CN111335904A - Shield downward-penetrating building construction monitoring method - Google Patents

Shield downward-penetrating building construction monitoring method Download PDF

Info

Publication number
CN111335904A
CN111335904A CN202010013405.4A CN202010013405A CN111335904A CN 111335904 A CN111335904 A CN 111335904A CN 202010013405 A CN202010013405 A CN 202010013405A CN 111335904 A CN111335904 A CN 111335904A
Authority
CN
China
Prior art keywords
monitoring
shield
points
settlement
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010013405.4A
Other languages
Chinese (zh)
Inventor
周祖斌
田作华
姚义
王天武
肖祥
廖友根
朱斌
刘光雨
李�杰
王丙吉
蒋华
刘红建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
Original Assignee
China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 22nd Bureau Group Co Ltd, China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd. filed Critical China Railway 22nd Bureau Group Co Ltd
Priority to CN202010013405.4A priority Critical patent/CN111335904A/en
Publication of CN111335904A publication Critical patent/CN111335904A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The invention discloses a shield under-penetration building construction monitoring method, which comprises the following steps: step 1: carrying out on-site inspection; step 2: monitoring surface subsidence and uplift; and step 3: monitoring the deformation of a building; and 4, step 4: and monitoring soil body layering and vertical displacement. The invention improves each step, and realizes the purpose of safe downward penetration of the shield zone through the construction of complex buildings.

Description

Shield downward-penetrating building construction monitoring method
Technical Field
The invention relates to the field of tunnel construction, in particular to a shield under-penetration building construction monitoring method.
Background
In the underground tunnel construction of a complex building which is penetrated downwards in the urban underground, an innovative construction method of a special construction section is needed, and the tunneling construction of the existing tunnel construction method is improved so as to achieve the aim of safely monitoring construction units.
Disclosure of Invention
The invention aims to solve the technical problem of providing a construction method for a tunnel under a shield region of a tunnel to penetrate around a city, and provides a new construction method.
The technical problem to be solved by the invention is realized by the following technical scheme:
a shield under-penetration building construction monitoring method comprises the following steps:
step 1: and (3) field patrol: taking a landform in an influence range and the interior of a tunnel as objects;
step 2: monitoring surface subsidence and uplift, taking the surface in an influence range as an object, and reasonably arranging section measuring points according to the buried depth and the line spacing; the measuring point layout comprises the following steps:
1) in the shield starting and arrival section, the section interval of the communication channel position is 5m, and 9-11 measuring points are transversely arranged on the section;
2) setting a monitoring section in the length of 10m, wherein the monitoring section is 50 m before the shield starts, except for a shield starting section, and 9-11 measuring points are transversely arranged on the section;
3) the shield launching is carried out for 50-100 meters, a monitoring section is arranged for 20 meters, and 9-11 measuring points are transversely arranged on the section;
4) 1 central line point is arranged every 5m along the tunnel axis on the left and right lines of the shield;
and step 3: monitoring the deformation of a building, taking a building (structure) in an influence range as an object, and including a distance range of about 1-2 times of the buried depth of the influenced finger in the tunnel, wherein the distance range comprises the following steps:
1) vertical displacement monitoring points are arranged along the outer wall of the building, and monitoring points are arranged at four corners and corners; when the building is located in a range of 1 time, 1 measuring point is arranged along every 10m or every 2 bearing columns of the outer wall, and 1 measuring point is arranged every 10 m-15 m or every 2-3 bearing columns of the rest of the outer wall;
2) the inclination monitoring points are preferably distributed on bearing columns or outer walls of buildings, and the maximum inclination of the tunnel line perpendicular to the shield zone of the influence source should be monitored in principle;
3) the crack monitoring points are distributed on the cracks at representative parts with larger stress or stress change or the like or the cracks with larger width.
And 4, step 4: monitoring soil body layering, vertical displacement to tunnel axis top stratum is the object, includes:
1) 2 monitoring points are respectively distributed on the left line and the right line within the range of 5-15 meters of the starting section and the arrival section of the shield;
2) 1 monitoring point is arranged at the tool changing position in the shield construction;
3) 1 monitoring point is arranged at the abnormal position of shield tunneling;
4) the shield penetrates through the front and back of the building by about 15 meters, 3 layered settlement points are respectively arranged on the left line and the right line, and the settlement points are spaced by 5 meters.
Preferably, the method further comprises the following steps: the monitoring frequency is increased when one of the following conditions is encountered:
1) monitoring data reaching an alarm value;
2) the monitoring data has larger variation or higher speed;
3) the existence of unfavorable geological conditions not found in the survey;
4) a shield and a large amount of accumulated water around the shield, long-time continuous rainfall and leakage of municipal pipelines occur;
5) the ground load near the shield suddenly increases or exceeds the design limit value;
6) sudden large settlement or severe cracking of the surrounding ground;
7) adjacent buildings exhibit sudden large settlement, uneven settlement or severe cracking.
Preferably, the method further comprises the following steps: the early warning parameters of the monitoring project are as follows:
surface sedimentation: cumulative control (mm): the ridge is +10 mm; settling to-30 mm; rate control (mm/d): the daily swelling variable is 3 mm; the daily variable of sedimentation is 3 mm; early warning standard (mm): the ridge is +6mm in total, and the daily variable is 3 mm; the settlement is accumulated to-15 mm, and the daily variable is 3 mm;
building settlement: cumulative control (mm): 10 mm; rate control (mm/d): the daily variable is 2 mm; early warning standard (mm): and (3) settling: accumulating to-15 mm, and daily variation to 3 mm;
vertical displacement of the deep layer of the soil body: cumulative control (mm): settling to-30 mm; rate control (mm/d): the daily variable of sedimentation is-5 mm; early warning standard (mm): the sedimentation is cumulative-18 mm, and the daily variable is 5 mm.
Preferably, the method further comprises the following steps: the measuring points are distributed as follows: the ground surface settlement monitoring points are buried in an excavation or drilling tool hole forming mode and penetrate through a pavement structure layer; and a protective cover is added at the measuring point, and the aperture is larger than 80 mm.
Preferably, the method further comprises the following steps: the measuring point of surface settlement monitoring is buried underground by adopting excavation or drilling tool pore-forming mode, and the burying steps are as follows:
a. excavating holes with the diameter of about 130mm and the depth of about 1m on the hard earth surface by using a Luoyang shovel, and tamping the bottoms of the holes;
b. removing residue soil, and injecting a proper amount of clear water into the hole for curing;
c. placing a steel bar mark with the length of more than 100cm in the center of the hole, exposing the filler surface by about 1-2 cm, and enabling the height of a measuring point to be lower than the height of a road surface so as to avoid the influence of a travelling crane on the measuring point, and backfilling and tamping with coarse sand;
d. a steel protective cover with the diameter larger than 110mm is additionally arranged at the upper part;
e. and maintaining for more than 15 days, and enabling the measuring points to directly reflect the soil layer change in an end-bearing mode.
Preferably, the method further comprises the following steps: the survey point of building settlement monitoring is laid and is included: drilling:
a. drilling a hole with the diameter of 18mm and the depth of about 120mm at the selected position by using an electric drilling tool;
b. removing slag in the holes, and injecting a proper amount of clear water for curing;
c. injecting a proper amount of anchoring agent which is uniformly stirred into the hole;
d. and (5) placing an observation point mark, backfilling a gap between the mark and the hole by using an anchoring agent, and maintaining for more than 15 days.
Preferably, the method further comprises the following steps: building (structure) is buried underground for direct-burried monitoring point, and the measurement station is laid and is included: the shield passes through the front and back of the building by about 15 meters, and 3 layered settlement points (5 meters intervals) are respectively arranged on the left line and the right line. When laying layered settlement points, the hole depth is 3-5 m above the top of the tunnel, then the settling tube is placed in the hole, and the installation of the magnetic ring and the positioning ring and the splicing of the settling tube are carried out; after the settling tube is placed to the required depth, the top cover is covered to carry out fine sand backfilling, and protective measures are added around the top of the tube to prevent the test data from being influenced.
Preferably, reinforcement must be simultaneously applied to complex buildings and drainage underground construction.
Compared with the prior art, the invention has the following advantages:
the shield under-penetration building construction monitoring method comprises the following steps: step 1: carrying out on-site inspection; step 2: monitoring surface subsidence and uplift; and step 3: monitoring the deformation of a building; and 4, step 4: and monitoring soil body layering and vertical displacement. The invention improves each step, and realizes the purpose of safe downward penetration of the shield zone through the construction of complex buildings.
Drawings
FIG. 1 is a shield reinforcing measure and geological profile
FIG. 2 is a reinforcing measure and geological profile of a newly opened flood drainage channel passing through the bottom of a shield tunnel
FIG. 3 is a schematic view of the buried structure of the surface subsidence monitoring point
FIG. 4 is a schematic view of a buried monitoring point of a building
FIG. 5 is a schematic view of a settling tube mounting structure
1-drilling, 2-guiding pipe, 3-positioning ring, 4-external connecting sleeve, 5-settlement magnetic ring, 6-spring piece on settlement magnetic ring, 7-bottom cover, 8-soil layer.
Detailed Description
The monitoring method for the construction of the shield under-shield penetration structure shown in fig. 1, fig. 2, fig. 3, fig. 4 and fig. 5 is carried out in the following tunnel construction:
as shown in fig. 1 and fig. 2, the shield interval from the gold stone road station to the three-color road station is as follows: the buildings around the line are dense, mainly office buildings and sewage treatment plants, the population is dense, and the road traffic above the section is busy. The interval is constructed by a shield method. Shield intervals of three-color road stations to a neutralization station: the current situation around the line is that the building heaped soil area, the villager residential house and the city winding are high in speed, and the sewage treatment plants and newly-built sewage treatment plants are located in the ground blocks along the interval, so that large-diameter pipelines are more. And (5) constructing by adopting a shield method. Firstly, curves are connected with straight lines, then the curves with the radius of 600m, 500m and 500m are respectively connected with the straight lines, and finally the curves enter the neutralizing station in the straight lines.
According to the hydrogeological data of the region and the occurrence conditions of the underground water, the underground water mainly submerges in the pores of the fourth series sand and pebble soil layers. The pebble soil layer of the field is thick and distributed in a layered manner, a thin layer of sand is partially sandwiched, a large amount of pores are formed among the pebble soil layer, the pebble soil layer is submerged, the water quantity is large, the water level is high, and atmospheric precipitation and regional surface water are main supply sources. Pore water in the pebble soil layer forms a through free water surface. The stratum penetrated by the shield of the section of the standard is mainly mudstone, and the intervals from the gold stone road station to the three-color road station to the neutralization station are mainly mudstone.
Under-penetrating factory building and civil house construction monitoring measure
1. Purpose of monitoring
The geological conditions and environment of the engineering passing region are very complex, and the construction difficulty is high. During construction, monitoring of important pipelines, structures and the like around a structural project and a construction line provides timely and reliable information for participating parties, so that the safety of the project during construction and the influence of construction on the surrounding environment are evaluated, and potential hazards or accidents which may endanger the safety of the construction and the surrounding environment are timely and accurately forecasted, so that effective measures are timely taken to eliminate the potential hazards, and the accidents are avoided.
(1) In the detection process, the protection of the site measuring points is enhanced, the problems are found to be timely connected with relevant units, and if the measuring points are damaged carelessly due to construction, the measuring points should be remedied with the best effort. For the measuring points which are damaged and can not be remedied, the standby monitoring points distributed nearby are utilized in time to ensure that the monitoring points are not lost, and the table 1 monitoring content and the distribution principle that the monitoring data can be accurate are ensured
Figure RE-GDA0002485411150000041
Figure RE-GDA0002485411150000051
2. Monitoring frequency, control reference and alarm value
The engineering monitoring frequency is determined to meet the requirement of reflecting the important change process of the project measured by the monitored object without omitting the change moment. The monitoring frequency of the shield project needs to be determined by comprehensively considering the shield type, different construction stages of the shield and the underground project, the change of the surrounding environment and natural conditions and local experience. Under the condition of no data abnormity and accident symptoms, the field monitoring frequency after excavation can be determined according to the construction process.
When one of the following conditions is met, the monitoring should be enhanced, and the monitoring frequency or the field inspection frequency should be properly increased:
(1) monitoring data reaching an alarm value;
(2) the monitoring data has larger variation or higher speed;
(3) the existence of unfavorable geological conditions not found in the survey;
(4) a shield and a large amount of accumulated water around the shield, long-time continuous rainfall and leakage of municipal pipelines occur;
(5) the ground load near the shield suddenly increases or exceeds the design limit value;
(6) sudden large settlement or severe cracking of the surrounding ground;
(7) sudden large settlement, uneven settlement or severe cracking of adjacent buildings (structures);
(8) and other abnormal conditions affecting the safety of the tunnel and the surrounding environment occur.
3. Control reference and alarm value
The monitoring and early warning are one of the purposes of monitoring work and are important measures for preventing engineering accidents and ensuring the safety of engineering structures and surrounding environments. The monitoring control value and the early warning value are the precondition for implementing the monitoring work and are important bases for judging whether the engineering structure and the surrounding environment are in normal, abnormal and dangerous states during the monitoring period, so that the monitoring control value and the warning value are determined necessarily. The monitoring control value and the alarm value are commonly controlled by two indexes of a monitoring variable accumulated value and a change rate.
The monitoring control values and alarm values adopted in the project are as follows:
TABLE 2 monitoring project control and early warning standards
Figure RE-GDA0002485411150000061
4. Surface subsidence monitoring, as shown in fig. 3:
the project monitoring aims to monitor the displacement of the soil around shield construction, know the stability of the soil and indirectly judge the safety condition of the enclosure structure.
Measuring form and working principle
For monitoring the surface subsidence, a vertical displacement monitoring network is established by taking an engineering elevation system as a reference through a closed and attached leveling route. The control point is composed of a reference point and a working base point. In general, the reference point may utilize a measurement control point provided by a design unit. If the measurement control point provided by the design unit can not be used, the self-manufacturing can select a more stable position.
Measuring point layout principle and method
The settlement monitoring points are arranged on the ground surface within the construction influence range according to the requirements in the design drawing, and the principle is as follows: the ground surface settlement monitoring points are buried in a mode of manual excavation or drilling tool hole forming, and are required to penetrate through a pavement structure layer. And a protective cover is added at the measuring point, and the aperture is not less than 80 mm. The road and ground surface settlement monitoring measuring points are buried flatly, so that the influence on the passing of personnel and vehicles due to the unevenness is prevented, and meanwhile, the measuring points are buried stably, clear marks are made, and the protection is facilitated.
The surface subsidence measuring point is buried underground by adopting a mode of manual excavation or drilling tool pore-forming, and the burying steps are as follows:
a. excavating holes with the diameter of about 130mm and the depth of about 1m on the hard earth surface by using a Luoyang shovel, and tamping the bottoms of the holes;
b. removing residue soil, and injecting a proper amount of clear water into the hole for curing;
c. placing a steel bar mark with the length not less than 100cm in the center of the hole, exposing the filler surface by about 1-2 cm, and enabling the height of a measuring point to be lower than the height of a road surface so as to avoid the influence of a travelling crane on the measuring point, and backfilling and compacting by using coarse sand;
d. a steel protective cover is additionally arranged at the upper part, and the diameter of the steel protective cover is not less than 110 mm;
e. and maintaining for more than 15 days, and enabling the measuring points to directly reflect the soil layer change in an end-bearing mode by the method.
Observation, calculation methods and requirements
The observation of the level monitoring network adopts a geometric leveling method, uses a precise level gauge to carry out observation,
the calculation method comprises the following steps: A. height difference between two points B: elevation HB of undetermined point B for hab (differential elevation-forward reading) is: HB-HA-hAB.
5. Building settlement monitoring, as shown in fig. 4:
purpose of monitoring
In order to comprehensively know the influence condition of the construction on surrounding buildings, measuring points are arranged on a bearing structure of a corner of the building during the construction period, the sinking and the inclination of the building in the shield construction process are observed, and the safety of the building and the reliability of adopted engineering protection measures are judged according to the measuring points.
Measuring point layout principle and method
The building settlement observation base point and the ground surface vertical displacement monitoring net base point are shared, and the building settlement monitoring point is incorporated into the base point to form a closed circuit, an attached circuit and the like. Settlement monitoring points distributed on a building adopt the following modes:
drilling:
a. drilling a hole with the diameter of 18mm and the depth of about 120mm at the selected position by using an electric drilling tool;
b. removing slag in the holes, and injecting a proper amount of clear water for curing;
c. injecting a proper amount of anchoring agent which is uniformly stirred into the hole;
d. and (5) placing an observation point mark, backfilling a gap between the mark and the hole by using an anchoring agent, and maintaining for more than 15 days.
6. Monitoring the layered settlement vertical displacement of the soil body, as shown in figure 5:
purpose of monitoring
The soil layers above different depth positions generate vertical displacement of different degrees. And (5) knowing the settlement conditions of the surrounding soil at different depths in the shield tunneling process. In the tunneling process, along with the removal of a large amount of soil in the tunnel, the tunnel structure deforms under the action of outside soil pressure; meanwhile, the soil around the tunnel is affected by the disturbance of tunneling and excavation, so that the tunnel is directly used, the underground displacement of a representative section needs to be monitored and measured in the tunneling process, and timely feedback is carried out to take targeted measures so as to ensure the construction safety of shield tunneling.
Test form and working principle
The displacement in the ground is monitored by a method of embedding a sedimentation pipe in the soil body and observing the soil body sedimentation at each depth through a sedimentation instrument. The known test device comprises two parts: a settlement gauge, a settlement guide pipe and a settlement magnetic ring 5.
The sedimentation magnetic ring is made of injection molding, magnetic materials are placed in the sedimentation magnetic ring to form a magnetic ring, and the spring piece 6 is installed outside the sedimentation magnetic ring. The magnetic ring is sleeved outside the external connecting pipe 4, and the spring leaf 6 is contacted with the soil layer 8 and moves along with the movement of the soil layer 8.
The measuring head of the settlement gauge is made of stainless steel, a magnetic field sensor is arranged in the settlement gauge, when the external magnetic field acts, the receiving system is connected, and when the external magnetic field does not act, the receiving system is automatically closed.
According to the measuring point layout principle and method, a shield penetrates through the front and back of a building structure by about 15 meters, and 3 layered settlement points (5-meter intervals) are respectively arranged on the left line and the right line. When laying layered settlement points, the depth of the hole 1 is 3-5 m above the top of the tunnel, then the settling tube 2 is placed in the hole 1, and the installation of the magnetic ring and the positioning ring and the splicing of the settling tube are carried out; after the settling tube is placed to the desired depth, the top cover is closed to allow for fine sand backfill and protective measures are applied around the top of the tube 2 to prevent impact on the test data.
Observation, calculation methods and requirements
During measurement, a fastening screw behind a wire spool is unscrewed, the wire spool rotates freely, a power supply button (a power supply indicator lamp is on) is pressed, a measuring head is placed in a guide pipe, a steel ruler cable is held by hand, the measuring head moves downwards slowly, when the measuring head contacts a magnetic ring in a soil layer, a sounder of a receiving system can give out continuous buzzing sound, the depth size of the steel ruler cable at the pipe opening is read and written at the moment, the hole bottom is measured little by little, process measurement and reading are called as Ji, when the measuring cable is retracted in the guide pipe, the sounder of the receiving system can also give out sound through the magnetic ring in the soil layer, the depth size of the measuring cable at the pipe opening is read and written at the moment, the hole opening is measured as return measurement and reading are called as Hi.
7. Control reference and alarm value
The monitoring and early warning are one of the purposes of monitoring work and are important measures for preventing engineering accidents and ensuring the safety of engineering structures and surrounding environments. The monitoring control value and the early warning value are the precondition for implementing the monitoring work and are important bases for judging whether the engineering structure and the surrounding environment are in normal, abnormal and dangerous states during the monitoring period, so that the monitoring control value and the warning value are determined necessarily. The monitoring control value and the alarm value are commonly controlled by two indexes of a monitoring variable accumulated value and a change rate.
The monitoring control values and alarm values adopted in the project are as follows:
Figure RE-GDA0002485411150000091
the invention improves each step, and realizes the purpose of safer downward penetration of the shield zone through the construction of complex buildings.

Claims (8)

1. A shield under-penetration building construction monitoring method comprises the following steps:
step 1: and (3) field patrol: taking a landform in an influence range and the interior of a tunnel as objects;
step 2: monitoring surface subsidence and uplift, taking the surface in an influence range as an object, and reasonably arranging section measuring points according to the buried depth and the line spacing; the measuring point layout comprises the following steps:
1) in the shield starting and arrival section, the section interval of the communication channel position is 5m, and 9-11 measuring points are transversely arranged on the section;
2) setting a monitoring section 50 meters and 10 meters before the shield starts, and transversely arranging 9-11 measuring points on the section;
3) the shield launching is carried out for 50-100 meters, a monitoring section is arranged for 20 meters, and 9-11 measuring points are transversely arranged on the section;
4) 1 central line point is arranged every 5m along the tunnel axis on the left and right lines of the shield;
and step 3: monitoring the deformation of a building, taking a building (structure) in an influence range as an object, and including a distance range of about 1-2 times of the buried depth of the influenced finger in the tunnel, wherein the distance range comprises the following steps:
1) vertical displacement monitoring points are arranged along the outer wall of the building, and monitoring points are arranged at four corners and corners; when the building is located in a range of 1 time, 1 measuring point is arranged along every 10m or every 2 bearing columns of the outer wall, and 1 measuring point is arranged every 10 m-15 m or every 2-3 bearing columns of the rest of the outer wall;
2) the inclination monitoring points are preferably distributed on bearing columns or outer walls of buildings, and the maximum inclination of the tunnel line perpendicular to the shield zone of the influence source should be monitored in principle;
3) the crack monitoring points are distributed on the cracks at representative parts with larger stress or stress change or the like or the cracks with larger width.
And 4, step 4: monitoring soil body layering, vertical displacement to tunnel axis top stratum is the object, includes:
1) 2 monitoring points are respectively distributed on the left line and the right line within the range of 5-15 meters of the starting section and the arrival section of the shield;
2) 1 monitoring point is arranged at the tool changing position in the shield construction;
3) 1 monitoring point is arranged at the abnormal position of shield tunneling;
4) the shield penetrates through the front and back of the building by about 15 meters, 3 layered settlement points are respectively arranged on the left line and the right line, and the settlement points are spaced by 5 meters.
2. The shield under-penetration construction monitoring method according to claim 1, comprising the steps of:
the monitoring frequency is increased when one of the following conditions is encountered:
1) monitoring data reaching an alarm value;
2) the monitoring data has larger variation or higher speed;
3) the existence of unfavorable geological conditions not found in the survey;
4) a shield and a large amount of accumulated water around the shield, long-time continuous rainfall and leakage of municipal pipelines occur;
5) the ground load near the shield suddenly increases or exceeds the design limit value;
6) sudden large settlement or severe cracking of the surrounding ground;
7) adjacent buildings exhibit sudden large settlement, uneven settlement or severe cracking.
3. The shield under-penetration construction monitoring method according to claim 1, further comprising the steps of: the early warning parameters of the monitoring project are as follows:
surface sedimentation: cumulative control (mm): the ridge is +10 mm; settling to-30 mm; rate control (mm/d): the daily swelling variable is 3 mm; the daily variable of sedimentation is 3 mm; early warning standard (mm): the ridge is +6mm in total, and the daily variable is 3 mm; the settlement is accumulated to-15 mm, and the daily variable is 3 mm;
building settlement: cumulative control (mm): 10 mm; rate control (mm/d): the daily variable is 2 mm; early warning standard (mm): and (3) settling: accumulating to-15 mm, and daily variation to 3 mm;
vertical displacement of the deep layer of the soil body: cumulative control (mm): settling to-30 mm; rate control (mm/d): the daily variable of sedimentation is-5 mm; early warning standard (mm): the sedimentation is cumulative-18 mm, and the daily variable is 5 mm.
4. The shield under-penetration construction monitoring method according to claim 1 or 3, further comprising the steps of: the measuring points are distributed as follows: the ground surface settlement monitoring points are buried in an excavation or drilling tool hole forming mode and penetrate through a pavement structure layer; and a protective cover is added at the measuring point, and the aperture is larger than 80 mm.
5. The shield under-penetration construction monitoring method according to claim 4, further comprising the steps of: the measuring point of surface settlement monitoring is buried underground by adopting excavation or drilling tool pore-forming mode, and the burying steps are as follows:
a. excavating holes with the diameter of about 130mm and the depth of about 1m on the hard earth surface by using a Luoyang shovel, and tamping the bottoms of the holes;
b. removing residue soil, and injecting a proper amount of clear water into the hole for curing;
c. placing a steel bar mark with the length of more than 100cm in the center of the hole, exposing the filler surface by about 1-2 cm, and enabling the height of a measuring point to be lower than the height of a road surface so as to avoid the influence of a travelling crane on the measuring point, and backfilling and tamping with coarse sand;
d. a steel protective cover with the diameter larger than 110mm is additionally arranged at the upper part;
e. and maintaining for more than 15 days, and enabling the measuring points to directly reflect the soil layer change in an end-bearing mode.
6. The shield under-penetration construction monitoring method according to claim 1 or 3, further comprising the steps of: the measuring point layout for monitoring the settlement of the building comprises the following steps:
a. drilling a hole with the diameter of 18mm and the depth of about 120mm at the selected position by using an electric drilling tool;
b. removing slag in the holes, and injecting a proper amount of clear water for curing;
c. injecting a proper amount of anchoring agent which is uniformly stirred into the hole;
d. and (5) placing an observation point mark, backfilling a gap between the mark and the hole by using an anchoring agent, and maintaining for more than 15 days.
7. The shield under-penetration construction monitoring method according to claim 6, further comprising the steps of: the building is buried for the direct burial formula monitoring point, and the measurement station is laid and is included: the shield penetrates through the front and back of the building by about 15 meters, and the left line and the right line are respectively provided with 3 layered settlement points; when laying layered settlement points, the hole depth is 3-5 m above the top of the tunnel, then the settling tube is placed in the hole, and the installation of the magnetic ring and the positioning ring and the splicing of the settling tube are carried out; after the settling tube is placed to the required depth, the top cover is covered to carry out fine sand backfilling, and protective measures are added around the top of the tube to prevent the test data from being influenced.
8. The shield under-penetration construction monitoring method according to claim 1, further comprising the steps of: and the method also comprises the reinforcement of a newly opened flood drainage channel passing through the lower part of the shield tunnel and a building.
CN202010013405.4A 2020-01-07 2020-01-07 Shield downward-penetrating building construction monitoring method Pending CN111335904A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010013405.4A CN111335904A (en) 2020-01-07 2020-01-07 Shield downward-penetrating building construction monitoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010013405.4A CN111335904A (en) 2020-01-07 2020-01-07 Shield downward-penetrating building construction monitoring method

Publications (1)

Publication Number Publication Date
CN111335904A true CN111335904A (en) 2020-06-26

Family

ID=71183361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010013405.4A Pending CN111335904A (en) 2020-01-07 2020-01-07 Shield downward-penetrating building construction monitoring method

Country Status (1)

Country Link
CN (1) CN111335904A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113236260A (en) * 2021-06-24 2021-08-10 中铁一局集团第二工程有限公司 Construction monitoring method for all-dimensional shield underpass of existing subway station
CN114198093A (en) * 2021-10-29 2022-03-18 中铁十九局集团第五工程有限公司 Measuring method of subway shield tunnel
CN115478567A (en) * 2022-08-05 2022-12-16 中建七局安装工程有限公司 Tunnel open excavation construction monitoring method with underground track penetrating upwards and adjacent to peripheral buildings

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113236260A (en) * 2021-06-24 2021-08-10 中铁一局集团第二工程有限公司 Construction monitoring method for all-dimensional shield underpass of existing subway station
CN114198093A (en) * 2021-10-29 2022-03-18 中铁十九局集团第五工程有限公司 Measuring method of subway shield tunnel
CN114198093B (en) * 2021-10-29 2023-11-24 中铁十九局集团第五工程有限公司 Measuring method for subway shield tunnel
CN115478567A (en) * 2022-08-05 2022-12-16 中建七局安装工程有限公司 Tunnel open excavation construction monitoring method with underground track penetrating upwards and adjacent to peripheral buildings

Similar Documents

Publication Publication Date Title
CN110631560B (en) Underground excavation interval monitoring and measuring method for subway station in dense building area
CN106894821B (en) It is a kind of originate, the monitoring method of received well and jacking construction
CN111335904A (en) Shield downward-penetrating building construction monitoring method
CN111101412B (en) Method for monitoring settlement and displacement of railway business line
CN104965994A (en) Determining and estimating method for surface subsidence characteristic parameters caused by subway tunnel construction
CN103046523B (en) Method for monitoring horizontal deformation of foundation pit and slope support
CN107023043A (en) A kind of deep foundation pit supporting construction monitoring and pre-alarming method
CN102425160A (en) Method for constructing engineering pile by combining rotary drilling rig with manual pile base chambering
CN111156006A (en) Construction method for shield underpass of dangerous pipeline
CN112836270B (en) Method for predicting influence of diving precipitation on building settlement
CN114017037A (en) Construction method for enabling shield to pass through municipal bridge area in short distance
CN112554247A (en) Foundation pit monitoring system
CN108225265A (en) A kind of soft soil roadbed deformation remote comprehensive monitoring system and installation method
CN111075460A (en) Shield construction and monitoring method for urban dense building
CN106759542A (en) The deformation monitoring of deep basal pit and the method for Deformation Prediction
CN113007611B (en) Monitoring system for gas pipeline crossing river bottom
CN114232607A (en) Frozen soil section drilled pile construction process
CN101319894A (en) Method for testing land subsidence caused by underground spacing
CN112187843A (en) BIM-based system and method for automatically monitoring capital construction risks of deep foundation pit
CN114482014B (en) Construction method for hammering pile sinking of precast pile in deep foundation pit in offshore ultra-thick silt region
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN116066109A (en) Municipal tunnel construction method
CN115450227A (en) Construction method for subway station to cut off underground river foundation pit support structure
CN211900605U (en) Shield construction monitoring structure for down-penetrating urban dense building pipeline
CN114993248A (en) Ground settlement monitoring method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination