CN111535489A - Method for arranging multipurpose additional steel bars of steel bar truss concrete laminated slab - Google Patents

Method for arranging multipurpose additional steel bars of steel bar truss concrete laminated slab Download PDF

Info

Publication number
CN111535489A
CN111535489A CN202010380142.0A CN202010380142A CN111535489A CN 111535489 A CN111535489 A CN 111535489A CN 202010380142 A CN202010380142 A CN 202010380142A CN 111535489 A CN111535489 A CN 111535489A
Authority
CN
China
Prior art keywords
steel bars
steel bar
concrete
side connecting
bar truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010380142.0A
Other languages
Chinese (zh)
Inventor
孟凡林
孟祥瑞
吴永亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin Zhongding Architectural Design Co ltd
Original Assignee
Jilin Zhongding Architectural Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Zhongding Architectural Design Co ltd filed Critical Jilin Zhongding Architectural Design Co ltd
Priority to CN202010380142.0A priority Critical patent/CN111535489A/en
Publication of CN111535489A publication Critical patent/CN111535489A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/18Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly cast between filling members
    • E04B5/19Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly cast between filling members the filling members acting as self-supporting permanent forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B2005/176Floor structures partly formed in situ with peripheral anchors or supports

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

A setting method of multipurpose additional steel bars of a concrete laminated slab of a steel bar truss belongs to the technical field of civil engineering, and comprises the steps of laying a bottom plate of the concrete laminated slab, manufacturing the multipurpose additional steel bars, binding single-side connecting steel bars, binding double-side connecting steel bars and pouring and maintaining concrete; meanwhile, the multipurpose additional steel bars for connecting the upper chord steel bars of the steel bar truss are bent downwards outside the lap joint area, so that the multipurpose additional steel bars are anchored at the top surface of the bottom plate of the concrete composite slab to replace a part of plate ends provided with additional steel bar sections extending into the support; therefore, the upper chord steel bar of the concrete composite slab steel bar truss plays a role in each stage of production, hoisting, installation construction and use, and the aims of saving the steel bar and reducing the construction cost are fulfilled.

Description

Method for arranging multipurpose additional steel bars of steel bar truss concrete laminated slab
Technical Field
The invention belongs to the technical field of civil engineering, relates to an assembly type building, and particularly relates to a method for setting multipurpose additional steel bars of a steel bar truss concrete composite slab.
Background
The concrete composite slab for prefabricated concrete structure building is constructed by adding a bottom plate of a steel bar truss concrete composite slab and a post-cast concrete composite layer. The upper chord steel bar of the concrete composite slab bottom plate steel bar truss is only used for increasing the rigidity of the concrete composite slab bottom plate in the production and construction stages so as to prevent the concrete composite slab bottom plate from generating overlarge deflection and cracks. When the concrete composite slab structure is designed, the upper chord steel bars of the concrete composite slab bottom plate steel bar truss are not used as negative-moment steel bars, so that the upper chord steel bars are in an idle state in the use stage of the concrete composite slab, and the waste of steel bar material resources is caused.
In order to facilitate the binding of reinforcing steel bars of structural members at the position of a support after the bottom plate of the concrete composite slab is laid, the form that the reinforcing steel bars cannot be produced when the bottom plate end of the bottom plate of the concrete composite slab is manufactured is a development trend, and in order to solve the problem that the reinforcing steel bars at the bottom of the plate end extend into the support end, an additional reinforcing steel bar section extending into the support and the waste reinforcing steel bars are arranged at the plate end.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the method for arranging the multipurpose additional reinforcing steel bars of the concrete composite slab of the steel bar truss is characterized in that the multipurpose additional reinforcing steel bars for connecting the upper chord reinforcing steel bars of the steel bar truss are arranged at the position of a support, the upper chord reinforcing steel bars of the steel bar truss are used as the negative bending moment reinforcing steel bars of the support of the concrete composite slab, and the upper chord reinforcing steel bars of the steel bar truss are effectively utilized; meanwhile, the multipurpose additional steel bars for connecting the upper chord steel bars of the steel bar truss are bent downwards outside the lap joint area, so that the multipurpose additional steel bars are anchored at the top surface of the bottom plate of the concrete composite slab to replace a part of plate ends provided with additional steel bar sections extending into the support; the purpose of saving the reinforcing steel bars can be achieved.
A method for arranging multipurpose additional steel bars of a steel bar truss concrete composite slab is characterized by comprising the following steps: comprises the following steps which are sequentially carried out,
step one, laying a bottom plate of the concrete composite slab
Adopting a traditional method, supporting a template of a concrete laminated slab support member, binding a steel bar of the template, and laying a concrete laminated slab bottom plate;
step two, manufacturing the multipurpose additional reinforcing steel bar
The multipurpose additional reinforcing steel bars comprise single-side connecting reinforcing steel bars and double-side connecting reinforcing steel bars;
manufacturing a single-side connecting steel bar, wherein the anchoring length of the single-side connecting steel bar anchored into the support member is taken according to the specified requirement of concrete structure design specification GB50010, the overlapping connection length of the single-side connecting steel bar and the upper chord steel bar of the steel bar truss is taken according to the specified requirement of concrete structure design specification GB50010, the single-side connecting steel bar is bent downwards to the upper surface position of the bottom plate of the concrete laminated slab at the outer end part of the overlapping connection section, and the anchoring length of the single-side connecting steel bar is reserved along the horizontal direction and then cut off;
manufacturing two-side connecting steel bars, wherein the lapping connection length of two sides of the two-side connecting steel bars and upper chord steel bars of a steel bar truss is selected according to the specified requirements of concrete structure design Specification GB50010, the two sides of the two-side connecting steel bars are bent downwards to the upper surface position of a bottom plate of the concrete laminated slab at the outer end part of a lapping connection section, and the two sides of the two-side connecting steel bars are cut off after the anchoring length of the two-side connecting steel bars is reserved along the horizontal direction;
step three, binding the unilateral connecting steel bar
The concrete composite slabs are arranged at the positions of end support members of the concrete composite slabs or on the two sides of the support members of the concrete composite slabs, but the positions of upper chord steel bars of steel bar trusses in bottom plates of the concrete composite slabs on the two sides of the support are not coaxially corresponding, single-side connecting steel bars are adopted to be bound on one side of the support ends of the upper chord steel bars of the steel bar trusses, and the single-side connecting steel bars and the upper chord steel bars of the steel bar trusses are bound, overlapped and connected;
step four, binding the connecting steel bars on two sides
The two sides of the concrete laminated slab support members are provided with the concrete laminated slabs, the positions of upper chord steel bars of the steel bar trusses in the bottom plates of the concrete laminated slabs on the two sides of the support are coaxially corresponding, and the steel bars are connected on the two sides by adopting double-side connection steel bars and are bound, overlapped and connected with the steel bar trusses on the two sides;
step five, pouring and curing concrete
Pouring the superposed layer concrete of the concrete superposed slab, and maintaining the concrete to reach the design strength;
thus, the method for arranging the multipurpose additional steel bars of the steel bar truss concrete composite slab is completed.
Through the design scheme, the invention can bring the following beneficial effects: a method for arranging multipurpose additional steel bars of a concrete laminated slab of a steel bar truss is characterized in that the multipurpose additional steel bars are arranged, upper chord steel bars of the steel bar truss are used as negative bending moment steel bars of a support of the concrete laminated slab, and the upper chord steel bars of the steel bar truss are effectively utilized; meanwhile, the multipurpose additional steel bars for connecting the upper chord steel bars of the steel bar truss are bent downwards outside the lap joint area, so that the multipurpose additional steel bars are anchored at the top surface of the bottom plate of the concrete composite slab to replace a part of plate ends provided with additional steel bar sections extending into the support; therefore, the upper chord steel bar of the concrete composite slab steel bar truss plays a role in each stage of production, hoisting, installation construction and use, and the aims of saving the steel bar and reducing the construction cost are fulfilled.
Drawings
The invention is further described with reference to the following figures and detailed description:
fig. 1 is a schematic cross-sectional view of the bottom plate laying of a concrete slab composite in an end-support position of a concrete slab according to the present invention.
Fig. 2 is a schematic view of a single-sided connecting bar according to the present invention.
FIG. 3 is a schematic cross-sectional view of the single-sided connecting reinforcement of the present invention after it has been tied.
Fig. 4 is a schematic cross-sectional view illustrating a concrete composite slab with a single-sided connection reinforcing bar position according to the present invention.
FIG. 5 is a schematic cross-sectional view of the bottom plate of the concrete composite slab with the steel bar positions connected at two sides according to the present invention.
Fig. 6 is a schematic view of the double-sided connecting steel bar of the present invention.
FIG. 7 is a schematic cross-sectional view of the double-sided connecting reinforcement of the present invention after it is tied.
Fig. 8 is a schematic cross-sectional view illustrating a concrete composite slab with reinforcing bars connected at two sides according to the present invention.
In the figure, 1-a concrete composite slab bottom plate, 2-steel bar truss upper chord steel bars, 3-templates, 4-single-side connecting steel bars, 5-support members and 6-double-side connecting steel bars are arranged.
Detailed Description
A method for arranging multi-purpose additional steel bars of a steel bar truss concrete composite slab, as shown in figures 1 to 8, comprises the following steps which are sequentially carried out,
step one, laying a bottom plate of the concrete composite slab
As shown in fig. 1 and 5, a formwork 3 for supporting a concrete composite slab support member 5 and reinforcing steel bars thereof are bound, and a concrete composite slab base plate 1 is laid by a conventional method;
step two, manufacturing the multipurpose additional reinforcing steel bar
The multipurpose additional reinforcing steel bars comprise single-side connecting reinforcing steel bars 4 and double-side connecting reinforcing steel bars 6;
as shown in fig. 2 to 4, the unilateral connecting steel bar 4 is manufactured, the anchoring length C of the unilateral connecting steel bar 4 anchored into the support member 5 is determined according to the specified requirements of the concrete structure design specification GB50010, the lap joint length a of the unilateral connecting steel bar 4 and the steel bar truss upper chord steel bar 2 is determined according to the specified requirements of the concrete structure design specification GB50010, the unilateral connecting steel bar 4 is bent downwards to the upper surface position of the concrete laminated slab bottom plate 1 at the outer end of the lap joint section, and is cut off after the anchoring length B of the unilateral connecting steel bar 4 is left in the horizontal direction;
as shown in fig. 6 to 8, the double-side connecting steel bars 6 are manufactured, the overlapping connection length a between the two ends of the double-side connecting steel bars 6 and the upper chord steel bars 2 of the steel bar truss is determined according to the specified requirement of the specification of concrete structure design GB50010, and the length of the integral overlapping section is the sum of 2 times of the overlapping length a between the two sides of the double-side connecting steel bars 6 and the upper chord steel bars 2 of the steel bar truss and the width D of the support member 5; the two sides of the double-side connecting steel bars 6 are downwards bent to the upper surface position of the concrete laminated slab bottom plate 1 at the outer end part of the lap joint connecting section, and are cut off after the anchoring length B of the double-side connecting steel bars 6 is reserved along the horizontal direction;
step three, binding the unilateral connecting steel bar 4
As shown in fig. 3, concrete composite slabs are arranged at the positions of end support members 5 of the concrete composite slabs or at the two sides of the support members 5 of the concrete composite slabs, but the positions of upper chord steel bars 2 of the steel bar trusses in the bottom plates 1 of the concrete composite slabs at the two sides of the support are not coaxially corresponding, a single-side connecting steel bar 4 is adopted to be bound at one side of the support end of the upper chord steel bar 2 of the steel bar truss, and the single-side connecting steel bar 4 and the upper chord steel bar 2 of the steel bar truss are bound and overlapped;
step four, binding the connecting steel bars 6 on two sides
As shown in fig. 7, concrete composite slabs are arranged on both sides of a concrete composite slab support member 5, and the positions of the steel bar truss upper chord steel bars 2 in the concrete composite slab bottom plates 1 on both sides of the support are coaxially corresponding, and then the steel bar truss upper chord steel bars 2 on both sides and the steel bar truss upper chord steel bars 4 on both sides are bound, overlapped and connected by adopting the connecting steel bars 6 on both sides;
step five, pouring and curing concrete
As shown in fig. 4 and 8, the concrete of the superimposed layer of the concrete superimposed sheet is poured, and the cured concrete reaches the designed strength;
thus, the method for arranging the multipurpose additional steel bars of the steel bar truss concrete composite slab is completed.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (1)

1. A method for arranging multipurpose additional steel bars of a steel bar truss concrete composite slab is characterized by comprising the following steps: comprises the following steps which are sequentially carried out,
step one, laying a bottom plate of the concrete composite slab
Adopting a traditional method, supporting a template (3) of a concrete laminated slab support member (5) and binding a steel bar thereof, and laying a concrete laminated slab bottom plate (1);
step two, manufacturing the multipurpose additional reinforcing steel bar
The multipurpose additional reinforcing steel bars comprise single-side connecting reinforcing steel bars (4) and double-side connecting reinforcing steel bars (6);
manufacturing a single-side connecting steel bar (4), wherein the anchoring length of the single-side connecting steel bar (4) anchored into a support member (5) is taken according to the specified requirement of concrete structure design Specification GB50010, the lap joint length of the single-side connecting steel bar (4) and a steel bar truss upper chord steel bar (2) is taken according to the specified requirement of concrete structure design Specification GB50010, the single-side connecting steel bar (4) is bent downwards to the upper surface position of a concrete laminated slab bottom plate (1) at the outer end part of the lap joint section, and the single-side connecting steel bar (4) is cut off after the anchoring length is reserved along the horizontal direction;
manufacturing two-side connecting steel bars (6), wherein the lapping connection length of two sides of the two-side connecting steel bars (6) and the upper chord steel bars (2) of the steel bar truss is selected according to the specified requirement of concrete structure design Specification GB50010, the two sides of the two-side connecting steel bars (6) are bent downwards to the upper surface position of the concrete laminated slab bottom plate (1) at the outer end part of the lapping connection section, and the two sides of the two-side connecting steel bars (6) are cut off after the anchoring length of the two-side connecting steel bars (6) is reserved along;
step three, binding single side connecting steel bar (4)
The concrete composite slabs are arranged at the positions of end support members (5) of the concrete composite slabs or on the two sides of the support members (5) of the concrete composite slabs, but the positions of upper chord steel bars (2) of a steel bar truss in the bottom plates (1) of the concrete composite slabs on the two sides of the support are not coaxially corresponding, and the single-side connecting steel bars (4) are adopted to be bound on one side of the support end of the upper chord steel bars (2) of the steel bar truss, and the single-side connecting steel bars (4) and the upper chord steel bars (2) of the steel bar truss are bound and overlapped;
step four, binding the connecting steel bars at two sides (6)
Concrete laminated slabs are arranged on two sides of a concrete laminated slab support member (5), steel bar truss upper chord steel bars (2) in concrete laminated slab bottom plates (1) on two sides of the support are coaxially corresponding in position, and the steel bar truss upper chord steel bars (2) on two sides and the steel bar truss upper chord steel bars (4) on two sides are connected in a binding and overlapping mode through double-side connecting steel bars (6);
step five, pouring and curing concrete
Pouring the superposed layer concrete of the concrete superposed slab, and maintaining the concrete to reach the design strength;
thus, the method for arranging the multipurpose additional steel bars of the steel bar truss concrete composite slab is completed.
CN202010380142.0A 2020-05-08 2020-05-08 Method for arranging multipurpose additional steel bars of steel bar truss concrete laminated slab Pending CN111535489A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010380142.0A CN111535489A (en) 2020-05-08 2020-05-08 Method for arranging multipurpose additional steel bars of steel bar truss concrete laminated slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010380142.0A CN111535489A (en) 2020-05-08 2020-05-08 Method for arranging multipurpose additional steel bars of steel bar truss concrete laminated slab

Publications (1)

Publication Number Publication Date
CN111535489A true CN111535489A (en) 2020-08-14

Family

ID=71973613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010380142.0A Pending CN111535489A (en) 2020-05-08 2020-05-08 Method for arranging multipurpose additional steel bars of steel bar truss concrete laminated slab

Country Status (1)

Country Link
CN (1) CN111535489A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022048326A1 (en) * 2020-09-07 2022-03-10 孖垚建筑科技(上海)有限公司 Floor slab member and manufacturing method therefor

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060124825A1 (en) * 2004-11-29 2006-06-15 Victor Amend Reinforced insulated forms for constructing concrete walls and floors
CN201202181Y (en) * 2008-05-14 2009-03-04 万科企业股份有限公司 Connection structure for precast concrete board and beam and construction including the same
CN206428968U (en) * 2016-12-30 2017-08-22 青建集团股份公司 A kind of steel bar girder formula is without supporting template system
CN107386512A (en) * 2017-07-05 2017-11-24 中建八局第建设有限公司 A kind of new fabrication and installation method of Prefabricated superposed beam plate
CN208472974U (en) * 2018-06-04 2019-02-05 浙江中益建材科技有限公司 A kind of steel bar girder plate end connects steel structure girder node structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060124825A1 (en) * 2004-11-29 2006-06-15 Victor Amend Reinforced insulated forms for constructing concrete walls and floors
CN201202181Y (en) * 2008-05-14 2009-03-04 万科企业股份有限公司 Connection structure for precast concrete board and beam and construction including the same
CN206428968U (en) * 2016-12-30 2017-08-22 青建集团股份公司 A kind of steel bar girder formula is without supporting template system
CN107386512A (en) * 2017-07-05 2017-11-24 中建八局第建设有限公司 A kind of new fabrication and installation method of Prefabricated superposed beam plate
CN208472974U (en) * 2018-06-04 2019-02-05 浙江中益建材科技有限公司 A kind of steel bar girder plate end connects steel structure girder node structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022048326A1 (en) * 2020-09-07 2022-03-10 孖垚建筑科技(上海)有限公司 Floor slab member and manufacturing method therefor

Similar Documents

Publication Publication Date Title
CN111155691A (en) Close-joint seam type concrete/ECC combined composite slab and construction method thereof
CN108265822A (en) A kind of prefabricated board connecting structure
CN110644662A (en) Prefabricated flat slab composite slab based on stress and splitting method thereof
CN111535489A (en) Method for arranging multipurpose additional steel bars of steel bar truss concrete laminated slab
CN211143474U (en) Concrete precast slab and connecting structure
CN102021954B (en) Laminated plate
CN110005110A (en) A kind of prestressing force laminated floor slab construction method for exempting from support
CN215211802U (en) Novel prefabricated floor slab and connecting structure thereof
CN213926977U (en) Prefabricated bottom plate with hidden beam and folded plate type laminated slab comprising prefabricated bottom plate
CN110820983B (en) Longitudinal connection method for assembled prefabricated superposed wall boards
CN212506971U (en) Laminated slab for building
CN210562896U (en) Close two-way prefabricated superimposed sheet structure of piece together formula
CN111705987A (en) Large-span prefabricated ribbed prestressed hollow bidirectional laminated slab
CN102477782A (en) Superposed slab
CN220565524U (en) Large-width prestressed reinforcement truss composite floor slab
CN220666645U (en) Ribbed steel bar truss concrete close-spliced laminated slab
CN214833903U (en) Novel prefabricated coincide beam slab system of formwork exempts from
CN220451170U (en) Double-sided superimposed shear wall with lap joint connection
CN216130355U (en) Plate seam joint of edge cast-in-situ composite floor slab and connection structure of plate seam joint and frame beam
CN219491436U (en) Assembled floor
CN213926978U (en) Folded plate type prefabricated bottom plate and folded plate type laminated slab comprising same
CN213952664U (en) Reinforced concrete prefabricated slab with bent anchor ends and additional steel bar connection
CN219690843U (en) Concrete prefabricated slab superposed floor structure
CN101200932A (en) Laminated slab
CN211548014U (en) Connection node of coincide air conditioner board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200814