CN111560982A - Installation method of cable prefabricated well - Google Patents

Installation method of cable prefabricated well Download PDF

Info

Publication number
CN111560982A
CN111560982A CN202010318835.7A CN202010318835A CN111560982A CN 111560982 A CN111560982 A CN 111560982A CN 202010318835 A CN202010318835 A CN 202010318835A CN 111560982 A CN111560982 A CN 111560982A
Authority
CN
China
Prior art keywords
well
chamber
well chamber
installing
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010318835.7A
Other languages
Chinese (zh)
Inventor
沈立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Guantong New Material Co ltd
Original Assignee
Hangzhou Guantong New Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Guantong New Material Co ltd filed Critical Hangzhou Guantong New Material Co ltd
Priority to CN202010318835.7A priority Critical patent/CN111560982A/en
Publication of CN111560982A publication Critical patent/CN111560982A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention discloses a method for installing a cable prefabricated well, which comprises the following steps: a. treating the foundation of the installation position of the cable precast well, and excavating foundation trenches: b. constructing cushion concrete in the foundation trench: c. the cable prefabricated well is prefabricated in four sections: lower well room, go up well room and well lid: d. a plurality of reserved pipeline mounting holes are formed in the wall of the lower well chamber as required: e. hoisting a lower well chamber to the cushion concrete, and then installing a corrugated pipe on the reserved pipeline installation hole: f. hoisting the middle well chamber to the lower well chamber, connecting the middle well chamber and the lower well chamber through a first connecting mechanism, and hoisting the upper well chamber to the middle well chamber: g. and installing the well cover on the upper well chamber.

Description

Installation method of cable prefabricated well
Technical Field
The invention belongs to the technical field of communication, and particularly relates to a method for installing a cable prefabricated well.
Background
In recent years, with the continuous development of urban construction, pipeline construction becomes more and more important, and communication pipeline construction is an important part of municipal infrastructure. In the construction of communication pipes, it is necessary to construct communication wells at intervals on a road surface along a laying path in order to lay cables. The existing communication well generally adopts a field building process. The construction process has the following defects: firstly, the construction method occupies more workers and has long construction time; secondly, the brick structure has poor strength and low bearing capacity and is easy to damage; thirdly, the site masonry construction is easily affected by the weather environment, and the failure of the construction in rainy and snowy weather may cause the delay of the work period.
Disclosure of Invention
The invention provides a method for installing a cable prefabricated well, aiming at overcoming the defects of the prior art.
In order to achieve the purpose, the invention adopts the following technical scheme: a method of installing a prefabricated well for a cable, the method comprising the steps of: a. and (3) treating the foundation of the installation position of the cable precast well, excavating a foundation trench:
b. constructing cushion concrete in the foundation trench:
c. the cable prefabricated well is prefabricated in four sections: lower well room, go up well room and well lid:
d. a plurality of reserved pipeline mounting holes are formed in the wall of the lower well chamber as required:
e. hoisting a lower well chamber to the cushion concrete, and then installing a corrugated pipe on the reserved pipeline installation hole:
f. hoisting the middle well chamber to the lower well chamber, connecting the middle well chamber and the lower well chamber through a first connecting mechanism, and hoisting the upper well chamber to the middle well chamber:
g. installing a well cover on the upper well chamber; before installation, all parts are processed, and during installation, all parts are only required to be respectively hoisted, so that the construction period is greatly shortened.
Preferably, the first connecting mechanism comprises an inserting plate and a screw which are arranged on the bottom of the middle well chamber and a slot which is arranged on the lower well chamber, and the inserting plate and the lower well chamber are both provided with threaded holes which are matched with the screw; when the well chamber is hoisted, the inserting plate is aligned to the inserting groove, then the inserting plate is inserted into the inserting groove, and then the bolt falls onto the inserting plate, so that the connection of the well chamber and the well chamber can be completed.
Preferably, elastic bulges are arranged on two sides of the inserting plate, and clamping grooves matched with the elastic bulges are arranged on the side walls of the inserting grooves; through the cooperation of elastic bulge and draw-in groove, can play good sealed effect.
Preferably, the upper part of the side wall of the slot is provided with an inclined surface; the inclined surface can play a guiding role for the insertion plate, so that the insertion plate is aligned with the slot conveniently.
In summary, all parts are processed before installation, and only need during installation hoist and mount respectively can, construction cycle has been reduced greatly.
Drawings
FIG. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a cross-sectional view of the present invention.
Fig. 3 is an enlarged view of fig. 2 at a.
Detailed Description
As shown in fig. 1 to 3, a method for installing a cable prefabricated well is characterized in that: the method comprises the following steps: a. treating the foundation of the installation position of the cable precast well, and excavating foundation trenches:
b. constructing cushion concrete in the foundation trench:
c. the cable prefabricated well is prefabricated in four sections: well chamber 1, well chamber 2, well chamber 3 and well lid 4 go up:
d. a plurality of reserved pipeline mounting holes 11 are formed in the wall of the lower well chamber 1 as required:
e. hoisting the lower well chamber to the cushion concrete, and then installing the corrugated pipe 12 on the reserved pipeline installation hole:
f. hoisting a middle well chamber onto a lower well chamber, connecting the middle well chamber and the lower well chamber through a first connecting mechanism, hoisting an upper well chamber onto the middle well chamber, wherein the first connecting mechanism comprises a plug board 41 and a screw 42 which are arranged on the bottom of the middle well chamber, and a slot 43 which is arranged on the lower well chamber, and the plug board and the lower well chamber are both provided with threaded holes matched with the screw; the slot 43 is arranged at the top of the well-descending chamber, and the upper part of the side wall of the slot is provided with an inclined surface 431; the inclined surface can guide the plugboard, so that the plugboard and the slot are aligned conveniently, when the well chamber is hoisted, the plugboard is aligned with the slot, then the plugboard is inserted into the slot, and then the bolt falls onto the plugboard, so that the connection of the well descending chamber and the well chamber can be completed; elastic bulges 43 are arranged on two sides of the inserting plate 41, and clamping grooves 44 matched with the elastic bulges are arranged on the side walls of the inserting grooves; through the cooperation of elastic bulge and draw-in groove, can play good sealed effect:
g. and installing the well cover on the upper well chamber.

Claims (4)

1. A method for installing a cable prefabricated well is characterized by comprising the following steps: the method comprises the following steps:
a. treating the foundation of the installation position of the cable precast well, and excavating foundation trenches:
b. constructing cushion concrete in the foundation trench:
c. the cable prefabricated well is prefabricated in four sections: lower well room (1), well room (2), upper well room (3) and well lid (4):
d. and a plurality of reserved pipeline mounting holes (11) are formed in the wall of the lower well chamber according to requirements:
e. hoisting the well-descending chamber to the cushion concrete, and then installing a corrugated pipe (12) on the reserved pipeline installation hole:
f. hoisting the middle well chamber to the lower well chamber, connecting the middle well chamber and the lower well chamber through a first connecting mechanism, and hoisting the upper well chamber to the middle well chamber:
g. and installing the well cover on the upper well chamber.
2. The method for installing a cable prefabricated well according to claim 1, wherein: the first connecting mechanism comprises an inserting plate (41) arranged at the bottom of the well chamber, a screw (42) and a slot (43) arranged on the well chamber, and threaded holes matched with the screw are formed in the inserting plate and the well chamber.
3. The method for installing a cable prefabricated well according to claim 2, wherein: elastic bulges (43) are arranged on two sides of the inserting plate, and clamping grooves (44) matched with the elastic bulges are arranged on the side walls of the inserting grooves.
4. The method for installing a cable prefabricated well according to claim 2, wherein: the upper part of the side wall of the slot (43) is provided with an inclined surface (431).
CN202010318835.7A 2020-04-21 2020-04-21 Installation method of cable prefabricated well Pending CN111560982A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010318835.7A CN111560982A (en) 2020-04-21 2020-04-21 Installation method of cable prefabricated well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010318835.7A CN111560982A (en) 2020-04-21 2020-04-21 Installation method of cable prefabricated well

Publications (1)

Publication Number Publication Date
CN111560982A true CN111560982A (en) 2020-08-21

Family

ID=72074407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010318835.7A Pending CN111560982A (en) 2020-04-21 2020-04-21 Installation method of cable prefabricated well

Country Status (1)

Country Link
CN (1) CN111560982A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113026910A (en) * 2021-03-16 2021-06-25 常熟市华诚建设工程有限责任公司 Adjustable steel mould concrete catch basin and installation and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09151472A (en) * 1995-11-30 1997-06-10 Techno Kuriito:Kk Construction method for propelling sunken shaft also used as manhole, sinking control device and sunken block
CN103615018A (en) * 2013-12-10 2014-03-05 国网上海市电力公司 High-strength composite material cable duct connection well
CN206956778U (en) * 2017-05-04 2018-02-02 南通电力设计院有限公司 A kind of prefabricated bolt arrangement cable shaft component
CN109024688A (en) * 2018-08-29 2018-12-18 华中科技大学 A kind of assembled cable work well and component on site construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09151472A (en) * 1995-11-30 1997-06-10 Techno Kuriito:Kk Construction method for propelling sunken shaft also used as manhole, sinking control device and sunken block
CN103615018A (en) * 2013-12-10 2014-03-05 国网上海市电力公司 High-strength composite material cable duct connection well
CN206956778U (en) * 2017-05-04 2018-02-02 南通电力设计院有限公司 A kind of prefabricated bolt arrangement cable shaft component
CN109024688A (en) * 2018-08-29 2018-12-18 华中科技大学 A kind of assembled cable work well and component on site construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113026910A (en) * 2021-03-16 2021-06-25 常熟市华诚建设工程有限责任公司 Adjustable steel mould concrete catch basin and installation and construction method thereof
CN113026910B (en) * 2021-03-16 2022-05-20 常熟市华诚建设工程有限责任公司 Adjustable steel mould concrete catch basin and installation and construction method thereof

Similar Documents

Publication Publication Date Title
CN103510640A (en) Fabricated shear wall and assembly method thereof
CN101168963A (en) Large depth underground continuous wall water-stop joint device
CN113513015A (en) Semi-prefabricated concrete reinforcement cage underground continuous wall and construction method
CN105544605A (en) Modular assembly type comprehensive pipe gallery
CN209873873U (en) Prefabricated assembled power pipeline working well
CN111560982A (en) Installation method of cable prefabricated well
CN110886311A (en) Large-volume assembly type ground tire mold
CN204167849U (en) Cable trough and cover plate thereof
CN218543388U (en) Push bench convenient to adjustment height
CN110863512A (en) Prefabricated cable utility tunnel
CN201125396Y (en) Underground continuous wall water stop joint device
CN111472390A (en) Prefabricated well of pin-connected panel cable
CN213682833U (en) Precast concrete wallboard
CN211922702U (en) Prefabricated cable utility tunnel
CN111877315B (en) Local prefabricated diaphragm wall guide wall under underground facility and construction method
CN212304531U (en) Prefabricated assembled cable duct bank
CN204732833U (en) Cordwood system type anti-silting pattern block cable trough
CN216587897U (en) Precast concrete bathroom chassis
CN214738579U (en) Stable form railway tunnel escape canal groove apron
CN218374460U (en) Prefabricated plate fetal membrane connection structure
CN218264177U (en) Bench type anti-corrosion combined movable cover plate
CN215105860U (en) Underground drainage pipeline system for rural sewage
CN210074728U (en) Concrete prefabricated part for laying underground cable
CN118029543B (en) Assembled building structure
CN221072722U (en) Underground utility tunnel connection structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200821