CN111222275A - Method for establishing segment ring floating and dislocation fine model separated from shield tail - Google Patents

Method for establishing segment ring floating and dislocation fine model separated from shield tail Download PDF

Info

Publication number
CN111222275A
CN111222275A CN202010015761.XA CN202010015761A CN111222275A CN 111222275 A CN111222275 A CN 111222275A CN 202010015761 A CN202010015761 A CN 202010015761A CN 111222275 A CN111222275 A CN 111222275A
Authority
CN
China
Prior art keywords
ring
segment
shield
segment ring
shield tail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010015761.XA
Other languages
Chinese (zh)
Other versions
CN111222275B (en
Inventor
钟小春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN202010015761.XA priority Critical patent/CN111222275B/en
Publication of CN111222275A publication Critical patent/CN111222275A/en
Application granted granted Critical
Publication of CN111222275B publication Critical patent/CN111222275B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a method for establishing a segment ring floating and slab staggering fine model separated from a shield tail. The invention utilizes the self-made buoyancy test device to accurately test the buoyancy borne by the duct piece, and can better reflect the upward floating condition of the duct piece in the condition of grouting and wrapping behind the wall. The change of the attitude of the shield tunneling machine, which causes the thrust of the shield tail jack to the segment ring, and the direction are considered, so that the longitudinal stress characteristic of the shield tail segment ring in the actual construction process of the tunnel and the influence on the floating of the segment are better reflected. The shearing rigidity of the ring joint of the adjacent pipe pieces is considered, the longitudinal characteristics of bending deformation and shearing deformation of the tail pipe piece ring of the shield can be better reflected, the displacement, dislocation and additional internal force caused by floating of the tail pipe piece ring of the shield can be more accurately determined, and a basis is provided for the process control of construction.

Description

Method for establishing segment ring floating and dislocation fine model separated from shield tail
Technical Field
The invention discloses a method for establishing a segment ring floating and slab staggering fine model separated from a shield tail, and belongs to the technical field of underground engineering construction.
Background
With the rapid development of national economy and the rapid expansion of urban scale in China, urban traffic congestion has become a common problem in large cities. The adoption of large-flow subway transportation is an effective traffic organization form for the efficient operation of large cities, and the shield tunnel construction method becomes a mainstream method for urban subway construction due to the functions of small influence on urban traffic and safe, efficient and rapid tunneling.
The construction process of segment splicing at the tail part of the shield tunneling machine inevitably causes an annular gap, namely a shield tail gap, to exist between a spliced segment ring and a stratum. And the shield segment wall post-grouting is to actively control the stratum settlement and stabilize the segments by pumping slurry into the gaps in a shield tunnel construction method. The dual-liquid grouting method has the advantages that the dual-liquid grouting with the quick setting characteristic is adopted for synchronous grouting in foreign countries, the functional requirements of the grouting process after the wall are met, but the requirements on the quality of operating personnel are high, otherwise, frequent shutdown is easily caused to block the pipe, and the construction period is seriously influenced. Because of this, the grouting liquid after the shield tail wall in the domestic subway construction generally adopts single grout, and the initial setting time is too long, so that the segment ring which is just separated is in the wrapping of the liquid grout for a long time. Through preliminary calculation, the buoyancy of the slurry borne by the segment ring at the initial stage is nearly 4 times of the self weight of the segment ring, and the segment ring floating from the shield tail is inevitable. The on-site construction monitoring result of the existing subway shield tunnel shows that the upward floating amount of a segment ring just separated from the shield tail is several centimeters to ten and several centimeters, so that the segment assembling quality cannot meet the design requirement, and the phenomena of segment breakage, crack, slab staggering and leakage are comparable, thereby bringing huge challenges to future subway operation safety and tunnel maintenance.
The following two problems exist for solving the problem at present: 1) how the floating force of the slurry on the pipe sheet ring is determined and the change rule of the slurry on the pipe sheet ring along with time are not clear at present; 2) in order to reduce segment ring dislocation, various positioning bolts, positioning tenons and other various forms are developed on the side surface of the segment ring, and the contribution of the positioning bolts, the positioning tenons and the like to the shearing rigidity of joints between the segment rings is not clear at present. With the increasing importance of China on the subway construction quality, the solution of the problem is on schedule, which causes the high importance of China in the engineering and academic circles.
Disclosure of Invention
The invention provides a method for establishing a segment ring floating and slab staggering refinement model separated from a shield tail, aiming at overcoming the defects in the prior art, and providing a method for establishing a segment ring floating and slab staggering refinement three-dimensional model separated from a shield tail.
The technical solution of the invention is as follows: a method for establishing a segment ring floating and slab staggering refinement model escaping from a shield tail comprises the following steps:
the method comprises the following steps of firstly, investigating the structural structure and mechanical parameters of a shield pipe sheet ring:
the structural parameters of the shield pipe sheet ring are as follows: the inner diameter and the outer diameter of the shield segment ring, the segment ring width, the segment concrete elastic modulus, the shear modulus, the friction coefficient, the model number and the number of the connecting bolts between the segment rings, the length of the bolts, the diameter of the bolts, the shear modulus of the bolts, the type number and the tenon size of the positioning tenons between the segment rings.
Secondly, determining the shearing rigidity of the adjacent pipe sheet ring joint:
and determining the shearing rigidity of the segment ring joint by establishing a finite element numerical model of staggering of adjacent two-ring or three-ring segment rings by considering the bolt between the segment rings, the positioning tenon connection and the segment ring seam contact.
Thirdly, testing the buoyancy of the grouting liquid after the tail pipe sheet ring of the shield is separated:
through the slurry buoyancy test device developed independently, the change rule of different types of slurry with time under the action of different grouting pressures is researched.
Fourthly, collecting the thrust of the shield tail jack to the shield tail just assembled pipe sheet ring and the direction:
and in the shield propelling process, determining the magnitude and direction of the thrust of the shield tail jack acting on the pipe sheet ring according to the reading of the pressure of the oil cylinder jack, the posture of the shield tunneling machine and the posture of the shield tail assembled pipe sheet ring.
And fifthly, establishing a three-dimensional calculation model of the segment ring floating from the shield tail:
and (3) obtaining the structural characteristics based on the first step to the fourth step, obtaining the shearing rigidity of the segment ring joint by the time-varying buoyancy of the segment ring or calculating and analyzing, establishing a shell-spring model accurately considering the actual structural stress characteristics of the shield segment ring, and determining the floating amount, the opening amount, the dislocation and the additional internal force caused by floating of the segment ring out of the shield tail. The shell is adopted to simulate the duct piece, and the spring is adopted to simulate the axial and shearing mechanical properties of the annular joint of the duct piece.
The thrust of the shield tail jack to the segment ring which is separated from the shield tail pipe is considered, and the influence of the shield tail jack on the thrust direction of the segment ring caused by the change of the posture of the shield machine and the posture of the segment is considered.
The shearing rigidity of the adjacent segment ring joint comprehensively considers the shearing resisting effect of the bolts and the positioning tenons connected with the adjacent segment rings and the friction of the annular concrete of the adjacent segment rings, so that the shearing rigidity of the segment ring joint is more accurate.
The segment ring floating fine model separated from the shield tail comprehensively considers the thrust of a shield tail jack, the direction and the buoyancy of slurry borne by a segment and the shearing rigidity of a segment ring joint, is more accurate and reliable compared with the former model, and the result obtained by calculation provides important reference for the floating of the segment ring of the subway shield and the dislocation control.
The invention has the beneficial effects that:
1) the invention can better reflect the longitudinal stress characteristic of the shield tail pipe ring and the influence on the floating of the pipe piece in the actual construction process of the tunnel by considering the change of the shield tail jack to the thrust of the pipe piece ring and the direction caused by the posture change of the shield tunneling machine.
2) According to the invention, the shearing rigidity of the adjacent pipe sheet ring joint is considered, so that the longitudinal characteristics of bending deformation and shearing deformation of the tail pipe sheet ring of the shield can be better reflected, the displacement, dislocation and additional internal force caused by floating of the tail pipe sheet ring of the shield can be more accurately determined, and a basis is provided for the process control of construction.
3) The method solves the engineering problem that the segment ring floating displacement from the shield tail is difficult to accurately determine, the platform is staggered and the additional internal force caused by floating is difficult to accurately determine in the shield tunnel construction process, can accurately simulate the influence of various factors of shield construction on the segment ring floating of the shield tail pipe, and provides important reference for the selection of segment floating prevention measures.
Drawings
FIG. 1 is a schematic view of 1/19 calculation model of three-ring joint shear.
FIG. 2 is a schematic diagram showing the variation of the buoyancy of the shield tail grouting liquid on the segment ring along with the shield process.
FIG. 3 is a schematic diagram of the stress analysis and boundary conditions after the segment ring is pulled out of the shield tail.
FIG. 4 is a schematic diagram showing the longitudinal variation of floating displacement of a segment ring from the tail of a shield.
FIG. 5 is a schematic view showing the change of the segment circumferential sewing staggering station along the longitudinal direction of the segment rings.
Detailed Description
The invention provides a method for establishing a segment ring floating and slab staggering fine model separated from a shield tail, which accurately determines the floating amount of segments dragged by the shield tail and the additional internal force of a shield tunnel caused by segment floating, and provides help for further analyzing the segment floating mechanism. And fitting by combining the data of the actually measured floating amount of the duct piece on the site. The shield tail out-of-segment floating amount and the additional internal force under the conditions of different shield tail thrust forces and directions and different adjacent segment ring shearing rigidity in different backfill grouting wrapping states are predicted, and the phenomena of platform dislocation, cracks, damage, even axis deviation and the like caused by segment floating are avoided.
A method for establishing a segment ring floating and slab staggering refinement model separated from a shield tail aims to overcome the defects in the prior art, and provides a method for establishing a segment ring floating and slab staggering refinement three-dimensional model separated from the shield tail.
The technical solution of the invention is as follows: a method for establishing a segment ring floating and slab staggering refinement model escaping from a shield tail comprises the following steps:
the method comprises the following steps of firstly, investigating the structural structure and mechanical parameters of a shield pipe sheet ring:
the structural parameters of the shield pipe sheet ring are as follows: the inner diameter and the outer diameter of the shield segment ring, the segment ring width, the segment concrete elastic modulus, the shear modulus, the friction coefficient, the model number and the number of the connecting bolts between the segment rings, the length of the bolts, the diameter of the bolts, the shear modulus of the bolts, the type number and the tenon size of the positioning tenons between the segment rings.
Secondly, determining the shearing rigidity of the adjacent pipe sheet ring joint:
and determining the shearing rigidity of the segment ring joint by establishing a finite element numerical model of staggering of adjacent two-ring or three-ring segment rings by considering the bolt between the segment rings, the positioning tenon connection and the segment ring seam contact.
Thirdly, testing the buoyancy of the grouting liquid after the tail pipe sheet ring of the shield is separated:
through the slurry buoyancy test device developed independently, the change rule of different types of slurry with time under the action of different grouting pressures is researched.
Fourthly, collecting the thrust of the shield tail jack to the shield tail just assembled pipe sheet ring and the direction:
and in the shield propelling process, determining the magnitude and direction of the thrust of the shield tail jack acting on the pipe sheet ring according to the reading of the pressure of the oil cylinder jack, the posture of the shield tunneling machine and the posture of the shield tail assembled pipe sheet ring.
And fifthly, establishing a three-dimensional calculation model of the segment ring floating from the shield tail:
and (3) obtaining the structural characteristics based on the first step to the fourth step, obtaining the shearing rigidity of the segment ring joint by the time-varying buoyancy of the segment ring or calculating and analyzing, establishing a shell-spring model accurately considering the actual structural stress characteristics of the shield segment ring, and determining the floating amount, the opening amount, the dislocation and the additional internal force caused by floating of the segment ring out of the shield tail. The shell is adopted to simulate the duct piece, and the spring is adopted to simulate the axial and shearing mechanical properties of the annular joint of the duct piece.
The thrust of the shield tail jack to the segment ring which is separated from the shield tail pipe is considered, and the influence of the shield tail jack on the thrust direction of the segment ring caused by the change of the posture of the shield machine and the posture of the segment is considered.
The shearing rigidity of the adjacent segment ring joint comprehensively considers the shearing resisting effect of the bolts and the positioning tenons connected with the adjacent segment rings and the friction of the annular concrete of the adjacent segment rings, so that the shearing rigidity of the segment ring joint is more accurate.
The segment ring floating fine model separated from the shield tail comprehensively considers the thrust of a shield tail jack, the direction and the buoyancy of slurry borne by a segment and the shearing rigidity of a segment ring joint, is more accurate and reliable compared with the former model, and the result obtained by calculation provides important reference for the floating of the segment ring of the subway shield and the dislocation control.
Example 1
In the construction process of a large-diameter shield of a certain Chengdu subway, a segment ring just separated from a shield tail has the risks of floating, dislocation and even leakage.
Firstly, investigating the structural structure and mechanical parameters of the shield segment ring
According to investigation, the outer diameter of the tunnel is 8.3m, the inner diameter is 7.5m, the ring width is 1.5m, the whole ring is composed of 7 pipe pieces (1 +2+ 4), and the split joint assembly is carried out. The section of jurisdiction adopts C50 concrete, and the main muscle is HRB400 level reinforcing bar, and the circumferential weld passes through 19M 30 bolted connection, and bolt mechanical properties is 8.8 levels, and the initial clearance 3mm in bolt and bolt hole sets up 19 independent location tenons, evenly distributed on the section of jurisdiction ring side, has 2.5mm free deformation space between location tenon and the draw-in groove.
Second, determining the shearing rigidity of the ring joint of the adjacent pipe sheets
Through investigation, adjacent pipe sheet ring joints are connected by adopting arc-shaped bolts and positioning tenons. The bolt refers to a steel bar constitutive model without yield point in concrete structure design Specifications (GB 50010-2010). The positioning tenon is a novel assembled tenon sleeve, and the mechanical property of the positioning tenon sleeve is measured according to GB/T32382 and 2015 determination of the shearing property of the heat insulation product for the building.
The shear force distribution can be carried out according to the average effect under the condition that the annular joints are all sheared under the longitudinal shearing action, so that the shear stiffness of the annular joint can be simply analyzed only aiming at local blocks comprising a group of shear members. The whole ring 1/19 of the segment is taken for modeling, the segment is simplified into a flat plate, and a finite element numerical model of the staggered platform of the adjacent two-ring or three-ring segment ring is established according to the design size, wherein bolts between the segments of the segment, positioning tenon connection and segment circular seam contact are considered, and is shown in figure 1. Other boundary conditions: the side surface restrains the displacement in the x direction, and the two ends restrain the displacement in the z direction.
And calculating to obtain a development rule of the shear stiffness of the circular seam, which is shown in table 1.
TABLE 1 non-linear shear rigidity value-taking table for circular seam joint
Stage of deformation Circular seam staggering step (mm) Circular seam shear stiffness (kN/m)
Friction at circular seam 0~2.5 17000
Positioning tenon engagement 2.5~6.0 180000
Bolt begins to shear 6.0~9.7 71500
Dislocation 20mm 9.7~20.0 33000
Dislocation 30mm 20.0~30.0 9000
Staggered platform>30mm >30.0 0
Thirdly, testing the buoyancy of the slurry injected into the wall from the tail pipe ring of the shield
Taking the case of penetrating through a silt stratum and grouting behind the wall as cement mortar (initial setting time is 10 h), the buoyancy test result acting on the pipe sheet ring is shown in figure 2.
Fourthly, collecting the thrust of the shield tail jack to the shield tail rigid assembled pipe sheet ring and the direction
Through investigation, the total thrust of the jack of the shield tunneling machine to the shield tail just assembled pipe piece ring is 10000kN, the direction is coincident with the axis of the pipe piece, and no eccentricity exists.
Fifthly, establishing a three-dimensional calculation model of segment ring floating from the shield tail
And establishing a three-dimensional calculation model of the floating of the tube sheet ring of the shield tunnel. The buoyancy of the duct piece coming out of the shield tail refers to the third step test result, and the restraint of the shield tail steel wire brush and the duct piece ring with stable solidified slurry is considered, and the boundary condition of the three-dimensional duct piece ring model is shown in figure 3.
After the model is built, the calculation results of the floating displacement and the slab staggering amount of the duct piece coming out of the shield tail are shown in fig. 4-5. The actually measured maximum segment ring floating displacement is 10.01cm, the dislocation amount is 0.35cm, and the actual test result is relatively close, which shows that the method for establishing the refined three-dimensional calculation model is reliable and has higher precision.

Claims (6)

1. A method for establishing a segment ring floating and slab staggering refinement model escaping from a shield tail is characterized by comprising the following steps:
(1) investigating the structural structure and mechanical parameters of the shield pipe sheet ring;
(2) determining the shearing rigidity of the adjacent segment ring joint;
(3) testing the buoyancy of the grouting liquid after the shield tail pipe sheet ring is pulled out;
(4) collecting the thrust magnitude and direction of the shield tail jack to the shield tail assembled pipe sheet ring;
(5) and establishing a three-dimensional calculation model of the segment ring floating from the shield tail.
2. The method for establishing the segment ring floating and slab staggering refinement model escaping from the shield tail according to claim 1, wherein the step (1) is used for investigating the structural structure and mechanical parameters of the segment ring of the shield: the structural construction and mechanical parameters comprise the inner diameter and the outer diameter of the shield segment ring, the segment ring width, the segment concrete elasticity modulus, the shear modulus, the friction coefficient, the type and the number of the connecting bolts between the segment rings, the bolt length, the bolt diameter, the bolt shear modulus, the type and the number of the positioning tenons between the segment rings and the tenon size.
3. The method for establishing the segment ring floating and slab staggering refinement model escaping from the shield tail according to claim 1, wherein the step (2) is used for determining the shearing rigidity of the adjacent segment ring joint: and determining the shearing rigidity of the segment ring joint by establishing a finite element numerical model of staggering of adjacent two-ring or three-ring segment rings by considering the bolt between the segment rings, the positioning tenon connection and the segment ring seam contact.
4. The method for establishing the segment ring floating and slab staggering refinement model for the unshielded shield tail according to claim 1, wherein the step (3) is used for testing the buoyancy of the grouting solution applied to the segment ring of the unshielded shield tail: through thick liquid floating force testing arrangement, study the thick liquid of different grade type under different slip casting pressure effects, its buoyancy is along with the change law of time.
5. The method for establishing the segment ring floating and slab staggering refinement model escaping from the shield tail according to claim 1, wherein the step (4) is used for collecting the thrust of a shield tail jack to a segment ring just assembled on the shield tail: and in the shield propelling process, determining the magnitude and direction of the thrust of the shield tail jack acting on the pipe sheet ring according to the reading of the pressure of the oil cylinder jack, the posture of the shield tunneling machine and the posture of the shield tail assembled pipe sheet ring.
6. The method for building the segment ring floating and dislocation fine model escaping from the shield tail as claimed in claim 1, wherein the step (5) is used for building a three-dimensional calculation model of the segment ring floating escaping from the shield tail: acquiring structural characteristics based on the first step to the fourth step, obtaining the shearing rigidity of a segment ring joint by the time-varying buoyancy of a segment ring or calculating and analyzing, establishing a shell-spring model accurately considering the actual structural stress characteristics of the shield segment ring, and determining the floating amount, the opening amount, the dislocation and the additional internal force caused by floating of the segment ring out of the shield tail; the shell is adopted to simulate the duct piece, and the spring is adopted to simulate the axial and shearing mechanical properties of the annular joint of the duct piece.
CN202010015761.XA 2020-01-07 2020-01-07 Method for establishing segment ring floating and dislocation fine model separated from shield tail Active CN111222275B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010015761.XA CN111222275B (en) 2020-01-07 2020-01-07 Method for establishing segment ring floating and dislocation fine model separated from shield tail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010015761.XA CN111222275B (en) 2020-01-07 2020-01-07 Method for establishing segment ring floating and dislocation fine model separated from shield tail

Publications (2)

Publication Number Publication Date
CN111222275A true CN111222275A (en) 2020-06-02
CN111222275B CN111222275B (en) 2022-08-02

Family

ID=70808803

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010015761.XA Active CN111222275B (en) 2020-01-07 2020-01-07 Method for establishing segment ring floating and dislocation fine model separated from shield tail

Country Status (1)

Country Link
CN (1) CN111222275B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112051139A (en) * 2020-09-09 2020-12-08 中山大学 Segment joint shear rigidity measuring method, system, equipment and storage medium
CN113255037A (en) * 2021-05-20 2021-08-13 中国建筑第五工程局有限公司 Novel estimation method for upward floating amount of double-mode shield tunnel segment in upper soft and lower hard stratum
CN113309533A (en) * 2021-06-17 2021-08-27 中铁十八局集团有限公司 Open type TBM expanding excavation anti-planting head method
CN114235250A (en) * 2021-12-01 2022-03-25 山东大学 Device and method for testing longitudinal resultant force of duct piece in slurry
CN114526088A (en) * 2022-01-25 2022-05-24 西南交通大学 Longitudinal joint equivalent model for researching shield tunnel segment dislocation

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004197386A (en) * 2002-12-18 2004-07-15 Railway Technical Res Inst Estimating method for ground displacement in shield machine passage in tunnel
CN102306225A (en) * 2011-09-27 2012-01-04 上海大学 Method for simulating construction course and tunnel deformation influence value of multiline overlapping tunnel
JP2015129377A (en) * 2014-01-07 2015-07-16 三菱重工メカトロシステムズ株式会社 Simultaneous construction method for shield excavation segment assembly
CN104989423A (en) * 2015-06-11 2015-10-21 同济大学 Visual single-circle shield tunneling synchronous grouting slurry diffusion mode study platform and application of platform
CN105952470A (en) * 2016-05-27 2016-09-21 宁波市交通规划设计研究院有限公司 A construction method for controlling shield ascent in a subway's penetration through a soft soil stratum having a soft bottom and a hard top
WO2016192320A1 (en) * 2015-06-03 2016-12-08 中铁第四勘察设计院集团有限公司 Continuous beam type anti-floating structure of shield tunnel
CN109241631A (en) * 2018-09-12 2019-01-18 上海隧道工程有限公司 Duct pieces of shield tunnel float-amount calculation method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004197386A (en) * 2002-12-18 2004-07-15 Railway Technical Res Inst Estimating method for ground displacement in shield machine passage in tunnel
CN102306225A (en) * 2011-09-27 2012-01-04 上海大学 Method for simulating construction course and tunnel deformation influence value of multiline overlapping tunnel
JP2015129377A (en) * 2014-01-07 2015-07-16 三菱重工メカトロシステムズ株式会社 Simultaneous construction method for shield excavation segment assembly
WO2016192320A1 (en) * 2015-06-03 2016-12-08 中铁第四勘察设计院集团有限公司 Continuous beam type anti-floating structure of shield tunnel
CN104989423A (en) * 2015-06-11 2015-10-21 同济大学 Visual single-circle shield tunneling synchronous grouting slurry diffusion mode study platform and application of platform
CN105952470A (en) * 2016-05-27 2016-09-21 宁波市交通规划设计研究院有限公司 A construction method for controlling shield ascent in a subway's penetration through a soft soil stratum having a soft bottom and a hard top
CN109241631A (en) * 2018-09-12 2019-01-18 上海隧道工程有限公司 Duct pieces of shield tunnel float-amount calculation method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JINXIU YUAN: "Study on Rising Displacement of Segment of Shield Tunnel in Soft Soils", 《APPLIED MECHANICS AND MATERIALS》 *
赵晋: "盾构隧道管片位移因素分析及控制措施研究", 《中国优秀硕士学位论文全文数据库(电子期刊)》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112051139A (en) * 2020-09-09 2020-12-08 中山大学 Segment joint shear rigidity measuring method, system, equipment and storage medium
CN113255037A (en) * 2021-05-20 2021-08-13 中国建筑第五工程局有限公司 Novel estimation method for upward floating amount of double-mode shield tunnel segment in upper soft and lower hard stratum
CN113309533A (en) * 2021-06-17 2021-08-27 中铁十八局集团有限公司 Open type TBM expanding excavation anti-planting head method
CN114235250A (en) * 2021-12-01 2022-03-25 山东大学 Device and method for testing longitudinal resultant force of duct piece in slurry
CN114526088A (en) * 2022-01-25 2022-05-24 西南交通大学 Longitudinal joint equivalent model for researching shield tunnel segment dislocation

Also Published As

Publication number Publication date
CN111222275B (en) 2022-08-02

Similar Documents

Publication Publication Date Title
CN111222275B (en) Method for establishing segment ring floating and dislocation fine model separated from shield tail
CN206512764U (en) A kind of horizontally loading test system for applying vertical load in stake top
Liu et al. Full-scale experimental investigation on stagger effect of segmental tunnel linings
CN102191940A (en) Water conveyance tunnel with prestressed composite lining for shield tunnelling
Liu et al. Experimental investigation of the ultimate bearing capacity of deformed segmental tunnel linings strengthened by epoxy-bonded filament wound profiles
CN112857988A (en) Asymmetric load loading test system and test method for full-scale test of pipe piece
Wang et al. Investigation of the mechanical properties of double lining structure of shield tunnel with different joint surface
CN110967252A (en) Device for simulating influence of shield tunnel construction on existing tunnel and using method thereof
Zhang et al. Full-scale experimental study on failure characteristics of the key segment in shield tunnel with super-large cross-section
Wang et al. Mechanical properties and analytic solutions of prestressed linings with un-bonded annular anchors under internal water loading
Do et al. Stress and strain state in the segmental linings during mechanized tunnelling
Zhou et al. Bearing characteristics and failure mechanism of a novel plate-short anchor structure for tunnel crack reinforcement
CN210071506U (en) Simulation device for pipe piece deformation during construction of large-diameter slurry balance shield through river bottom
Gao et al. Influence of Benoto bored pile construction on nearby existing tunnel: A case study
CN110991009B (en) Method for determining stress deformation of buried pipeline by soil body loss below pipeline
CN114593927B (en) Method for carrying out prototype test of shield tunnel by using middle wind well
Feng et al. Study on mechanical behaviors of large diameter shield tunnel during assembling
CN109187198B (en) Method for testing strength and shear strength of calculus in grouting body on site
Gehwolf et al. Deformation measurements of tunnel segments at a newly developed test rig/Deformationsmessungen an Tübbingen mit einem neu entwickelten Prüfstand
CN211292345U (en) Device for simulating influence of shield tunnel construction on existing tunnel
Bilotta et al. Ground movements and strains in the lining of a tunnel in cohesionless soil
Proksch‐Weilguni et al. Optimized reinforcement in longitudinal joints of segmental tunnel linings
Wang et al. Influence of secondary lining thickness on mechanical behaviours of double-layer lining in large-diameter shield tunnels
Ma et al. A Study on the Improvement of Connection Method for Segment in Tunnel Lining System Using Prestressed Steel Cable by Real-scale Test
Lorenzo et al. Structural monitoring of concrete segmental lining tunnels during construction with conventional and fibre optic instrumentation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant