CN111456739A - Tunnel step method construction method based on finite elements - Google Patents

Tunnel step method construction method based on finite elements Download PDF

Info

Publication number
CN111456739A
CN111456739A CN202010159071.1A CN202010159071A CN111456739A CN 111456739 A CN111456739 A CN 111456739A CN 202010159071 A CN202010159071 A CN 202010159071A CN 111456739 A CN111456739 A CN 111456739A
Authority
CN
China
Prior art keywords
excavation
tunnel
support
finite element
steps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010159071.1A
Other languages
Chinese (zh)
Inventor
路希鑫
钱浩
王申杰
刘文峰
孙亚辉
刘子祥
刘志强
刘奇奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN202010159071.1A priority Critical patent/CN111456739A/en
Publication of CN111456739A publication Critical patent/CN111456739A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a finite element-based tunnel step method construction method, and relates to a tunnel excavation method, which comprises the following steps: and establishing a numerical simulation model, performing numerical simulation calculation, and installing on site. According to the method, visual models of all sections of the step excavation are created through finite elements, the stress state of the section and the stress states of other sections during each step of step excavation are analyzed, stability evaluation is carried out, support parameters in the next step are adjusted in real time by combining actual monitoring data, and support parameters which are caused by multiple soil body disturbances in the excavation process are prevented from being inconsistent with the actual conditions. The method can greatly improve the safety of the tunnel bench method excavation process, reduce the engineering cost, shorten the construction period and obtain better social benefit and economic benefit.

Description

Tunnel step method construction method based on finite elements
Technical Field
The invention relates to a tunnel excavation method, in particular to a finite element-based tunnel step method construction method.
Background
Along with the rapid development of highway engineering in China, more and more mountain-penetrating tunnels are used. The tunnel construction method comprises a full-section excavation method, a step method, an annular excavation core soil retaining method, a middle partition wall method, a cross middle partition wall method and the like. The step method has enough working space and equivalent construction speed, the tunnel step method construction is an information dynamic adjustment process, the dynamic optimization of the construction scheme mainly comprises the optimization of excavation footage and support parameters, the optimization aims to improve the construction efficiency as much as possible and reduce the cost on the safe basis, and essentially relates to the mechanical analysis and optimization problem of tunnel construction, but the excavation frequency is increased for multiple steps, so that the disturbance frequency of surrounding rocks is increased, and the safety risk is increased to a certain extent.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a finite element-based tunnel step method construction method.
In order to achieve the purpose, the invention adopts the technical scheme that: a tunnel step method construction method based on finite elements comprises the following steps:
(1) establishing a numerical simulation model
Firstly, establishing visual models of each section of step method segmental excavation based on finite elements, simulating excavation stages of a grotto by setting different excavation steps, performing the steps at different load release rates, and additionally setting an anchor-shotcrete support or a lining structure to simulate the influence of the construction time of the support, thereby achieving the purpose of simulating the grotto excavation and support construction process;
(2) numerical simulation calculation
Determining a transverse calculation range, a vertical calculation range and boundary conditions according to the section size of the tunnel, analyzing the stress state of the section and the stress states of other sections during each step of step excavation, performing stability evaluation, and implementing advanced support according to the stress states and the stability evaluation;
(3) installation in situ
Firstly, arranging monitoring measurement points, transmitting data to a finite element analysis system in real time, dynamically correcting relevant support parameters according to actual monitoring data during each excavation, excavating an arc guide pit at the upper part of a tunnel, performing primary support, excavating upper steps to reserve core soil, excavating steps of the second step, the third step and the like in a staggered mode in sequence from left to right, performing primary support, and finally excavating the bottom of the tunnel in sections and performing primary support; applying an inverted arch and filling.
Preferably, step (1) further comprises: the finite element step establishing method is characterized in that a tunnel unit is subjected to grid division, a grid close to a structure is dense, a grid far from the structure is sparse, a finite element grid is generated after discrete optimization, and the number of units and the number of nodes are determined.
Preferably, step (2) further comprises: and vertical pressure is applied to the top of the boundary condition, horizontal and vertical constraint are applied to the bottom of the boundary condition, and horizontal constraint is applied to the left side and the right side of the boundary condition.
Preferably, step (1) further comprises: in the process of establishing the visual model, the beam units and the anchor rod units are set to be dead units, and when excavation and supporting are carried out, the beam units and the anchor rod units are activated according to actual construction steps.
Preferably, during primary support, temporary support is needed, the temporary support is to be supported at the upper and lower bench excavation parts of the main tunnel, and the temporary support is made of 18-gauge I-steel.
Preferably, the advance support is implemented by using a small advance guide pipe.
The invention has the beneficial effects that: and establishing visual models of all sections of the step excavation by finite element, analyzing the stress state of the section and the stress states of other sections when each step of step excavation, evaluating the stability, and adjusting the support parameters of the next step in real time by combining actual monitoring data, so as to avoid the support parameters which are caused by multiple soil disturbance in the excavation process from being inconsistent with the actual conditions. The method can greatly improve the safety of the tunnel bench method excavation process, reduce the engineering cost, shorten the construction period and obtain better social benefit and economic benefit.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
The embodiment provided by the invention comprises the following steps: a tunnel step method construction method based on finite elements comprises the following steps:
(1) establishing a numerical simulation model
Firstly, establishing visual models of each section of step method segmental excavation based on finite elements, simulating excavation stages of a grotto by setting different excavation steps, performing the steps at different load release rates, and additionally setting an anchor-shotcrete support or a lining structure to simulate the influence of the construction time of the support, thereby achieving the purpose of simulating the grotto excavation and support construction process;
(2) numerical simulation calculation
Determining a transverse calculation range, a vertical calculation range and boundary conditions according to the section size of the tunnel, analyzing the stress state of the section and the stress states of other sections during each step of step excavation, performing stability evaluation, and implementing advanced support according to the stress states and the stability evaluation;
(3) installation in situ
Firstly, arranging monitoring measurement points, transmitting data to a finite element analysis system in real time, dynamically correcting relevant support parameters according to actual monitoring data during each excavation, excavating an arc guide pit at the upper part of a tunnel, performing primary support, excavating upper steps to reserve core soil, excavating steps of the second step, the third step and the like in a staggered mode in sequence from left to right, performing primary support, and finally excavating the bottom of the tunnel in sections and performing primary support; applying an inverted arch and filling.
Wherein: the step (1) further comprises: the finite element step establishing method is that a tunnel unit is subjected to grid division, a grid close to a structure is dense, a grid far from the structure is sparse, a finite element grid is generated after discrete optimization, and the number of units and the number of nodes are determined; the step (2) further comprises: applying vertical pressure to the top of the boundary condition, adding horizontal and vertical constraints to the bottom of the boundary condition, and applying horizontal constraints to the left side and the right side of the boundary condition; the step (1) further comprises: in the process of establishing the visual model, the beam units and the anchor rod units are firstly set as dead units, and when excavation and supporting are carried out, the beam units and the anchor rod units are activated according to actual construction steps; during primary supporting, temporary supports are required, the temporary supports are supported at the upper step excavation part and the lower step excavation part of the main tunnel, and the temporary supports are made of 18-size I-steel; the advance support is implemented by adopting an advanced small conduit.
According to the method, visual models of all sections of the step excavation are created through finite elements, the stress state of the section and the stress states of other sections during each step of step excavation are analyzed, stability evaluation is carried out, support parameters in the next step are adjusted in real time by combining actual monitoring data, and support parameters which are caused by multiple soil body disturbances in the excavation process are prevented from being inconsistent with the actual conditions. The method can greatly improve the safety of the tunnel bench method excavation process, reduce the engineering cost, shorten the construction period and obtain better social benefit and economic benefit.
It is to be understood that the invention is not limited to the specific embodiments described above, but is intended to cover various insubstantial modifications of the inventive process concepts and solutions, or its application to other applications without modification.

Claims (6)

1. A tunnel step method construction method based on finite elements is characterized by comprising the following steps:
(1) establishing a numerical simulation model
Firstly, establishing visual models of each section of step method segmental excavation based on finite elements, simulating excavation stages of a grotto by setting different excavation steps, performing the steps at different load release rates, and additionally setting an anchor-shotcrete support or a lining structure to simulate the influence of the construction time of the support, thereby achieving the purpose of simulating the grotto excavation and support construction process;
(2) numerical simulation calculation
Determining a transverse calculation range, a vertical calculation range and boundary conditions according to the section size of the tunnel, analyzing the stress state of the section and the stress states of other sections during each step of step excavation, performing stability evaluation, and implementing advanced support according to the stress states and the stability evaluation;
(3) installation in situ
Firstly, arranging monitoring measurement points, transmitting data to a finite element analysis system in real time, dynamically correcting relevant support parameters according to actual monitoring data during each excavation, excavating an arc guide pit at the upper part of a tunnel, performing primary support, excavating upper steps to reserve core soil, excavating steps of the second step, the third step and the like in a staggered mode in sequence from left to right, performing primary support, and finally excavating the bottom of the tunnel in sections and performing primary support; applying an inverted arch and filling.
2. The finite element-based tunnel step method construction method according to claim 1, wherein the finite element-based tunnel step method construction method comprises the following steps: the step (1) further comprises: the finite element step establishing method is characterized in that a tunnel unit is subjected to grid division, a grid close to a structure is dense, a grid far from the structure is sparse, a finite element grid is generated after discrete optimization, and the number of units and the number of nodes are determined.
3. The finite element-based tunnel step method construction method according to claim 1, wherein the finite element-based tunnel step method construction method comprises the following steps: the step (2) further comprises: and vertical pressure is applied to the top of the boundary condition, horizontal and vertical constraint are applied to the bottom of the boundary condition, and horizontal constraint is applied to the left side and the right side of the boundary condition.
4. A finite element-based tunnel step method construction method based on claim 1, characterized in that: the step (1) further comprises: in the process of establishing the visual model, the beam units and the anchor rod units are set to be dead units, and when excavation and supporting are carried out, the beam units and the anchor rod units are activated according to actual construction steps.
5. A finite element-based tunnel step method construction method based on claim 1, characterized in that: during preliminary bracing, need carry out interim support, interim support will be strutted at the upper and lower bench excavation position in main hole, and interim support adopts 18I-steel preparation to form.
6. The finite element-based tunnel step method construction method according to claim 1, wherein the finite element-based tunnel step method construction method comprises the following steps: the advance support is implemented by adopting an advanced small conduit.
CN202010159071.1A 2020-03-09 2020-03-09 Tunnel step method construction method based on finite elements Pending CN111456739A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010159071.1A CN111456739A (en) 2020-03-09 2020-03-09 Tunnel step method construction method based on finite elements

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010159071.1A CN111456739A (en) 2020-03-09 2020-03-09 Tunnel step method construction method based on finite elements

Publications (1)

Publication Number Publication Date
CN111456739A true CN111456739A (en) 2020-07-28

Family

ID=71677800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010159071.1A Pending CN111456739A (en) 2020-03-09 2020-03-09 Tunnel step method construction method based on finite elements

Country Status (1)

Country Link
CN (1) CN111456739A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112765864A (en) * 2021-02-04 2021-05-07 中交四公局第五工程有限公司 Method for analyzing stress deformation in process of simulating excavation of weak surrounding rock of tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195443A (en) * 2013-04-02 2013-07-10 山东科技大学 Deep mining method capable of optimizing support parameters and preventing roadway delaying water gushing
CN104598296A (en) * 2015-01-23 2015-05-06 陈建永 Numerical simulation analysis method for deformation of soft soil deep foundation pit
CN110195598A (en) * 2019-06-14 2019-09-03 浙江交工路桥建设有限公司 A kind of highway tunnel construction integrated control method
CN110259458A (en) * 2019-07-01 2019-09-20 中铁七局集团有限公司 The construction method that small-clear-distance tunnel Shallow Section double -side approach excavates
CN110688696A (en) * 2019-09-16 2020-01-14 中铁第五勘察设计院集团有限公司 Parameter determination method and device for tunnel supporting structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195443A (en) * 2013-04-02 2013-07-10 山东科技大学 Deep mining method capable of optimizing support parameters and preventing roadway delaying water gushing
CN104598296A (en) * 2015-01-23 2015-05-06 陈建永 Numerical simulation analysis method for deformation of soft soil deep foundation pit
CN110195598A (en) * 2019-06-14 2019-09-03 浙江交工路桥建设有限公司 A kind of highway tunnel construction integrated control method
CN110259458A (en) * 2019-07-01 2019-09-20 中铁七局集团有限公司 The construction method that small-clear-distance tunnel Shallow Section double -side approach excavates
CN110688696A (en) * 2019-09-16 2020-01-14 中铁第五勘察设计院集团有限公司 Parameter determination method and device for tunnel supporting structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112765864A (en) * 2021-02-04 2021-05-07 中交四公局第五工程有限公司 Method for analyzing stress deformation in process of simulating excavation of weak surrounding rock of tunnel

Similar Documents

Publication Publication Date Title
CN107917839B (en) Test system and method for testing and evaluating composite bearing performance of tunnel anchoring surrounding rock
CN110608054B (en) Deformation prediction method and device for tunnel support structure excavated by full-section method
CN108286442B (en) Excavation method suitable for -time rapid sealing and ring forming of two steps of weak surrounding rock tunnel
CN105675840A (en) Dynamic pressure roadway support physical model test apparatus and dynamic pressure roadway support physical model test method
CN102953394B (en) Precise foundation bolt positioning device
CN112035937B (en) Tunnel construction surrounding rock deformation analysis and informatization construction method
CN205538273U (en) A indoor test device for simulating deep tunnel excavation
CN113356219A (en) Synchronous excavation construction method for foundation pits at different depths on two sides of operation subway
CN111456739A (en) Tunnel step method construction method based on finite elements
CN111814234A (en) Construction treatment method for broken rock mass flood discharge tunnel
CN102979109A (en) Design method of assembled-type prestressed concrete cylindrical column base
CN215180018U (en) Test device for simulating excavation of urban tunnel with super-large section and variable cross section
CN108982246B (en) Shear strength detection device for porous brick wall masonry and use method thereof
CN113311107B (en) Test device and method for simulating ultra-large section variable cross section urban tunnel excavation
CN111709065B (en) Method for determining hole distance of ultra-front deep hole grouting drilling under complex surrounding environment
CN113378423B (en) Intelligent inverse analysis quick inversion method and system for urban rail protection MJS construction method piles
CN112257154B (en) Transparent construction monitoring method and system for urban tunnel
Ramoni et al. The effect of advance rate on shield loading in squeezing ground
CN211905013U (en) Test device for simulating influence of seepage on front stratum during shield starting
CN113958325A (en) Mechanized safe and rapid construction supporting method for weak surrounding rock of large-section tunnel
CN114282420A (en) Method for obtaining reinforcing parameters of glass fiber ribs on tunnel face of soft soil tunnel
CN108333332B (en) Large scale tunnel model test excavating device
CN113006084A (en) Construction method and dynamic design method of support-free foundation pit supporting system
CN102704438B (en) Test method for operation safety of tunnel under effect of external water pressure
CN102213098A (en) Test device for simulating local special loads of tunnel and underground engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200728

WD01 Invention patent application deemed withdrawn after publication