CN111550062A - Hoisting steel frame design method applied to field of building curtain wall - Google Patents

Hoisting steel frame design method applied to field of building curtain wall Download PDF

Info

Publication number
CN111550062A
CN111550062A CN202010484064.9A CN202010484064A CN111550062A CN 111550062 A CN111550062 A CN 111550062A CN 202010484064 A CN202010484064 A CN 202010484064A CN 111550062 A CN111550062 A CN 111550062A
Authority
CN
China
Prior art keywords
checking
load
steel frame
hoisting
calculation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010484064.9A
Other languages
Chinese (zh)
Inventor
丁杰
徐金胜
王攀攀
李鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN202010484064.9A priority Critical patent/CN111550062A/en
Publication of CN111550062A publication Critical patent/CN111550062A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention discloses a design method of a hoisting steel frame applied to the field of building curtain walls, which comprises the following steps: 1) analyzing load and working conditions; 2) checking and calculating a steel frame: determining a steel frame structure calculation unit, wherein the steel frame structure calculation unit is subjected to load arrangement, bearing capacity calculation and deformation calculation; 3) checking and calculating the steel wire rope: 4) checking and calculating a supporting structure of the winch: determining the specific size and the section shape of the structure calculation unit, the load arrangement on the structure calculation unit, the bearing capacity calculation and the deformation calculation; 5) checking and calculating the bolt; checking the shear strength of the bolt; 6) and (6) checking and calculating the welding seam. The invention effectively ensures the safety of hoisting the large glass plate by the hoisting steel frame and avoids accidents in the hoisting process.

Description

Hoisting steel frame design method applied to field of building curtain wall
Technical Field
The invention relates to the technical field of building construction, in particular to a design method of a hoisting steel frame applied to the field of building curtain walls.
Background
As is well known, building curtain is one of ubiquitous building structure in the existing market, also receive liking of people deeply because of its pleasing to the eye degree height, aluminum plate glass molding curtain, bright frame glass curtain, in the work progress such as full glass curtain and aluminum plate furred ceiling, must carry out the installation of large plate glass behind the just ability of the large plate glass hoist to corresponding installation floor of waiting to install, however, must use the hoist and mount steelframe to accomplish among the large plate glass hoist and mount process, current hoist and mount steelframe produces huge security threat to the constructor because of bearing the weight of the atress problem.
Disclosure of Invention
The invention provides a design method of a hoisting steel frame applied to the field of building curtain walls, which can effectively solve the technical problems mentioned in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme:
a design method of a hoisting steel frame applied to the field of building curtain walls comprises the following steps:
1) analyzing load and working conditions;
1.1) load value: according to the steel frame stress condition and the calculation model, the load is input according to the node load, wherein:
constant load: self-weight of the steel frame;
live load: calculating the hollow toughened glass according to 50kg/m 2; the glass plate is 2.8m x3m, the hoisting power amplification coefficient is 1.3, and the single-point load is calculated according to the hoisting power amplification coefficient;
wind load: wk ═ β z μ s μ zw 0;
1.2) calculating load combination;
load combination of the structure during the checking calculation of the strength: 1.3 dead load +1.5 live load +1.5 wind load
And (3) load combination of the structure during deformation checking calculation: 1.0 constant load +1.0 live load
2) Checking and calculating a steel frame: determining a steel frame structure calculation unit, wherein the steel frame structure calculation unit is subjected to load arrangement, bearing capacity calculation and deformation calculation;
3) checking and calculating the steel wire rope: the tensile force borne by the steel wire rope in the hoisting process of the steel wire rope to be used on site is as follows:
Figure BDA0002518284700000021
the safety coefficient of the steel wire rope during hoisting is not less than 6;
in the formula: qD-a construction calculated value (kN) of the tension experienced by the power steel cord;
k is a safety coefficient, and 6 is selected;
the calculation proves that the tensile force borne by the steel wire rope is less than the breaking tensile force during hoisting;
4) checking and calculating a supporting structure of the winch: determining the specific size and the section shape of the structure calculation unit, the load arrangement on the structure calculation unit, the bearing capacity calculation and the deformation calculation;
5) checking and calculating the bolt; checking the shear strength of the bolt;
6) and (6) checking and calculating the welding seam.
Preferably, in step 3) wire rope checking calculation, the wire rope structure to be used on site is 431SW + NF, the diameter is 8.3mm, the nominal strength is 2160MPa, the breaking tension is not less than 55KN, and in the hoisting process, the tension borne by the wire rope is as follows:
Figure BDA0002518284700000022
preferably, the weld seam checking in the step 6) comprises fillet weld strength checking and fillet weld structure checking, wherein the checking content of the fillet weld strength checking is normal stress under axial force and angular point maximum comprehensive stress.
Preferably, in step 6), the calculated weld is a four-side girth welding fillet weld, the height of the welding leg is 4mm, the thickness of the connecting plate is 10mm, the height of the weld is 4mm, and the internal force value is 31.9 kN.
Preferably, in step 6), the fillet configuration inspection requires checking fillet web minimum thickness, configuration required maximum fillet height, web fillet web maximum thickness, and configuration required minimum web fillet height.
Compared with the prior art, the invention has the beneficial effects that:
according to the invention, by analyzing the load and working condition of the hoisting steel frame, calculating the bearing capacity and deformation of the steel frame, and checking the steel wire rope, the winch supporting structure, the bolt and the welding line, the safety of hoisting the large plate glass by the hoisting steel frame is effectively ensured, and accidents in the hoisting process are avoided.
Drawings
FIG. 1 is a schematic structural view of a large glass-hanging steel frame according to an embodiment of the present invention;
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The first embodiment is as follows:
as shown in fig. 1, a method for designing a hoisting steel frame applied to the field of building curtain walls comprises the following steps:
1) analyzing load and working conditions;
1.1) load value: according to the steel frame stress condition and the calculation model, the load is input according to the node load, wherein:
constant load: self-weight of the steel frame;
live load: calculating the hollow toughened glass according to 50kg/m 2; the glass plate is 2.8m x3m, the hoisting power amplification coefficient is 1.3, and the single-point load is calculated according to the hoisting power amplification coefficient;
wind load: wk ═ β z μ s μ zw 0;
1.2) calculating load combination;
load combination of the structure during the checking calculation of the strength: 1.3 dead load +1.5 live load +1.5 wind load
And (3) load combination of the structure during deformation checking calculation: 1.0 constant load +1.0 live load
2) Checking and calculating a steel frame: determining a steel frame structure calculation unit, wherein the steel frame structure calculation unit is subjected to load arrangement, bearing capacity calculation and deformation calculation;
3) checking and calculating the steel wire rope: the tensile force borne by the steel wire rope in the hoisting process of the steel wire rope to be used on site is as follows:
Figure BDA0002518284700000031
the safety coefficient of the steel wire rope during hoisting is not less than 6;
in the formula: qD-power wireA construction calculated value (kN) of the tension to which the rope is subjected;
k is a safety coefficient, and 6 is selected;
the calculation proves that the tensile force borne by the steel wire rope is less than the breaking tensile force during hoisting;
4) checking and calculating a supporting structure of the winch: determining the specific size and the section shape of the structure calculation unit, the load arrangement on the structure calculation unit, the bearing capacity calculation and the deformation calculation;
5) checking and calculating the bolt; and (4) checking the shear strength of the bolt.
6) Checking and calculating the welding line: the welding seam checking calculation comprises fillet welding seam strength checking calculation and fillet welding seam structure inspection, wherein the checking calculation content of the fillet welding seam strength checking calculation is normal stress and angular point maximum comprehensive stress under axial force.
Example two:
as shown in fig. 1, a method for designing a hoisting steel frame applied to the field of building curtain walls comprises the following steps:
1) analyzing load and working conditions;
1.1) load value: according to the steel frame stress condition and the calculation model, the load is input according to the node load, wherein:
constant load: self-weight of the steel frame;
live load: calculating the hollow toughened glass according to 50kg/m 2; the glass plate is 2.8mx3m, the hoisting power amplification coefficient is 1.3, and the single-point load is calculated according to the hoisting power amplification coefficient;
wind load: wk ═ β z μ s μ zw 0;
1.2) calculating load combination;
load combination of the structure during the checking calculation of the strength: 1.3 dead load +1.5 live load +1.5 wind load
And (3) load combination of the structure during deformation checking calculation: 1.0 constant load +1.0 live load
2) Checking and calculating a steel frame: determining a steel frame structure calculation unit, wherein the steel frame structure calculation unit is subjected to load arrangement, bearing capacity calculation and deformation calculation;
3) checking and calculating the steel wire rope: the steel wire rope structure that the scene was planned to use is 431SW + NF, diameter 8.3mm, and nominal strength is 2160MPa, and breaking tension is not less than 55KN, and the hoist and mount in-process, the pulling force that the wire rope receives is:
Figure BDA0002518284700000051
the safety coefficient of the steel wire rope during hoisting is not less than 6;
in the formula: qD-a construction calculated value (kN) of the tension experienced by the power steel cord;
k is a safety coefficient, and 6 is selected;
the calculation proves that the tensile force borne by the steel wire rope is less than the breaking tensile force during hoisting;
4) checking and calculating a supporting structure of the winch: determining the specific size and the section shape of the structure calculation unit, the load arrangement on the structure calculation unit, the bearing capacity calculation and the deformation calculation;
5) checking and calculating the bolt; checking the shear strength of the bolt;
6) checking and calculating the welding line: the checking content of the fillet weld strength checking calculation is normal stress under axial force and the maximum comprehensive stress of an angular point;
the checked welding line is a four-side girth welding fillet welding line, the height of a welding leg is 4mm, the thickness of the connecting plate is 10mm, the height of the welding line is 4mm, and the internal force value is N which is 31.9 kN;
fillet weld construction inspection requires inspection of fillet weld web minimum thickness, construction required maximum fillet height, web fillet weld web maximum thickness, and construction required minimum web fillet height.
According to the invention, by analyzing the load and working condition of the hoisting steel frame, calculating the bearing capacity and deformation of the steel frame, and checking the steel wire rope, the winch supporting structure, the bolt and the welding line, the safety of hoisting the large plate glass by the hoisting steel frame is effectively ensured, and accidents in the hoisting process are avoided.
The foregoing is merely exemplary and illustrative of the present invention and various modifications, additions and substitutions may be made by those skilled in the art to the specific embodiments described without departing from the scope of the invention as defined in the following claims.

Claims (5)

1. A design method of a hoisting steel frame applied to the field of building curtain walls is characterized by comprising the following steps:
1) analyzing load and working conditions;
1.1) load value: according to the steel frame stress condition and the calculation model, the load is input according to the node load, wherein:
constant load: self-weight of the steel frame;
live load: calculating the hollow toughened glass according to 50kg/m 2; the glass plate is 2.8m x3m, the hoisting power amplification coefficient is 1.3, and the single-point load is calculated according to the hoisting power amplification coefficient;
wind load: wk ═ β z μ s μ zw 0;
1.2) calculating load combination;
load combination of the structure during the checking calculation of the strength: 1.3 dead load +1.5 live load +1.5 wind load
And (3) load combination of the structure during deformation checking calculation: 1.0 constant load +1.0 live load
2) Checking and calculating a steel frame: determining a steel frame structure calculation unit, wherein the steel frame structure calculation unit is subjected to load arrangement, bearing capacity calculation and deformation calculation;
3) checking and calculating the steel wire rope: the tensile force borne by the steel wire rope in the hoisting process of the steel wire rope to be used on site is as follows:
Figure FDA0002518284690000011
the safety coefficient of the steel wire rope during hoisting is not less than 6;
in the formula: qD-a construction calculated value (kN) of the tension experienced by the power steel cord;
k is a safety coefficient, and 6 is selected;
the calculation proves that the tensile force borne by the steel wire rope is less than the breaking tensile force during hoisting;
4) checking and calculating a supporting structure of the winch: determining the specific size and the section shape of the structure calculation unit, the load arrangement on the structure calculation unit, the bearing capacity calculation and the deformation calculation;
5) checking and calculating the bolt; checking the shear strength of the bolt;
6) and (6) checking and calculating the welding seam.
2. The design method of the hoisting steel frame applied to the field of building curtain walls as claimed in claim 1, wherein the design method comprises the following steps: in step 3) wire rope checking calculation, the wire rope structure that the scene was planned to use is 431SW + NF, diameter 8.3mm, and nominal strength is 2160MPa, and breaking force is not less than 55KN, and in the hoist and mount process, the pulling force that the wire rope receives is:
Figure FDA0002518284690000021
3. the design method of the hoisting steel frame applied to the field of building curtain walls as claimed in claim 2, wherein the design method comprises the following steps: the welding seam checking in the step 6) comprises fillet welding seam strength checking and fillet welding seam structure checking, wherein the checking content of the fillet welding seam strength checking is normal stress and angular point maximum comprehensive stress under axial force.
4. The design method of the hoisting steel frame applied to the field of building curtain walls as claimed in claim 3, wherein the design method comprises the following steps: in the step 6), the calculated welding line is a four-side girth welding fillet welding line, the height of a welding leg is 4mm, the thickness of the connecting plate is 10mm, the height of the welding line is 4mm, and the internal force value is N which is 31.9 kN.
5. The design method of the hoisting steel frame applied to the field of building curtain walls as claimed in claim 4, wherein the design method comprises the following steps: in step 6), fillet weld configuration inspection requires inspection of fillet weld web minimum thickness, configuration required maximum fillet height, web fillet weld web maximum thickness, and configuration required minimum web fillet height.
CN202010484064.9A 2020-06-01 2020-06-01 Hoisting steel frame design method applied to field of building curtain wall Pending CN111550062A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010484064.9A CN111550062A (en) 2020-06-01 2020-06-01 Hoisting steel frame design method applied to field of building curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010484064.9A CN111550062A (en) 2020-06-01 2020-06-01 Hoisting steel frame design method applied to field of building curtain wall

Publications (1)

Publication Number Publication Date
CN111550062A true CN111550062A (en) 2020-08-18

Family

ID=72005161

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010484064.9A Pending CN111550062A (en) 2020-06-01 2020-06-01 Hoisting steel frame design method applied to field of building curtain wall

Country Status (1)

Country Link
CN (1) CN111550062A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103774855A (en) * 2014-01-15 2014-05-07 浙江东驰钢结构有限公司 Construction method for external wall basket
CN205804987U (en) * 2016-06-24 2016-12-14 中国十七冶集团有限公司 A kind of heavy construction sub-truss lifting detection device
CN205908004U (en) * 2016-08-22 2017-01-25 中国电建集团核电工程公司 Special hoist and mount fixing device of hanging flower basket
EP3351699A1 (en) * 2017-01-20 2018-07-25 Hexagon Technology Center GmbH Construction management system and method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103774855A (en) * 2014-01-15 2014-05-07 浙江东驰钢结构有限公司 Construction method for external wall basket
CN205804987U (en) * 2016-06-24 2016-12-14 中国十七冶集团有限公司 A kind of heavy construction sub-truss lifting detection device
CN205908004U (en) * 2016-08-22 2017-01-25 中国电建集团核电工程公司 Special hoist and mount fixing device of hanging flower basket
EP3351699A1 (en) * 2017-01-20 2018-07-25 Hexagon Technology Center GmbH Construction management system and method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
田娥等: "《钢结构施工实例计算》", 31 October 2015 *
郭子洲: "浅议电动吊篮在外装饰施工过程中的几点思考", 《安徽建筑》 *

Similar Documents

Publication Publication Date Title
CN201221193Y (en) High altitude packway ceiling construction operating platform
CN104060840A (en) Construction method for lifting large-span dome net rack by using bolt sphere truss lifter
CN113152873A (en) Heightening hanging basket system
CN212772802U (en) Suspension structure system with weak correlation of each layer
CN108894329B (en) Overhanging type pipe truss and mounting method of supporting rod thereof
CN104153586A (en) Construction method for installing purline through suspension cable cranes
CN111550062A (en) Hoisting steel frame design method applied to field of building curtain wall
CN106144832A (en) A kind of special extended type wall-attached frame and preparation method thereof
CN110965797A (en) Steel beam edge protection device
CN216007760U (en) Non-counterweight ultrahigh hanging basket suspension device
CN105888269A (en) Suspended cable type safety protection device for building construction overhead operation, and construction method of suspended cable type safety protection device
CN205000632U9 (en) From jumping formwork job platform
CN113356556A (en) Steel structure-based counterweight-free hanging basket installation method
CN213569398U (en) Hanging basket device fixed by steel wire rope
CN220150968U (en) Mounting structure of indoor overhead operation life rope
CN204626927U (en) The sliding safe operation platform of elevator shaft guide rail
CN104806001A (en) Safety operation platform for sliding and lifting of elevator shaft guide rail and construction method
CN216974142U (en) Non-standard hanging basket mounting structure
CN220998884U (en) Assembled superimposed sheet adjustable angle hoist device
CN216157113U (en) Gallery support system encorbelments
CN218406412U (en) Secondary anti-falling device for bottom of anti-falling gate of steel platform
CN218623410U (en) Attached discharging platform device
CN211080961U (en) Telescopic adjustable core section of thick bamboo regularization protection work platform
CN219840385U (en) Cantilever concrete structure I-steel high formwork platform
CN215803083U (en) Fixed subassembly of modular scaffold frame of encorbelmenting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200818