CN111422763A - Suspension arm assembling method under condition that obstacles exist in rod assembling area - Google Patents

Suspension arm assembling method under condition that obstacles exist in rod assembling area Download PDF

Info

Publication number
CN111422763A
CN111422763A CN201911283794.6A CN201911283794A CN111422763A CN 111422763 A CN111422763 A CN 111422763A CN 201911283794 A CN201911283794 A CN 201911283794A CN 111422763 A CN111422763 A CN 111422763A
Authority
CN
China
Prior art keywords
subsection
suspension arm
assembling
boom
chord
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911283794.6A
Other languages
Chinese (zh)
Other versions
CN111422763B (en
Inventor
戚昌卫
雷克祥
何峻
熊伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Jian'an Petrochemical Engineering Co ltd
Original Assignee
Wuhan Jian'an Petrochemical Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Jian'an Petrochemical Engineering Co ltd filed Critical Wuhan Jian'an Petrochemical Engineering Co ltd
Priority to CN201911283794.6A priority Critical patent/CN111422763B/en
Publication of CN111422763A publication Critical patent/CN111422763A/en
Application granted granted Critical
Publication of CN111422763B publication Critical patent/CN111422763B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/64Jibs
    • B66C23/70Jibs constructed of sections adapted to be assembled to form jibs or various lengths

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The invention discloses a boom assembling method under the condition that obstacles exist in a boom assembling area, which comprises the following steps: firstly, assembling a bottom part section and a top part section of the suspension arm; the bottom of the bottom subsection is hinged with the vehicle body, and the other end of the bottom subsection is lifted to exceed the height of the barrier; thirdly, hoisting one end of the top section, which is positioned in the middle of the hoisting arm, to be higher than the height of the barrier; gradually approaching the bottom subsection and the top subsection to enable the bottom chord of the bottom subsection to be folded with the bottom chord of the top subsection, and inserting a pin shaft to enable the bottom subsection and the top subsection to be in a semi-connection state capable of rotating around the hinge point of the bottom chord; and fifthly, hoisting the top of the top subsection, enabling the top subsection to rotate upwards around the hinge point of the lower chord until the upper chord of the bottom subsection and the upper chord of the top subsection are folded, and inserting a pin shaft at the folded position to finish the assembly of the suspension arm. The invention has the characteristics of simple and convenient operation and high safety, and can be widely applied to the field of construction.

Description

Suspension arm assembling method under condition that obstacles exist in rod assembling area
Technical Field
The invention relates to the field of construction, in particular to a suspension arm assembling method under the condition that obstacles exist in a combined rod area.
Background
When a large-scale track crane lattice-shaped suspension arm is assembled on a construction site, the common method is as follows: in a flat open area in front of the crane body, a plurality of suspension arms are sequentially assembled into a straight line on the ground and are pulled up after being connected with the crane body, so that the crane achieves the use working condition. However, in practical situations, obstacles which protrude beyond the ground by a certain height are often encountered in the rod assembling area in front of the vehicle body, so that the suspension arms cannot form a straight line on the ground, and therefore, a plurality of suspension arms cannot be assembled into a whole in a short time, and the purpose of efficiently connecting and wrenching the whole suspension arm with the vehicle body and smoothly obtaining the use working condition cannot be achieved.
Disclosure of Invention
The invention aims to overcome the defects of the background technology and provide a suspension arm assembling method under the condition that obstacles exist in a rod assembling area, so that the suspension arm assembling method has the characteristics of simple and convenient operation and high safety.
The invention provides a boom assembling method under the condition that obstacles exist in a boom assembling area, which comprises the following steps: step one, respectively completing the assembly of the bottom section and the top section of the suspension arm; step two, the bottom of the bottom section is hinged with the vehicle body, the other end of the bottom section is hoisted by a first auxiliary crane, and the hoisting height exceeds the height h of the barrier; step three, hoisting one end of the top section, which is positioned in the middle of the hoisting arm, by using a second auxiliary crane, wherein the hoisting height is higher than the height h of the barrier; step four, gradually approaching one ends of the bottom subsection and the top subsection close to the barrier respectively by means of a first auxiliary crane and a second auxiliary crane, finally enabling a bottom subsection lower chord of the bottom subsection to be folded with a top subsection lower chord of the top subsection, and inserting a pin shaft at the folding position to enable the bottom subsection and the top subsection to be in a half-connection state capable of rotating around a hinge point of the lower chord; and step five, hoisting the top of the top subsection by using a third auxiliary crane, enabling the top subsection to rotate upwards around the hinge point of the lower chord until the upper chord of the bottom subsection and the upper chord of the top subsection are folded, and inserting a pin shaft at the folded position, so that the assembly of the suspension arm is completed.
In a preferred embodiment, in the first step, a bottom subsection and a top subsection are respectively assembled on both sides of the obstacle, the bottom section of the suspension arm and the plurality of middle sections of the suspension arm are assembled into the bottom subsection in the area of the maximum ground accommodating length between the vehicle body and the obstacle, and the plurality of middle sections of the suspension arm and the top section of the suspension arm are assembled in the area of the ground on the other side of the obstacle, so that the top subsection is completed.
In a preferred embodiment, the top section of the top segment is placed on the ground engaging traction device in step three.
In a preferred embodiment, the method further comprises a sixth step of utilizing a self-contained lifting device of the vehicle body to lift the whole suspension arm to a working state with a certain elevation angle α so as to achieve the working condition.
The suspension arm assembling method under the condition that the obstacle exists in the rod assembling area has the following beneficial effects: in the traditional method, the boom completes the connection of the upper and lower hinge points of the chord rod at the height of the obstacle at one time, the top subsection arm tip is positioned in the air at the height H away from the ground, the height H is far higher than the height H of the obstacle, arm assembling personnel have to complete the rope winding and threading work of the winding running of the arm tip pulley block in the air at the height, and the method is difficult to operate, high in danger and not beneficial to popularization in the field of facility building workers; in contrast, when the boom is assembled according to the boom assembling method, the lower hinge point and the upper hinge point of the boom segment are successively connected twice, and the boom tip of the top segment is kept on the ground before the boom tip is connected with the upper hinge point of the chord member, so that arm assembling personnel can complete the assembling work of the boom and the threading and winding work of the winding running rope of the boom tip pulley block on the ground only near the height h of the obstacle, the working difficulty is reduced, the assembling work is smoothly completed, and the safety of the personnel is ensured.
Drawings
FIG. 1 is a schematic flow chart of a boom assembling method under the condition that an obstacle exists in a boom assembling area according to the present invention;
FIG. 2 is a schematic view of a construction process of a first step in the boom assembling method under the condition that an obstacle exists in a boom assembling area according to the present invention;
FIG. 3 is a schematic view of a construction process from step two to step four in the boom assembling method under the condition that an obstacle exists in the boom assembling area according to the present invention;
FIG. 4 is a schematic view of the construction process of step five in the boom assembling method under the condition that the obstacle exists in the boom assembling area according to the present invention
Fig. 5 is a schematic view of the construction process of the sixth step in the boom assembling method under the condition that the obstacle exists in the boom assembling area.
Detailed Description
The invention is described in further detail below with reference to the following figures and examples, which should not be construed as limiting the invention.
Referring to fig. 1, the boom assembling method under the condition that the obstacle exists in the boom assembling area of the invention comprises the following steps:
with reference to fig. 2, the assembly of the bottom section 1.1 and the top section 1.2 of the boom 1 is completed separately, step one, by:
respectively assembling a bottom subsection 1.1 and a top subsection 1.2 at two sides of an obstacle 6, assembling a bottom section of a suspension arm 1 and a plurality of intermediate sections of the suspension arm 1 into the bottom subsection 1.1 in a ground accommodating maximum length area between a vehicle body 2 and the obstacle 6, and assembling the intermediate sections of the suspension arm 1 and a top section of the suspension arm 1 in a ground area at the other side of the obstacle 6, thereby completing the top subsection 1.2;
referring to fig. 3, step two, the bottom 1.1.1 of the bottom section 1.1 is hinged with the car body 2, and the other end of the bottom section 1.1 is hoisted by the first auxiliary crane 3, and the hoisting height exceeds the height h of the barrier 6;
step three, hoisting one end of the top subsection 1.2 positioned in the middle of the suspension arm 1 by using a second auxiliary crane 4, wherein the hoisting height is higher than the height h of the barrier 6, and placing the top section of the top subsection 1.2 on a grounding travelling wheel device (not shown in the figure) so as to facilitate the top subsection 1.2 to move along the ground along with the engineering progress;
step four, respectively approaching one ends of the bottom subsection 1.1 and the top subsection 1.2 close to the barrier 6 by means of a first auxiliary crane 3 and a second auxiliary crane 4, finally folding the bottom subsection lower chord of the bottom subsection 1.1 and the top subsection lower chord of the top subsection 1.2, and inserting a pin shaft at the folding position to enable the bottom subsection 1.1 and the top subsection 1.2 to be in a half-connection state capable of rotating around a lower chord hinge point 1.3;
step five, the top of the top subsection 1.2 is hoisted by a third auxiliary crane 5, the top subsection 1.2 is rotated upwards around the hinge point 1.3 of the lower chord until the bottom subsection upper chord 1.1.2 of the bottom subsection 1.1 and the top subsection upper chord 1.2.1 of the top subsection 1.2 are folded, and a pin shaft is inserted into the folded position, so that the assembly of the boom 1 is completed;
referring to fig. 5, in step six, the whole boom 1 is lifted to a working state with a certain elevation α by using a lifting device of the vehicle body 2, so as to achieve a working condition.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.
Those not described in detail in this specification are within the skill of the art.

Claims (4)

1. A boom assembling method under the condition that obstacles exist in a boom assembling area is characterized in that: the method comprises the following steps:
step one, respectively finishing the assembly of a bottom subsection (1.1) and a top subsection (1.2) of the suspension arm (1);
step two, the bottom (1.1.1) of the bottom section (1.1) is hinged with the trolley body (2), the other end of the bottom section (1.1) is hoisted by a first auxiliary crane (3), and the hoisting height exceeds the height h of the barrier (6);
thirdly, hoisting one end of the top section (1.2) positioned in the middle of the boom (1) by using a second auxiliary crane (4), wherein the hoisting height is higher than the height h of the barrier (6);
step four, respectively approaching one ends of the bottom subsection (1.1) and the top subsection (1.2) close to the barrier (6) gradually by means of a first auxiliary crane (3) and a second auxiliary crane (4), finally enabling a bottom subsection lower chord of the bottom subsection (1.1) to be folded with a top subsection lower chord of the top subsection (1.2), and inserting a pin shaft at the folding position to enable the bottom subsection (1.1) and the top subsection (1.2) to be in a half-connection state capable of rotating around a lower chord hinge point (1.3);
and fifthly, hoisting the top of the top subsection (1.2) by using a third auxiliary crane (5), enabling the top subsection (1.2) to rotate upwards around a hinge point (1.3) of the lower chord until the bottom subsection upper chord (1.1.2) of the bottom subsection (1.1) and the top subsection upper chord (1.2.1) of the top subsection (1.2) are folded, and inserting a pin shaft at the folded position, so that the assembly of the suspension arm (1) is completed.
2. A method of assembling a boom in the presence of obstacles in a gang bar area as claimed in claim 1, wherein: in the first step, a bottom subsection (1.1) and a top subsection (1.2) are respectively assembled on two sides of an obstacle (6), a bottom section of a suspension arm (1) and a plurality of middle sections of the suspension arm (1) are assembled into the bottom subsection (1.1) in a ground accommodating maximum length area between a vehicle body (2) and the obstacle (6), and the plurality of middle sections of the suspension arm (1) and a top section of the suspension arm (1) are assembled in a ground area on the other side of the obstacle (6), so that the top subsection (1.2) is completed.
3. A method of assembling a boom in the presence of obstacles in a gang bar area as claimed in claim 2, wherein: and in the third step, the top section of the top subsection (1.2) is placed on the ground walking wheel device.
4. The assembling method of the suspension arm under the condition that the obstacle exists in the pole assembling area according to the claim 3, characterized by further comprising a sixth step of utilizing the self-provided lifting device of the vehicle body (2) to lift the whole suspension arm (1) to a working state with a certain elevation angle α to achieve the working condition.
CN201911283794.6A 2019-12-13 2019-12-13 Suspension arm assembling method under condition that obstacles exist in rod assembling area Active CN111422763B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911283794.6A CN111422763B (en) 2019-12-13 2019-12-13 Suspension arm assembling method under condition that obstacles exist in rod assembling area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911283794.6A CN111422763B (en) 2019-12-13 2019-12-13 Suspension arm assembling method under condition that obstacles exist in rod assembling area

Publications (2)

Publication Number Publication Date
CN111422763A true CN111422763A (en) 2020-07-17
CN111422763B CN111422763B (en) 2021-11-26

Family

ID=71546884

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911283794.6A Active CN111422763B (en) 2019-12-13 2019-12-13 Suspension arm assembling method under condition that obstacles exist in rod assembling area

Country Status (1)

Country Link
CN (1) CN111422763B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2004100868A (en) * 2004-01-15 2005-06-20 Евгений Ефимович Лунден (RU) METHOD FOR INSTALLATION OF A SECTIONAL ARROW OF A TOWED CRANE AND A DEVICE FOR IMPLEMENTING THE METHOD
CN1767998A (en) * 2003-04-02 2006-05-03 德雷克斯-德马格股份有限公司 Two-piece main boom for a latice-boom crane and method for erection thereof
CN101955132A (en) * 2009-05-01 2011-01-26 马尼托瓦克起重机有限责任公司 Hoisting crane with crane arm lifting supplementary structure
CN102040169A (en) * 2009-10-14 2011-05-04 唐纳德·C·米勒 Collapsible tower
CN102390783A (en) * 2010-06-10 2012-03-28 利勃海尔爱茵根有限公司 Method of moving large cranes in the setup system and system of carrying out this method
CN102408071A (en) * 2010-09-20 2012-04-11 马尼托瓦克起重机有限责任公司 Pinned connection system for crane column segments
CN202643173U (en) * 2012-06-18 2013-01-02 山东永力重工科技发展有限公司 Movable arm type crane with detachable hoisting arm
CN106379821A (en) * 2016-11-01 2017-02-08 山东电力建设第工程公司 Construction method for assemble cargo boom of crawling crane through breaking-off method
EP3498655A1 (en) * 2017-12-18 2019-06-19 Kobelco Construction Machinery Co., Ltd. Crane assembling method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1767998A (en) * 2003-04-02 2006-05-03 德雷克斯-德马格股份有限公司 Two-piece main boom for a latice-boom crane and method for erection thereof
RU2004100868A (en) * 2004-01-15 2005-06-20 Евгений Ефимович Лунден (RU) METHOD FOR INSTALLATION OF A SECTIONAL ARROW OF A TOWED CRANE AND A DEVICE FOR IMPLEMENTING THE METHOD
CN101955132A (en) * 2009-05-01 2011-01-26 马尼托瓦克起重机有限责任公司 Hoisting crane with crane arm lifting supplementary structure
CN102040169A (en) * 2009-10-14 2011-05-04 唐纳德·C·米勒 Collapsible tower
CN102390783A (en) * 2010-06-10 2012-03-28 利勃海尔爱茵根有限公司 Method of moving large cranes in the setup system and system of carrying out this method
CN102408071A (en) * 2010-09-20 2012-04-11 马尼托瓦克起重机有限责任公司 Pinned connection system for crane column segments
CN202643173U (en) * 2012-06-18 2013-01-02 山东永力重工科技发展有限公司 Movable arm type crane with detachable hoisting arm
CN106379821A (en) * 2016-11-01 2017-02-08 山东电力建设第工程公司 Construction method for assemble cargo boom of crawling crane through breaking-off method
EP3498655A1 (en) * 2017-12-18 2019-06-19 Kobelco Construction Machinery Co., Ltd. Crane assembling method

Also Published As

Publication number Publication date
CN111422763B (en) 2021-11-26

Similar Documents

Publication Publication Date Title
CN107013080B (en) A kind of power grid electric pole erection construction method
CN203813323U (en) Folding bracing frame for power transmission line crossing rack
WO2014015757A1 (en) Bridge maintenance vehicle with hinge-connected type hanging bracket and capable of avoiding bridge-side obstacles
CN107097866A (en) Power line operation walking robot and its obstacle-detouring method
CN105226560B (en) A kind of crossing frame and its construction method
CN110697590A (en) Wire lifting device for electrified pole erection removal and ground potential pole erection removal method
CN102910532B (en) Method for butting and hoisting large box type derricks in air
CN204714403U (en) A kind of extension mast and configure the engineering machinery vehicle of this mast
CN113928203A (en) Trade trolley
CN111422763B (en) Suspension arm assembling method under condition that obstacles exist in rod assembling area
CN203096920U (en) Hardwired sludge grabbing vehicle
CN206299332U (en) A kind of electric power cable maintenance ladder
CN216945934U (en) Double-rocker floor holding pole
CN215208137U (en) Trolley with cantilever
CN103437699B (en) Ladder component applied to a pump truck
CN206051351U (en) Hang a kind of purlin for assembling and disassembling construction for bridge-collision-avoidance wall form
CN205442494U (en) Channel prefabricated plate handling instrument
CN205346676U (en) High -speed railway of not stopping transport across device's span beam becomes width of cloth rotary mechanism
CN211908208U (en) Multifunctional high-voltage cable hoisting and laying guide arm
CN210915049U (en) Self-moving quick erecting tower crane
CN203813325U (en) Extension ladder and transmission line crossing rack having same
CN210111479U (en) Automatic crossing frame
CN208280209U (en) It digs pit, upright bar, lifting all-in-one machine
CN207108289U (en) Possesses the gantry crane of monitoring function
CN220787831U (en) Curb installation handling equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant