CN1112485C - Cast-in-situ method for forming piles by drilling hole and pouring grout - Google Patents

Cast-in-situ method for forming piles by drilling hole and pouring grout Download PDF

Info

Publication number
CN1112485C
CN1112485C CN99108024A CN99108024A CN1112485C CN 1112485 C CN1112485 C CN 1112485C CN 99108024 A CN99108024 A CN 99108024A CN 99108024 A CN99108024 A CN 99108024A CN 1112485 C CN1112485 C CN 1112485C
Authority
CN
China
Prior art keywords
hole
grout
drilling
pouring
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN99108024A
Other languages
Chinese (zh)
Other versions
CN1240860A (en
Inventor
张树峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN99108024A priority Critical patent/CN1112485C/en
Publication of CN1240860A publication Critical patent/CN1240860A/en
Application granted granted Critical
Publication of CN1112485C publication Critical patent/CN1112485C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a method for forming piles by drilling hole and pouring grout, which comprises the following steps: drilling to designed depth; injecting slow-setting cement grout to a hole bottom via a grouting hole arranged on a drill bit before a drill is lifted; injecting grout while evenly lifting the drill; grouting to positions without diameter reduction and collapse danger; after a drilling rod is completely lifted out, putting a reinforcing cage into the hole; then, pouring concrete into the hole, and simultaneously, recovering the slow-setting cement grout for circularly using. The present invention can improve and enhance the mechanical properties of earth bodies, ensure the quality of steel reinforced concrete on a pile body and a pile end, largely save cement content, and reduce engineering cost.

Description

Cast-in-situ method for forming piles by drilling hole and pouring grout
The present invention relates to a kind of cast-in-situ method for forming piles by drilling hole and pouring grout, mainly supply in the engineerings such as ground stabilization, pattern foundation pit supporting structure, pile foundation, transportation and energy's harbour and reservoir leak stopping, be used for forming reinforced concrete pile or form diaphragm wall by annotating stake.
On October 12nd, 1987, bore slurry pressuring pile-forming (patent No. is 86100705, and the applying date is 860125) was announced in authorization.Be bored into desired depth, carry brill and spray light water mud by the nozzle that is located on the drill bit to the hole inner high voltage simultaneously, to the slurries face reach do not have a hole danger position that collapses till, in the hole, place reinforcing cage after pulling out of hole, throw full pellet, and put into Grouting Pipe at the bottom of at least one clear opening and make the 2nd sub-high pressure and mend slurry, arrive the aperture to slurries till.Its weak point is: the input pellet is a coarse aggregate, and coarse aggregate influences the bonding of itself and cement outward for foreign material such as soil, stone flour, and pile body is a non-fine concrete, thereby causes the intensity of pile body low bigger with fragility; Again because pile crown place grouting pressure reduces, and impurity is many and be difficult for getting rid of in the cement paste, thereby cause the pile crown place easily broken, loose and intensity is lower; Also, cause the cement paste consumption big, thereby cause the wasting of resources and cost height owing to throw in coarse aggregate and high pressure injection benefit slurry.
The objective of the invention is to overcome above-mentioned weak point of the prior art and provide a kind of on soft the moulding, quicksand, high underground water, easily collapse under the various complex geological conditions such as hole pore-forming pile, pile body smoothly and surrounding soil is combined closely, cost is lower and can guarantee the cast-in-situ method for forming piles by drilling hole and pouring grout of quality.
Purpose of the present invention can reach by following measure: be bored into projected depth, before carrying brill, go into the retarded cement slurries to the hole rising pouring by the injected hole that is located on the drill bit, brill is evenly carried on marginal not slurry limit, slip casting does not extremely take place till the position of the undergauge and the hole danger of collapsing, drilling rod proposes the back fully and put into reinforcing cage in the hole, concrete perfusion in the hole then, reclaim the retarded cement slurries simultaneously, in order to recycling, the height of going into the retarded cement slurries to the hole rising pouring equals stake 5-8 directly doubly, annotates the extended slurry liquid level when carrying brill and needs 3-5 rice on drill bit.
The grouting amount that injects the retarded cement slurries be the 0.3-0.5 cubic meter/minute.
The invention will be further described below in conjunction with embodiment:
Earlier be bored into projected depth with existing rig with by existing boring method, before carrying brill, go into to be equivalent to the directly retarded cement slurries of 5-10 (being preferably 5-8) double-length degree of stake to the hole rising pouring by the injected hole on the drill bit, brill is evenly carried on marginal not slurry limit then, carrying when boring liquid level must remain on the drill bit about 3-5 rice, slip casting is to there not being undergauge to collapse till the danger position of hole, drilling rod proposes the back fully and put into reinforcing cage in the hole, use concrete perfusion at the bottom of the hole of existing notes bucket deferent in reinforcing cage again, the marginal not limit is carried and is annotated the bucket deferent to the aperture, receive the retarded cement slurries with blowback simultaneously, in order to recycling.
Variation according to formation condition, grouting pressure changes in father-in-law's 5-100 jin/square thick rice, grouting amount is more than per minute 0.3-0.5 cubic meter, and retarded cement slurries setting time 8-12 (being preferably 7-10) hour, the concrete perfusion strength grade was by designing requirement.
Embodiments of the invention: pour into 600 millimeters, long 27 meters reinforced concrete foundation stake, geological conditions is that 0-6.0 rice is miscellaneous fill and silt, 6.0-13.1 rice is silty clay and clay, 13.1-29.0 be flour sand, underground is a underground water for 2 meters, is the artesian water of 8.5 heads below 7 meters.The retarded cement slurries consist of the retardation water reducing agent of No. 425 cement+cement weights 0.5%, and water/binder ratio is 0.5-0.6, and slurries are annotated the aperture, perfusion C25 concrete, and with the accumulation load method test, ultimate bearing capacity of single pile is 4400KN at last.
The present invention contrasts prior art and has following advantage: because slow-setting cement grout is under pressure to stake end and stake The expansion of week soil oozes, compacted, full, reinforcing and retaining wall effect, improved the mechanical property of the soil body, quicksand, Soft mould under the complex geological conditions such as soil, underground high artesian all can pile, and concrete perfusion is design strength, has guaranteed Pile quality, pile concrete was upward combined closely by slow-setting cement grout with an end and stake week simultaneously, avoided because of perfusion Concrete shrinkage and the problems such as the space constriction that causes and fracture, stake end bearing capacity and side friction improve greatly, The pile body actual strength is guaranteed. The slow-setting cement grout setting time can be cycled to repeat use at 7-12 hour, and is big Saved greatly cement consumption, prior art is every cubic meter of concrete cement 0.9-1.9 ton, and the present invention only needs 0.4 ton About. Reduce cost, avoided waste, improved economic benefit. Therefore the present invention has wide adaptability, bearing capacity High, cost is low and the pile strength advantages of higher.

Claims (2)

1, a kind of cast-in-situ method for forming piles by drilling hole and pouring grout, be bored into projected depth, go into the retarded cement slurries by the injected hole that is located on the drill bit to the hole rising pouring before carrying brill, brill is evenly carried on marginal not slurry limit, and slip casting does not extremely take place till the position of the undergauge and the hole danger of collapsing, drilling rod proposes the back fully and put into reinforcing cage in the hole, concrete perfusion in the hole reclaims the retarded cement slurries simultaneously then, in order to recycling, it is characterized in that the height of going into the retarded cement slurries to the hole rising pouring equals stake 5-8 directly doubly.Annotate the extended slurry liquid level when carrying brill and need 3-5 rice on drill bit.
2, cast-in-situ method for forming piles by drilling hole and pouring grout according to claim 1 is characterized in that, the grouting amount that injects the retarded cement slurries be the 0.3-0.5 cubic meter/minute.
CN99108024A 1999-06-07 1999-06-07 Cast-in-situ method for forming piles by drilling hole and pouring grout Expired - Fee Related CN1112485C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN99108024A CN1112485C (en) 1999-06-07 1999-06-07 Cast-in-situ method for forming piles by drilling hole and pouring grout

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN99108024A CN1112485C (en) 1999-06-07 1999-06-07 Cast-in-situ method for forming piles by drilling hole and pouring grout

Publications (2)

Publication Number Publication Date
CN1240860A CN1240860A (en) 2000-01-12
CN1112485C true CN1112485C (en) 2003-06-25

Family

ID=5273082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN99108024A Expired - Fee Related CN1112485C (en) 1999-06-07 1999-06-07 Cast-in-situ method for forming piles by drilling hole and pouring grout

Country Status (1)

Country Link
CN (1) CN1112485C (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1306121C (en) * 2004-08-05 2007-03-21 陈佳训 Method for pile foundation construction of geologic structure with flow plastic half-flow plastic and its application apparatus
CN100447347C (en) * 2003-11-26 2008-12-31 株式会社丸德基业 Construction method of cement earth pile

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100335257C (en) * 2004-05-09 2007-09-05 中山市三和建材有限公司 Novel circulating use method for residual grout of PHC pipe pile
CN101713189B (en) * 2008-10-06 2012-10-17 吴保全 Construction process of floral tube dry filling piles
CN105862990B (en) * 2016-03-24 2019-05-24 上海市机械施工集团有限公司 A kind of prefabrication and assembly construction shaft wall structure and its construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
化学建材1996年第4期 1996-01-01 "CLB型超流态混凝土泵剂"赵炎龙 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100447347C (en) * 2003-11-26 2008-12-31 株式会社丸德基业 Construction method of cement earth pile
CN1306121C (en) * 2004-08-05 2007-03-21 陈佳训 Method for pile foundation construction of geologic structure with flow plastic half-flow plastic and its application apparatus

Also Published As

Publication number Publication date
CN1240860A (en) 2000-01-12

Similar Documents

Publication Publication Date Title
AU2020376449B2 (en) Construction method of pressurized grouting pile based on reinforcing fiber and metakaolin
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN101806059B (en) Drilling, grouting and sand-throwing process of ground surface of mined-out region under highway
CN104612134A (en) Cast-in place pile post-grouting construction method for pouring construction
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN110374134A (en) A kind of combined member increased suitable for retaining wall and construction method
CN101812843A (en) Centre grouted poured post-grouting pile construction methods, and grouter and grout injector used thereby
CN106337413A (en) Water-draining stiff geo-textile bag cement-soil composite pile and construction method thereof
CN107191188A (en) The bad water-bearing layer positioning targeting slip casting Mine Shaft Lining of rock section, constructing device and method
CN103195060B (en) Soft soil foundation prestressing bolt anchorage structure and uses thereof
CN103806433A (en) Foundation backfill reinforcement method
CN103556551B (en) Reinforce the construction method of the dumb-bell shape drilled pile composite foundation structure of embankment widening
CN103556554A (en) Bored pile composite foundation structure used for reinforcing soft foundations of embankment and construction method thereof
CN1112485C (en) Cast-in-situ method for forming piles by drilling hole and pouring grout
CN101838957A (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN111810185B (en) Tunnel bottom pre-reinforcement construction method
CN105714827A (en) Post-grouting construction method of cast-in-situ bored pile
CN106192987B (en) It is a kind of to be crushed the construction method that geology is reinforced to stake periphery
CN206418517U (en) A kind of prefabricated anchor foundation for frozen soil foundation
CN202672132U (en) Reinforcing structure for basement backfilling
CN104047285A (en) Technical device and construction method for improving bearing capacity of CFG pressure pouring piles
CN103556555A (en) Nail-shaped bored pile compound foundation structure for reinforcing embankment soft foundation, and construction method thereof
CN205012333U (en) Recoverable FRP stock with enlarged footing
CN212001139U (en) Deep foundation pit supporting structure capable of preventing deformation
CN203514141U (en) Drilling pile composite foundation structure for reinforcing soft ground under highway embankment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee