CN111335256A - Fixed folding flood control board - Google Patents

Fixed folding flood control board Download PDF

Info

Publication number
CN111335256A
CN111335256A CN202010184802.8A CN202010184802A CN111335256A CN 111335256 A CN111335256 A CN 111335256A CN 202010184802 A CN202010184802 A CN 202010184802A CN 111335256 A CN111335256 A CN 111335256A
Authority
CN
China
Prior art keywords
mainboard
board
plate
sets
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010184802.8A
Other languages
Chinese (zh)
Inventor
孟伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Denilko Environmental Technology Suzhou Co ltd
Original Assignee
Denilko Environmental Technology Suzhou Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Denilko Environmental Technology Suzhou Co ltd filed Critical Denilko Environmental Technology Suzhou Co ltd
Priority to CN202010184802.8A priority Critical patent/CN111335256A/en
Publication of CN111335256A publication Critical patent/CN111335256A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention discloses a fixed and foldable flood control board which comprises a main board, a buffer device, a first fixing device and a second fixing device, wherein the vertical section of the main board is arranged in an L shape, the main board consists of three sets of auxiliary boards rotationally connected through spring hinges, the side surface of the main board is connected with a placing device and the buffer device, the placing device is arranged below the buffer device, the side surface of the main board, far away from the placing device, is connected with a plurality of sets of first fixing devices and a plurality of sets of second fixing devices, the second fixing devices are arranged below the first fixing devices, a plurality of sets of connecting threaded holes are formed in the main board in a digging mode, an adjusting device is connected with the connecting threaded holes in a threaded mode, the placing device comprises connecting boards, inclined boards and object placing boards, the connecting boards are welded on the two sides of the inclined boards, and the connecting boards above the inclined. This fixed folding flood control board, multinomial connection and fixed can promote the stability of mainboard, reduces the production and the continuation of risk.

Description

Fixed folding flood control board
Technical Field
The invention belongs to the technical field of flood control boards, and particularly relates to a fixed foldable flood control board.
Background
In flood control engineering, need utilize some facilities to block the flood, by city or river lake, need set up to enclose to keep off the protection low-lying area and not invaded by the flood, present flood control baffle kind is also more various, the positive flood velocity of flow of flood control baffle is very fast, during water impact flood control baffle, the load that the support of flood control board back bore is great, traditional flood control board only has a fixed measure, the impact that the rivers relapse can cause the unstability of flood control board gradually, it is long-time, cause the potential safety hazard.
Therefore, in view of the current situation, there is a need to design and manufacture a fixed foldable flood protection plate to meet the needs of practical use.
Disclosure of Invention
The present invention is directed to a fixed and foldable flood barrier to solve the above problems.
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides a fixed folding flood control board, includes mainboard, buffer, first fixing device and second fixing device, the vertical section of mainboard sets up to the L style of calligraphy, the mainboard comprises three spring hinge rotation connection's of group subplates, and the adjacent side of adjacent two sets of subplates all bonds and is used for sealed the pad that fills up, the side of mainboard is connected with placer and buffer, and placer sets up the below at buffer, the side that placer was kept away from to the mainboard is connected with the first fixing device of multiunit and multiunit second fixing device, and second fixing device sets up the below at first fixing device, the mainboard is dug and is equipped with multiunit connecting screw hole, and connecting screw hole female connection has adjusting device.
Preferably, placer is including linking board, swash plate and putting the thing board, the both sides of swash plate have all been welded and have been linked the board, and the board that links of top passes through connecting bolt and mainboard connection, and the board that links of below passes through connecting bolt and puts the thing board and be connected, the multiunit the swash plate is putting the equidistant range of thing board.
Preferably, buffer includes guard plate, support column and hollow column, the one side of keeping away from the mainboard of guard plate has the rubber slab through the viscose bonding, and guard plate and rubber slab still dig the passageway that is equipped with multiunit rectangle array and arranges, one side fixed weld that the guard plate kept away from the rubber slab has the support column that the multiunit is rectangle array and distributes, the side welding of mainboard has the hollow column that multiunit rectangle array arranged, and a side tip of support column sets up the inner chamber at the hollow column, it has pressure spring to bond between support column and the mainboard.
Preferably, the first fixing device comprises a lifting lug, an inclined supporting plate and a supporting plate, the lifting lug is welded on the side face of the main plate and is hinged to the inclined supporting plate through a rotating shaft, the supporting plate is welded at the bottom end of the inclined supporting plate, and a vertical bolt used for connection is arranged in a connecting through hole formed in the supporting plate in an excavating mode.
Preferably, the second fixing device comprises a thread block, a threaded rod, a drill rod and a twisting plate, the side face of the thread block and the side face of the main plate are bonded and fixed through viscose, the thread block is connected with the threaded rod through an internal thread of a vertical threaded hole formed in an excavating mode, the drill rod is welded at the bottom end of the threaded rod, and the twisting plate is welded at the top end of the threaded rod.
Preferably, adjusting device includes screw thread post, elliptical plate, ring board and rubber slab, the connecting thread hole threaded connection of screw thread post and mainboard, the periphery welding of screw thread post has a set of ring board and two sets of elliptical plate, and two sets of elliptical plates set up about screw thread post symmetry, the ring board sets up between elliptical plate and mainboard, the mainboard sets up between ring board and placer, the side that the ring board is close to the mainboard bonds and has the rubber slab.
Preferably, one side welding of mainboard has the lug, the opposite side of mainboard is dug and is equipped with the slot with the lug adaptation, and the inner wall of slot bonds and has the rubber pad, the bottom of mainboard also bonds and has the rubber pad.
Preferably, the top of mainboard still welds the handle, and the periphery of handle bonds and has the antiskid cover, the vertical section of handle sets up to the arc, mainboard, placer and buffer's periphery all coats and has coated waterproof paint.
Preferably, a sealing plate is bonded to a side surface of the lateral portion of the main plate, a bottom end of the sealing plate is flush with a bottom end of the lateral portion of the main plate, and the side surface of the sealing plate is configured in a circular arc shape.
The invention has the technical effects and advantages that: according to the fixed foldable flood control board, a placing board of a placing device of the main board can be used for placing a counterweight, so that stability can be provided on one side, and a first fixing device and a second fixing device on the other side of the main board can provide the other two stabilities; the balance weight of the placing plate can be obtained according to local conditions, the arrangement of the lifting lugs facilitates the support plate to be fixed in a manner of adapting to the ground with different landforms and planeness, and the drill rod can be fixed in a manner of adapting to different ground, so that different fixing requirements are met; the protection plate of the buffer device can protect the main board, and the arrangement of the pressure spring enables the protection plate to be buffered and moved when being blocked, so that the protection effect is achieved; the matching of the convex block and the slot facilitates the assembly and connection of a plurality of groups of whole bodies, the disassembly of the whole bodies and the folding of the main board, and the storage of the whole bodies; this fixed folding flood control board, multinomial connection and fixed can promote the stability of mainboard, reduces the production and the continuation of risk.
Drawings
FIG. 1 is a front view of the present invention;
FIG. 2 is a right side view of the present invention;
FIG. 3 is a top view of a first fixture of the present invention;
FIG. 4 is a schematic structural view of a second fixing device according to the present invention;
fig. 5 is a schematic structural diagram of the adjusting device of the present invention.
In the figure: the device comprises a main board 1, a placement device 2, a buffer device 3, a first fixing device 4, a second fixing device 5, an adjusting device 6, a connecting plate 7, an inclined plate 8, a storage plate 9, a protection plate 10, a support column 11, a hollow column 12, a lifting lug 13, an inclined support plate 14, a support plate 15, a thread block 16, a threaded rod 17, a drill rod 18, a twisting plate 19, a thread column 20, an elliptical plate 21, a ring plate 22, a lug 23 and a handle 24.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Unless otherwise indicated, all references to up, down, left, right, front, back, inner and outer directions herein are to be interpreted as referring to up, down, left, right, front, back, inner and outer directions in the drawings to which the invention is directed.
The invention provides a fixed foldable flood control board as shown in figures 1-5, which comprises a main board 1, a buffer device 3, a first fixing device 4 and a second fixing device 5, wherein the vertical section of the main board 1 is arranged in an L shape, the main board 1 consists of three groups of auxiliary boards which are rotationally connected through spring hinges, the adjacent side surfaces of two adjacent groups of auxiliary boards are respectively bonded with a sealing gasket for sealing, the adjacent side surfaces are bonded with rubber gaskets for providing sealing performance after rotation, the two sides are not sticky, the side surface of the main board 1 is connected with a placing device 2 and the buffer device 3, the placing device 2 is arranged below the buffer device 3, the side surface of the main board 1 far away from the placing device 2 is connected with a plurality of groups of first fixing devices 4 and a plurality of groups of second fixing devices 5, the second fixing device 5 is arranged below the first fixing device 4, and a plurality of groups of connecting threaded holes are dug in the main board 1, and threaded connection has adjusting device 6 in the connecting thread hole, and holistic stability can be promoted in the setting of the left and right sides, plays good flood control effect.
Specifically, placer 2 is including linking board 7, swash plate 8 and putting thing board 9, even board 7 has all been welded to the both sides of swash plate 8, and the even board 7 of top passes through connecting bolt and is connected with mainboard 1, and even board 7 of below passes through connecting bolt and puts thing board 9 and be connected, the multiunit swash plate 8 is putting the equidistant range on putting thing board 9, can place the counter weight thing in putting the horizontal portion of thing board 9 and mainboard 1, promotes stability, and both cooperate, promote the leakproofness.
Specifically, buffer 3 includes guard plate 10, support column 11 and hollow column 12, one side of keeping away from mainboard 1 of guard plate 10 has the rubber slab through the viscose bonding, and guard plate 10 and rubber slab still dig the passageway that is equipped with multiunit rectangle array and arranges, one side fixed weld that guard plate 10 kept away from the rubber slab has the support column 11 that the multiunit is rectangle array and distributes, the side welding of mainboard 1 has the hollow column 12 that multiunit rectangle array arranged, and a side end setting of support column 11 is at the inner chamber of hollow column 12, it has pressure spring to bond between support column 11 and the mainboard 1, and buffer 3 reduces the impact of outside foreign matter, reduces the possibility that mainboard 1 damaged.
Specifically, first fixing device 4 includes lug 13, inclined supporting plate 14 and extension board 15, lug 13 welds the side at mainboard 1, lug 13 is articulated through pivot and inclined supporting plate 14, and the rotation of lug and inclined supporting plate 14 make things convenient for extension board 15 and vertical bolt to connect on the ground of different roughness, the bottom welding of inclined supporting plate 14 has extension board 15, and is provided with the vertical bolt that is used for the connection in the connecting hole that extension board 15 dug established.
Specifically, second fixing device 5 includes screw block 16, threaded rod 17, drilling rod 18 and twist plate 19, the side of screw block 16 and the side of mainboard 1 are fixed through the viscose bonding, screw block 16 digs the vertical screw hole female connection who establishes and has threaded rod 17, the bottom welding of threaded rod 17 has drilling rod 18, the top welding of threaded rod 17 has twist plate 19, and drilling of drilling rod 18 can promote fixed stability.
Specifically, adjusting device 6 includes threaded column 20, elliptical plate 21, ring plate 22 and rubber slab, threaded column 20 and mainboard 1's connecting thread hole threaded connection, threaded column 20's periphery welding has a set of ring plate 22 and two sets of elliptical plate 21, and two sets of elliptical plate 21 set up about threaded column 20 symmetry, ring plate 22 sets up between elliptical plate 21 and mainboard 1, mainboard 1 sets up between ring plate 22 and placer 2, ring plate 22 is close to the side bonding of mainboard 1 and has the rubber slab, seals up waterproofly, and adjusting device 6's dismantlement conveniently carries out the logical water of different degrees, carries out the protection of draining, realizes the needs of different situations.
Specifically, the welding of one side of mainboard 1 has lug 23, the opposite side of mainboard 1 digs the slot that is equipped with lug 23 adaptation, and the inner wall bonding of slot has the rubber pad, promotes stability and leakproofness, reduces the possibility of leaking, the bottom of mainboard 1 also bonds and has the rubber pad, and the L style of calligraphy shape of cooperation main part 1 promotes the leakproofness of the below of mainboard 1.
Specifically, handle 24 has still been welded on mainboard 1's top, and handle 24's periphery bonds and has anti-skidding cover, handle 24's vertical section sets up to the arc, portable, mainboard 1, placer 2 and buffer 3's periphery has all coated waterproof paint, and waterproof paint sets up to Shandong high industry waterproof material limited's acrylic acid waterproof paint.
Specifically, the sealing plate is bonded to the side face of the transverse portion of the main board 1, the bottom end of the sealing plate is flush with the bottom end of the transverse portion of the main board 1, and the side face of the sealing plate is arc-shaped, so that the sealing plate can be conveniently attached to the ground, and good water blocking performance is guaranteed.
Concretely, this fixed folding flood control board, predetermine the assigned position with mainboard 1, then rotate twisting plate 19 and threaded rod 17, make drilling rod 18 bore into ground, realize first heavy fixed, according to the topography, rotate inclined supporting plate 14, and utilize vertical bolt to fix extension board 15 subaerial of needs, realize the second heavy fixed, utilize connecting bolt to connect even board 7 and put thing board 9 at mainboard 1's opposite side, and place nearby counter weight thing (or from taking) on putting the thing board, realize triple fixed, if the interception area is very big, can insert the lug of a set of mainboard 1 in the slot of another set of mainboard 1, make the multiunit whole carry out assembled joint.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (9)

1. The utility model provides a fixed folding flood protection board, includes mainboard (1), buffer (3), first fixing device (4) and second fixing device (5), its characterized in that: the vertical section of mainboard (1) sets up to the L style of calligraphy, mainboard (1) comprises three group spring hinge rotation connected subplates, and the adjacent side of adjacent two sets of subplates all bonds and is used for sealed the pad, the side of mainboard (1) is connected with placer (2) and buffer (3), and placer (2) set up the below in buffer (3), the side that placer (2) were kept away from in mainboard (1) is connected with first fixing device of multiunit (4) and multiunit second fixing device (5), and second fixing device (5) set up the below in first fixing device (4), mainboard (1) is dug and is equipped with multiunit connection screw hole, and connection screw hole female connection has adjusting device (6).
2. A fixed foldable flood barrier according to claim 1, wherein: placer (2) are including linking board (7), swash plate (8) and putting thing board (9), the both sides of swash plate (8) all weld and have linking board (7), and the linking board (7) of top are connected with mainboard (1) through connecting bolt, and even board (7) of below are connected with putting thing board (9) through connecting bolt, and the multiunit swash plate (8) are being put equidistant range on thing board (9).
3. A fixed foldable flood barrier according to claim 1, wherein: buffer (3) are including guard plate (10), support column (11) and hollow column (12), one side of keeping away from mainboard (1) of guard plate (10) is bonded through the viscose has the rubber slab, and guard plate (10) and rubber slab still dig the passageway that is equipped with multiunit rectangle array and arranges, one side fixed weld that the rubber slab was kept away from in guard plate (10) has support column (11) that the multiunit is rectangle array and distributes, the side welding of mainboard (1) has hollow column (12) that multiunit rectangle array arranged, and a side end of support column (11) sets up the inner chamber at hollow column (12), it has pressure spring to bond between support column (11) and mainboard (1).
4. A fixed foldable flood barrier according to claim 1, wherein: first fixing device (4) include lug (13), inclined supporting plate (14) and extension board (15), lug (13) welding is in the side of mainboard (1), lug (13) are articulated through pivot and inclined supporting plate (14), the bottom welding of inclined supporting plate (14) has extension board (15), and is provided with the vertical bolt that is used for connecting in the connecting hole that extension board (15) dug to establish.
5. A fixed foldable flood barrier according to claim 1, wherein: second fixing device (5) are including screw block (16), threaded rod (17), drilling rod (18) and twist board (19), the side of screw block (16) and the side of mainboard (1) are fixed through the viscose bonding, screw block (16) dig the vertical screw hole female connection who establishes have threaded rod (17), the bottom welding of threaded rod (17) has drilling rod (18), the top welding of threaded rod (17) has twist board (19).
6. A fixed foldable flood barrier according to claim 1, wherein: adjusting device (6) are including screw thread post (20), elliptical plate (21), ring board (22) and rubber slab, the connecting thread hole threaded connection of screw thread post (20) and mainboard (1), the periphery welding of screw thread post (20) has a set of ring board (22) and two sets of elliptical plate (21), and two sets of elliptical plate (21) set up about screw thread post (20) symmetry, ring board (22) set up between elliptical plate (21) and mainboard (1), mainboard (1) set up between ring board (22) and placer (2), the side that ring board (22) are close to mainboard (1) bonds there is the rubber slab.
7. A fixed foldable flood barrier according to claim 1, wherein: the welding of one side of mainboard (1) has lug (23), the opposite side of mainboard (1) is dug and is equipped with the slot with lug (23) adaptation, and the inner wall of slot bonds and has the rubber pad, the bottom of mainboard (1) also bonds and has the rubber pad.
8. A fixed foldable flood barrier according to claim 1, wherein: handle (24) still weld on the top of mainboard (1), and the periphery of handle (24) bonds and has anti-skidding cover, the vertical section of handle (24) sets up to the arc, mainboard (1), placer (2) and buffer (3)'s periphery has all been coated with water proof coating.
9. A fixed foldable flood barrier according to claim 1, wherein: and a sealing plate is bonded on the side surface of the transverse part of the main plate (1), the bottom end of the sealing plate is flush with the bottom end of the transverse part of the main plate (1), and the side surface of the sealing plate is in a circular arc shape.
CN202010184802.8A 2020-03-17 2020-03-17 Fixed folding flood control board Pending CN111335256A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010184802.8A CN111335256A (en) 2020-03-17 2020-03-17 Fixed folding flood control board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010184802.8A CN111335256A (en) 2020-03-17 2020-03-17 Fixed folding flood control board

Publications (1)

Publication Number Publication Date
CN111335256A true CN111335256A (en) 2020-06-26

Family

ID=71182461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010184802.8A Pending CN111335256A (en) 2020-03-17 2020-03-17 Fixed folding flood control board

Country Status (1)

Country Link
CN (1) CN111335256A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112761108A (en) * 2020-12-23 2021-05-07 平国文 Water plugging mechanism for flood control
CN113529648A (en) * 2021-07-17 2021-10-22 包文峰 Municipal administration is ponding drainage device for flood discharge
CN115305867A (en) * 2022-08-26 2022-11-08 巢湖市水利建设有限公司 Foldable flood fighting baffle device for hydraulic engineering and flood fighting method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1262602A2 (en) * 2001-05-30 2002-12-04 plettac assco GmbH & Co. KG. Mobile high water protection system
CN106192891A (en) * 2016-08-30 2016-12-07 北京北排装备产业有限公司 A kind of detachable movable anti-flood valve
CN207047784U (en) * 2017-08-11 2018-02-27 温州博富市政建筑工程有限公司 One kind, which is harnessed the river, uses protective plate
CN207159931U (en) * 2017-09-14 2018-03-30 王野 Water uptake expansion bag flood-control water retaining device
CN109083094A (en) * 2018-08-17 2018-12-25 合肥五凡建筑工程有限公司 A kind of flood control water fender of excellent shock resistance
CN109914342A (en) * 2019-04-24 2019-06-21 合肥工业大学 Folding type movable anti-flood wall
CN209619936U (en) * 2019-01-10 2019-11-12 沈瑞海 A kind of water conservancy flood control baffle
CN110700183A (en) * 2019-11-01 2020-01-17 上海市城市建设设计研究总院(集团)有限公司 Foldable assembled self-stabilizing flood prevention blocking drainage facility

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1262602A2 (en) * 2001-05-30 2002-12-04 plettac assco GmbH & Co. KG. Mobile high water protection system
CN106192891A (en) * 2016-08-30 2016-12-07 北京北排装备产业有限公司 A kind of detachable movable anti-flood valve
CN207047784U (en) * 2017-08-11 2018-02-27 温州博富市政建筑工程有限公司 One kind, which is harnessed the river, uses protective plate
CN207159931U (en) * 2017-09-14 2018-03-30 王野 Water uptake expansion bag flood-control water retaining device
CN109083094A (en) * 2018-08-17 2018-12-25 合肥五凡建筑工程有限公司 A kind of flood control water fender of excellent shock resistance
CN209619936U (en) * 2019-01-10 2019-11-12 沈瑞海 A kind of water conservancy flood control baffle
CN109914342A (en) * 2019-04-24 2019-06-21 合肥工业大学 Folding type movable anti-flood wall
CN110700183A (en) * 2019-11-01 2020-01-17 上海市城市建设设计研究总院(集团)有限公司 Foldable assembled self-stabilizing flood prevention blocking drainage facility

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112761108A (en) * 2020-12-23 2021-05-07 平国文 Water plugging mechanism for flood control
CN113529648A (en) * 2021-07-17 2021-10-22 包文峰 Municipal administration is ponding drainage device for flood discharge
CN113529648B (en) * 2021-07-17 2022-09-20 新疆凯悦鑫工程建设有限责任公司 Municipal administration is ponding drainage device for flood discharge
CN115305867A (en) * 2022-08-26 2022-11-08 巢湖市水利建设有限公司 Foldable flood fighting baffle device for hydraulic engineering and flood fighting method thereof
CN115305867B (en) * 2022-08-26 2023-11-14 巢湖市水利建设有限公司 Foldable flood fighting baffle device for hydraulic engineering and flood fighting method thereof

Similar Documents

Publication Publication Date Title
CN111335256A (en) Fixed folding flood control board
CN207659983U (en) A kind of steel-pipe pile steel construction cushion cap tower crane foundation structure
CN207362792U (en) A kind of construction of hydro project water baffle plate device
CN217267667U (en) Bottom sealing-free steel crane bottom plate plugging device
CN106368174A (en) Rotary hinge type drain grating floating gate
CN214993544U (en) Slope protection net structure for hydraulic engineering
CN206844769U (en) New mobile type anti-flood wall
CN211550749U (en) Building engineering preprocessing pipeline based on BIM technology
CN208088156U (en) A kind of assembly type highway Air Filter that can be reused
CN208650490U (en) A kind of water conservancy and hydropower foundation grouting supervising platform
CN207775827U (en) A kind of novel floating groove repaiies canal device
CN212203386U (en) A water conservancy pipeline supports connection structure for hydraulic engineering
CN206245286U (en) A kind of turning hinge formula blocks dirty drift row
CN207032338U (en) A kind of swing arm of excavator
CN201091053Y (en) Wiring equipment for laying underground cable
CN213508636U (en) One-time excavation molding bucket for ditch at any angle
CN214656802U (en) Water conservancy flood control slope protection structure
CN110552626B (en) Engineering driller drill boom structure
CN218950727U (en) Construction elevator protector
CN213442995U (en) Fixed effectual suspension isolation ball for traffic engineering construction on water
CN215718501U (en) Integral winch mounting structure of rotary drilling rig
CN212270821U (en) Hydraulic engineering is with emergent wall component that blocks water
CN114855833B (en) Engineering protective structure is administered to geological disaster
CN206554938U (en) A kind of simple and practical shield machine articulated mounting
CN214738342U (en) Bucket structure with adjustable slope angle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200626