system
CN105404507A (en) Process template construction method and system
CN105653508A (en) Document template management method, document calling method and related device
CN109213758B (en) Data access method, device, equipment and computer readable storage medium
CN110443531A (en) The method and apparatus for determining the bit information of article in order
CN104572125A (en) Methods and devices for drawing and storing entity relation diagrams
CN107301269B (en) Method for carrying out data interaction on power distribution device based on BIM technology
CN110135814A (en) The correlating method of BIM and project data, system and terminal device
CN116051248B (en) Furniture large-scale custom business quick response method and device
CN112309313B (en) Module controller configuration method, device and system and computer readable storage medium
CN108710716B (en) Design drawing generation method and device for optical amplifier station in optical transmission system
KR102418541B1 (en) Wire bundle production method, and apparatus therefor
CN114970792A (en) Novel digital management label of power grid physical equipment
CN115033936A (en) Material model management method for SolidWorks system
CN113987102A (en) Interactive power data visualization method and system
CN113127408A (en) Data conversion method and device
CN117273270B (en) Engineering quota evaluation method and device, terminal equipment and storage medium
CN117113011B (en) Coal mine power setting data splicing method and device based on XML technology
CN113742897B (en) Electric primary equipment graphic data and model data linkage verification method
CN106326380A (en) Commodity cloud database creating method and device
CN116091707A (en) Three-dimensional model arrangement method, device, terminal and medium based on maya
CN117151600A (en) Pluggable module material management method, pluggable module material management system, pluggable module terminal and storage medium
CN114398409A (en) Two-dimensional logic model and three-dimensional model association method for electrical secondary design optical cable loop

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant