CN111206570A - Prefabricated building structure - Google Patents
Prefabricated building structure Download PDFInfo
- Publication number
- CN111206570A CN111206570A CN202010130209.5A CN202010130209A CN111206570A CN 111206570 A CN111206570 A CN 111206570A CN 202010130209 A CN202010130209 A CN 202010130209A CN 111206570 A CN111206570 A CN 111206570A
- Authority
- CN
- China
- Prior art keywords
- prefabricated building
- building structure
- pile
- cage
- pile body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000003292 glue Substances 0.000 claims abstract description 50
- 239000007787 solid Substances 0.000 claims abstract description 45
- 238000003860 storage Methods 0.000 claims abstract description 27
- 238000007789 sealing Methods 0.000 claims description 3
- 230000001070 adhesive effect Effects 0.000 abstract description 35
- 239000000853 adhesive Substances 0.000 abstract description 34
- 230000005574 cross-species transmission Effects 0.000 abstract description 3
- 229910000831 Steel Inorganic materials 0.000 description 48
- 239000010959 steel Substances 0.000 description 48
- 238000010276 construction Methods 0.000 description 22
- 230000035882 stress Effects 0.000 description 21
- 239000004567 concrete Substances 0.000 description 16
- 238000003032 molecular docking Methods 0.000 description 16
- 238000000034 method Methods 0.000 description 14
- 239000003822 epoxy resin Substances 0.000 description 10
- 229920000647 polyepoxide Polymers 0.000 description 10
- 230000005540 biological transmission Effects 0.000 description 9
- 230000001012 protector Effects 0.000 description 8
- 239000002994 raw material Substances 0.000 description 8
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 7
- 230000002093 peripheral effect Effects 0.000 description 7
- 239000002689 soil Substances 0.000 description 7
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 7
- 239000003673 groundwater Substances 0.000 description 6
- 238000003780 insertion Methods 0.000 description 6
- 230000037431 insertion Effects 0.000 description 6
- 210000001503 joint Anatomy 0.000 description 6
- 238000004519 manufacturing process Methods 0.000 description 6
- 238000012545 processing Methods 0.000 description 6
- 239000011247 coating layer Substances 0.000 description 5
- 238000010586 diagram Methods 0.000 description 5
- 230000002787 reinforcement Effects 0.000 description 5
- 229910001220 stainless steel Inorganic materials 0.000 description 5
- 239000010935 stainless steel Substances 0.000 description 5
- 238000003466 welding Methods 0.000 description 5
- RTZKZFJDLAIYFH-UHFFFAOYSA-N Diethyl ether Chemical compound CCOCC RTZKZFJDLAIYFH-UHFFFAOYSA-N 0.000 description 4
- 230000007797 corrosion Effects 0.000 description 4
- 238000005260 corrosion Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 239000011513 prestressed concrete Substances 0.000 description 4
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 description 3
- 229910052799 carbon Inorganic materials 0.000 description 3
- 238000009792 diffusion process Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 230000002035 prolonged effect Effects 0.000 description 3
- 239000002699 waste material Substances 0.000 description 3
- 229910000975 Carbon steel Inorganic materials 0.000 description 2
- 229910001209 Low-carbon steel Inorganic materials 0.000 description 2
- 239000010962 carbon steel Substances 0.000 description 2
- 239000003054 catalyst Substances 0.000 description 2
- 230000008602 contraction Effects 0.000 description 2
- 230000006378 damage Effects 0.000 description 2
- 230000003111 delayed effect Effects 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 230000018109 developmental process Effects 0.000 description 2
- 238000001125 extrusion Methods 0.000 description 2
- 239000012535 impurity Substances 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000010410 layer Substances 0.000 description 2
- 210000003205 muscle Anatomy 0.000 description 2
- 239000011541 reaction mixture Substances 0.000 description 2
- 238000009991 scouring Methods 0.000 description 2
- 230000035939 shock Effects 0.000 description 2
- 229910000851 Alloy steel Inorganic materials 0.000 description 1
- 229910001065 Chromium-vanadium steel Inorganic materials 0.000 description 1
- 229910000976 Electrical steel Inorganic materials 0.000 description 1
- 239000004593 Epoxy Substances 0.000 description 1
- CWYNVVGOOAEACU-UHFFFAOYSA-N Fe2+ Chemical compound [Fe+2] CWYNVVGOOAEACU-UHFFFAOYSA-N 0.000 description 1
- 229910000746 Structural steel Inorganic materials 0.000 description 1
- 229910000797 Ultra-high-strength steel Inorganic materials 0.000 description 1
- GYIFSXKTFMKQNG-UHFFFAOYSA-N [Si][Mn][Cr] Chemical compound [Si][Mn][Cr] GYIFSXKTFMKQNG-UHFFFAOYSA-N 0.000 description 1
- 238000004026 adhesive bonding Methods 0.000 description 1
- 230000032683 aging Effects 0.000 description 1
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 description 1
- 230000004323 axial length Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000009172 bursting Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- VNTLIPZTSJSULJ-UHFFFAOYSA-N chromium molybdenum Chemical compound [Cr].[Mo] VNTLIPZTSJSULJ-UHFFFAOYSA-N 0.000 description 1
- OGSYQYXYGXIQFH-UHFFFAOYSA-N chromium molybdenum nickel Chemical compound [Cr].[Ni].[Mo] OGSYQYXYGXIQFH-UHFFFAOYSA-N 0.000 description 1
- VNNRSPGTAMTISX-UHFFFAOYSA-N chromium nickel Chemical compound [Cr].[Ni] VNNRSPGTAMTISX-UHFFFAOYSA-N 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000010292 electrical insulation Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 125000003700 epoxy group Chemical group 0.000 description 1
- 238000005429 filling process Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
- 125000002887 hydroxy group Chemical group [H]O* 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 239000007769 metal material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 231100000252 nontoxic Toxicity 0.000 description 1
- 230000003000 nontoxic effect Effects 0.000 description 1
- 239000001301 oxygen Substances 0.000 description 1
- 229910052760 oxygen Inorganic materials 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000002441 reversible effect Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 238000004383 yellowing Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/30—Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/06—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against corrosion by soil or water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/52—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
- E02D5/523—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
- E02D5/526—Connection means between pile segments
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/58—Prestressed concrete piles
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention provides a prefabricated building structure which comprises a pile body, wherein the pile body comprises a hollow part and a solid part which are connected with each other, the hollow part is hollow and surrounds to form a core groove, and the end part of the solid part, which is relatively far away from the hollow part, is provided with a glue storage groove. The prefabricated building structure is provided with a glue storage groove at the end part of the solid part, and can be used for connecting other structures and/or containing an adhesive; glue storage tank can hold more adhesives than smooth tip to, when burying prefabricated building structure underground, because there is pressure differential between underground and the earth's surface, the adhesive that holds in the glue storage tank can spill over and spread to two prefabricated building structure's junction, thereby has strengthened the joint strength between two prefabricated building structure.
Description
Technical Field
The invention relates to the technical field of buildings, in particular to a prefabricated building structure.
Background
In the field of building technology, in order to facilitate production and processing and reduce construction time, a prefabricated building structure is generally manufactured in a factory and then transported to a construction site for use. Most of the existing prefabricated building structures are solid structures or hollow structures, but the solid structures have the problems of overlarge weight, difficulty in transportation, waste of raw materials and the like; on the other hand, although the hollow structure can save raw materials, the shock resistance mechanical property and durability of the hollow structure cannot be guaranteed. Therefore, there is a need for an improved prefabricated building structure that can not only reduce weight and save raw materials, but also ensure its seismic mechanical properties and durability.
Disclosure of Invention
In view of the above, there is a need for an improved prefabricated building structure.
The invention provides a prefabricated building structure which comprises a pile body, wherein the pile body comprises a hollow part and a solid part which are connected with each other, the hollow part is hollow and surrounds to form a core groove, and the end part of the solid part, which is relatively far away from the hollow part, is provided with a glue storage groove.
The pile body in the prefabricated building structure provided by the invention comprises the hollow part and the solid part, so that the consumption of raw materials is reduced, the weight is reduced, and the manufacturing cost is saved; when the prefabricated building structure is buried underground, the central part is located in a depth area with the highest earthquake wave frequency below the foundation, so that the earthquake resistance of the prefabricated building structure can be ensured, and the reliability of the prefabricated building structure in service is ensured. In addition, when the core slot is used with the opening facing downwards, the prefabricated building structure exerts pressure on the solid part when being buried underground, and the phenomenon that the prefabricated building structure is damaged due to overlarge pressure intensity can be avoided; at this time, the core groove can be sealed by matching with external components such as pile tip and the like to prevent the groundwater from entering. When the core slot is used with the opening facing upwards, the solid part can prevent underground water from entering the interior of the prefabricated building structure, effectively resists the corrosion of the underground water to the interior of the prefabricated building structure, and ensures the durability of the prefabricated building structure without core filling treatment. In the construction process, in order to ensure the length of the pile body, two or even a plurality of prefabricated building structures are often connected for use. In order to increase the connection strength between the two prefabricated building structures, glue can be applied between the two prefabricated building structures besides the connection by the quick connecting piece. The prefabricated building structure is provided with a glue storage groove at the end part of the solid part, and can be used for connecting other structures and/or containing an adhesive; glue storage tank can hold more adhesives than smooth tip to, when burying prefabricated building structure underground, because there is pressure differential between underground and the earth's surface, the adhesive that holds in the glue storage tank can spill over and spread to two prefabricated building structure's junction, thereby has strengthened the joint strength between two prefabricated building structure.
In one embodiment of the invention, the glue storage tank has a depth of 1mm to 200mm in the axial direction of the prefabricated building structure.
So set up, can enough hold more adhesive, can not make prefabricated building structure's intensity reduce again to the adhesive in the glue storage tank of being convenient for overflows and spreads to two prefabricated building structure's the connection face, increases the leakproofness of connecting the face, improves anticorrosive assurance rate.
In one embodiment of the present invention, the size of the peripheral wall of the glue storage tank is equal to or smaller than the size of the core groove.
By the arrangement, the speed of the adhesive diffusion can be improved, the abutting area between the two prefabricated building structures cannot be reduced, and the connection strength between the two prefabricated building structures can be greatly improved.
In one embodiment of the invention, the cross-sectional shape of the glue storage tank along the axial direction of the prefabricated building structure is a rectangle, a trapezoid, an arc or a triangle.
By the arrangement, the rectangle can store more adhesives; the shapes of trapezoid, arc, triangle and the like enable the resistance of the adhesive to be small during diffusion, so that the adhesive can be conveniently diffused to the periphery, and the connection strength between two prefabricated building structures is improved.
In an embodiment of the present invention, the prefabricated building structure further comprises a pile tip, the pile tip is located at an end of the pile body, and a first protrusion is arranged on the pile tip, and the first protrusion is adapted to the glue storage tank.
So set up, the stake point makes prefabricated building structure the penetrability on soil layer increase when sinking construction, can play the guide effect, can also reduce prefabricated building structure and appear the probability of bursting absolutely. The pile body and the pile tip can be connected through at least one of threaded connection, welding and glue joint, the first bulge is matched with the glue storage groove, so that the pile tip and the pile body can be conveniently positioned, and the installation time between the pile tip and the pile body is saved; and when the adhesive is arranged between the pile body and the pile tip, the contact area between the pile body and the pile tip can be increased by the first bulge and the adhesive storage groove, and the connection strength between the pile body and the pile tip is further enhanced.
In one embodiment of the invention, the pile tip is detachably connected with the pile body.
So set up, the stake point is for dismantling, and is more nimble, can satisfy the demand of different operating modes.
In one embodiment of the invention, the pile tip is fixedly connected with the pile body.
By the arrangement, the connection strength between the pile tip and the pile body is high, and the pile tip and the pile body are not easy to misplace.
In an embodiment of the present invention, the prefabricated building structure further includes an embedded connector, the embedded connector is disposed at an end of the pile body, the pile tip is provided with a first through hole, and the first through hole is aligned with the embedded connector.
Due to the arrangement, when the pile body is detachably connected with the pile tip, the connection between the embedded connecting piece and the detachable connecting piece is simple, the processing cost is low, the firmness after connection is good, the embedded connecting piece can be matched with an external electric tool for use, and the construction time is saved; when the pile body is fixedly connected with the pile tip, the tensioning machine can directly tension the prefabricated building structure containing the pile tip, so that the bearing capacity of the prefabricated building structure is improved, the construction time can be shortened, and the construction cost is reduced.
In an embodiment of the present invention, the prefabricated building structure further includes a detachable connecting member, and the detachable connecting member is detachably connected to the embedded connecting member through the first through hole.
So set up, can promote the connecting speed between stake point and the pile body, save the engineering time.
In one embodiment of the present invention, the first through hole has a filling stopper therein for filling and sealing the first through hole.
So set up, can prevent that prefabricated building structure is in the in-service process, during groundwater or other underground impurity got into the pile body from first through-hole, prevented that first cage from being corroded, prolonged prefabricated building structure's life.
Drawings
FIG. 1 is a schematic view of a prefabricated building structure according to a first embodiment of the present invention;
FIG. 2 is a cross-sectional view of the prefabricated building structure of FIG. 1 taken along section A-A;
FIG. 3 is a cross-sectional view of the prefabricated building structure of FIG. 1 taken at section B-B;
FIG. 4 is a schematic view of a prefabricated building structure according to a second embodiment of the present invention;
FIG. 5 is a schematic view of the use of the pre-buried connector shown in FIG. 1;
FIG. 6 is a schematic view of the use of two prefabricated building structures in abutting joint;
FIG. 7 is a schematic diagram of a quick docking assembly according to one embodiment;
FIG. 8 is a schematic structural view of a quick docking assembly according to another embodiment;
FIG. 9 is a schematic view of a prefabricated building structure and a platform;
fig. 10 is a partially enlarged view of the portion C shown in fig. 9.
Description of the main elements
100. Prefabricating a building structure; 101. a pile body; 102. pile tip; 10. a hollow portion; 20. a solid portion; 30. a first cage; 40. a second cage; 11. a core groove; 111. an opening; 21. a glue storage tank; 1021. a first protrusion; 1023. a first through hole; 50. mounting a plate; 31. a first axial rib body; 32. a first radial rib; 41. a second axial rib; 42. a second radial rib body; 60. a corner protecting sleeve; 70. pre-burying a connecting piece; 311. heading; 71. a constriction; 72. an annular projection; 80. positioning ribs; 200. a quick docking assembly; 210. a first insert table; 211. a first fixed part; 212. a first insertion part; 213. a first extension portion; 214. a first step surface; 220. a first base; 221. a second fixed part; 222. a fin; 230. a second insert table; 231. a third fixed part; 232. a second insertion part; 233. a first groove; 240. a second base; 241. a first end face; 242. a second end face; 250. looping; 300. a pile hoop; 400. a bearing platform; 410. force transmission rib body.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It will be understood that when an element is referred to as being "mounted on" another element, it can be directly mounted on the other element or intervening elements may also be present. When a component is referred to as being "disposed on" another component, it can be directly on the other component or intervening components may also be present. When an element is referred to as being "secured to" another element, it can be directly secured to the other element or intervening elements may also be present.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terminology used in the description of the invention herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used herein, the term "or/and" includes any and all combinations of one or more of the associated listed items.
The prefabricated building structure 100 refers to various pile bodies which are transported to a construction site for use after being prefabricated. The prefabricated building structure 100 may be produced centrally in a factory or prefabricated around a site. The axial length and the radial circumference of the prefabricated building structure 100 can be made as required, and the reinforcement ratio can be designed according to the stress during the transportation, hoisting and pressing of the pile, so that the flexibility is high. In addition, the prefabricated building structure 100 belongs to a part of soil-squeezing piles, so that the cross-sectional area of a bearing platform is effectively saved, the manufacturing cost is saved, the stress release of soil bodies after the soil bodies are damaged is facilitated, the phenomena of pile body inclination and the like caused by soil body squeezing are reduced, and the construction of other nearby pile bodies is facilitated.
Referring to fig. 1 to 3, fig. 1 is a schematic view of a prefabricated building structure 100 according to a first embodiment of the present invention; FIG. 2 is a cross-sectional view of prefabricated building structure 100 of FIG. 1 at section A-A; fig. 3 is a cross-sectional view of the prefabricated building structure 100 shown in fig. 1, taken along section B-B.
The present invention provides a prefabricated building structure 100 for use in a foundation building in the field of construction technology. In this embodiment, the prefabricated building structure 100 is used to prefabricate a vertically stressed pile. It is understood that in other embodiments, the prefabricated building structure 100 may also be used in other engineering fields, such as fabricated buildings, etc., and may also be used for horizontal load-bearing piles or composite load-bearing piles, etc.
Most of the existing prefabricated building structures are solid structures or hollow structures, but the solid structures have the problems of overlarge weight, difficulty in transportation, waste of raw materials and the like; on the other hand, although the hollow structure can save raw materials, the shock resistance mechanical property and durability of the hollow structure cannot be guaranteed. Therefore, there is a need for an improved prefabricated building structure that can not only reduce weight and save raw materials, but also ensure its seismic mechanical properties and durability.
The invention provides a prefabricated building structure 100 which comprises a pile body 101, wherein the pile body 101 comprises a hollow part 10 and a solid part 20 which are connected with each other, the hollow part 10 is hollow and surrounds to form a core groove 11, and the end part of the solid part 20, which is relatively far away from the hollow part 10, is provided with a glue storage groove 21.
The pile body 101 in the prefabricated building structure 100 provided by the invention comprises the hollow part 10 and the solid part 20, so that the consumption of raw materials is reduced, the weight is lightened, and the manufacturing cost is saved; when the prefabricated building structure 100 is buried underground, the central unit 20 is located in a depth region where seismic waves having the highest frequency of occurrence below a foundation are located, so that the seismic capacity of the prefabricated building structure 100 can be ensured, and the reliability of the prefabricated building structure 100 in service is ensured. In addition, when the core groove 11 is used with the opening 111 facing downward, the prefabricated building structure 100 applies pressure to the solid part 20 when buried underground, so that the phenomenon that the prefabricated building structure 100 is damaged due to excessive pressure can be avoided; at this time, the core hole 11 can be sealed with an external member such as the pile tip 102 to prevent the entry of groundwater. When the core hole 11 is used with the opening 111 facing upward, the solid portion 20 prevents groundwater from entering the interior of the prefabricated construction structure 100, effectively resists corrosion of groundwater to the interior of the prefabricated construction structure 100, and ensures durability of the prefabricated construction structure 100 without a core filling process. In the construction process, two or even a plurality of prefabricated building structures 100 are often connected to ensure the length of the pile body 101. In order to increase the strength of the connection between the two prefabricated building structures 100, glue may be applied between the two prefabricated building structures 100, in addition to the quick connection. The prefabricated building structure 100 of the invention is provided with a glue storage groove 21 at the end part of the solid part 20, and can be used for connecting other structures and/or containing adhesives; glue storage tank 21 can hold more adhesives than the smooth tip to, when burying prefabricated building structure 100 underground, because there is pressure differential between underground and the earth's surface, the adhesive that holds in glue storage tank 21 can spill over and spread to two prefabricated building structure 100's the connection face, thereby has strengthened the joint strength between two prefabricated building structure 100.
In one embodiment of the present invention, the glue reservoir 21 has a depth of 1mm to 200mm in the axial direction of the prefabricated building structure 100.
So set up, can enough hold more adhesive, can not make prefabricated building structure 100's intensity reduce again to the adhesive that is convenient for in the glue storage tank 21 overflows and spreads to two prefabricated building structure 100's the connection face, increases the leakproofness of connecting the face, improves anticorrosive assurance rate.
In one embodiment of the present invention, the size of the peripheral wall of the glue reservoir 21 is equal to or smaller than the size of the core hole 11.
With this arrangement, the speed of the adhesive diffusion can be increased without reducing the contact area between the two prefabricated building structures 100, and the connection strength between the two prefabricated building structures 100 can be greatly increased.
In one embodiment of the present invention, the cross-sectional shape of the glue tank 21 along the axial direction of the prefabricated building structure 100 is a rectangle, a trapezoid, an arc or a triangle.
By the arrangement, the rectangle can store more adhesives; the trapezoidal, arc, triangular, etc. shape makes the adhesive have less resistance when diffusing, facilitates the adhesive to diffuse to the periphery, improves the connection strength between two prefabricated building structures 100.
Specifically, the groove shape of the glue storage groove 21 may be a rectangular parallelepiped shape, a square shape, a cylindrical shape, a spherical shape, a conical shape, or the like, which is not specifically listed here. It is understood that in other embodiments, the glue reservoir 21 may have other shapes as long as it can store the glue.
In one embodiment, a glue coating (not shown) is also provided between two prefabricated building structures 100. The glue coating layer fills the gap between the two prefabricated building structures 100 and the gap between the prefabricated building structures 100 and the quick butt joint component 200, prevents water or oxygen from corroding the first cage body 30, the second cage body 40 and the quick butt joint component 200 after being immersed, and increases the corrosion resistance of the components; after the glue coating layer is cured, the two prefabricated building structures 100 can be shaken or rotated, the rapid butt joint assembly and the prefabricated building structures 100 can be prevented from shaking or rotating, and the stability of the prefabricated building structures 100 is improved; the cured glue coating layer can bear the force, so that the two prefabricated building structures 100 are combined more tightly and firmly, and the stress performance is better; in addition, the glue coating layer can also play a role in uniform stress after being cured, even if the situation that the stress is slightly uneven exists between the two prefabricated building structures 100 or between the prefabricated building structures 100 and the quick butt joint assembly 200, the cured glue coating layer can also balance the stress, the vertical stress capacity of the prefabricated building structures 100 is improved, and the service life of the prefabricated building structures 100 is prolonged.
In one embodiment, the adhesive is in a colloidal state, has certain fluidity and cannot be lost when being applied.
It is understood that in other embodiments, the adhesive may also be in the form of a paste or water, as long as the adhesive effect is achieved.
In one embodiment of the invention, the adhesive is a two-fluid hybrid cured adhesive (AB adhesive).
So set up, AB glue has that warehousing and transportation performance is good, uses more in a flexible way, and bonding strength is high, has advantages such as good vertical atress performance after the solidification.
In one embodiment of the invention, the adhesive is an epoxy.
According to the arrangement, the epoxy resin has strong adhesive force, the chemical structure of the epoxy resin contains aliphatic hydroxyl, ether and extremely active epoxy groups, and the hydroxyl and the ether have high polarity, so that the epoxy resin has strong adhesive force, and the epoxy resin can firmly bond concrete, stone and various metal materials; the epoxy resin AB glue can be prepared into glue with different viscosities, the curing degree of the AB glue can be adjusted through normal-temperature curing, heating curing and other modes, and the curing time can be controlled within minutes to hours; in addition, the epoxy resin AB glue has good performance, and the cured epoxy resin AB glue has good performance, high mechanical strength, yellowing resistance, medium resistance, long aging resistance time, good electrical insulation, water resistance and moisture resistance and small volume shrinkage; the epoxy resin AB glue is nontoxic, has no three-waste emission in production, does not bring harm to the environment when in use, and meets the requirement of environmental protection; in addition, the epoxy resin AB glue has wide and easily available sources, low price and low cost.
Referring to fig. 4, fig. 4 is a schematic view of a prefabricated building structure 100 according to a second embodiment of the present invention.
In one embodiment of the present invention, the prefabricated building structure 100 further comprises a pile tip 102, the pile tip 102 is located at the end of the pile body 101, and a first protrusion 1021 is arranged on the pile tip 102, and the first protrusion 1021 is adapted to the glue storage tank 21.
With the arrangement, the pile tip 102 increases the penetration capability of the soil layer of the prefabricated building structure 100 during the sinking construction, can play a guiding role, and can also reduce the probability of the prefabricated building structure 100 breaking. The pile body 101 and the pile tip 102 can be connected through at least one of threaded connection, welding and gluing, the matching of the first protrusion 1021 and the glue storage groove 21 is convenient for positioning the pile tip 102 and the pile body 101, and the installation time between the pile tip 102 and the pile body 101 is saved; when the adhesive is provided between the pile body 101 and the pile tip 102, the first protrusion 1021 and the adhesive storage groove 21 can increase the contact area between the pile body 101 and the pile tip 102, and further enhance the connection strength between the pile body 101 and the pile tip 102.
In one embodiment of the invention, the stake tip 102 is removably attached to the stake body 101.
So set up, stake point 102 is for dismantling, and is more nimble, can satisfy the demand of different operating modes.
In one embodiment of the invention, the stake tip 102 is fixedly attached to the stake body 101.
With such an arrangement, the connection strength between the pile tip 102 and the pile body 101 is high, and the pile tip 102 and the body are not easily displaced.
In an embodiment of the present invention, the prefabricated building structure 100 further includes a pre-buried connector 70, the pre-buried connector 70 is disposed at an end of the pile body 101, the pile tip 102 is provided with a first through hole 1023, and the first through hole 1023 is aligned with the pre-buried connector 70.
With the arrangement, when the pile body 101 is detachably connected with the pile tip 102, the connection between the embedded connecting piece 70 and the detachable connecting piece is simple, the processing cost is low, the firmness after connection is good, the embedded connecting piece can be matched with an external electric tool for use, and the construction time is saved; when the pile body 101 is fixedly connected with the pile tip 102, the tensioning machine can directly tension the prefabricated building structure 100 containing the pile tip 102, so that the bearing capacity of the prefabricated building structure 100 is improved, the construction time can be shortened, and the construction cost is reduced.
In an embodiment of the present invention, the prefabricated building structure 100 further includes a detachable connector, which is detachably connected to the embedded connector 70 through the first through hole 1023.
By the arrangement, the connection speed between the pile tip 102 and the pile body 101 can be increased, and the construction time is saved.
In one embodiment of the present invention, first through-hole 1023 has a filling stopper therein for filling and sealing first through-hole 1023.
So set up, can prevent that prefabricated building structure 100 is in the in-service process, during groundwater or other underground impurity get into pile 101 from first through-hole 1023, prevented that first cage 30 from being corroded, prolonged prefabricated building structure 100's life.
Specifically, the filling plugging material is cement mixture, epoxy resin, structural adhesive and the like, and the filling plugging material can be sealed in an anticorrosion way.
In one embodiment of the present invention, the prefabricated building structure 100 further comprises a first cage 30, the first cage 30 is disposed inside the pile body and the first cage 30 is made of prestressed reinforcement steel; the first cage body 30 comprises a plurality of first axial rib bodies 31, and the first axial rib bodies 31 are arranged along the axial direction of the pile body; the embedded connector 70 is connected to an end of the first axial rib 31.
According to the arrangement, before the prefabricated building structure 100 is used, prestress is applied to the steel bars in advance through a pre-tensioning method or a post-tensioning method to form prestressed steel bars, when the prefabricated building structure 100 bears tensile force generated by external load, the existing prestress in concrete is firstly counteracted, then the prestressed steel bars are stressed, and finally, the concrete is tensioned and then cracks appear along with the increase of the load, so that the appearance and the development of the cracks of the prefabricated building structure 100 are delayed, and the loads such as soil body extrusion, underground water scouring, earthquake load and self-gravity load which can be borne by the prefabricated building structure 100 are improved. The deformed steel bar is a steel bar with a rib on the surface, and can better bear the action of external force due to the function of the rib and the larger bonding capacity of concrete. The first cage 30 is made of prestressed steel bars, so that the solid portion 20 and the hollow portion 10 have high vertical stress capability, and an integral stress foundation is formed. The tensioning machine can be connected with the first axial rib body 31, prestress is applied to the first axial rib body 31, and bearing capacity of the prefabricated building structure 100 is improved; the tensioning machine and the first axial rib body 31 are connected simply and conveniently, so that the construction time can be shortened, and the construction cost can be reduced.
It is understood that the outer edge of the cross section of the first cage 30 is circular or polygonal, and the polygonal is triangular, square/rectangular, pentagonal, hexagonal, etc., which are not listed here.
With such an arrangement, the first cages 30 of different shapes can be designed according to the practical application and the corresponding stress condition of the prefabricated building structure 100, so as to achieve different force bearing effects.
In one embodiment of the present invention, the first cage 30 is made of prestressed steel bars.
According to the arrangement, before the prefabricated building structure 100 is used, prestress is applied to the steel bars in advance through a pre-tensioning method or a post-tensioning method to form prestressed steel bars, when the prefabricated building structure 100 bears tensile force generated by external load, the existing prestress in concrete is firstly counteracted, then the prestressed steel bars are stressed, and finally, the concrete is tensioned and then cracks appear along with the increase of the load, so that the appearance and the development of the cracks of the prefabricated building structure 100 are delayed, and the loads such as soil body extrusion, underground water scouring, earthquake load and self-gravity load which can be borne by the prefabricated building structure 100 are improved. The deformed steel bar is a steel bar with a rib on the surface, and can better bear the action of external force due to the function of the rib and the larger bonding capacity of concrete. The first cage 30 is made of prestressed steel bars, so that the solid portion 20 and the hollow portion 10 have high vertical stress capability, and an integral stress foundation is formed.
In one embodiment of the present invention, the first cage 30 comprises a first axial rib 31 and a first radial rib 32, the first axial ribs 31 forming a frame of the first cage 30, the first radial rib 32 spirally surrounding the frame of the first cage 30; the first radial rib 32 and the first axial rib 31 are fixed by spot welding.
With the arrangement, the first cage body 30 has high bearing strength and simple processing, and only the first radial rib bodies 32 are wound on the frame formed by the first axial rib bodies 31 while the plurality of first axial rib bodies 31 are axially transported, so that the working hours are saved; and can increase the number of turns and the encryption length that first radial muscle body 32 spirals around at the great position of atress degree as required, for example increase the number of turns and the encryption length that first radial muscle body 32 spirals around at the both ends of first cage 30, prevent that prefabricated building structure 100 from suffering structural failure when burying underground the excessive strength of bearing.
It is understood that, in other embodiments, the first radial rib 32 and the first axial rib 31, and the second axial rib 41 and the second radial rib 42 may be fixed by snapping, binding, or the like, which is not listed here.
In one embodiment, the first axial reinforcement 31 is made of at least one of a steel bar for prestressed concrete (PC steel bar), a stainless steel bar, a hot rolled steel bar, a medium strength prestressed wire, a stress relief wire, a stranded wire, and a prestressed twisted steel; and/or the presence of a catalyst in the reaction mixture,
the first radial rib 32 is made of at least one of a steel bar for prestressed concrete (PC steel bar), a stainless steel bar, a hot rolled steel bar, a medium strength prestressed wire, a stress-relief wire, a strand, a prestressed twisted steel, a low carbon hot rolled steel disc strip, and a cold drawn low carbon wire for concrete products.
Preferably, the hollow portion 10 and the solid portion 20 are made of a concrete material, and the outer peripheral walls of the hollow portion 10 and the solid portion 20 are substantially the same shape.
In one embodiment of the present invention, the prefabricated building structure 100 further comprises a second cage 40, the second cage 40 being disposed within the solid portion 20, the first cage 30 being disposed within the solid portion 20 and the hollow portion 10 and enclosing the second cage 40.
With such an arrangement, the arrangement of the second cage body 40 improves the local reinforcement ratio at the solid part 20, so that the longitudinal stress capacity and the anti-shearing force capacity are not lowered or raised relative to the solid pile, and the tensile capacity, the compressive capacity, the seismic capacity and the durability of the prefabricated building structure 100 are improved.
In one embodiment, the prefabricated building structure 100 is a partially hollow square pile. At this time, the prefabricated building structure 100 is substantially rectangular parallelepiped, the hollow portion 10 and the solid portion 20 are also substantially rectangular parallelepiped and made of concrete, and a core groove 11 having a cylindrical peripheral wall is opened in the middle of the hollow portion 10; the second cage 40 and the first cage 30 are both substantially rectangular, the second cage 40 is disposed in the solid portion 20, the first cage 30 is disposed in the hollow portion 10 and the solid portion 20, and the second cage 40 is fitted over the first cage 30.
It is understood that in other embodiments, the prefabricated building structure 100 may also be substantially cylindrical or polygonal (e.g., triangular, pentagonal, hexagonal, octagonal, etc.) cylindrical; the peripheral wall of the core hole 11 may have a polygonal (e.g., triangular, square, rectangular, pentagonal, hexagonal, octagonal, etc.) cylindrical shape.
In one embodiment of the present invention, the second cage 40 extends onto the end of the solid portion 20 relatively far from the hollow portion 10.
With such an arrangement, the end portion of the solid portion 20 relatively far away from the hollow portion 10 can be supported by the second cage 40, so as to prevent the end portion of the solid portion 20 from deforming and falling off during use or service, and the end portion of the solid portion 20 can bear larger pressure when the prefabricated building structure 100 is buried underground, and the prefabricated building structure 100 can be buried underground quickly.
In other embodiments, the second cage 40 may be located inside the solid portion 20, which may prevent the second cage 40 from being exposed to air and corroded.
It is understood that the outer edge of the cross-section of the second cage 40 is circular or polygonal, and the polygonal shape is triangular, square/rectangular, pentagonal, hexagonal, etc., which are not listed here.
With the arrangement, the second cages 40 in different shapes can be designed according to the practical application and the corresponding stress condition of the prefabricated building structure 100, so as to achieve different force bearing effects.
In one embodiment of the present invention, the second cage 40 is made of prestressed or threaded steel.
So set up, second cage 40 can select prestressing steel or screw-thread steel as required, and prestressing steel can further improve prefabricated building structure 100's vertical atress ability, and the screw-thread steel can reduce prefabricated building structure 100's cost of manufacture.
In one embodiment of the present invention, the second cage 40 comprises a second axial rib 41 and a second radial rib 42, the second axial ribs 41 forming a frame of the second cage 40, the second radial rib 42 spirally surrounding the frame of the second cage 40; the second radial rib 42 and the second axial rib 41 are fixed by spot welding.
With the arrangement, the second cage body 40 and the first cage body 30 are simple and convenient in processing method and easy to produce, and meanwhile, the binding force between the axial rib bodies and the radial rib bodies is strong, so that the cage body is high in strength and not easy to deform in the using process.
In one embodiment, the second axial rib body 41 is made of at least one of deformed steel bars, steel bars for prestressed concrete (PC steel bars), stainless steel bars, hot rolled steel bars, medium strength prestressed wires, stress relief wires, steel strands, and prestressed deformed steel bars; and/or the presence of a catalyst in the reaction mixture,
the second radial rib 42 is made of at least one of deformed steel bars, prestressed concrete steel bars (PC steel bars), stainless steel bars, hot-rolled steel bars, medium-strength prestressed steel wires, stress-relief steel wires, steel strands, prestressed twisted steel bars, low-carbon steel hot-rolled disc strips, and cold-drawn low-carbon steel wires for concrete products.
It is understood that the first cage 30 and the second cage 40 may be provided simultaneously or alternatively.
In one embodiment of the present invention, the prefabricated building structure 100 further includes a mounting plate 50, the mounting plate 50 being disposed on a wall surface of the core hole 11 near one end of the solid portion 20, and the second cage 40 extending to the mounting plate 50 and being coupled to the mounting plate 50.
So set up, the mounting panel 50 not only can make the second cage body 40 fixed, prevents that the second cage body 40 from warping and misplacing in the in-service process, can also prevent that the core print 11 from being close to the lateral wall of solid portion 20 relatively on the concrete drops, avoids the second cage body 40 to expose in the air, prevents the corruption of the second cage body 40, influences the use strength of the second cage body 40.
Specifically, the mounting plate 50 is a steel plate. The second cage 40 is welded to the mounting plate 50.
In one embodiment of the present invention, the prefabricated building structure 100 further includes a corner protector 60, the corner protector 60 being disposed on an end of the solid portion 20 relatively far from the hollow portion 10, and/or the corner protector 60 being disposed on an end of the hollow portion 10 relatively far from the solid portion 20.
With such an arrangement, the precast building structure 100 can be prevented from falling off the concrete on the end of the precast building structure 100 during the process of being buried in the ground or during service, which causes the second cage 40 or the first cage 30 to be exposed to corrosion, so that the strength of the precast building structure 100 is reduced.
Specifically, the corner protector 60 is carbon structural steel, preferably Q235 steel; the thickness of the corner protector 60 is 0.5mm to 12mm, and the height of the corner protector 60 in the axial direction of the prefabricated building structure 100 is 60mm to 500 mm. Preferably, the corner protector 60 has a thickness of 1mm to 8mm, and the height of the corner protector 60 in the axial direction of the prefabricated building structure 100 is 80mm to 200 mm.
Referring to fig. 5, fig. 5 is a schematic structural diagram of the embedded connector 70 shown in fig. 1.
In one embodiment of the present invention, the first and/or second cage 30, 40 is provided with an embedded connector 70, and the embedded connector 70 is located at an end of the solid portion 20 relatively far from the hollow portion 10.
So configured, at the time of building construction, the prefabricated building structure 100 is generally required to be spliced with another prefabricated building structure to extend the length of the prefabricated building structure 100, or a cap 400 is poured after reinforcing bars are connected to the top of the prefabricated building structure 100 to bear superstructure. The second cage body 40 is provided with the embedded connecting piece 70, so that the combination rate of the two prefabricated building structures 100 can be increased; or the reinforcement ratio of the bearing platform 400 is improved, the connection mode between the prefabricated building structure 100 and the bearing platform 400 is simplified, the force transmission link in the stress process is reduced, the integral vertical stress capacity of the prefabricated building structure 100 is improved, and the mechanical property of the prefabricated building structure 100 and the bearing platform is guaranteed.
In one embodiment, the embedded connector 70 has an internal thread, the second axial rib 41 has an external thread, and the second axial rib 41 is connected with the embedded connector 70 through a thread.
In one embodiment, the pre-embedded connector 70 has a contraction opening 71 for connecting with the second axial rib 41 or the first axial rib 31; the end of the second axial rib 41 or the first axial rib 31 connected with the embedded connector 70 is provided with an upset 311, and the contraction opening 71 is used for limiting the upset 311.
In one embodiment of the present invention, the embedded connector 70 is further protruded with an annular protrusion 72 on the outer circumferential wall relatively near the end of the prefabricated building structure 100. Preferably, the outer diameter of the annular protrusion 72 is gradually reduced from the end part of the embedded connector 70 to the middle part; the outer peripheral wall of the annular projection 72 is an arc surface.
With such an arrangement, the annular protrusion 72 can homogenize the prestress, so that the prestress which can be borne by the second cage 40 and/or the first cage 30 during the pre-stretching is larger, and the damage of the pre-buried connecting piece 70 is prevented.
It should be noted that the embedded connectors 70 in the two prefabricated building structures 100 may be of the same type or different types, and may be selected according to the working conditions.
In one embodiment of the present invention, the embedded connector 70 is formed together with the prefabricated building structure 100. It is understood that in other embodiments, the pre-embedded connectors 70 may be later connected to the second cage 40 or the first cage 30. The operation steps are that the concrete at the end of the prefabricated building structure 100 is chiseled to expose the first axial direction reinforcing steel bar or the second axial direction reinforcing steel bar, then the embedded connector 70 is connected to the end of the first axial direction reinforcing steel bar or the second axial direction reinforcing steel bar, and then the end of the first axial direction reinforcing steel bar or the second axial direction reinforcing steel bar is formed with the upset 311 by hot working, thus completing the connection.
The prefabricated building structures 100 may be used not only alone, but in combination with a plurality of prefabricated building structures 100. For example, two, three, four or even more prefabricated building structures 100 may be docked for use as required by the operating conditions.
Referring to fig. 6, fig. 6 is a schematic view illustrating the butt joint of two prefabricated building structures 100.
In one embodiment, the first cage 30 of each of the two prefabricated building structures 100 is provided with a quick connector, and the two quick connectors can be connected by a quick docking assembly 200 to extend the length of the prefabricated building structure 100.
In one embodiment, the quick docking assembly 200 is a ferrous metal. Preferably, the quick dock assembly 200 is carbon steel or alloy steel. Specifically, the quick butt joint assembly 200 is carbon steel, chromium vanadium steel, chromium nickel steel, chromium molybdenum steel, chromium nickel molybdenum steel, chromium manganese silicon steel, ultra-high strength steel or stainless steel. It is understood that in other embodiments, the quick dock assembly 200 may be constructed of other materials.
Referring to fig. 7, fig. 7 is a schematic structural diagram of a quick docking assembly according to an embodiment.
The quick docking assembly 200 in the first embodiment includes a first docking station 210 and a first base 220, the first docking station 210 includes a first fixing portion 211, a first inserting portion 212 and a first extending portion 213 located between the first fixing portion 211 and the first inserting portion 212, the first base 220 includes a second fixing portion 221 and a plurality of fins 222 connected to the second fixing portion 221, the first docking station 210 is connected to the quick connector of one of the prefabricated building structures 100 through the first fixing portion 211, and the first base 220 is connected to the quick connector of another prefabricated building structure 100 through the second fixing portion 221; the first plug part 212 is convexly arranged on the first extension part 213, and a first step surface 214 is formed between the first plug part 212 and the first extension part 213; the plurality of fins 222 are arranged around each other; the first inserting stage 210 can pass through the openings defined by the plurality of fins 222 through elastic expansion of the fins 222, the fins 222 can elastically contract and enclose the first extending portion 213, and the end surfaces of the fins 222 and the first step surface 214 of the first inserting stage 210 are oppositely arranged.
In this embodiment, the rapid docking assembly 200 is used in a process that the first socket 210 is connected to the embedded connector 70 in one prefabricated building structure 100 through the first fixing portion 211, the first base 220 is connected to the embedded connector 70 in the other prefabricated building structure 100 through the second fixing portion 221, the first inserting portion 212 and the first extending portion 213 of the first socket 210 extend into the inner wall of the first base 220 and move along the inserting direction α, the first inserting portion 212 of the first socket 210 applies pressure to the fin 222 so that the fin 222 elastically expands until the first inserting portion 212 passes through the fin 222, the fin 222 elastically contracts and encloses the first extending portion 213 at the moment when the first inserting portion 212 passes through the fin 222, and when a force in a direction opposite to the inserting direction α is applied to the first socket 210, the end of the fin 222 abuts against the first step surface 214 between the first inserting portion 212 and the first extending portion 213 and limits the first socket 210.
The rapid docking assembly 200 and the embedded connector 70 provided by the embodiment are simple and convenient to mount, after the first plugging portion 212 of the first plugging platform 210 is inserted into the first base 220, the fin 222 can elastically contract and close the extension portion of the first base 220, the end portion of the fin 222 abuts against the step surface of the first plugging platform 210, and the abutting surface between the end portion of the fin 222 and the first step surface 214 of the first plugging platform 210 is approximately annular, so that the abutting area is large, the joint strength between two prefabricated building structures 100 can be ensured, and particularly, the vertical stress performance is greatly improved; the fins 222 not only can enclose the first extension part 213 of the insert table, but also can limit the first extension part 213, and prevent the first extension part 213 from shaking in the radial direction. In addition, the rapid docking assembly 200 provided by the embodiment has the advantages of simple processing technology, low cost and wide application range.
Referring to fig. 8, fig. 8 is a schematic structural diagram of another embodiment of a quick docking assembly 200.
The quick docking assembly 200 of the second embodiment includes a second socket 230, a second base 240 and a ring buckle 250, wherein the second socket 230 includes a third fixing portion 231 and a second plugging portion 232 disposed oppositely, and the second plugging portion 232 is formed with a first groove 233; the second base 240 includes a first end surface 241 and a second end surface 242 which are oppositely arranged; the ring buckle 250 has an opening (not shown) and can be elastically contracted, and the ring buckle 250 is sleeved on the second insert stage 230 and accommodated in the first groove 233; the ring buckle 250 can be inserted into the second base 240 along the insertion direction together with the second insertion portion 232 of the second socket 230, and the ring buckle 250 can abut against the second end surface 242 of the second base 240 through elastic expansion and limit the reverse movement of the second socket 230 along the insertion direction.
After the second inserting portion 232 of the second inserting stage 230 is inserted into the second base 240, the ring buckle 250 can be ejected out of the first groove 233 through the elastic expansion portion and abuts against the second end face 242 of the second base 240, an abutting surface between the ring buckle 250 and the second end face 242 is approximately annular, an abutting area is large, the joint strength between two embedded connectors 70 can be ensured, and particularly, the vertical stress performance is greatly improved. In addition, the rapid docking assembly 200 provided by the embodiment has the advantages of simple processing technology, low cost and wide application range.
It is understood that the insertion direction α may be, but is not limited to, the above-described directions, and that even partial angular offsets are intended to be within the scope of the present invention.
In one embodiment, after the two prefabricated building structures 100 are butted, a pile collar 300 is disposed on the peripheral wall of the junction between the two prefabricated building structures, and the pile collar 300 is used for fastening the butted joint of the two prefabricated building structures 100 to prevent the two prefabricated building structures 100 from being dislocated during use or service.
It is understood that the two prefabricated building structures 100 may be the same prefabricated pile or different prefabricated piles; the pile can be a solid pile, a hollow pile or a local hollow pile; can be a square pile or a tubular pile.
Referring to fig. 9, fig. 9 is a schematic structural diagram of the prefabricated building structure 100 and the platform 400.
In one embodiment, prefabricated building structure 100 is mated to a cap 400.
In this embodiment, the solid portion 20 of the prefabricated building structure 100 is connected to the cap 400. The ends of the second cage body 40 and the first cage body 30, which are relatively far away from the hollow part 10, are provided with pre-embedded connectors 70, the pre-embedded connectors 70 are fixedly connected with the force transmission rib bodies 410, a plurality of force transmission rib bodies 410 form a stress frame in the bearing platform 400, then concrete is poured into a mold, and the bearing platform 400 is formed after the concrete is dried and formed. In the embodiment, the second cage body 40 and the first cage body 30 are both provided with the embedded connecting pieces 70, so that the reinforcement ratio in the bearing platform 400 can be greatly improved, the bearing capacity of the bearing platform 400 can be improved, the force transmission link is reduced, and the method is safer and more reliable; but also better transfer the forces experienced by the cap 400 to the underlying foundation.
It is understood that in other embodiments, if the bearing platform 400 does not need to have very high bearing capacity, only the second cage 40 or the first cage 30 may be provided with the embedded connector 70 at the end relatively far from the hollow portion 10, and the embedded connector 70 is fixedly connected with the force transmission rib 410.
Referring to fig. 10, fig. 10 is a partially enlarged view of the portion C shown in fig. 9.
In one embodiment, the embedded connector 70 is provided with a through thread, one end of the embedded connector 70 is in threaded connection with the first axial rib 31 or the second axial rib 41, and the other end is in threaded connection with the force transmission rib 410.
Preferably, the force transmitting rib body 410 is a threaded steel.
It is understood that, in other embodiments, the embedded connector 70 may also be another type of steel bar, and the embedded connector 70 may also be fixedly connected to the first axial rib 31, the second axial rib 41, or the force transmission rib 410 by welding, clamping, or the like. Preferably, the embedded connector 70 is provided with an internal thread, the force transmission rib body 410 is provided with an external thread, and the two are connected in a threaded fit manner, so that the connection is simple and convenient, and the time cost during construction is saved.
The technical features of the above embodiments can be arbitrarily combined, and for the sake of brevity, all possible combinations of the technical features in the above embodiments are not described, but should be considered as the scope of the present specification as long as there is no contradiction between the combinations of the technical features.
It should be understood by those skilled in the art that the above embodiments are only for illustrating the present invention and are not to be used as a limitation of the present invention, and that suitable changes and modifications of the above embodiments are within the scope of the claimed invention as long as they are within the spirit and scope of the present invention.
Claims (10)
1. The prefabricated building structure (100) is characterized by comprising a pile body (101), wherein the pile body (101) comprises a hollow part (10) and a solid part (20) which are connected with each other, the hollow part (10) is hollow and surrounds to form a core groove (11), and the solid part (20) is relatively far away from the end part of the hollow part (10) and is provided with a glue storage groove (21).
2. Prefabricated building structure (100) according to claim 1, characterised in that said glue reservoir (21) has a depth in the axial direction of said prefabricated building structure (100) of 1mm to 200 mm.
3. Prefabricated building structure (100) according to claim 1, characterised in that the size of the circumferential wall of said glue reservoir (21) is equal to or smaller than the size of said core hole (11).
4. Prefabricated building structure (100) according to claim 1, characterised in that said glue reservoir (21) has a rectangular, trapezoidal, arched or triangular cross-sectional shape along the axial direction of said prefabricated building structure (100).
5. The prefabricated building structure (100) of claim 1, wherein said prefabricated building structure (100) further comprises a pile tip (102), said pile tip (102) being located at an end of said pile body (101), and said pile tip (102) being provided with a first protrusion (1021), said first protrusion (1021) being adapted to said glue storage groove (21).
6. Prefabricated building structure (100) according to claim 5, characterized in that said pile tip (102) is removably connected to said pile body (101).
7. Prefabricated building structure (100) according to claim 5, characterized in that said pile tip (102) is fixedly connected to said pile body (101).
8. The prefabricated building structure (100) of claim 5, wherein the prefabricated building structure (100) further comprises a pre-buried connector (70), the pre-buried connector (70) is disposed at an end of the pile body (101), the pile tip (102) is provided with a first through hole (1023), and the first through hole (1023) is aligned with the pre-buried connector (70).
9. The prefabricated building structure (100) of claim 8, wherein the prefabricated building structure (100) further comprises a detaching connector (80), and the detaching connector (80) is detachably connected with the embedded connector (70) through the first through hole (1023).
10. Prefabricated building structure (100) according to claim 8, characterized in that said first through holes (1023) have a filling plug therein for filling and sealing said first through holes (1023).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010130209.5A CN111206570A (en) | 2020-02-28 | 2020-02-28 | Prefabricated building structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010130209.5A CN111206570A (en) | 2020-02-28 | 2020-02-28 | Prefabricated building structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111206570A true CN111206570A (en) | 2020-05-29 |
Family
ID=70782947
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010130209.5A Pending CN111206570A (en) | 2020-02-28 | 2020-02-28 | Prefabricated building structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111206570A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111877325A (en) * | 2020-07-08 | 2020-11-03 | 许顺良 | Pile body angle bead cover and prefabricated building structure |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103938620A (en) * | 2014-04-10 | 2014-07-23 | 盐城市同力新型建材有限公司 | Fast pile connecting method for prestressed concrete precast piles and lock-type connector pile |
CN105040685A (en) * | 2015-06-09 | 2015-11-11 | 周兆弟 | Prefabricated member with hollow structure |
WO2017054402A1 (en) * | 2015-09-30 | 2017-04-06 | 连云港神舟新能源有限公司 | Corner bead for solar photovoltaic assembly |
CN110241857A (en) * | 2019-07-09 | 2019-09-17 | 沈阳建筑大学 | Underground pipe gallery section of jurisdiction waterproof splicing structure and its installation method |
KR20200013275A (en) * | 2018-07-30 | 2020-02-07 | 김상남 | A device that can be separated after entering a PHC pile using a steel pipe |
CN211898335U (en) * | 2020-02-28 | 2020-11-10 | 许顺良 | Prefabricated building structure |
-
2020
- 2020-02-28 CN CN202010130209.5A patent/CN111206570A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103938620A (en) * | 2014-04-10 | 2014-07-23 | 盐城市同力新型建材有限公司 | Fast pile connecting method for prestressed concrete precast piles and lock-type connector pile |
CN105040685A (en) * | 2015-06-09 | 2015-11-11 | 周兆弟 | Prefabricated member with hollow structure |
WO2017054402A1 (en) * | 2015-09-30 | 2017-04-06 | 连云港神舟新能源有限公司 | Corner bead for solar photovoltaic assembly |
KR20200013275A (en) * | 2018-07-30 | 2020-02-07 | 김상남 | A device that can be separated after entering a PHC pile using a steel pipe |
CN110241857A (en) * | 2019-07-09 | 2019-09-17 | 沈阳建筑大学 | Underground pipe gallery section of jurisdiction waterproof splicing structure and its installation method |
CN211898335U (en) * | 2020-02-28 | 2020-11-10 | 许顺良 | Prefabricated building structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111877325A (en) * | 2020-07-08 | 2020-11-03 | 许顺良 | Pile body angle bead cover and prefabricated building structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN215052912U (en) | Prefabricated building structure | |
CN211898332U (en) | Prefabricated building structure | |
CN211898335U (en) | Prefabricated building structure | |
CN111335300A (en) | Prefabricated building structure | |
CN211898334U (en) | Prefabricated building structure | |
CN111206570A (en) | Prefabricated building structure | |
CN211898333U (en) | Prefabricated building structure | |
CN212452596U (en) | Prefabricated building structure | |
CN212452597U (en) | Prefabricated building structure | |
CN212452594U (en) | Prefabricated building structure | |
CN212294622U (en) | Prefabricated building structure | |
CN212294628U (en) | Prefabricated building structure | |
CN212294624U (en) | Prefabricated building structure | |
CN212294623U (en) | Prefabricated building structure | |
CN212477702U (en) | Prefabricated building structure | |
CN212294625U (en) | Prefabricated building structure | |
CN212452595U (en) | Prefabricated building structure | |
CN111441341A (en) | Prefabricated building structure | |
CN212452598U (en) | Prefabricated building structure | |
CN212452593U (en) | Prefabricated building structure | |
CN212452613U (en) | Pile body angle bead cover and prefabricated building structure | |
CN111172978A (en) | Prefabricated building structure | |
CN111206571A (en) | Prefabricated building structure | |
CN111172979A (en) | Prefabricated building structure | |
CN111206568A (en) | Prefabricated building structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |