CN111585273A - Power distribution network fault power failure recovery plan generation method - Google Patents

Power distribution network fault power failure recovery plan generation method Download PDF

Info

Publication number
CN111585273A
CN111585273A CN202010214203.6A CN202010214203A CN111585273A CN 111585273 A CN111585273 A CN 111585273A CN 202010214203 A CN202010214203 A CN 202010214203A CN 111585273 A CN111585273 A CN 111585273A
Authority
CN
China
Prior art keywords
path
transfer
distribution network
load
power failure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010214203.6A
Other languages
Chinese (zh)
Inventor
徐艳琨
任娴婷
吴昌
李震
留益斌
胡继军
王绍强
章华
司海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Zhejiang Longyou County Power Supply Co ltd
State Grid Corp of China SGCC
Quzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Zhejiang Longyou County Power Supply Co ltd
State Grid Corp of China SGCC
Quzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Zhejiang Longyou County Power Supply Co ltd, State Grid Corp of China SGCC, Quzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Zhejiang Longyou County Power Supply Co ltd
Priority to CN202010214203.6A priority Critical patent/CN111585273A/en
Publication of CN111585273A publication Critical patent/CN111585273A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F17/00Digital computing or data processing equipment or methods, specially adapted for specific functions
    • G06F17/10Complex mathematical operations
    • G06F17/11Complex mathematical operations for solving equations, e.g. nonlinear equations, general mathematical optimization problems
    • G06F17/12Simultaneous equations, e.g. systems of linear equations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/26Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/04Constraint-based CAD
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/04Power grid distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • Y04S10/52Outage or fault management, e.g. fault detection or location

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Mathematical Physics (AREA)
  • Theoretical Computer Science (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Algebra (AREA)
  • Databases & Information Systems (AREA)
  • Software Systems (AREA)
  • Operations Research (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention relates to the technical field of distribution network operation and maintenance, in particular to a method for generating a power failure recovery plan of a power distribution network fault, which comprises the following steps: (1) acquiring a topological structure of a power distribution network and related parameters of power transfer; (2) selecting a certain transformer substation in the power distribution network, calculating the maximum transfer load capacity of the single-path feeder line, and entering the step (6) if the maximum transfer load capacity is equal to the power failure load capacity; (3) establishing a multi-path transfer scheme; (4) establishing a plurality of multipath transfer schemes to obtain the transfer load quantity of each scheme; (5) evaluating and sequencing the multi-path transfer scheme to obtain an optimal multi-path transfer scheme; (6) and (5) carrying out the steps (2) to (5) on all the substations in the power distribution network to obtain a power failure recovery plan of the power distribution network. The substantial effects of the invention are as follows: the link of the power supply capacity of the power distribution network can be effectively found and identified, the related plan can be quickly generated, and the power failure recovery time is shortened.

Description

Power distribution network fault power failure recovery plan generation method
Technical Field
The invention relates to the technical field of distribution network operation and maintenance, in particular to a method for generating a power failure recovery plan of a power distribution network.
Background
In order to improve the reliability of power supply, the power distribution network often adopts a closed-loop design and an open-loop operation mode. When a local power failure occurs in the power distribution network, an operator usually transfers the power loss load of a non-fault area to the opposite side of a line through the interconnection switch after isolating the fault, so that power supply is restored to the non-fault area.
The whole recovery of the power loss load is the direction that power distribution network regulation and control are pursued in an effort continuously, and during the design of the existing power distribution network, due to the lack of comprehensive deep calculation of various transfer schemes, a quantitative scientific evaluation method is lacked for weak links of the power distribution network, the power distribution network is often excessively transformed according to line load rate indexes, the economic spread waste is caused, and sometimes the weak links of the power distribution network cannot be effectively improved.
The known feeder load rate index can only reflect the maximum power transfer and supply capacity which can be transferred to the opposite side after a single feeder is powered off, and can not comprehensively and objectively reflect the problem of insufficient capacity when a plurality of feeders are possibly transferred to a main transformer simultaneously when the transformer substation is completely stopped, and the main transformer load rate index only reflects the load bearing capacity of the main transformer and can not reflect the weak link which limits the load transfer and supply of the transformer substation after the transformer substation is completely stopped.
When a transformer substation is completely stopped, the problem of cross influence of the transfer capacity of a plurality of feeders and the load bearing capacity of a plurality of main transformers exists, and the weak link of the distribution network cannot be found comprehensively and accurately only by depending on the load rate indexes of the feeders and the main transformers, so that the improvement of the transfer capacity of the distribution network is limited, the transformation of the distribution network cannot be further quantitatively guided, when the transfer capacity is insufficient, part of power loss loads cannot be recovered effectively and quickly, and the customer satisfaction and the enterprise economic benefit are reduced.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the technical problem that the power supply capacity of the existing power distribution network is insufficient is solved. A power distribution network fault power failure recovery plan generation method which is more optimized in switching is provided.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows: a power distribution network fault power failure recovery plan generation method comprises the following steps: (1) acquiring a topological structure of a power distribution network and related parameters of power transfer; (2) selecting a certain transformer substation in the power distribution network, calculating the maximum transfer load capacity of the single-path feeder line when the transformer substation is completely stopped, if the maximum transfer load capacity is equal to the power failure load capacity, taking the single-path feeder line transfer scheme as a power failure recovery plan and entering the step (6), otherwise, entering the step (3); (3) establishing a multi-path transfer scheme, constructing a linear programming equation, and solving the multi-path transfer load amount by applying a simplex method; (4) establishing a plurality of multipath transfer schemes to obtain the transfer load quantity of each scheme; (5) evaluating and sequencing the multi-path transfer scheme to obtain an optimal multi-path transfer scheme, and taking the single-path feeder transfer scheme and the optimal multi-path transfer scheme obtained in the step (2) and the step (5) as a power failure recovery plan; (6) and (5) carrying out the steps (2) to (5) on all the substations in the power distribution network to obtain a power failure recovery plan of the power distribution network.
Preferably, in the step (2), the method for calculating the maximum transfer load of the single-path feeder line when the substation is completely stopped comprises the following steps: (2.1) establishing line quota constraints
Xi≤min(Ri(1-ai),kLi)
Figure BDA0002423841330000021
Wherein, XiFor loads, R, recoverable by a single-path feeder iiFor the opposite line capacity, aiFor the actual load factor on the opposite side, LiIs the loss load of the feeder line i, k is the recovery load of the non-fault area of the feeder line i, 0<k is less than or equal to 1, and omega 3 is a set of all the feeders transferred to the same opposite side line; (2.2) establishing main transformer quota constraint
Figure BDA0002423841330000022
Omega 1 is the set of all single path blackout feeders transferred to the same main transformer, TiIs the quota of the main transformer, biThe load factor of the main transformer before transfer; (2.3) establishing an objective function
Figure BDA0002423841330000023
Wherein n is the number of the single-path feeder lines, and F is the maximum load amount which can be recovered by single-path switching of the power failure transformer substation; (2.4) solving the optimal solution of the objective function
And solving by using a simplex method to obtain the maximum load F which can be recovered by the single-path transfer of the power failure transformer substation.
Preferably, step (2.2) further comprises: and (3) constraining the constraint inequality into an equality constraint:
Xi+X′i≤min(Ri(1-ai),kLi)
Figure BDA0002423841330000024
Figure BDA0002423841330000025
wherein, X'i、X″iAnd X'iFor relaxing variables, the objective function established in step (2.3) is instead:
Figure BDA0002423841330000026
wherein m is the number of main transformers to be transformed, and p is the number of various single-path feeders transferred to the same feeder.
Preferably, before the multi-path switching scheme is established in step (3), all the paths of the hand-pulling line are eliminated.
Preferably, in step (3), the method for constructing the linear programming equation comprises the following steps: (3.1) establishing line quota constraints
Xj≤min(Rj(1-aj),kLj)
Wherein, XjFor loads recoverable by feeder j using multi-path switchingjTo transfer the line capacity of the side, ajTo divert the current load factor, LjBefore power failure, a feeder j is selected, and k is the ratio of the recovery load of a non-fault area of the feeder j; (3.2) establishing main transformer quota constraint
Figure BDA0002423841330000031
Wherein, omega 2 is the set of all single-path blackout feeders transferred to the same main transformer, TjIs the quota of the main transformer, bjTo transfer toThe load factor of the main transformer is obtained; (3.3) establishing an objective function
Figure BDA0002423841330000032
Wherein, XjThe load which can be recovered is supplied to the feeder j through multi-path transfer, d is the number of the multi-path feeders, and F' is the maximum load which can be recovered by the multi-path transfer of the power failure transformer substation; (3.4) solving the optimal solution of the objective function,
and solving by using a simplex method to obtain the maximum load F' which can be recovered by the power-off transformer substation through multi-path transfer.
Preferably, step (3.2) further comprises: and (3) constraining the constraint inequality into an equality constraint:
Xj+X′j≤min(Rj(1-aj),kLj)
Figure BDA0002423841330000033
wherein, X'jAnd X ″)jFor relaxing variables, the objective function established in step (3.3) is instead:
Figure BDA0002423841330000034
wherein q is the number of main transformers to be transformed.
Preferably, the method for evaluating the multipath forwarding scheme in step (5) is to take the multipath forwarding scheme corresponding to the maximum value of the objective function F' as the optimal multipath forwarding scheme.
The substantial effects of the invention are as follows: the efficiency of the generation of the power supply transfer scheme is improved through a single path, the link of the power supply transfer capability of the power distribution network is effectively found and identified through multi-path power supply transfer, a scheme generation method is provided, a related scheme is quickly generated, the power failure recovery time is shortened, and the economic benefit is improved.
Drawings
Fig. 1 is a flowchart of a method for generating a fault power outage restoration plan according to an embodiment.
Fig. 2 is a block diagram of a flow chart of a method for calculating a maximum transfer load of a single-path feeder according to an embodiment.
Detailed Description
The following provides a more detailed description of the present invention, with reference to the accompanying drawings.
The first embodiment is as follows:
a method for generating a power failure recovery plan for a power distribution network fault, as shown in fig. 1, in this embodiment, includes the following steps: (1) and acquiring a topological structure of the power distribution network and related parameters of power transfer. And collecting load parameters and contact relations of all substations which supply power to the power distribution network, such as 110kV and 35kV related main transformers, buses and related feeders. And acquiring a network transfer path of the transformer substation. And calculating the limit constraint of the transfer line according to the load and capacity limit before the line is transferred. And calculating the limit constraint of the main transformer to be converted and supplied according to the load and capacity limit before the main transformer is converted and supplied.
(2) And selecting a certain transformer substation in the power distribution network, and calculating the maximum transfer load of the single-path feeder line when the transformer substation is completely stopped. The single path refers to a power failure feeder line with only one transfer path. As shown in fig. 3, the transfer path from longnan 421 to the chengcang change I main transformer, the transfer path from san city 415 to the yangqing change III main transformer, the transfer path from Yongfeng 428 to the yangqing change I main transformer, the transfer path from Liudong 411 to the yangqing change I main transformer, and the transfer path from Wenchang 425 to the culture II main transformer are single paths.
As shown in fig. 2, in step (2), the method for calculating the maximum transfer load of the single-path feeder line when the substation is completely stopped includes the following steps: (2.1) establishing line quota constraints
Xi≤min(Ri(1-ai),kLi)
Figure BDA0002423841330000041
Wherein, XiFor loads, R, recoverable by a single-path feeder iiFor the opposite line capacity, aiFor the actual load factor on the opposite side, LiIs the loss load of the feeder line i, k is the recovery load of the non-fault area of the feeder line i, 0<k is less than or equal to 1, and omega 3 is a set of all the feeders transferred to the same opposite side line; for the calculation of the transfer capacity, k is 1, that is, the non-fault area recovery amount of each feeder line is the load of the feeder line before power failure. The load is transferred to the main transformer of Yanqing transformer III through a zijin N155 line by a three city 415 line in figure 3, and R at the pointiThe line capacity of the zijin N155 line. For Ω 3, it can be considered as a set of multiple single-path feeders transferred to the same feeder, like the chunzhi 415 line and the nursery 430 line in fig. 1, which are transferred to the allied bumper I main transformer through the cockscomb N241.
(2.2) establishing main transformer quota constraint
Figure BDA0002423841330000051
Omega 1 is the set of all single path blackout feeders transferred to the same main transformer, TiIs the quota of the main transformer, biFor the load rate of the main transformer before transfer, the limit of the main transformer is not invariable, and the limit can be adjusted along with the adjustment of the mode and can be taken as the limit of the main transformer in a typical mode; in FIG. 1, the 415 lines and 430 lines of Chun Zhi are transferred to the I-type main transformer of Bifeng transformer where T isiNumber I main transformer quota of finger joint Feng transform, biThe method comprises transferring 415 lines of the spring glossy ganoderma and 430 lines of a nursery garden to a No. I main transformer of the combined harvest and transformation.
And (3) constraining the constraint inequality into an equality constraint:
Xi+X′i≤min(Ri(1-ai),kLi)
Figure BDA0002423841330000052
Figure BDA0002423841330000053
wherein, X'i、X″iAnd X'iIs a relaxation variable;
(2.3) establishing an objective function
Figure BDA0002423841330000054
Wherein m is the number of main transformers to be converted, and p is the number of various single-path feeders transferred to the same feeder;
and (2.4) solving the optimal solution of the objective function, and solving by using a simplex method to obtain the maximum load F which can be recovered by the single-path transfer of the power failure transformer substation.
And (4) if the maximum transfer load amount is equal to the power failure load amount, taking the single-path feeder line transfer scheme as a power failure recovery plan and entering the step (6), otherwise, entering the step (3).
(3) The paths of all the hand-pulling lines are eliminated, the outgoing lines of the same transformer substation are provided with interconnected single paths, and the switching path fails when power is cut off, and is excluded; establishing a multi-path transfer scheme, wherein the transfer scheme has the following characteristics:
a. when each scheme is generated, one multi-path feeder line can only select one of the feasible transfer schemes;
b. all multipath feeders must be selected once for each scenario generation;
c. each option has at least one transfer path that is different from the others.
The method for constructing the linear programming equation comprises the following steps: (3.1) all the single-path loads are transferred to the opposite side, the main transformer with zero main transformer margin after the transfer is eliminated, and the limitation constraint of the multipath maximum transfer power line is established
Xj≤min(Rj(1-aj),kLj)
Wherein, XjFor loads recoverable by feeder j using multi-path switchingjTo transfer the line capacity of the side, ajTo divert the current load factor, LjBefore power failure, a feeder j is selected, and k is the ratio of the recovery load of a non-fault area of the feeder j; (3.2) establishing main transformer quota constraint
Figure BDA0002423841330000061
Wherein, omega 2 is the set of all single-path blackout feeders transferred to the same main transformer, TjIs the quota of the main transformer, bjThe load factor of the main transformer before transfer;
and (3) constraining the constraint inequality into an equality constraint:
Xj+X′j≤min(Rj(1-aj),kLj)
Figure BDA0002423841330000062
wherein, X'jAnd X ″)jIn order to be a function of the relaxation variable,
(3.3) establishing an objective function
Figure BDA0002423841330000063
Wherein q is the number of main transformers to be supplied, XjThe load which can be recovered is supplied to the feeder j through multi-path transfer, d is the number of the multi-path feeders, and F' is the maximum load which can be recovered by the multi-path transfer of the power failure transformer substation; and (3.4) solving the optimal solution of the objective function, and solving by using a simplex method to obtain the maximum load F' which can be recovered by the power failure transformer substation through multi-path transfer. The expression of the objective function is established on the basis of the following conditions: a. different multi-path feeder lines can be transferred to the same main transformer; b. at least two multipath feeder transfer paths are provided. The distribution network operating the method of the embodiment should meet the above conditions.
(4) And establishing a plurality of multipath transfer schemes to obtain the transfer load quantity of each scheme. (5) And (5) evaluating and sequencing the multi-path transfer schemes to obtain an optimal multi-path transfer scheme, and taking the single-path feeder line transfer scheme and the optimal multi-path transfer scheme obtained in the step (2) and the step (5) as a power failure recovery plan.
If the optimal solution value is equal to the summary of all the single-path power failure loads of the transformer substation, the fact that weak links do not exist in the single-path feeder load supply of the transformer substation is shown. If the sum of the power failure loads of all the single paths of the transformer substation is less than the sum of the power failure loads of all the single paths of the transformer substation, it is indicated that weak links exist in some single-path feeder lines of the transformer substation.
(6) And (5) carrying out the steps (2) to (5) on all the substations in the power distribution network to obtain a power failure recovery plan of the power distribution network.
Whether the power loss load can be quickly transferred out after the power failure of the power distribution network is directly influenced by the transfer capacity of the power distribution network, and for a single feeder line, the transfer capacity is determined by the capacity of the feeder line and the margin after the transfer and is influenced by the load rate of a main transformer after the transfer. The load margin after the transfer generally determines whether a weak link exists in the feeder line. For a transformer substation, the load rate of a feeder line and the load rate of a main transformer cannot completely reflect the power transfer capacity of a power distribution network. The load rate index only indicates the acceptable ratio of load to capacity, and only reflects the capacity of a feeder line or a main transformer capable of bearing extra load; when a substation is completely stopped, even if all the load factors of the transfer lines are not overloaded, the main transformer after transfer is still overloaded. Whether the main transformer is overloaded or not is related to different transfer paths. Therefore, different transfer paths are transferred, and the allowed load amount is different, so that an optimal transfer scheme needs to be established.
Whether weak links exist in the power transfer capacity of the power distribution network or not is judged by taking the maximum value of the power transfer capacity of various power transfer schemes as an evaluation standard, if the maximum power transfer scheme still cannot meet the requirement of power loss load transfer, the weak links exist in the power distribution network, and targeted treatment measures such as transformation or change of a topological structure are required. The embodiment can effectively provide the power grid recovery plan under the most severe condition.
The above-described embodiments are only preferred embodiments of the present invention, and are not intended to limit the present invention in any way, and other variations and modifications may be made without departing from the spirit of the invention as set forth in the claims.

Claims (7)

1. A power distribution network fault power failure recovery plan generation method is characterized in that,
the method comprises the following steps:
(1) acquiring a topological structure of a power distribution network and related parameters of power transfer;
(2) selecting a certain transformer substation in the power distribution network, calculating the maximum transfer load capacity of the single-path feeder line when the transformer substation is completely stopped, if the maximum transfer load capacity is equal to the power failure load capacity, taking the single-path feeder line transfer scheme as a power failure recovery plan and entering the step (6), otherwise, entering the step (3);
(3) establishing a multi-path transfer scheme, constructing a linear programming equation, and solving the multi-path transfer load amount by applying a simplex method;
(4) establishing a plurality of multipath transfer schemes to obtain the transfer load quantity of each scheme;
(5) evaluating and sequencing the multi-path transfer scheme to obtain an optimal multi-path transfer scheme, and taking the single-path feeder transfer scheme and the optimal multi-path transfer scheme obtained in the step (2) and the step (5) as a power failure recovery plan;
(6) and (5) carrying out the steps (2) to (5) on all the substations in the power distribution network to obtain a power failure recovery plan of the power distribution network.
2. The method for generating the power distribution network fault and power failure recovery plan according to claim 1, wherein in the step (2), the method for calculating the maximum transfer load of the single-path feeder line when the substation is completely stopped comprises the following steps:
(2.1) establishing line quota constraints
Xi≤min(Ri(1-ai),kLi)
Figure FDA0002423841320000011
Wherein, XiFor loads, R, recoverable by a single-path feeder iiFor the opposite line capacity, aiFor the actual load factor on the opposite side, LiIs the loss load of the feeder line i, k is the recovery load of the non-fault area of the feeder line i, 0<k is less than or equal to 1, and omega 3 is a set of all the feeders transferred to the same opposite side line;
(2.2) establishing main transformer quota constraint
Figure FDA0002423841320000012
Omega 1 is the set of all single path blackout feeders transferred to the same main transformer, TiIs the quota of the main transformer, biThe load factor of the main transformer before transfer;
(2.3) establishing an objective function
Figure FDA0002423841320000021
Wherein n is the number of the single-path feeder lines, and F is the maximum load amount which can be recovered by single-path switching of the power failure transformer substation;
(2.4) solving the optimal solution of the objective function
And solving by using a simplex method to obtain the maximum load F which can be recovered by the single-path transfer of the power failure transformer substation.
3. The method for generating the power distribution network fault and power failure recovery plan according to claim 2, wherein the step (2.2) further comprises the following steps:
and (3) constraining the constraint inequality into an equality constraint:
Xi+X′i≤min(Ri(1-ai),kLi)
Figure FDA0002423841320000022
Figure FDA0002423841320000023
wherein, X'i、X″iAnd X'iIn order to be a function of the relaxation variable,
the objective function established in the step (2.3) is changed into:
Figure FDA0002423841320000024
wherein m is the number of main transformers to be transformed, and p is the number of various single-path feeders transferred to the same feeder.
4. The method for generating the power distribution network failure and power failure recovery plan according to claim 1, 2 or 3,
and (4) before the multi-path transfer scheme is established in the step (3), removing all paths of the hand-in-hand line.
5. The method for generating the power distribution network failure and power failure recovery plan according to claim 1, 2 or 3,
in the step (3), the method for constructing the linear programming equation comprises the following steps:
(3.1) establishing line quota constraints
Xj≤min(Rj(1-aj),kLj)
Wherein, XjFor loads recoverable by feeder j using multi-path switchingjTo transfer the line capacity of the side, ajTo divert the current load factor, LjBefore power failure, a feeder j is selected, and k is the ratio of the recovery load of a non-fault area of the feeder j;
(3.2) establishing main transformer quota constraint
Figure FDA0002423841320000031
Wherein, omega 2 is the set of all single-path blackout feeders transferred to the same main transformer, TjIs the quota of the main transformer, bjThe load factor of the main transformer before transfer;
(3.3) establishing an objective function
Figure FDA0002423841320000032
Wherein, XjThe load which can be recovered is supplied to the feeder j through multi-path transfer, d is the number of the multi-path feeders, and F' is the maximum load which can be recovered by the multi-path transfer of the power failure transformer substation;
(3.4) solving the optimal solution of the objective function
And solving by using a simplex method to obtain the maximum load F' which can be recovered by the power-off transformer substation through multi-path transfer.
6. The method for generating the power distribution network fault and power failure recovery plan according to claim 5, wherein the step (3.2) further comprises the following steps:
and (3) constraining the constraint inequality into an equality constraint:
Xj+X′j≤min(Rj(1-aj),kLj)
Figure FDA0002423841320000033
wherein, X'jAnd X ″)jIn order to be a function of the relaxation variable,
the objective function established in step (3.3) is changed into:
Figure FDA0002423841320000034
wherein q is the number of main transformers to be transformed.
7. The method as claimed in claim 6, wherein the method for evaluating the multi-path forwarding scheme in step (5) is to take the multi-path forwarding scheme corresponding to the maximum value of the objective function F' as the optimal multi-path forwarding scheme.
CN202010214203.6A 2020-03-24 2020-03-24 Power distribution network fault power failure recovery plan generation method Pending CN111585273A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010214203.6A CN111585273A (en) 2020-03-24 2020-03-24 Power distribution network fault power failure recovery plan generation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010214203.6A CN111585273A (en) 2020-03-24 2020-03-24 Power distribution network fault power failure recovery plan generation method

Publications (1)

Publication Number Publication Date
CN111585273A true CN111585273A (en) 2020-08-25

Family

ID=72117199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010214203.6A Pending CN111585273A (en) 2020-03-24 2020-03-24 Power distribution network fault power failure recovery plan generation method

Country Status (1)

Country Link
CN (1) CN111585273A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112491050A (en) * 2020-12-04 2021-03-12 国网浙江省电力有限公司金华供电公司 Main and distribution network accident recovery processing method based on index set weight
CN113013871A (en) * 2021-01-25 2021-06-22 浙江华云信息科技有限公司 Load transfer method for power distribution network equipment during fault and maintenance
CN113507116A (en) * 2021-07-08 2021-10-15 国网河北省电力有限公司电力科学研究院 Power distribution network load transfer method, device, equipment and storage medium
CN114285161A (en) * 2021-12-06 2022-04-05 南京国电南自电网自动化有限公司 Distributed power distribution protection fault self-healing overload processing method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107046284A (en) * 2017-04-12 2017-08-15 国网浙江省电力公司 A kind of power distribution network turns energy supply power weak link appraisal procedure
CN107171312A (en) * 2017-05-15 2017-09-15 国家电网公司 A kind of fast quick-recovery optimal path choosing method of power distribution network large-area power-cuts

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107046284A (en) * 2017-04-12 2017-08-15 国网浙江省电力公司 A kind of power distribution network turns energy supply power weak link appraisal procedure
CN107171312A (en) * 2017-05-15 2017-09-15 国家电网公司 A kind of fast quick-recovery optimal path choosing method of power distribution network large-area power-cuts

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112491050A (en) * 2020-12-04 2021-03-12 国网浙江省电力有限公司金华供电公司 Main and distribution network accident recovery processing method based on index set weight
CN113013871A (en) * 2021-01-25 2021-06-22 浙江华云信息科技有限公司 Load transfer method for power distribution network equipment during fault and maintenance
CN113507116A (en) * 2021-07-08 2021-10-15 国网河北省电力有限公司电力科学研究院 Power distribution network load transfer method, device, equipment and storage medium
CN113507116B (en) * 2021-07-08 2022-07-22 国网河北省电力有限公司电力科学研究院 Power distribution network load transfer method, device, equipment and storage medium
CN114285161A (en) * 2021-12-06 2022-04-05 南京国电南自电网自动化有限公司 Distributed power distribution protection fault self-healing overload processing method
CN114285161B (en) * 2021-12-06 2024-03-19 南京国电南自电网自动化有限公司 Distributed power distribution protection fault self-healing overload processing method

Similar Documents

Publication Publication Date Title
CN111585273A (en) Power distribution network fault power failure recovery plan generation method
CN107046284B (en) Power distribution network energy conversion power weak link evaluation method
Sarimuthu et al. A review on voltage control methods using on-load tap changer transformers for networks with renewable energy sources
Ochoa et al. Evaluating distributed generation impacts with a multiobjective index
Ghasemi et al. Radial distribution systems reconfiguration considering power losses cost and damage cost due to power supply interruption of consumers.
Elmitwally et al. A fuzzy-multiagent self-healing scheme for a distribution system with distributed generations
CN103746368B (en) Method of optimizing static safe and stable operation limit of electric power system
CN110097284B (en) Power distribution network reliability assessment method and device based on feeder line capacity constraint
Lim et al. An optimal composition and placement of automatic switches in DAS
CN110137939B (en) Method for converting full-stop load of transformer substation into power supply
CN111049149B (en) Power grid terminal low voltage treatment method
Zidan et al. Service restoration in balanced and unbalanced distribution systems with high DG penetration
CN102290798B (en) Quick power supply restoring rule based on distribution network wire connecting way
Gao et al. Automatic compensation voltage control strategy for on-load tap changer transformers with distributed generations
Abubakar et al. Optimal reconfiguration of radial distribution networks using improved genetic algorithm
CN105846422B (en) A kind of large capacity grid short circuit current control stimulation optimization configuration method
CN109635331B (en) Economic short-circuit current limiter optimal configuration method
CN116247737A (en) Analysis method based on dynamic load margin of active power distribution network planning
CN113991653A (en) Three-stage topological operation mode optimization method considering load importance degree
Fila et al. Coordinated voltage control for active network management of distributed generation
CN110148934A (en) Consider that the distribution network load of secondary turn of confession turns for method
CN109768544A (en) Area power grid load transfer method
CN109245117B (en) Automatic generation method for static safety aid decision of regional power grid
Simović et al. An improved experimental power distribution system simulator for the analysis of power quality parameters
Schäfer et al. Derivation of recommendations for the future reactive power exchange at the interface between distribution and transmission grid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200825

RJ01 Rejection of invention patent application after publication