CN111411650A - Building jacking deviation rectifying method - Google Patents
Building jacking deviation rectifying method Download PDFInfo
- Publication number
- CN111411650A CN111411650A CN202010299656.3A CN202010299656A CN111411650A CN 111411650 A CN111411650 A CN 111411650A CN 202010299656 A CN202010299656 A CN 202010299656A CN 111411650 A CN111411650 A CN 111411650A
- Authority
- CN
- China
- Prior art keywords
- pile
- bearing platform
- original
- platform
- jacking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
- E02D35/005—Lowering or lifting of foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/64—Repairing piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2220/00—Temporary installations or constructions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention provides a building jacking deviation correcting method, which comprises the following steps: s1: arranging a new bearing platform, wherein a pile pressing hole is reserved in the new bearing platform; s2: reliably connecting the newly-added bearing platform with an original bearing platform; s3: constructing a anchor rod static pressure pile in the pile pressing hole; s4: utilizing a jacking system and the anchor rod static pressure pile to jack up the newly added platform and the original bearing platform; s5: cutting off the original pile of the original bearing platform; s6: jacking the newly-added platform and the original bearing platform by using the jacking system; s7: completely filling gaps below the newly added platform and the original bearing platform; s8: and sealing the pile pressing hole. The building jacking deviation rectifying method reduces the damage of jacking to the building, does not need to damage the original structure of the building, and is high in safety.
Description
Technical Field
The invention relates to the technical field of jacking deviation correction, in particular to a building jacking deviation correction method.
Background
The existing jacking deviation rectifying method comprises the following steps:
1. and in the area with larger settlement, underpinning the structural column, cutting off the column, putting a jack into the column for jacking, and removing the jack and recovering the structural column after deviation correction meets the design requirement.
2. And (4) chiseling a hole on the shear wall of the area with the larger sedimentation side, putting a jack into the shear wall for underpinning, chiseling off the residual shear wall, starting jacking, and removing the jack and recovering the shear wall after the jacking is finished.
The two methods damage the structural columns or the shear walls, and the structural columns or the shear walls need to be repaired again in the later period, so that the integrity, the safety and the reliability of the house are adversely affected, and the construction period is long.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides a building jacking deviation correcting method, which reduces the damage of jacking to a building, and has the advantages that the original structure of the building is not required to be damaged, and the safety is higher by additionally arranging bearing platforms beside a column edge and a shear wall, supplementing piles, and jacking a foundation by using a jack through a underpinning device.
In order to achieve the purpose, the invention provides a building jacking deviation rectifying method, which comprises the following steps:
s1: arranging a new bearing platform, wherein a pile pressing hole is reserved in the new bearing platform;
s2: reliably connecting the newly-added bearing platform with an original bearing platform;
s3: constructing a anchor rod static pressure pile in the pile pressing hole;
s4: utilizing a jacking system and the anchor rod static pressure pile to jack up the newly added platform and the original bearing platform;
s5: cutting off the original pile of the original bearing platform;
s6: jacking the newly-added platform and the original bearing platform by using the jacking system;
s7: completely filling gaps below the newly added platform and the original bearing platform;
s8: and sealing the pile pressing hole.
Preferably, in the step S2, the newly added bearing platform is reliably connected to the original bearing platform in a manner of bar planting and chiseling.
Preferably, the step of S3 further comprises the steps of:
s31: constructing a anchor rod static pressure pile in the pile pressing hole;
s32: pile repairing is carried out on the anchor rod static pressure pile to obtain a repaired pile;
s33: and filling the filling pile with a core by using concrete.
Preferably, in the step S4, the jacking system includes a jack and a transmission rod; the dowel bar is arranged at the top of the pile repairing and partially extends out of the pile pressing hole; the jack is arranged at the top of the dowel bar and connected with the newly added bearing platform.
Preferably, in the step S5, a pile cutting working surface is excavated from a side of the original bearing platform far from the new bearing platform, and the original pile of the original bearing platform is cut.
Preferably, in the step S7, the gap below the new platform and the original platform is completely filled with cement slurry.
Due to the adoption of the technical scheme, the invention has the following beneficial effects:
the method for adding the bearing platform and filling the pile can be suitable for various soil layers, and the single pile has high bearing capacity and can provide larger jacking force. A large amount of soil bodies do not need to be excavated downwards, and the construction is simple and convenient. The hole sealing method is simple and has low technical requirements. And the building jacking can be smoothly completed without cutting structural columns, shear walls and other members and influencing the integrity, safety and reliability of the original structure.
Drawings
FIG. 1 is a flow chart of a method for correcting deviation of building jacking according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a system of a building jacking deviation rectifying method according to an embodiment of the invention.
Detailed Description
The following description of the preferred embodiments of the present invention, with reference to the accompanying drawings 1 and 2, will provide a better understanding of the function and features of the invention.
Referring to fig. 1 and fig. 2, a method for correcting a jacking of a building according to an embodiment of the present invention includes the steps of:
s1: a new bearing platform 1 is arranged, and a pile pressing hole 2 is reserved in the new bearing platform 1.
S2: the newly added bearing platform 1 is reliably connected with an original bearing platform 3.
And in the step S2, reliably connecting the newly added bearing platform 1 with the original bearing platform 3 in a rib planting and chiseling mode.
S3: and constructing a anchor rod static pressure pile in the pile pressing hole 2.
The step of S3 further includes the steps of:
s31: constructing an anchor rod static pressure pile in the pile pressing hole 2;
s32: a pile repairing 4 is obtained after pile repairing is carried out on the anchor rod static pressure pile;
s33: the filling pile 4 is cored with concrete.
S4: and (5) utilizing a jacking system 5 and the anchor rod static pressure pile to lift the newly added platform and the original bearing platform 3.
S4, the jacking system 5 includes a jack 51 and a transmission rod 52; the dowel bar 52 is arranged at the top of the pile repairing 4 and partially extends out of the pile pressing hole 2; the jack is arranged on the top of the dowel bar 52 and connected with the newly added bearing platform 1.
S5: and cutting off the original pile 6 of the original bearing platform 3.
In step S5, a pile cutting working surface is excavated from the side of the original bearing platform 3 away from the new bearing platform 1, and the original pile 6 of the original bearing platform 3 is cut off.
S6: and jacking the newly added platform and the original bearing platform 3 by utilizing a jacking system 5.
S7: completely filling the gap between the newly added platform and the original bearing platform 3.
In the step S7, the gap between the new platform and the original platform 3 is completely filled with cement slurry.
S8: and (5) sealing the pile pressing hole 2 to restore the bearing platform.
While the present invention has been described in detail and with reference to the embodiments thereof as illustrated in the accompanying drawings, it will be apparent to one skilled in the art that various changes and modifications can be made therein. Therefore, certain details of the embodiments are not to be interpreted as limiting, and the scope of the invention is to be determined by the appended claims.
Claims (6)
1. A building jacking deviation rectifying method comprises the following steps:
s1: arranging a new bearing platform, wherein a pile pressing hole is reserved in the new bearing platform;
s2: reliably connecting the newly-added bearing platform with an original bearing platform;
s3: constructing a anchor rod static pressure pile in the pile pressing hole;
s4: utilizing a jacking system and the anchor rod static pressure pile to jack up the newly added platform and the original bearing platform;
s5: cutting off the original pile of the original bearing platform;
s6: jacking the newly-added platform and the original bearing platform by using the jacking system;
s7: completely filling gaps below the newly added platform and the original bearing platform;
s8: and sealing the pile pressing hole.
2. The building jacking deviation rectifying method according to claim 1, wherein in the step S2, the newly added bearing platform is reliably connected with the original bearing platform in a rib planting and chiseling manner.
3. The building jacking deviation rectifying method according to claim 1, wherein the step of S3 further comprises the steps of:
s31: constructing a anchor rod static pressure pile in the pile pressing hole;
s32: pile repairing is carried out on the anchor rod static pressure pile to obtain a repaired pile;
s33: and filling the filling pile with a core by using concrete.
4. The method for rectifying deviation of building jacking according to claim 3, wherein in the step S4, the jacking system comprises a jack and a force transmission rod; the dowel bar is arranged at the top of the pile repairing and partially extends out of the pile pressing hole; the jack is arranged at the top of the dowel bar and connected with the newly added bearing platform.
5. The building jacking deviation rectifying method according to claim 4, wherein in the step S5, a pile cutting working surface is excavated from a side of the original platform far from the added platform, and the original pile of the original platform is cut.
6. The building jacking deviation rectifying method according to claim 5, wherein in the step S7, the gap below the new platform and the original bearing platform is completely filled with cement slurry.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010299656.3A CN111411650A (en) | 2020-04-16 | 2020-04-16 | Building jacking deviation rectifying method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010299656.3A CN111411650A (en) | 2020-04-16 | 2020-04-16 | Building jacking deviation rectifying method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111411650A true CN111411650A (en) | 2020-07-14 |
Family
ID=71488416
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010299656.3A Pending CN111411650A (en) | 2020-04-16 | 2020-04-16 | Building jacking deviation rectifying method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111411650A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113756353A (en) * | 2021-09-09 | 2021-12-07 | 四川路桥桥梁工程有限责任公司 | Prepressing device and prepressing method for newly added pile foundations of bridge pile group foundation |
CN113802475A (en) * | 2021-09-10 | 2021-12-17 | 中国一冶集团有限公司 | Bridge active pile lifting prepressing method |
CN113882443A (en) * | 2021-10-25 | 2022-01-04 | 广东睿固建设科技有限公司 | Unidirectional deviation rectifying method for building |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2236508C2 (en) * | 2002-07-22 | 2004-09-20 | Туманов Вячеслав Александрович | Connection unit for two-leg eccentrically loaded column with foundation and method for restoring design level of foundation and building frame |
CN104652842A (en) * | 2015-02-15 | 2015-05-27 | 上海天演建筑物移位工程股份有限公司 | Building integral deviation correcting and raising lifting method and equipment thereof |
CN206189482U (en) * | 2016-11-16 | 2017-05-24 | 贵州正业工程技术投资有限公司 | Rectify based on self -locking underpinned pile basis and consolidate piling bar structure |
CN107090860A (en) * | 2017-05-09 | 2017-08-25 | 广东省建筑科学研究院集团股份有限公司 | A kind of shallow foundation rectifying of leaned building ruggedized construction and its construction method |
CN110499928A (en) * | 2019-07-25 | 2019-11-26 | 广东庆余堂建筑科技有限公司 | The construction method and basement of existing building basement raising chamber height |
-
2020
- 2020-04-16 CN CN202010299656.3A patent/CN111411650A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2236508C2 (en) * | 2002-07-22 | 2004-09-20 | Туманов Вячеслав Александрович | Connection unit for two-leg eccentrically loaded column with foundation and method for restoring design level of foundation and building frame |
CN104652842A (en) * | 2015-02-15 | 2015-05-27 | 上海天演建筑物移位工程股份有限公司 | Building integral deviation correcting and raising lifting method and equipment thereof |
CN206189482U (en) * | 2016-11-16 | 2017-05-24 | 贵州正业工程技术投资有限公司 | Rectify based on self -locking underpinned pile basis and consolidate piling bar structure |
CN107090860A (en) * | 2017-05-09 | 2017-08-25 | 广东省建筑科学研究院集团股份有限公司 | A kind of shallow foundation rectifying of leaned building ruggedized construction and its construction method |
CN110499928A (en) * | 2019-07-25 | 2019-11-26 | 广东庆余堂建筑科技有限公司 | The construction method and basement of existing building basement raising chamber height |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113756353A (en) * | 2021-09-09 | 2021-12-07 | 四川路桥桥梁工程有限责任公司 | Prepressing device and prepressing method for newly added pile foundations of bridge pile group foundation |
CN113802475A (en) * | 2021-09-10 | 2021-12-17 | 中国一冶集团有限公司 | Bridge active pile lifting prepressing method |
CN113882443A (en) * | 2021-10-25 | 2022-01-04 | 广东睿固建设科技有限公司 | Unidirectional deviation rectifying method for building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111411650A (en) | Building jacking deviation rectifying method | |
CN109356210B (en) | Pile foundation building inclination correction pile interception underpinning limiting structure and construction method thereof | |
CN103195114B (en) | High-rise building foundation strengthening construction method on weak geological conditions | |
CA2561144A1 (en) | Method for erecting a tower | |
CN105863287A (en) | Method for jacking storey-addition and shock insulation of framework-structure building | |
CN108547336B (en) | Sedimentation, reinforcement, jacking and leveling method suitable for independent pile foundation of industrial plant | |
CN102758458B (en) | Underground continuous wall repairing method | |
JP2007182741A (en) | Differentially settled foundation correcting and reinforcing method by underpinning | |
CN102877463B (en) | Recyclable foundation pit support pipe pile and application and recovery method thereof | |
CN110468873B (en) | Underpinning structure for abutment pile foundation in small space and using method | |
CN110241817B (en) | Construction method for damaged anti-slide pile hole of emergency rescue project | |
CN109869009B (en) | Inclination correcting method for broken columns of frame structure building | |
CN110725344A (en) | Method for preventing existing tunnel from floating upwards during earthwork unloading | |
CN114215093B (en) | Construction method of bearing platform foundation | |
CN206916543U (en) | Structure is repaired in a kind of non-fragment orbit railway tunnel arch | |
CN114329741A (en) | BIM parameterization-based end-bearing pile length calculation method | |
CN104912084B (en) | Building dense district deep basal pit external sealing type static press piling construction method | |
CN114941453B (en) | Foundation reinforcement construction method based on ancient building repair | |
CN114991194B (en) | Pile foundation construction method for multistage slope cutting | |
CN110029693B (en) | Experimental method for simulating influence of blasting demolition of deep foundation pit support beam on reserved structure | |
CN103711128B (en) | A kind of construction method of shallow foundation structural beam slab | |
CN217128207U (en) | Rotary spraying, reinforcing, lifting and leveling structure for soft soil foundation settlement terrace | |
US20080008538A1 (en) | Foundation system | |
CN114575270B (en) | Bridge jacking and reinforcing method | |
CN110777859B (en) | Horizontal foundation replacement and pile body jacking reinforcement deviation rectifying method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200714 |