CN111221289B - Ammeter data interaction system and method - Google Patents

Ammeter data interaction system and method Download PDF

Info

Publication number
CN111221289B
CN111221289B CN202010215542.6A CN202010215542A CN111221289B CN 111221289 B CN111221289 B CN 111221289B CN 202010215542 A CN202010215542 A CN 202010215542A CN 111221289 B CN111221289 B CN 111221289B
Authority
CN
China
Prior art keywords
meter
electric energy
meter reading
time point
disassembly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010215542.6A
Other languages
Chinese (zh)
Other versions
CN111221289A (en
Inventor
上官霞
蔡继东
曾庆饶
周德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Fujian Electric Power Co Ltd filed Critical State Grid Fujian Electric Power Co Ltd
Publication of CN111221289A publication Critical patent/CN111221289A/en
Application granted granted Critical
Publication of CN111221289B publication Critical patent/CN111221289B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/042Programme control other than numerical control, i.e. in sequence controllers or logic controllers using digital processors
    • G05B19/0428Safety, monitoring
    • GPHYSICS
    • G08SIGNALLING
    • G08CTRANSMISSION SYSTEMS FOR MEASURED VALUES, CONTROL OR SIMILAR SIGNALS
    • G08C23/00Non-electrical signal transmission systems, e.g. optical systems
    • G08C23/04Non-electrical signal transmission systems, e.g. optical systems using light waves, e.g. infrared
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/26Pc applications
    • G05B2219/2612Data acquisition interface

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Multimedia (AREA)
  • Signal Processing (AREA)
  • Automation & Control Theory (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides an ammeter data interaction system and method. The electric energy meter disassembly data processing system comprises an electric energy meter data automatic acquisition device, a data server and a data processing device, wherein the electric energy meter disassembly data processing device is used for acquiring meter reading readings of an electric energy meter and transmitting the meter reading readings together with the current meter reading time point and the asset number of the electric energy meter to the electric energy meter data server; the electric energy meter data server is used for storing the received meter reading readings of the electric energy meter, the meter reading time points and the asset numbers of the electric energy meter into a meter reading database in an associated manner; the electric power marketing business server is used for calling meter disassembly time points of the electric energy meters, meter reading readings corresponding to the meter disassembly time points and asset numbers of the electric energy meters, and filling the meter reading readings and the asset numbers of the electric energy meters into a preset electric energy meter disassembly record meter template item by item to form an electric energy meter disassembly record meter; and calling a meter reading number corresponding to the previous meter reading time point of the electric energy meter disassembly time point, comparing the meter reading number with the meter reading number corresponding to the meter disassembly time point, and if the meter reading number is larger than the meter reading number corresponding to the meter disassembly time point, generating compensation flow information containing a comparison result and filling the compensation flow information into the corresponding electric energy meter disassembly recording meter.

Description

Ammeter data interaction system and method
Technical Field
The invention belongs to the field of electric power, and particularly relates to an ammeter data interaction system and method.
Background
The statements in this section merely provide background information related to the present disclosure and may not necessarily constitute prior art.
In recent years, with rapid development of social economy and popularization of power consumption information acquisition, the number of electric energy meters managed by power supply companies is multiplied, and the number of electric energy meters to be disassembled is huge due to rotation, failure, functional replacement, policy disassembly and the like every year. The management of disassembling the electric energy meter is taken as the last ring of the whole life cycle management, and the method has important significance in the aspects of electric quantity rechecking, sorting and recycling, data collection, auxiliary decision making and the like. The inventor finds that along with the increase of the number of the detached electric meters, the difficulty of the handling work of detaching the intelligent electric meter is increased, the current warehousing work of detaching the electric meter mainly adopts manual operation as the main work, the efficiency is not high, and errors are easy to occur.
Disclosure of Invention
In order to solve the above problems, a first aspect of the present invention provides an electric meter data interaction system, which is capable of automatically reading a frozen reading of an intelligent electric meter, accurately and reliably transmitting the frozen reading to an electric power marketing service server, and accurately and reliably transmitting a detached reading.
In order to achieve the purpose, the invention adopts the following technical scheme:
an electricity meter data interaction system comprising:
the electric meter data automatic acquisition device is used for acquiring the meter reading readings of the electric energy meter and transmitting the meter reading readings together with the current meter reading time point and the asset number of the electric energy meter to the electric energy meter data server;
the electric energy meter data server is used for storing the received meter reading readings of the electric energy meter, the meter reading time points and the asset numbers of the electric energy meter into a meter reading database in an associated manner;
the electric power marketing business server is used for calling meter disassembly time points of the electric energy meters, meter reading readings corresponding to the meter disassembly time points and asset numbers of the electric energy meters, and filling the meter reading readings and the asset numbers of the electric energy meters into a preset electric energy meter disassembly record meter template item by item to form an electric energy meter disassembly record meter;
transferring a meter reading number corresponding to a meter reading time point before the meter reading time point of the electric energy meter, comparing the meter reading number with the meter reading number corresponding to the meter reading time point, and if the meter reading number is larger than the meter reading number corresponding to the meter reading time point, generating compensation flow information containing a comparison result and filling the compensation flow information into a corresponding electric energy meter disassembly recording meter; if the former is less than or equal to the latter, the electric energy meter disassembly recording meter is directly stored.
The second aspect of the invention provides an ammeter data interaction method, which can automatically read the frozen readings of the intelligent ammeter, accurately and reliably transmit the frozen readings to a power marketing service server, and realize accurate and reliable transmission of the detached readings.
In order to achieve the purpose, the invention adopts the following technical scheme:
an electricity meter data interaction method comprises the following steps:
the electric energy meter data automatic acquisition device acquires the meter reading number of the electric energy meter and transmits the meter reading number, the current meter reading time point and the asset number of the electric energy meter to the electric energy meter data server;
the electric energy meter data server stores the received meter reading number of the electric energy meter, the meter reading time point and the asset number of the electric energy meter into a meter reading database in an associated manner;
the electric power marketing business server calls meter disassembly time points of the electric energy meters, meter reading readings corresponding to the meter disassembly time points and asset numbers of the electric energy meters, and the meter reading readings and the asset numbers of the electric energy meters are filled into a preset electric energy meter disassembly record meter template item by item to form an electric energy meter disassembly record meter;
transferring a meter reading number corresponding to a meter reading time point before the meter reading time point of the electric energy meter, comparing the meter reading number with the meter reading number corresponding to the meter reading time point, and if the meter reading number is larger than the meter reading number corresponding to the meter reading time point, generating compensation flow information containing a comparison result and filling the compensation flow information into a corresponding electric energy meter disassembly recording meter; if the former is less than or equal to the latter, the electric energy meter disassembly recording meter is directly stored.
The invention has the beneficial effects that:
(1) according to the invention, through the automatic ammeter data acquisition device, the frozen readings of the intelligent ammeter can be read quickly and accurately, the developed device has the characteristics of convenience, safety and the like, the automatic reading rate of the readings of the intelligent ammeter is realized by being disassembled to be 100%, and the electric quantity loss caused by human factors is reduced.
(2) The invention realizes the integrated intelligent reading device for the daily frozen data of the disassembled intelligent electric meter, realizes the automatic reading of the frozen readings of the intelligent electric meter, can accurately and reliably transmit the frozen readings to the marketing system, realizes the accurate and reliable transmission of the disassembled readings, and realizes the 100 percent correct rate of writing the read readings into the marketing system after the disassembled intelligent electric meter is successfully read.
(3) The reading efficiency of the disassembled intelligent electric meter is improved by 5 times compared with the original reading efficiency, the data reading work of one meter is completed within 10 seconds, and compared with the previous working method of looking up the reading photo and manually inputting the reading, the working time of reading input and reading check is reduced, and the working efficiency is improved.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate exemplary embodiments of the invention and together with the description serve to explain the invention and not to limit the invention.
Fig. 1 is a schematic structural diagram of an automatic electric meter data acquisition device according to an embodiment of the present invention.
Fig. 2 is a flowchart of an electricity meter data interaction method according to an embodiment of the present invention.
Detailed Description
The invention is further described with reference to the following figures and examples.
It is to be understood that the following detailed description is exemplary and is intended to provide further explanation of the invention as claimed. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.
It is noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of exemplary embodiments according to the invention. As used herein, the singular forms "a", "an" and "the" are intended to include the plural forms as well, and it should be understood that when the terms "comprises" and/or "comprising" are used in this specification, they specify the presence of stated features, steps, operations, devices, components, and/or combinations thereof, unless the context clearly indicates otherwise.
In the present invention, terms such as "upper", "lower", "left", "right", "front", "rear", "vertical", "horizontal", "side", "bottom", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only terms of relationships determined for convenience of describing structural relationships of the parts or elements of the present invention, and are not intended to refer to any parts or elements of the present invention, and are not to be construed as limiting the present invention.
In the present invention, terms such as "fixedly connected", "connected", and the like are to be understood in a broad sense, and mean either a fixed connection or an integrally connected or detachable connection; may be directly connected or indirectly connected through an intermediate. The specific meanings of the above terms in the present invention can be determined according to specific situations by persons skilled in the relevant scientific or technical field, and are not to be construed as limiting the present invention.
Example one
As shown in fig. 2, the electric meter data interaction system of the embodiment includes:
the electric meter data automatic acquisition device is used for acquiring the meter reading readings of the electric energy meter and transmitting the meter reading readings together with the current meter reading time point and the asset number of the electric energy meter to the electric energy meter data server;
the electric energy meter data server is used for storing the received meter reading readings of the electric energy meter, the meter reading time points and the asset numbers of the electric energy meter into a meter reading database in an associated manner;
the electric power marketing business server is used for calling meter disassembly time points of the electric energy meters, meter reading readings corresponding to the meter disassembly time points and asset numbers of the electric energy meters, and filling the meter reading readings and the asset numbers of the electric energy meters into a preset electric energy meter disassembly record meter template item by item to form an electric energy meter disassembly record meter;
transferring a meter reading number corresponding to a meter reading time point before the meter reading time point of the electric energy meter, comparing the meter reading number with the meter reading number corresponding to the meter reading time point, and if the meter reading number is larger than the meter reading number corresponding to the meter reading time point, generating compensation flow information containing a comparison result and filling the compensation flow information into a corresponding electric energy meter disassembly recording meter; if the former is less than or equal to the latter, the electric energy meter disassembly recording meter is directly stored.
Wherein, ammeter data automatic acquisition device is as follows function:
1) supporting an infrared mode to communicate with the intelligent electric meter;
2) the power information intranet has a network communication function and can be safely accessed;
3) the device has the function of acquiring the access key of the electric energy meter from the encryption system;
4) the device has the function of multiple protocol adaptation, and supports reading of the daily frozen data of the electric energy meter through protocols such as national network standard 1376.1.
The electric power marketing system realizes the following functions:
1) the method supports data interaction with an automatic ammeter data acquisition device, and data interaction is carried out with hardware in a mode of loading activex in a marketing system;
TABLE 1 electric marketing system interface List
Figure BDA0002424276000000051
Figure BDA0002424276000000061
2) The ammeter reading number or the ammeter reading photo read through the interface can quickly position the ammeter disassembling process of the ammeter in the electric power marketing system according to the asset information of the intelligent ammeter, automatically match ammeter disassembling records, and automatically fill the disassembling number into the ammeter disassembling process;
3) the historical meter reading data of the intelligent meter can be quickly positioned according to the asset information of the intelligent meter, the historical meter reading data is compared with the frozen data, and a back-filling process is initiated according to the abnormal condition of the readings.
As shown in fig. 1, the automatic electric meter data acquisition device of this embodiment includes an acquisition end, a processing end, and a sending end. The acquisition end comprises a 485 communication module, an infrared communication module and a camera acquisition module which are respectively connected with the main control chip;
a first communication interface of the 485 communication module is connected with the ammeter, and the degree on the ammeter is read;
a data collector of the infrared communication module is connected with the electric meter and reads an ID number (namely an asset number) on the electric meter; the ID number is the unique identification of the electricity meter.
The processing end comprises a communication indicator light, a power indicator light, a main control chip and a power module for supplying power to the main control chip;
the communication indicator light, the power indicator light and the power module are respectively connected with the main control chip.
The sending end comprises a USB communication interface connected with the main control chip; the USB communication interface is connected with a peripheral PC.
The degree, the ID number and the photo of the ammeter are automatically acquired by the 485 communication module, the infrared communication module and the camera acquisition module of the acquisition end, and the automatic uploading of ammeter data and the automatic shooting and storing of the ammeter photo are realized by the seamless butt joint of the USB communication port of the sending end and the acquisition system on the PC.
And the electric power marketing service server carries out real-time data interaction with the electric energy meter data server in a mode of loading activex. The electric power marketing system carries out real-time data interaction with hardware in a mode of loading activex, the method has the advantages that the electric power marketing system can be reused by most application programs, no matter what language is developed, special functions can be added to websites, desktop application programs and development tools quickly by using activex controls. All the access parameters of the method are a JSON format character string, so that flexible expansion can be conveniently carried out according to each service. The data interaction method is good in instantaneity and high in reliability, and efficiency is greatly improved compared with that of a traditional system and an acquisition mode.
The electric power marketing system carries out real-time data interaction with hardware in an activex loading mode. All the access parameters of the method are a JSON format character string, so that flexible expansion can be conveniently carried out according to each service.
The "name/value pair" is represented by JSON as follows:
{"firstName":"Brett"}
a plurality of "name/value pairs" are expressed by JSON:
{"firstName":"Brett","lastName":"McLaughlin","email":"aaaa"}
the array is represented in the form:
{"people":[
{"firstName":"Brett","lastName":"McLaughlin","email":"aaaa"},
{"firstName":"Jason","lastName":"Hunter","email":"bbbb"},
{"firstName":"Elliotte","lastName":"Harold","email":"cccc"}
]}
in the electric power marketing business server, transfer the electric energy meter and tear down the table time point, tear down the corresponding registration of checking meter of the table time point and the asset number of electric energy meter and fill one by one to predetermine before the electric energy meter dismantles the record table template, still include:
and judging whether the meter reading number corresponding to the meter disassembly time point is matched with the type of the meter reading number corresponding to the previous meter reading time point of the electric energy meter.
The electric energy meter disassembling record comprises information such as an asset number of the electric energy meter, a work order number of the meter disassembling process and the like, and the work order number is unique. Searching for the on-the-way electric energy meter disassembling record according to the acquired electric energy meter asset number, and positioning the work order number of the meter disassembling process; the corresponding ammeter assembly and disassembly index records are searched according to the asset number of the ammeter and the work order number of the ammeter disassembly process, the storage mode is a fixed space distribution method, namely, a fixed storage space and fixed record interval time are distributed for each data record, so that the storage address can be accurately calculated according to the time point needing to be searched during searching because the records are uniform in both interval and data length, and the searching is very rapid. The electric energy meters are of various types, and real number display positions and modes of the electric energy meters of different types are different, so that the obtained electric energy representation number types are matched with the number types in the number mounting and dismounting records of the electric meter, the obtained number is written into the corresponding number type mounting and dismounting record of the electric meter when the matching is successful, the number types are consistent, the obtained number type can be written into the corresponding number type mounting and dismounting record of the electric meter, and the number reading judgment is manually carried out on the electric meter which is not successfully matched and uploaded to the terminal.
Example two
The embodiment provides an electricity meter data interaction method, which comprises the following steps:
the electric energy meter data automatic acquisition device acquires the meter reading number of the electric energy meter and transmits the meter reading number, the current meter reading time point and the asset number of the electric energy meter to the electric energy meter data server;
the electric energy meter data server stores the received meter reading number of the electric energy meter, the meter reading time point and the asset number of the electric energy meter into a meter reading database in an associated manner;
the electric power marketing business server calls meter disassembly time points of the electric energy meters, meter reading readings corresponding to the meter disassembly time points and asset numbers of the electric energy meters, and the meter reading readings and the asset numbers of the electric energy meters are filled into a preset electric energy meter disassembly record meter template item by item to form an electric energy meter disassembly record meter;
transferring a meter reading number corresponding to a meter reading time point before the meter reading time point of the electric energy meter, comparing the meter reading number with the meter reading number corresponding to the meter reading time point, and if the meter reading number is larger than the meter reading number corresponding to the meter reading time point, generating compensation flow information containing a comparison result and filling the compensation flow information into a corresponding electric energy meter disassembly recording meter; if the former is less than or equal to the latter, the electric energy meter disassembly recording meter is directly stored.
And the electric power marketing service server performs real-time data interaction with the electric energy meter data server in an activex loading mode.
Wherein, transfer the electric energy meter and tear down the table time point, tear down the corresponding registration of checking meter of table time point and electric energy meter's asset number fill one by one to predetermine before the electric energy meter dismantles the record table template, still include:
and judging whether the meter reading number corresponding to the meter disassembly time point is matched with the type of the meter reading number corresponding to the previous meter reading time point of the electric energy meter.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. An electricity meter data interaction system, comprising:
the electric meter data automatic acquisition device is used for acquiring the meter reading readings of the electric energy meter and transmitting the meter reading readings together with the current meter reading time point and the asset number of the electric energy meter to the electric energy meter data server;
the electric energy meter data server is used for storing the received meter reading readings of the electric energy meter, the meter reading time points and the asset numbers of the electric energy meter into a meter reading database in an associated manner;
the electric power marketing business server is used for calling meter disassembly time points of the electric energy meters, meter reading readings corresponding to the meter disassembly time points and asset numbers of the electric energy meters, and filling the meter reading readings and the asset numbers of the electric energy meters into a preset electric energy meter disassembly record meter template item by item to form an electric energy meter disassembly record meter;
in the electric power marketing business server, transfer the electric energy meter and tear down the table time point, tear down the corresponding registration of checking meter of the table time point and the asset number of electric energy meter and fill one by one to predetermine before the electric energy meter dismantles the record table template, still include:
judging whether the meter reading number corresponding to the meter disassembly time point is matched with the type of the meter reading number corresponding to the previous meter reading time point of the electric energy meter;
transferring a meter reading number corresponding to a meter reading time point before the meter reading time point of the electric energy meter, comparing the meter reading number with the meter reading number corresponding to the meter reading time point, and if the meter reading number is larger than the meter reading number corresponding to the meter reading time point, generating compensation flow information containing a comparison result and filling the compensation flow information into a corresponding electric energy meter disassembly recording meter; if the former is less than or equal to the latter, the electric energy meter disassembly recording meter is directly stored.
2. The electric meter data interaction system according to claim 1, wherein the electric meter data automatic acquisition device comprises an acquisition end, the acquisition end is connected with a processing end, and the processing end is connected with a sending end; the acquisition end comprises a 485 communication module and a camera acquisition module which are respectively connected with the main control chip; the 485 communication module is connected with the electric energy meter and reads the degree on the electric energy meter to obtain a meter reading number; the camera acquisition module is used for reading the asset number of the electric energy meter.
3. An electricity meter data interaction system as claimed in claim 2, wherein the processing terminal comprises a main control chip, the main control chip is connected with the power module, and the main control chip is used for receiving the meter reading readings and the asset number of the electric energy meter and transmitting the meter reading readings and the asset number together with the meter reading time point to the transmitting terminal.
4. A meter data interaction system as claimed in claim 3, wherein said master control chip is further connected to a communication indicator light and a power indicator light, respectively.
5. An electricity meter data interaction system as claimed in claim 3, wherein said transmitting end includes a USB communication interface connected to the main control chip; and the USB communication interface is connected with the electric energy meter data server.
6. A meter data interaction system as claimed in claim 1, wherein the electricity marketing service server performs real-time data interaction with the electric energy meter data server by loading activex.
7. An interaction method for a meter data interaction system according to any one of claims 1 to 6, comprising:
the electric energy meter data automatic acquisition device acquires the meter reading number of the electric energy meter and transmits the meter reading number, the current meter reading time point and the asset number of the electric energy meter to the electric energy meter data server;
the electric energy meter data server stores the received meter reading number of the electric energy meter, the meter reading time point and the asset number of the electric energy meter into a meter reading database in an associated manner;
the electric power marketing business server calls meter disassembly time points of the electric energy meters, meter reading readings corresponding to the meter disassembly time points and asset numbers of the electric energy meters, and the meter reading readings and the asset numbers of the electric energy meters are filled into a preset electric energy meter disassembly record meter template item by item to form an electric energy meter disassembly record meter;
the method for transferring the electric energy meter disassembly time point, the corresponding meter reading readings of the meter disassembly time point and the asset number of the electric energy meter are filled item by item before the preset electric energy meter disassembly recording meter template, and the method further comprises the following steps:
judging whether the meter reading number corresponding to the meter disassembly time point is matched with the type of the meter reading number corresponding to the previous meter reading time point of the electric energy meter;
transferring a meter reading number corresponding to a meter reading time point before the meter reading time point of the electric energy meter, comparing the meter reading number with the meter reading number corresponding to the meter reading time point, and if the meter reading number is larger than the meter reading number corresponding to the meter reading time point, generating compensation flow information containing a comparison result and filling the compensation flow information into a corresponding electric energy meter disassembly recording meter; if the former is less than or equal to the latter, the electric energy meter disassembly recording meter is directly stored.
8. The interaction method of the electric meter data interaction system as claimed in claim 7, wherein the electric power marketing service server performs real-time data interaction with the electric energy meter data server by loading activex.
CN202010215542.6A 2019-04-09 2020-03-25 Ammeter data interaction system and method Active CN111221289B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2019102808631 2019-04-09
CN201910280863 2019-04-09

Publications (2)

Publication Number Publication Date
CN111221289A CN111221289A (en) 2020-06-02
CN111221289B true CN111221289B (en) 2021-07-27

Family

ID=70832688

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010215542.6A Active CN111221289B (en) 2019-04-09 2020-03-25 Ammeter data interaction system and method

Country Status (1)

Country Link
CN (1) CN111221289B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112529653A (en) * 2020-12-04 2021-03-19 广东电网有限责任公司 Method for automatically checking return material information by intelligent system and intelligent system
CN114169663A (en) * 2021-09-23 2022-03-11 深圳供电局有限公司 Electric energy meter assembly and disassembly business normative supervision method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101183356A (en) * 2007-12-14 2008-05-21 华为技术有限公司 Realization method of Excel report forms and Excel reporting system
CN101794280A (en) * 2010-03-11 2010-08-04 北京中科辅龙计算机技术股份有限公司 Form automatic generation method and system based on form template set
CN103927616A (en) * 2014-03-31 2014-07-16 国家电网公司 Method for collector correlation and electric energy meter calibration
CN103955783A (en) * 2014-03-31 2014-07-30 国家电网公司 Low-voltage carrier wave installation site information collecting method
CN104301406A (en) * 2014-10-09 2015-01-21 国家电网公司 Mobile operation terminal platform and access method based on marketing system and acquisition system
CN105574652A (en) * 2015-12-10 2016-05-11 国网山东省电力公司经济技术研究院 Planning big data management and control system of smart power distribution network and method
CN105577694A (en) * 2016-02-15 2016-05-11 北京锁定精密科技有限公司 Method for transmitting data packet
CN205845301U (en) * 2016-07-29 2016-12-28 国网福建省电力有限公司 A kind of ammeter registration automatic acquisition device
CN208270748U (en) * 2018-06-21 2018-12-21 杭州德创能源设备有限公司 Single-phase meter, which is torn open, moves back special plane

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204302484U (en) * 2014-08-22 2015-04-29 杭州德创能源设备有限公司 Portable electric meter degree of depositing intelligence checking device
CN104202512A (en) * 2014-09-25 2014-12-10 国家电网公司 Electricity meter image acquisition and automatic meter parameter identification device and system
CN104469113A (en) * 2014-12-05 2015-03-25 国家电网公司 Special shooting device for detached electric energy meter
MX2019006808A (en) * 2016-12-12 2019-11-18 Ventbusters Inc Gas meter and associated methods.
CN107529652A (en) * 2017-09-11 2018-01-02 国网天津市电力公司电力科学研究院 A kind of phenomenon of the failure correlation analysis for tearing back electric energy meter open
CN107730074A (en) * 2017-09-12 2018-02-23 国网福建省电力有限公司 Based on tearing the quality supervision and control platform that moves back intelligent meter flow-line equipment open
CN108445437A (en) * 2018-03-07 2018-08-24 国网天津市电力公司电力科学研究院 One kind tearing back electric energy meter calibration state recovery method open

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101183356A (en) * 2007-12-14 2008-05-21 华为技术有限公司 Realization method of Excel report forms and Excel reporting system
CN101794280A (en) * 2010-03-11 2010-08-04 北京中科辅龙计算机技术股份有限公司 Form automatic generation method and system based on form template set
CN103927616A (en) * 2014-03-31 2014-07-16 国家电网公司 Method for collector correlation and electric energy meter calibration
CN103955783A (en) * 2014-03-31 2014-07-30 国家电网公司 Low-voltage carrier wave installation site information collecting method
CN104301406A (en) * 2014-10-09 2015-01-21 国家电网公司 Mobile operation terminal platform and access method based on marketing system and acquisition system
CN105574652A (en) * 2015-12-10 2016-05-11 国网山东省电力公司经济技术研究院 Planning big data management and control system of smart power distribution network and method
CN105577694A (en) * 2016-02-15 2016-05-11 北京锁定精密科技有限公司 Method for transmitting data packet
CN205845301U (en) * 2016-07-29 2016-12-28 国网福建省电力有限公司 A kind of ammeter registration automatic acquisition device
CN208270748U (en) * 2018-06-21 2018-12-21 杭州德创能源设备有限公司 Single-phase meter, which is torn open, moves back special plane

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
基于智能电表拆退管理新方式的技术研究;上官霞;《通讯世界》;20161125(第22期);第192-193页 *
论费控智能电能表电价异常产生退补电费相关原因及处理方案;任玉兰;《科技创新与应用》;20140728(第21期);第170页 *

Also Published As

Publication number Publication date
CN111221289A (en) 2020-06-02

Similar Documents

Publication Publication Date Title
CN111221289B (en) Ammeter data interaction system and method
CN103236951A (en) Method and system for distributing and identifying optical network resource
CN103955783A (en) Low-voltage carrier wave installation site information collecting method
CN112230095B (en) Load identification module hardware interface detection equipment and automatic detection method thereof
CN103235976A (en) Patrol optimization management platform for 10kV user patrol
CN102117473A (en) Meter reading management system with image and text
CN109150669A (en) A kind of use based on Ethernet fells and transports the telecommunication system and processing method of dimension
CN112949601A (en) Electronic account book associated certificate analysis method, device and system
CN106779100A (en) A kind of elevator repair and maintenance handheld terminal and its application method
CN103198534B (en) A kind of method and device utilizing ear recognition work attendance
CN201563246U (en) Mobile communication base station and optical cable patrol management system
CN109509076A (en) A kind of management-control method based on battalion's wealth integrated management system
CN112712265A (en) Business operation analysis management system based on big data management
CN107818453A (en) A kind of intelligent learning type project management device based on cloud
CN113904928A (en) Telesignaling configuration rapid checking system and method for telemechanical device
CN203118119U (en) Bidding file lending returning management system
CN111679946A (en) Novel computer application automatic detection equipment and operation steps thereof
CN110727667A (en) Power equipment consistency management system
CN110765797A (en) Portable intelligent terminal with electric energy meter overall process management and control function
CN105355025B (en) A method of electric energy meter is quickly accessed into metering automation system
CN109738847A (en) Correction method based on meter active self-correcting
CN112367207B (en) Universal Internet of things equipment suitable for tobacco leaf baking controller and matching method
CN117522285B (en) Data conversion management method and system for commercial vehicle pipeline products
CN204010306U (en) Dorsal clamp type infrared copying instrument
CN108628211A (en) A kind of data concentrator and application method of installation and repairing quality intelligent control platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant