- CN111594194B CN111594194B CN202010599947.4A CN202010599947A CN111594194B CN 111594194 B CN111594194 B CN 111594194B CN 202010599947 A CN202010599947 A CN 202010599947A CN 111594194 B CN111594194 B CN 111594194B
- Authority
- CN
- China
- Prior art keywords
- construction
- shield
- muddy water
- module
- water loop
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 claims abstract description 130
- 238000012544 monitoring process Methods 0.000 claims abstract description 91
- 238000004891 communication Methods 0.000 claims abstract description 7
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 53
- 238000000034 method Methods 0.000 claims description 31
- 238000005070 sampling Methods 0.000 claims description 22
- 238000010586 diagram Methods 0.000 claims description 20
- 230000008569 process Effects 0.000 claims description 19
- 230000005641 tunneling Effects 0.000 claims description 18
- 239000010802 sludge Substances 0.000 claims description 12
- 238000004458 analytical method Methods 0.000 claims description 9
- 239000002689 soil Substances 0.000 claims description 8
- 238000013461 design Methods 0.000 claims description 5
- 230000035515 penetration Effects 0.000 claims description 4
- 238000005516 engineering process Methods 0.000 abstract description 6
- 230000006870 function Effects 0.000 description 12
- 238000003860 storage Methods 0.000 description 11
- 238000004590 computer program Methods 0.000 description 9
- 238000012545 processing Methods 0.000 description 9
- 230000008859 change Effects 0.000 description 5
- 230000000694 effects Effects 0.000 description 5
- 230000002159 abnormal effect Effects 0.000 description 4
- 230000003287 optical effect Effects 0.000 description 3
- 239000000243 solution Substances 0.000 description 3
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000011160 research Methods 0.000 description 2
- 239000002002 slurry Substances 0.000 description 2
- 238000012800 visualization Methods 0.000 description 2
- 206010063385 Intellectualisation Diseases 0.000 description 1
- 230000005856 abnormality Effects 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 230000010485 coping Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 238000012954 risk control Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000007619 statistical method Methods 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/003—Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010599947.4A CN111594194B (zh) | 2020-06-28 | 2020-06-28 | 一种盾构机作业状态监控*** |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010599947.4A CN111594194B (zh) | 2020-06-28 | 2020-06-28 | 一种盾构机作业状态监控*** |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111594194A CN111594194A (zh) | 2020-08-28 |
CN111594194B true CN111594194B (zh) | 2022-07-12 |
Family
ID=72182994
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010599947.4A Active CN111594194B (zh) | 2020-06-28 | 2020-06-28 | 一种盾构机作业状态监控*** |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111594194B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113294163A (zh) * | 2021-03-19 | 2021-08-24 | 中国电建集团华东勘测设计研究院有限公司 | 盾构掘进监控数据可视化配置方法 |
CN117235874B (zh) * | 2023-11-14 | 2024-02-20 | 中电建铁路建设投资集团有限公司 | 一种基于盾构隧道掘进的轨道变形预测方法及*** |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1619280A (zh) * | 2004-12-09 | 2005-05-25 | 上海隧道工程股份有限公司 | 大型盾构掘进模拟试验平台 |
CN101148989A (zh) * | 2007-08-09 | 2008-03-26 | 上海港机重工有限公司 | 盾构掘进机本地及远程监控方法 |
CN103473720A (zh) * | 2013-09-06 | 2013-12-25 | 上海大学 | 基于bim的盾构法隧道施工管理*** |
CN104156536A (zh) * | 2014-08-19 | 2014-11-19 | 中交隧道工程局有限公司 | 一种盾构机刀具磨损的可视化定量标定及分析方法 |
CN106383931A (zh) * | 2016-08-31 | 2017-02-08 | 广州市市政集团有限公司 | 基于csm模型的隧道掘进机刀盘有效推力和扭矩计算方法 |
CN106776679A (zh) * | 2016-11-04 | 2017-05-31 | 中交第二航务工程局有限公司工程装备分公司 | 盾构机掘进施工远程集中监控方法 |
CN107091098A (zh) * | 2017-06-30 | 2017-08-25 | 中铁局集团有限公司 | 一种盾构设备在高粘度泥岩中的掘进方法 |
CN107315370A (zh) * | 2017-07-13 | 2017-11-03 | 合肥引力波数据科技有限公司 | 一种盾构机施工进度监控*** |
CN108425680A (zh) * | 2018-03-29 | 2018-08-21 | 广州地铁设计研究院有限公司 | 一种盾构推进地面塌陷复推处理方法及其支护结构 |
CN111335907A (zh) * | 2020-03-20 | 2020-06-26 | 中铁十四局集团有限公司 | 盾构施工过程地层变形的控制方法、控制装置和存储介质 |
-
2020
- 2020-06-28 CN CN202010599947.4A patent/CN111594194B/zh active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1619280A (zh) * | 2004-12-09 | 2005-05-25 | 上海隧道工程股份有限公司 | 大型盾构掘进模拟试验平台 |
CN101148989A (zh) * | 2007-08-09 | 2008-03-26 | 上海港机重工有限公司 | 盾构掘进机本地及远程监控方法 |
CN103473720A (zh) * | 2013-09-06 | 2013-12-25 | 上海大学 | 基于bim的盾构法隧道施工管理*** |
CN104156536A (zh) * | 2014-08-19 | 2014-11-19 | 中交隧道工程局有限公司 | 一种盾构机刀具磨损的可视化定量标定及分析方法 |
CN106383931A (zh) * | 2016-08-31 | 2017-02-08 | 广州市市政集团有限公司 | 基于csm模型的隧道掘进机刀盘有效推力和扭矩计算方法 |
CN106776679A (zh) * | 2016-11-04 | 2017-05-31 | 中交第二航务工程局有限公司工程装备分公司 | 盾构机掘进施工远程集中监控方法 |
CN107091098A (zh) * | 2017-06-30 | 2017-08-25 | 中铁局集团有限公司 | 一种盾构设备在高粘度泥岩中的掘进方法 |
CN107315370A (zh) * | 2017-07-13 | 2017-11-03 | 合肥引力波数据科技有限公司 | 一种盾构机施工进度监控*** |
CN108425680A (zh) * | 2018-03-29 | 2018-08-21 | 广州地铁设计研究院有限公司 | 一种盾构推进地面塌陷复推处理方法及其支护结构 |
CN111335907A (zh) * | 2020-03-20 | 2020-06-26 | 中铁十四局集团有限公司 | 盾构施工过程地层变形的控制方法、控制装置和存储介质 |
Non-Patent Citations (3)
Title |
---|
京张高铁清华园隧道施工管理BIM关键技术;智鹏等;《现代隧道技术》;20180815;第3-4节、图1-7 * |
基于BIM的清华园隧道施工管理关键技术研究及应用实践;杨威等;《轨道标准设计》;20200415;第3-4节,图1-11 * |
智鹏等.京张高铁清华园隧道施工管理BIM关键技术.《现代隧道技术》.2018, * |
Also Published As
Publication number | Publication date |
---|---|
CN111594194A (zh) | 2020-08-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109376194B (zh) | 一种基于大数据的隧道掘进机远程监控平台 | |
CN112985304B (zh) | 一种隧道施工辅助监测*** | |
CN111594194B (zh) | 一种盾构机作业状态监控*** | |
CN103233741B (zh) | 定量化评价超大型地下洞室群施工期围岩稳定性的方法 | |
CN205260036U (zh) | 监控装置 | |
CN100387806C (zh) | 煤矿生产矿井瓦斯防治导航方法 | |
CN109064037B (zh) | 基坑施工风险管控方法、***和设备 | |
CN107610421A (zh) | 一种地质灾害预警分析***及方法 | |
CN103106542A (zh) | 一种数据分析及处理*** | |
US20060090379A1 (en) | Autonomous loading shovel system | |
CN108984817B (zh) | 一种tbm刀具磨损量实时评估方法 | |
CN108153985B (zh) | 一种轨道交通岩土工程三维智能信息*** | |
CN110017147A (zh) | 一种盾构刀具磨损实时监测***及监测方法 | |
CN107642347A (zh) | 页岩气压裂井下事故预测预警方法及装置 | |
CN114238543A (zh) | 一种排水管网地理信息*** | |
CN107633325A (zh) | 一种页岩气压裂井下事故早期诊断报警方法及装置 | |
Conrads et al. | Assessing maintenance strategies for cutting tool replacements in mechanized tunneling using process simulation | |
CN103899357A (zh) | 矿井底板水害实时可视化监测预警***与方法 | |
CN116090823A (zh) | 煤矿灾害的风险监测方法、装置、电子设备及存储介质 | |
CN114648418A (zh) | 井下采空区安全分级预警监测方法及*** | |
Zhang et al. | Application of block theory for evaluating face stability under disc cutters loading of TBM, case study of a water-conveyance tunnel project | |
CN113505911B (zh) | 基于自动巡航的刀具寿命预测***及其预测方法 | |
CN116596484B (zh) | 一种装配式建筑施工智能管理方法及*** | |
Zhang et al. | WebGIS-based collaborative construction quality control of RCC gravity dam using sensing devices | |
CN116579601B (zh) | 矿山安全生产风险监测预警***及方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Zhao Taoning Inventor after: Liu Shanfu Inventor after: Fang Xinsheng Inventor after: Li Ruiguang Inventor after: Chen Shuang Inventor after: Lu Hangyu Inventor after: Zhao Haitao Inventor after: Shi Wenming Inventor after: Du Guixin Inventor after: Liu Lei Inventor after: Gao Shijun Inventor after: Zhao Bin Inventor before: Chen Shuang Inventor before: Zhao Haitao Inventor before: Du Guixin Inventor before: Liu Lei Inventor before: Gao Shijun Inventor before: Zhao Bin Inventor before: Liu Shanfu Inventor before: Fang Xinsheng Inventor before: Li Ruiguang |
|
TR01 | Transfer of patent right |
Effective date of registration: 20240612 Address after: No. 158 Chongchuan Road, Chongchuan District, Nantong City, Jiangsu Province, 226004 Patentee after: Nantong Rail Transit Group Co.,Ltd. Country or region after: China Patentee after: CHINA RAILWAY 14TH BUREAU GROUP SHIELD ENGINEERING Co.,Ltd. Patentee after: CHINA RAILWAY SHISIJU Group Corp. Address before: 211800 No. 120, Xinpu Road, Pukou District, Nanjing, Jiangsu Patentee before: CHINA RAILWAY 14TH BUREAU GROUP SHIELD ENGINEERING Co.,Ltd. Country or region before: China Patentee before: CHINA RAILWAY SHISIJU Group Corp. |