CN111309129B - Remote resetting method and system for automatic startup failure of well site data acquisition unit - Google Patents

Remote resetting method and system for automatic startup failure of well site data acquisition unit Download PDF

Info

Publication number
CN111309129B
CN111309129B CN202010074199.8A CN202010074199A CN111309129B CN 111309129 B CN111309129 B CN 111309129B CN 202010074199 A CN202010074199 A CN 202010074199A CN 111309129 B CN111309129 B CN 111309129B
Authority
CN
China
Prior art keywords
collector
remote
state
automatic
well site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010074199.8A
Other languages
Chinese (zh)
Other versions
CN111309129A (en
Inventor
钱浩东
罗月
张治发
何恩鹏
张果
张娟
谢寅溥
宋鑫
温馨
乔李华
雍鹏
李翼杉
黄微
刘洋
陈星玮
冉桂东
张圣
杨明富
吴敬恒
刘素君
齐玉
李杨鹏程
王楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Chuanqing Drilling Engineering Co Ltd
Original Assignee
China National Petroleum Corp
CNPC Chuanqing Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Petroleum Corp, CNPC Chuanqing Drilling Engineering Co Ltd filed Critical China National Petroleum Corp
Priority to CN202010074199.8A priority Critical patent/CN111309129B/en
Publication of CN111309129A publication Critical patent/CN111309129A/en
Application granted granted Critical
Publication of CN111309129B publication Critical patent/CN111309129B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/26Power supply means, e.g. regulation thereof
    • G06F1/266Arrangements to supply power to external peripherals either directly from the computer or under computer control, e.g. supply of power through the communication port, computer controlled power-strips
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Power Sources (AREA)
  • Debugging And Monitoring (AREA)

Abstract

The invention discloses a remote resetting method and a remote resetting system for automatic startup failure of a well site data acquisition unit; the method comprises an automatic starting step and a remote resetting step; the automatic starting-up step comprises the following steps: the local operation management controller monitors the power state of the collector, monitors the starting state of a host computer of the collector, monitors whether an operating system of the collector operates normally, and performs starting or restarting control according to monitoring information; the remote reset step comprises the following steps: the remote management operation platform confirms a system reset flow and issues a reset control instruction to the local operation management controller; the local operation management controller monitors whether the power index of the collector and the start-up indicator lamp are normal or not, and carries out reset control according to the power index and the start-up indicator lamp. According to the invention, after the continuous repeated automatic startup of the well site collector fails, the remote reset control is performed, so that the abnormal protection and locking of the collector are avoided, and compared with the traditional field maintenance method, the labor cost is reduced.

Description

Remote resetting method and system for automatic startup failure of well site data acquisition unit
Technical Field
The invention relates to well site data acquisition, in particular to a remote resetting method and a remote resetting system for automatic startup failure of a well site data acquisition device.
Background
Along with the continuous improvement of the technology level, a plurality of oil gas production enterprises in recent years provide intelligent development directions of oil field construction. The primary acquisition data (data information such as temperature, pressure, electric parameters, work patterns and the like of various equipment of the well site) of the well site in the oil field is used as a basis of a digital oil field, and the bottommost data support is provided for the early warning and control of the subsequent oil field and meeting various requirements in the oil field production, so that the data acquisition device of the well site is needed.
Under normal conditions, the well site data collector has the function of automatic startup and operation of incoming calls, and the automatic operation capability of unmanned supervision is ensured. According to regional operation and maintenance personnel feedback of a user: the collector can be locked due to system protection caused by external reasons, and operation and maintenance personnel are required to go to the site for recovery processing. The personnel maintenance cost is high, the long-distance aging is low, and the untimely finding is not considered factors.
Disclosure of Invention
The invention aims to overcome the defects of the prior art, and provides a remote reset method and a remote reset system for automatic startup failure of a well site data acquisition unit.
The aim of the invention is realized by the following technical scheme: the remote reset method for the automatic start failure of the well site data collector comprises the steps that when the well site data collector works normally, an external power supply supplies power, and when the external power supply is abnormally powered off for many times, a power supply provided by a ROM battery enables a system of the well site data collector to generate a protection locking instruction, and the well site data collector cannot be started; after the ROM battery is disconnected for a set time, the locking instruction is cleared, and the remote resetting method comprises an automatic starting step and a remote resetting step;
the automatic starting-up step comprises
S01, monitoring an external power supply state of a collector by a local operation management controller:
if the external power supply state is abnormal, after the power supply state is normal, controlling the collector to execute automatic starting operation;
if the external power supply state is normal, directly controlling the collector to execute automatic starting operation;
s102, monitoring a host starting state of a collector by a local operation management controller:
if the power-on is not started, the output signal triggers the acquisition unit to restart, the remote management operation platform is reported after the continuous 3 times of power-on failure, and the remote reset step is carried out;
if the power is turned on, the step S103 is entered;
s103, the local operation management controller monitors whether the collector operating system operates in a normal state:
if the operation system of the collector operates normally, entering a monitoring mode, monitoring the operation state of the collector in real time, and reporting to a remote management operation platform;
if the operation of the collector operating system is abnormal, entering an automatic restarting mode, controlling the collector to restart automatically, after 3 times of automatic restarting, stopping the automatic restarting process, and reporting to a remote management operation platform;
the remote reset step comprises the following steps:
s201, the remote management operation platform confirms a system reset flow and issues a reset control instruction to the local operation management controller;
s202, monitoring the external power state of the collector by a local operation management controller, and judging whether a startup indicator lamp is normal or not;
if the external power state is normal and the starting signal of the collector is normal, the collector is controlled to enter an automatic restarting process again, and the step S103 is returned to wait for monitoring the running condition of the operating system of the collector;
if the external power state is normal and the collector start-up indication signal is abnormal, entering step S203;
s203, monitoring the power state of the collector again, if the power state is normal, entering a step S204, otherwise, stopping the action, and returning to the step S202;
s204, monitoring the key state of the collector by the local operation management controller, and when the key state is at a preset value:
controlling the ROM battery to be disconnected for a set number of minutes, and then recovering the battery, and executing automatic starting operation; and after the collector equipment is normally started and runs normally, delaying a set time, and resetting the times of startup failure and the times of automatic restarting of the system.
Preferably, the external power supply state includes a power supply state of external 220V mains supply and a power supply state of an external lithium battery pack:
if the 220V commercial power and the lithium battery pack cannot supply power, the external power supply state is abnormal;
if any one of the 220V commercial power and the lithium battery pack can supply power, the external power supply is considered to be in a normal state;
reasons why the lithium battery pack cannot supply power include: the lithium battery pack is disconnected with the well site data acquisition unit and the lithium battery pack has insufficient electric quantity; the reason why 220V mains supply cannot supply power is as follows: and is disconnected with the well site data collector.
In the well site data collector, a ROM battery is externally connected with a main board by adopting a cable, a connecting wire is provided with an MOS electric control switch, and the operation management controller is used for controlling the automatic reset and the automatic start-up functions.
The remote reset method further comprises a client query control step:
accessing a remote management operation platform through a remote management client installed in the intelligent equipment, and remotely inquiring and displaying the state of the collector; or the remote management client sets a management control instruction and issues the management control instruction through the remote management operation platform.
A system adopted by a remote reset method for automatic startup failure of a well site data acquisition unit comprises the well site data acquisition unit, a local operation control manager, a remote operation management platform and a remote management client;
the local operation controller is used for interacting with the well site data collector, automatically starting up the well site data collector, monitoring the power state information and the operating system information of the well site data collector in the automatic starting up process, judging whether the automatic starting up is successful according to the power state information and the operating system information, reporting the remote management operation platform when continuous automatic starting up fails, and carrying out resetting control on the well site data collector according to a remote resetting control instruction of the remote management operation platform and combining with a collector power index and a starting-up indicator lamp;
the remote operation management platform is used for receiving and storing the information uploaded by the local operation controller, confirming a system reset flow when receiving the information of continuous startup failure, generating a remote reset control instruction and transmitting the remote reset control instruction to the local operation controller;
the remote management client is used for a user to access the remote management operation platform and remotely inquiring and displaying the state of the collector; or the remote management client sets a management control instruction and issues the management control instruction through the remote management operation platform.
The beneficial effects of the invention are as follows: according to the invention, after the continuous repeated automatic startup of the well site collector fails, the remote reset control is performed, so that the abnormal protection and locking of the collector are avoided, and compared with the traditional field maintenance method, the labor cost is reduced.
Drawings
FIG. 1 is a flow chart of the method of the present invention;
fig. 2 is a system schematic block diagram of the present invention.
Detailed Description
The technical solution of the present invention will be described in further detail with reference to the accompanying drawings, but the scope of the present invention is not limited to the following description.
As shown in fig. 1, a remote reset method for automatic startup failure of a well site data collector is provided, when the well site data collector works normally, an external power supply supplies power, when the external power supply is abnormally powered off for a plurality of times, a power supply provided by a ROM battery enables a system of the well site data collector to generate a protection locking instruction, and the well site data collector cannot be started up; after the ROM battery is disconnected for a set time, the locking instruction is cleared, and the remote resetting method comprises an automatic starting step and a remote resetting step;
the automatic starting-up step comprises
S01, monitoring an external power supply state of a collector by a local operation management controller:
if the external power supply state is abnormal, after the power supply state is normal, controlling the collector to execute automatic starting operation;
if the external power supply state is normal, directly controlling the collector to execute automatic starting operation;
s102, monitoring a host starting state of a collector by a local operation management controller:
if the power-on is not started, the output signal triggers the acquisition unit to restart, the remote management operation platform is reported after the continuous 3 times of power-on failure, and the remote reset step is carried out;
if the power is turned on, the step S103 is entered;
s103, the local operation management controller monitors whether the collector operating system operates in a normal state:
if the operation system of the collector operates normally, entering a monitoring mode, monitoring the operation state of the collector in real time, and reporting to a remote management operation platform;
if the operation of the collector operating system is abnormal, entering an automatic restarting mode, controlling the collector to restart automatically, after 3 times of automatic restarting, stopping the automatic restarting process, and reporting to a remote management operation platform; this is an operating system problem that requires the operator of the management platform to schedule operating system remote or near field maintenance tasks.
The remote reset step comprises the following steps:
s201, the remote management operation platform confirms a system reset flow and issues a reset control instruction to the local operation management controller;
s202, monitoring the external power state of the collector by a local operation management controller, and judging whether a startup indicator lamp is normal or not;
if the external power state is normal and the starting signal of the collector is normal, the collector is controlled to enter an automatic restarting process again, and the step S103 is returned to wait for monitoring the running condition of the operating system of the collector;
if the external power state is normal and the collector start-up indication signal is abnormal, entering step S203;
s203, monitoring the power state of the collector again, if the power state is normal, entering a step S204, otherwise, stopping the action, and returning to the step S202;
s204, monitoring the key state of the collector by the local operation management controller, and when the key state is at a preset value:
controlling the ROM battery to be disconnected for a set number of minutes, and then recovering the battery, and executing automatic starting operation; and after the collector equipment is normally started and runs normally, resetting the times of startup failure and the times of automatic restarting of the system after a set time is delayed.
Preferably, the external power supply state includes a power supply state of external 220V mains supply and a power supply state of an external lithium battery pack:
if the 220V commercial power and the lithium battery pack cannot supply power, the external power supply state is abnormal;
if any one of the 220V commercial power and the lithium battery pack can supply power, the external power supply is considered to be in a normal state;
reasons why the lithium battery pack cannot supply power include: the lithium battery pack is disconnected with the well site data acquisition unit and the lithium battery pack has insufficient electric quantity; the reason why 220V mains supply cannot supply power is as follows: and is disconnected with the well site data collector.
In the well site data collector, a ROM battery is externally connected with a main board by adopting a cable, a connecting wire is provided with an MOS electric control switch, and the operation management controller is used for controlling the automatic reset and the automatic start-up functions.
The remote reset method further comprises a client query control step:
accessing a remote management operation platform through a remote management client installed in the intelligent equipment, and remotely inquiring and displaying the state of the collector; or the remote management client sets a management control instruction and issues the management control instruction through the remote management operation platform.
As shown in fig. 2, a system adopted by a remote reset method for automatic startup failure of a well site data acquisition unit comprises the well site data acquisition unit, a local operation control manager, a remote operation management platform and a remote management client;
the local operation controller is used for interacting with the well site data collector, automatically starting up the well site data collector, monitoring the power state information and the operating system information of the well site data collector in the automatic starting up process, judging whether the automatic starting up is successful according to the power state information and the operating system information, reporting the remote management operation platform when continuous automatic starting up fails, and carrying out resetting control on the well site data collector according to a remote resetting control instruction of the remote management operation platform and combining with a collector power index and a starting-up indicator lamp;
the remote operation management platform is used for receiving and storing the information uploaded by the local operation controller, confirming a system reset flow when receiving the information of continuous startup failure, generating a remote reset control instruction and transmitting the remote reset control instruction to the local operation controller;
the remote management client is used for a user to access the remote management operation platform and remotely inquiring and displaying the state of the collector; or the remote management client sets a management control instruction and issues the management control instruction through the remote management operation platform.
According to the invention, after the continuous and repeated automatic startup of the well site collector fails, the remote reset control is performed, so that the abnormal protection and locking of the collector are avoided.
The foregoing is a preferred embodiment of the invention, and it is to be understood that the invention is not limited to the form disclosed herein, but is not to be construed as limited to other embodiments, but is capable of other combinations, modifications and environments and is capable of changes or modifications within the scope of the inventive concept, either as a result of the foregoing teachings or as a result of the knowledge or knowledge of the relevant art. And that modifications and variations which do not depart from the spirit and scope of the invention are intended to be within the scope of the appended claims.

Claims (4)

1. A remote resetting method for automatic startup failure of a well site data acquisition unit is characterized in that: when the external power supply is abnormally powered off for a plurality of times, the power supply provided by the ROM battery enables a system of the well site data acquisition unit to generate a protection locking instruction, and the well site data acquisition unit cannot be started; after the ROM battery is disconnected for a set time, the locking instruction is cleared, and the remote resetting method comprises an automatic starting step and a remote resetting step;
the automatic starting-up step comprises
S01, monitoring an external power supply state of a collector by a local operation management controller:
if the external power supply state is abnormal, after the power supply state is normal, controlling the collector to execute automatic starting operation;
if the external power supply state is normal, directly controlling the collector to execute automatic starting operation;
s102, monitoring a host starting state of a collector by a local operation management controller:
if the power-on is not started, the output signal triggers the acquisition unit to restart, the remote management operation platform is reported after the continuous 3 times of power-on failure, and the remote reset step is carried out;
if the power is turned on, the step S103 is entered;
s103, the local operation management controller monitors whether the collector operating system operates in a normal state:
if the operation system of the collector operates normally, entering a monitoring mode, monitoring the operation state of the collector in real time, and reporting to a remote management operation platform;
if the operation of the collector operating system is abnormal, entering an automatic restarting mode, controlling the collector to restart automatically, after 3 times of automatic restarting, stopping the automatic restarting process, and reporting to a remote management operation platform;
the remote reset step comprises the following steps:
s201, the remote management operation platform confirms a system reset flow and issues a reset control instruction to the local operation management controller;
s202, monitoring the external power state of the collector by a local operation management controller, and judging whether a startup indicator lamp is normal or not;
if the external power state is normal and the starting signal of the collector is normal, the collector is controlled to enter an automatic restarting process again, and the step S103 is returned to wait for monitoring the running condition of the operating system of the collector;
if the external power state is normal and the collector start-up indication signal is abnormal, entering step S203;
s203, monitoring the power state of the collector again, if the power state is normal, entering a step S204, otherwise, stopping the action, and returning to the step S202;
s204, monitoring the key state of the collector by the local operation management controller, and when the key state is at a preset value:
controlling the ROM battery to be disconnected for a set number of minutes, and then recovering the battery, and executing automatic starting operation; after the collector equipment is normally started and runs normally, delaying a set time, and resetting the times of startup failure and the times of automatic restarting of the system;
the external power supply state comprises a power supply state of external 220V mains supply and a power supply state of an external lithium battery pack:
if the 220V commercial power and the lithium battery pack cannot supply power, the external power supply state is abnormal;
if any one of the 220V commercial power and the lithium battery pack can supply power, the external power supply is considered to be in a normal state;
reasons why the lithium battery pack cannot supply power include: the lithium battery pack is disconnected with the well site data acquisition unit and the lithium battery pack has insufficient electric quantity; the reason why 220V mains supply cannot supply power is as follows: and is disconnected with the well site data collector.
2. The remote reset method for automatic power-on failure of a wellsite data collector of claim 1, wherein the method comprises the steps of: in the well site data collector, a ROM battery is externally connected with a main board by adopting a cable, a connecting wire is provided with an MOS electric control switch, and the local operation management controller is used for controlling the automatic reset and the automatic start-up functions.
3. The remote reset method for automatic power-on failure of a wellsite data collector of claim 1, wherein the method comprises the steps of: the remote reset method further comprises a client query control step:
accessing a remote management operation platform through a remote management client installed in the intelligent equipment, and remotely inquiring and displaying the state of the collector; or the remote management client sets a management control instruction and issues the management control instruction through the remote management operation platform.
4. A system for a remote reset method for automatic power failure of a wellsite data collector according to any one of claims 1-3, wherein: the system comprises a well site data acquisition unit, a local operation control manager, a remote operation management platform and a remote management client;
the local operation management controller is used for interacting with the well site data collector, automatically starting up the well site data collector, monitoring the power state information and the operating system information of the well site data collector in the automatic starting up process, judging whether the automatic starting up is successful according to the power state information and the operating system information, reporting the remote management operation platform when continuous automatic starting up fails, and carrying out resetting control on the well site data collector according to a remote resetting control instruction of the remote management operation platform and by combining a collector power index and a starting-up indicator lamp;
the remote operation management platform is used for receiving and storing the information uploaded by the local operation management controller, confirming a system reset flow when receiving the information of continuous startup failure, generating a remote reset control instruction and transmitting the remote reset control instruction to the local operation management controller;
the remote management client is used for a user to access the remote management operation platform and remotely inquiring and displaying the state of the collector; or the remote management client sets a management control instruction and issues the management control instruction through the remote management operation platform.
CN202010074199.8A 2020-01-22 2020-01-22 Remote resetting method and system for automatic startup failure of well site data acquisition unit Active CN111309129B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010074199.8A CN111309129B (en) 2020-01-22 2020-01-22 Remote resetting method and system for automatic startup failure of well site data acquisition unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010074199.8A CN111309129B (en) 2020-01-22 2020-01-22 Remote resetting method and system for automatic startup failure of well site data acquisition unit

Publications (2)

Publication Number Publication Date
CN111309129A CN111309129A (en) 2020-06-19
CN111309129B true CN111309129B (en) 2023-06-30

Family

ID=71148992

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010074199.8A Active CN111309129B (en) 2020-01-22 2020-01-22 Remote resetting method and system for automatic startup failure of well site data acquisition unit

Country Status (1)

Country Link
CN (1) CN111309129B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112269331A (en) * 2020-09-24 2021-01-26 中国石油天然气股份有限公司 Oil well site digital equipment fault recovery system and recovery method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003076751A (en) * 2001-09-03 2003-03-14 Yanmar Co Ltd Control system for remote monitoring for cooling container
JP2003316466A (en) * 2002-04-25 2003-11-07 Sharp Corp Information processing system and resetting method therefor
CN102148841A (en) * 2010-02-05 2011-08-10 中国长城计算机深圳股份有限公司 Method for remotely monitoring multiple operating systems
CN108885484A (en) * 2016-03-29 2018-11-23 日本电气株式会社 Remote terminal equipment, its control method, computer system and program

Family Cites Families (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57187703A (en) * 1981-05-13 1982-11-18 Matsushita Electric Ind Co Ltd Program controller for equipment
JPH0553672A (en) * 1991-08-23 1993-03-05 Toshiba Corp Computer system
JPH1049450A (en) * 1996-07-31 1998-02-20 Kyocera Corp Recovery system for abnormal time of remote monitor system
JPH10111737A (en) * 1996-10-09 1998-04-28 Nec Home Electron Ltd Resetting device
JP2002055741A (en) * 2000-08-11 2002-02-20 Toshiba Tec Corp Power source managing device
JP3465674B2 (en) * 2000-09-08 2003-11-10 株式会社ニプロン Unit insertion / removal structure for uninterruptible redundant power supply
JP2003316465A (en) * 2002-04-25 2003-11-07 Canon Inc Network device control device, network device control method and program for realizing the same
JP2005202549A (en) * 2004-01-14 2005-07-28 Nec Corp Reset circuit and reset method
US8843241B2 (en) * 2008-05-20 2014-09-23 LiveMeters, Inc. Remote monitoring and control system comprising mesh and time synchronization technology
KR101782137B1 (en) * 2010-11-08 2017-09-27 삼성전자주식회사 Power on reset circuit
CN103176873A (en) * 2011-12-23 2013-06-26 鸿富锦精密工业(深圳)有限公司 Counting card
CN102693164B (en) * 2012-05-03 2014-09-17 中国石油集团川庆钻探工程有限公司地球物理勘探公司 Equipment and method for preventing buffer overflow
CN102841589B (en) * 2012-09-17 2015-04-01 广州市怡文环境科技股份有限公司 Remote intelligent maintenance system for online environment monitoring instrument
CN104699215A (en) * 2013-12-04 2015-06-10 鸿富锦精密电子(天津)有限公司 Power supply protection system and power supply protection method
CN105137898A (en) * 2015-08-27 2015-12-09 国网新疆电力公司昌吉供电公司 Unmanned substation monitoring host restart system and restart method
CN105387944A (en) * 2015-11-04 2016-03-09 南京富岛信息工程有限公司 Fault elimination method of modem of infrared journal temperature detection system
CN207301719U (en) * 2017-09-18 2018-05-01 内蒙古自治区大气探测技术保障中心 Remote controllers and automatic weather station
CN107942775A (en) * 2017-10-18 2018-04-20 安徽蓝盾光电子股份有限公司 A kind of laser radar intelligent starting and loss protecting system
CN108196484A (en) * 2018-01-22 2018-06-22 珠海格力电器股份有限公司 Display panel control method, device and system, display panel and equipment unit

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003076751A (en) * 2001-09-03 2003-03-14 Yanmar Co Ltd Control system for remote monitoring for cooling container
JP2003316466A (en) * 2002-04-25 2003-11-07 Sharp Corp Information processing system and resetting method therefor
CN102148841A (en) * 2010-02-05 2011-08-10 中国长城计算机深圳股份有限公司 Method for remotely monitoring multiple operating systems
CN108885484A (en) * 2016-03-29 2018-11-23 日本电气株式会社 Remote terminal equipment, its control method, computer system and program

Also Published As

Publication number Publication date
CN111309129A (en) 2020-06-19

Similar Documents

Publication Publication Date Title
CN109445981B (en) Computer running state monitoring device
CN110045719B (en) Remote fault diagnosis method
CN104454198B (en) Generating set Intelligent integrated formula controller and control method thereof
CN105680566A (en) Dispatching data network-based restarting device and restarting method for fault recording device
CN111608733A (en) Unattended safety early warning system for underground coal mine drainage system
CN111309129B (en) Remote resetting method and system for automatic startup failure of well site data acquisition unit
CN105020045A (en) Controller with CAN bus
CN111341063A (en) Intelligent control system, method and device for safety early warning and monitoring of electric equipment and terminal equipment
CN113404679A (en) Centralized control system for coal mine ground air compressor
CN111668940A (en) Power station control system and control method
CN204851453U (en) Take controller of CAN bus
CN104898509A (en) Industrial control computer monitoring method and system based on secure short message
CN107102633B (en) A kind of distribution terminal fault self-diagnosis method and system
CN103001323B (en) Relay and data processing method
CN112350307A (en) Control method and control device for regional distribution network and computer readable storage medium
CN205429888U (en) Device that restarts of ripples device is recorded to trouble based on dispatching data network
CN109656213B (en) Man-machine interface system with power-loss protection mechanism and distributed control system
CN204116904U (en) Diesel generator set microcomputer removing supervise control system
CN109299874A (en) A kind of PMS power management system and method, information data processing terminal
CN111176194A (en) Delayed soft-off protection method for well site data acquisition unit system
CN114204679A (en) Power guarantee method and equipment for communication base station
CN113225216A (en) Method for automatically restarting data transmission exchanger and data transmission exchange device
CN113098698A (en) Communication recovery method, equipment, storage medium and communication interruption restarting device
CN112510823A (en) Power supply remote control system
CN107505900B (en) Method for controlling energy of remote equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20210202

Address after: 100007 No. 9 North Main Street, Dongcheng District, Beijing, Dongzhimen

Applicant after: CHINA NATIONAL PETROLEUM Corp.

Applicant after: CNPC CHUANQING DRILLING ENGINEERING Co.,Ltd.

Address before: 618399 south 2nd section of Zhongshan Avenue, Guanghan City, Deyang City, Sichuan Province

Applicant before: CNPC CHUANQING DRILLING ENGINEERING Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant