CN111396121A - Excavation-free backfill construction method for underground old civil air defense works - Google Patents

Excavation-free backfill construction method for underground old civil air defense works Download PDF

Info

Publication number
CN111396121A
CN111396121A CN202010120071.0A CN202010120071A CN111396121A CN 111396121 A CN111396121 A CN 111396121A CN 202010120071 A CN202010120071 A CN 202010120071A CN 111396121 A CN111396121 A CN 111396121A
Authority
CN
China
Prior art keywords
underground
air defense
civil air
old
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010120071.0A
Other languages
Chinese (zh)
Inventor
冯文锦
张火军
江涌波
张坚
黎强
林先环
林君伟
陈嘉威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Fourth Construction Co ltd
Original Assignee
Guangzhou Fourth Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Fourth Construction Co ltd filed Critical Guangzhou Fourth Construction Co ltd
Priority to CN202010120071.0A priority Critical patent/CN111396121A/en
Publication of CN111396121A publication Critical patent/CN111396121A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/02Supporting means, e.g. shuttering, for filling-up materials
    • E21F15/04Stowing mats; Goaf wire netting; Partition walls
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/005Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/06Filling-up mechanically

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses an excavation-free backfill construction method for underground old civil air defense works, which comprises the following steps: finding out the technical parameters of the position, the length, the width, the height and the burial depth of the old underground civil air defense works through underground exploration; lofting the position of the underground old civil air defense worker to the ground; vertically driving at least two rows of Larsen steel sheet piles into the backfill section at equal intervals for isolation to form one or more isolation sections in the old underground civil air defense works; a plurality of grouting holes which are arranged at equal intervals and communicated with the isolation sections are arranged on the ground corresponding to each isolation section; injecting concrete into the isolation section through each grouting hole at the same time until the concrete is filled up and compacted; and when the backfilled concrete reaches the preset strength, pulling out the Larsen steel sheet pile to finish the construction of the whole backfilling section. By adopting the invention, excavation is not needed, and the problems that collapse and traffic troubles are easily caused when underground old civil air defense works are backfilled and excavated and the stability of surrounding buildings is influenced can be effectively solved.

Description

Excavation-free backfill construction method for underground old civil air defense works
Technical Field
The invention belongs to the field of backfill engineering of underground old civil air defence works, and particularly relates to an excavation-free backfill construction method of the underground old civil air defence works.
Background
From the beginning of the 20 th century, underground civil air defense works played an extremely important role in the civil air defense industry of China. However, nowadays, the aging of underground civil air defense works not only makes the civil air defense function lost, but also restricts the expansion, upgrading and reconstruction of cities. With the rapid promotion of urbanization in China and the requirement of city expansion and upgrading, the backfilling of old underground civil air defense works is not slow at all. Due to the complexity of underground rock soil, the aging strength of the underground old civil air defense works, busy ground traffic and dense surrounding buildings, the collapse problem is easily caused when the underground old civil air defense works are backfilled and excavated, the traffic trouble caused by the collapse problem is caused, and the stability of the surrounding buildings is influenced, so that great difficulty is caused to the backfilling construction of the underground old civil air defense works.
Disclosure of Invention
The invention aims to solve the problems that the excavation-free backfill construction method for the underground old civil air defence works does not need excavation, and can effectively solve the problems that collapse and traffic troubles are easily caused and the stability of surrounding buildings is influenced when the underground old civil air defence works are backfilled and excavated.
In order to solve the technical problem, the invention provides an excavation-free backfill construction method for underground old civil air defence works, which comprises the following steps:
s1, finding out technical parameters of position, length, width, height and burial depth of the old underground civil air defense works through underground exploration; wherein, no accumulated water exists inside the underground old civil air defense works;
s2, lofting the position of the old underground civil air defense worker to the ground;
s3, vertically driving at least two rows of Larsen steel sheet piles into the backfill section required by the old civil air defense works at equal intervals for isolation to form one or more isolation sections;
s4, a plurality of grouting holes which are arranged at equal intervals and communicated with the isolation sections are formed in the ground corresponding to each isolation section;
s5, simultaneously injecting concrete into the isolation section through each grouting hole until the concrete is filled up and compacted;
and S6, when the backfilled concrete reaches the preset strength, pulling out the Larsen steel sheet pile to finish the construction of the whole backfilling section.
In a preferred embodiment of the present invention, in step S1, the underground exploration is performed by a geological radar method.
In a preferred embodiment of the present invention, in step S2, the lofting is performed by using a total station lofting apparatus.
In a preferred embodiment of the present invention, in step S3, the larsen steel sheet pile has a model of SP-IV larsen steel sheet pile.
In a preferred embodiment of the present invention, in step S3, the top end of the larsen steel sheet pile extends out of the ground, and the distance between the top end of the larsen steel sheet pile and the ground is greater than or equal to 300 mm.
As a preferable embodiment of the present invention, in step S3, the bottom end of the larsen steel sheet pile is inserted into a foundation below the underground old civil air defense, and a distance between the bottom end of the larsen steel sheet pile and the bottom of the underground old civil air defense is greater than or equal to 500 mm.
In a preferred embodiment of the present invention, in step S3, a distance between two adjacent rows of larsen steel sheet piles is less than or equal to 15 m.
In a preferred embodiment of the present invention, in the step S4, the diameter of the injection hole is 300 mm.
In a preferred embodiment of the present invention, in step S4, the distance between two adjacent grouting holes is 3m to 5 m.
In a preferred embodiment of the present invention, in the step S5, the concrete is used in a dry density grade of 500kg/m3The foam concrete.
Compared with the prior art, the excavation-free backfill construction method for the underground old civil air defense works has the following beneficial effects that:
the construction method comprises the steps of vertically driving at least two rows of Larsen steel sheet piles into a backfilling section required by underground old civil air defence works for isolation to form one or more isolation sections, and backfilling each isolation section by adopting a concrete guniting injection mode; whole work progress need not to excavate, can backfill old man's air defense worker in underground fast, greatly shortens construction period, does not cause too big load to the environment moreover, is favorable to environmental protection to effectively solve old man's air defense worker in underground and backfill the problem that causes landslide, traffic puzzlement and influence its peripheral building stability easily when excavating.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings of the embodiments will be briefly described below.
FIG. 1 is a schematic longitudinal section view of an excavation-free backfill construction method for underground old civil air defence works provided by the invention.
The labels in the figure are: 1. larsen steel sheet pile 2, grouting hole 3, ground 4, civil air defense engineering 5 and foundation.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "left", "right", "top", "bottom", and the like, indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience in describing the present invention and simplifying the description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. It should be understood that the terms "first", "second", etc. are used herein to describe various information, but the information should not be limited to these terms, which are only used to distinguish one type of information from another. For example, "first" information may also be referred to as "second" information, and similarly, "second" information may also be referred to as "first" information, without departing from the scope of the present invention.
In addition, in the description of the present invention, the terms "front" and "rear" refer to: when the underground old civil air defense construction method is in a use state, one surface close to a user is front, and the other surface far away from the user is back.
As shown in fig. 1, a preferable embodiment of the present invention is an excavation-free backfill construction method for old underground civil air defence works, which comprises the following steps:
s1, finding out technical parameters of the position, the length, the width, the height and the burial depth of the old underground civil air defense works 4 through underground exploration. In this embodiment, the underground old civil air defense works 4 are brick masonry structures, and no accumulated water exists in the underground old civil air defense works; the underground exploration adopts a geological radar method, and an instrument adopted by the geological radar method is an SIR-20 geological radar.
S2, lofting the position of the old underground civil air defense works 4 to the ground 3. In this embodiment, the lofting is performed by using a total station instrument.
S3, vertically driving at least two rows of Larsen steel sheet piles 1 into the backfilling sections of the underground old civil air defense works 4 at equal intervals for isolation to form one or more isolation sections. In the embodiment, the mechanical equipment for vertically driving the Larsen steel sheet pile 1 is a vibrating hydraulic pile driver, and the model is BY-VH 250; the Larsen steel sheet pile 1 is SP-IV Larsen steel sheet pile 1 in model number; the distance between two adjacent rows of Larsen steel sheet piles 1 is smaller than or equal to 15m, so that the later backfilling construction is facilitated; the top end of the Larsen steel plate pile 1 extends out of the ground 3, and the distance between the top end of the Larsen steel plate pile 1 and the ground is more than or equal to 300mm, so that pile pulling operation in the later period is facilitated; the bottom end of the Larsen steel plate pile 1 is inserted into a foundation 5 below the underground old civil air defense construction 4, the distance between the bottom end of the Larsen steel plate pile 1 and the bottom of the underground old civil air defense construction 4 is larger than or equal to 500mm, the sealing performance between each isolation area section is guaranteed, and meanwhile, the installation strength of the Larsen steel plate pile 1 is improved.
And S4, a plurality of grouting holes 2 which are arranged at equal intervals and communicated with the isolation sections are formed in the ground 3 corresponding to each isolation section. In this embodiment, the diameter of the grouting hole 2 is 300 mm; the distance between two adjacent grouting holes 2 is 3-5 m, so that concrete can be conveniently and uniformly injected into the isolation section.
And S5, simultaneously injecting concrete into the isolation section through each grouting hole 2 until the concrete is filled up and compacted. In the embodiment, each grouting hole 2 on one isolation section must be simultaneously injected with grouting until the concrete is filled up to be compact, and then the next isolation section is injected with grouting; the dry density grade of the concrete is 500kg/m3The foam concrete has the following technical parameters of the mixing ratio of each cube of the concrete: 105kg of fly ash, 312kg of common cement, 208.5kg of water and 1.16kg of foaming agent. It should be noted that the foam concrete has better fluidity, can be backfilled and compacted in a 360-degree blind angle-free manner, has enough strength, and is beneficial to the stability of the foundation.
And S6, when the backfilled concrete reaches the preset strength, pulling out the Larsen steel plate pile 1 to finish the construction of the whole backfilling section.
In conclusion, according to the excavation-free backfill construction method for the underground old civil air defense works, at least two rows of Larsen steel sheet piles 1 are vertically driven into the sections, needing to be backfilled, of the underground old civil air defense works 4 for isolation to form one or more isolation sections, and each isolation section is backfilled in a concrete guniting injection mode; whole work progress need not the excavation, can backfill old man's air defense worker 4 in underground fast, greatly shortens construction period, does not cause too big load to the environment moreover, is favorable to the environmental protection to effectively solve old man's air defense worker 4 in underground and backfill the excavation and cause landslide easily, traffic puzzlement and influence its peripheral building stability's problem.
The above disclosure is only for the purpose of illustrating the preferred embodiments of the present invention, and it is therefore to be understood that the invention is not limited by the scope of the appended claims.

Claims (10)

1. The excavation-free backfill construction method for the underground old civil air defense workers is characterized by comprising the following steps of:
s1, finding out technical parameters of position, length, width, height and burial depth of the old underground civil air defense works through underground exploration; wherein, no accumulated water exists inside the underground old civil air defense works;
s2, lofting the position of the old underground civil air defense worker to the ground;
s3, vertically driving at least two rows of Larsen steel sheet piles into the backfill section required by the old civil air defense works at equal intervals for isolation to form one or more isolation sections;
s4, a plurality of grouting holes which are arranged at equal intervals and communicated with the isolation sections are formed in the ground corresponding to each isolation section;
s5, simultaneously injecting concrete into the isolation section through each grouting hole until the concrete is filled up and compacted;
and S6, when the backfilled concrete reaches the preset strength, pulling out the Larsen steel sheet pile to finish the construction of the whole backfilling section.
2. The excavation-free backfill construction method for underground old civil air defense as claimed in claim 1, wherein in the step S1, the underground exploration adopts a geological radar method.
3. The excavation-free backfill construction method for the underground old civil air defense as claimed in claim 1, wherein in the step S2, the lofting is performed by using a total station instrument.
4. The excavation-free backfill construction method for the underground old civil air defense industry as claimed in claim 1, wherein in the step S3, the Larsen steel sheet pile is SP-IV Larsen steel sheet pile.
5. The excavation-free backfill construction method for the underground old civil air defense industry as claimed in claim 1, wherein in the step S3, the top end of the Larsen steel sheet pile extends out of the ground, and the distance between the top end of the Larsen steel sheet pile and the ground is greater than or equal to 300 mm.
6. The excavation-free backfill construction method for the old underground civil air defense as claimed in claim 1, wherein in the step S3, the bottom end of the larsen steel sheet pile is inserted into a foundation below the old underground civil air defense, and the distance between the bottom end of the larsen steel sheet pile and the bottom of the old underground civil air defense is greater than or equal to 500 mm.
7. The excavation-free backfill construction method for the underground old civil air defense industry as claimed in claim 1, wherein in the step S3, the distance between two adjacent rows of Larsen steel sheet piles is less than or equal to 15 m.
8. The excavation-free backfill construction method for the underground old civil air defense industry according to claim 1, wherein in the step S4, the diameter of the grouting hole is 300 mm.
9. The excavation-free backfill construction method for the underground old civil air defense industry as claimed in claim 1, wherein in the step S4, the distance between two adjacent grouting holes is 3 m-5 m.
10. The excavation-free backfill construction method for the underground old civil air defense works as claimed in claim 1, wherein in the step S5, the concrete is adopted with a dry density grade of 500kg/m3The foam concrete.
CN202010120071.0A 2020-02-26 2020-02-26 Excavation-free backfill construction method for underground old civil air defense works Pending CN111396121A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010120071.0A CN111396121A (en) 2020-02-26 2020-02-26 Excavation-free backfill construction method for underground old civil air defense works

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010120071.0A CN111396121A (en) 2020-02-26 2020-02-26 Excavation-free backfill construction method for underground old civil air defense works

Publications (1)

Publication Number Publication Date
CN111396121A true CN111396121A (en) 2020-07-10

Family

ID=71434054

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010120071.0A Pending CN111396121A (en) 2020-02-26 2020-02-26 Excavation-free backfill construction method for underground old civil air defense works

Country Status (1)

Country Link
CN (1) CN111396121A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104099943A (en) * 2014-06-30 2014-10-15 中铁四局集团第四工程有限公司 Underground diaphragm wall and deserted underground civil air defense engineering intersection processing method
CN104196034A (en) * 2014-09-18 2014-12-10 中建交通建设集团有限公司 Foundation pit construction method employing steel sheet piles as support cofferdam
CN105735354A (en) * 2015-12-16 2016-07-06 贵州建工集团第建筑工程有限责任公司 Covered-excavation full-top-down construction method of municipal underground engineering
CN106759473A (en) * 2016-11-11 2017-05-31 中国建筑第八工程局有限公司 The constructing structure and its construction method of underground pipe gallery and road
CN110374112A (en) * 2019-07-26 2019-10-25 中国能源建设集团湖南省电力设计院有限公司 Weak soil site system of deep foundation pit support and its construction method
CN110512594A (en) * 2019-08-20 2019-11-29 北京建材地质工程有限公司 The simple and easy method of churning driven opportunity cavity pore-forming

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104099943A (en) * 2014-06-30 2014-10-15 中铁四局集团第四工程有限公司 Underground diaphragm wall and deserted underground civil air defense engineering intersection processing method
CN104196034A (en) * 2014-09-18 2014-12-10 中建交通建设集团有限公司 Foundation pit construction method employing steel sheet piles as support cofferdam
CN105735354A (en) * 2015-12-16 2016-07-06 贵州建工集团第建筑工程有限责任公司 Covered-excavation full-top-down construction method of municipal underground engineering
CN106759473A (en) * 2016-11-11 2017-05-31 中国建筑第八工程局有限公司 The constructing structure and its construction method of underground pipe gallery and road
CN110374112A (en) * 2019-07-26 2019-10-25 中国能源建设集团湖南省电力设计院有限公司 Weak soil site system of deep foundation pit support and its construction method
CN110512594A (en) * 2019-08-20 2019-11-29 北京建材地质工程有限公司 The simple and easy method of churning driven opportunity cavity pore-forming

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN101270579B (en) Foundation pit guard method for expansion construction from deep foundation pit to shallow foundation pit
US20140215959A1 (en) Method for forming a retaining wall, and corresponding retaining wall
Budania et al. Soil nailing for slope stabilization: an overview
CN102733413A (en) Method for controlling subsidence of operating subway tunnel
CN102660955B (en) Quick construction method for foundation pit slope support
US9359725B2 (en) Stepwise repeated destabilization and stabilization of highly collapsible soil mass by ‘soil nailing technique’ used for construction of railway/road underpass
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN108532586A (en) A kind of construction method of garage parking diaphram wall
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
CN111396084A (en) Underground old civil air defense construction method with accumulated water inside
CN207211158U (en) Assembled pile board wall foundation pit supporting construction
CN107143149B (en) A kind of existing masonry structure building adds the construction method of basement
JP2000352296A (en) Method o constructing passage just under underground structure
CN108035360A (en) A kind of method for pattern foundation pit supporting structure
CN114622574B (en) Water-rich throwing filling deep foundation pit water interception excavation supporting method and supporting device
CN111396121A (en) Excavation-free backfill construction method for underground old civil air defense works
CN111441794B (en) Underground excavation construction method and structure for rebuilding existing tunnel into double-layer tunnel
KR101052363B1 (en) Freestanding Digging Method for Deep Excavation
CN111379307A (en) Construction method of municipal sewage pipe engineering based on underground old civil air defense works
KR101091081B1 (en) Excavation method and construction of dual tunnel
CN100593052C (en) Open cut foundation pit supporting and protecting method
CN110965585B (en) Multi-multi-arch rectangular tunnel arch division construction method
KR200297427Y1 (en) Retaining Pile for Retaining Wall Engineer
CN111472389B (en) Open excavation construction method for rebuilding existing tunnel into double-layer tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200710