CN111173543A - Heat-insulation high-temperature-resistant structure of high-ground-temperature diversion tunnel and construction method thereof - Google Patents

Heat-insulation high-temperature-resistant structure of high-ground-temperature diversion tunnel and construction method thereof Download PDF

Info

Publication number
CN111173543A
CN111173543A CN202010122438.2A CN202010122438A CN111173543A CN 111173543 A CN111173543 A CN 111173543A CN 202010122438 A CN202010122438 A CN 202010122438A CN 111173543 A CN111173543 A CN 111173543A
Authority
CN
China
Prior art keywords
temperature
layer
heat
insulating
resistant structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010122438.2A
Other languages
Chinese (zh)
Inventor
姜海波
侍克斌
王凯生
王海娟
杨丰春
惠强
李唱唱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shihezi University
Original Assignee
Shihezi University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shihezi University filed Critical Shihezi University
Priority to CN202010122438.2A priority Critical patent/CN111173543A/en
Publication of CN111173543A publication Critical patent/CN111173543A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a heat-insulating high-temperature-resistant structure of a high-ground-temperature diversion tunnel and a construction method thereof, which relate to the technical field of hydraulic engineering, wherein the structure comprises a combined supporting structure; the combined supporting structure comprises an anchor rod, a fiber concrete layer and a mesh-hanging reinforcing steel layer which are sequentially laid from the hole wall to the center along the hole diameter, a composite heat-insulating lining is laid in the mesh-hanging reinforcing steel layer, and the composite heat-insulating lining comprises a heat-insulating layer, a waterproof protective layer and a molded concrete layer which are sequentially arranged. The heat-insulating high-temperature-resistant structure of the high-ground-temperature diversion tunnel and the construction method thereof provided by the invention have the advantages that the temperature stress in the tunnel is reduced, and the stability of the tunnel is improved.

Description

Heat-insulation high-temperature-resistant structure of high-ground-temperature diversion tunnel and construction method thereof
Technical Field
The invention relates to the technical field of hydraulic engineering, in particular to a heat-insulating and high-temperature-resistant structure of a high-ground-temperature diversion tunnel and a construction method thereof.
Background
The western regions of China are severe in environment and complex in geological structure, and in hydraulic engineering construction, many engineering geological problems such as seepage, rock burst, high ground temperature and high ground stress often occur, wherein the high ground temperature is a common geological disaster in underground caverns. The Hadbit hydropower station is positioned in an upstream main stream river section of the frontal Qissy river, is a long-tunnel high-head water diversion type hydropower station, and has high-temperature geothermal disasters in partial tunnel sections, the average temperature in the tunnel is as high as 51 ℃, the water temperature change in winter and summer is large, and the tunnel sections belong to high-ground-stress areas, so the construction difficulty is large; the Qihaha Tuer hydropower station engineering is positioned on a TashKuer dry river in TashKuer Ganjik county of KashShi city of Uygur autonomous region, Xinjiang, and has the pile numbers of water diversion tunnels between 8+200-9+400, the actual measurement of the temperature of the tunnel wall can reach 90 ℃ at most, the water temperature for many years is only about 7 ℃, the tunnel wall belongs to a high ground stress area, and the influence of temperature stress is obviously unreasonable without consideration in the structural design process; in a Brillon-Gorgol hydropower station in a karyon mountain area, the problem of high ground temperature exists in a hole section (with the pile number of 2+688 m-6 +799m), the initial highest temperature is 105 ℃, the temperature of a rock mass is generally measured at 60-80 ℃ in the follow-up process, and the hole section belongs to an extremely high rock temperature hole section. Most scholars analyze the temperature and stress change rules of surrounding rocks and supporting structures under the high ground temperature working condition, but the study on the aspect of heat insulation material selection in the process of designing the composite supporting structure is less, most scholars only put forward the principle of heat insulation material selection, and the material comparison analysis is less performed on the overall performance of the supporting structure. By analyzing the temperature change rule and the stress characteristic of surrounding rocks of the high-ground-temperature diversion tunnel, a heat-insulating high-temperature-resistant structure suitable for the diversion tunnel in the high-temperature area is developed, and the heat-insulating high-temperature-resistant structure has important engineering significance and social benefit for solving the technical problems of the engineering of the underground cavern and the diversion tunnel in the high-temperature area and promoting the comprehensive prevention and control technology of rock disasters of the underground cavern in the high-temperature area in China.
In the high ground temperature diversion tunnel excavation process, the temperature is too high in the hole not only can reduce construction operation efficiency, still can threaten constructor's life safety under the serious condition, in addition, makes the interior cooling of hole through the ventilation effect, can produce additional temperature stress with the inside self high temperature of country rock, and additional temperature stress can arouse the lining cutting fracture to influence the stability of whole tunnel.
Disclosure of Invention
The invention aims to provide a heat-insulating high-temperature-resistant structure of a high-ground-temperature diversion tunnel and a construction method thereof, which are used for solving the problems in the prior art, reducing the temperature stress in the tunnel and improving the stability of the tunnel.
In order to achieve the purpose, the invention provides the following scheme:
the invention provides a heat-insulating high-temperature-resistant structure of a high-ground-temperature diversion tunnel, which comprises a combined supporting structure; the combined supporting structure comprises an anchor rod, a fiber concrete layer and a mesh-hanging reinforcing steel layer which are sequentially laid from the hole wall to the center along the hole diameter, a composite heat-insulating lining is laid in the mesh-hanging reinforcing steel layer, and the composite heat-insulating lining comprises a heat-insulating layer, a waterproof protective layer and a molded concrete layer which are sequentially arranged.
Optionally, the anchor rods are arranged in a quincunx structure, the length of each anchor rod is 3m, the diameter of each anchor rod is 25mm, and the interval row spacing is 2m by 2 m.
Optionally, the fiber concrete layer has a thickness of 10cm and a barrier rating of at least W8.
Optionally, the diameter of the steel bar of the mesh hanging steel bar layer is 8mm, and the mesh spacing is 200mm by 200 mm.
Optionally, the heat insulation layer is formed by laying polystyrene foam polystyrene boards with the thickness of 10 cm.
Optionally, the waterproof layer is a CPU polyurethane waterproof coating layer, and the thickness is 1-2 mm.
Optionally, the thickness of the molded concrete layer is 40 cm.
The invention also provides a construction method of the heat-insulating high-temperature-resistant structure of the high-ground-temperature diversion tunnel, which comprises the following steps:
step one; checking the size of the opened section, cleaning the sprayed section, spraying 5cm thick fiber concrete for the first time, adding a high-efficiency setting accelerator, drilling holes, washing with cold water, applying a cement explosive roll anchor rod as an anchor rod immediately, laying a steel bar net layer, cleaning dust and spraying 5cm thick fiber concrete again;
step two; laying a heat insulation layer, prefabricating a polystyrene foam polystyrene board outside the hole according to the size of the cavity, and bonding the boards by using a polystyrene bonding material;
step three; spraying a CPU polyurethane waterproof coating on the base surface of the laid heat insulation layer, wherein the thickness of the CPU polyurethane waterproof coating is 1-2 mm;
step four; after the laying quality of the waterproof protective layer is checked, pouring a common concrete lining by adopting a molding method, wherein the concrete is marked as C25 and the thickness is 40 cm;
step five; expansion joints are arranged every 50 meters, the width of each joint is 3cm, and the joints are filled with flexible and compressible materials.
Compared with the prior art, the invention has the following technical effects:
the thermal insulation high temperature resistant structure outer layer middle spraying layer of the high-ground-temperature diversion tunnel provided by the invention is a fiber concrete spraying layer, so that the conductivity of the spraying layer is improved, the tensile strength of the spraying layer is improved, the influence of additional temperature stress on the spraying layer is reduced, and the probability of being pulled apart is reduced. In addition, the fiber concrete has higher conductivity than common concrete, and is relatively superior in other properties, such as seepage resistance, compressive strength and the like. Compared with the method of directly using the mixed concrete with heat insulation effect as the permanent lining, the strength and the toughness of the lining to cope with the temperature stress caused by the sudden temperature difference are relatively unstable. The structure of the invention can design the whole heat-insulating high-temperature-resistant structure aiming at different hole diameters according to similar high-ground temperature disasters.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without inventive exercise.
FIG. 1 is a schematic view of a heat-insulating and high-temperature-resistant structure of the high-ground-temperature diversion tunnel of the invention;
FIG. 2 is a detailed sectional view of the heat-insulating and high-temperature-resistant structure of the high-ground-temperature diversion tunnel according to the present invention;
wherein, 1 is the stock, 2 is the fibre concrete layer, 3 is the hanging net reinforcing bar layer, 4 is the insulating layer, 5 is the waterproof protective layer, 6 is the mould concrete layer.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention aims to provide a heat-insulating high-temperature-resistant structure of a high-ground-temperature diversion tunnel and a construction method thereof, which are used for solving the problems in the prior art, reducing the temperature stress in the tunnel and improving the stability of the tunnel.
In order to make the aforementioned objects, features and advantages of the present invention comprehensible, embodiments accompanied with figures are described in further detail below.
The invention provides a heat-insulating high-temperature-resistant structure of a high-ground-temperature diversion tunnel, which comprises a combined supporting structure as shown in figures 1 and 2; the combined supporting structure comprises an anchor rod 1, a fiber concrete layer 2 and a mesh-hanging reinforcing steel layer 3 which are sequentially paved from the hole wall to the center along the hole diameter, a composite heat-insulating lining is paved in the mesh-hanging reinforcing steel layer 3, and the composite heat-insulating lining comprises a heat-insulating layer 4, a waterproof protective layer 5 and a molded concrete layer 6 which are sequentially arranged.
Further preferably, the anchor rods 1 are arranged in a quincunx structure, the length of each anchor rod 1 is 3m, the diameter of each anchor rod 1 is 25mm, and the spacing is 2m by 2 m. The fibre concrete layer 2 has a thickness of 10cm and a impermeability rating of at least W8. The diameter of the steel bar of the mesh hanging steel bar layer 3 is 8mm, and the mesh interval is 200mm x 200 mm. The heat insulation layer 4 is formed by laying polystyrene foam polystyrene boards with the thickness of 10 cm. The waterproof protective layer 5 is a CPU polyurethane waterproof coating layer with the thickness of 1-2 mm. The thickness of the molded concrete layer 6 was 40 cm.
The construction method of the heat insulation high temperature resistant structure comprises the following steps: checking the size of the opened section, cleaning the sprayed section, primarily spraying C25 fiber concrete with the thickness of about 5cm, adding a high-efficiency accelerator, shortening the initial setting time of the concrete, then drilling, paving the anchor rod 1 in a quincunx shape, flushing the drilled hole with cold water, reducing the temperature in the hole, immediately applying the anchor rod 1 as a cement explosive roll anchor rod to meet the requirement of drawing force, then paving a net hanging reinforcing steel bar layer 3, and after cleaning dust, re-spraying C25 fiber concrete with the thickness of 5 cm. In order to ensure that the thermal insulation layer 4 laid later is tightly attached to the sprayed layer, the base surface of the sprayed layer needs to be trimmed and leveled.
The material of the heat insulation layer 4 is polystyrene foam polystyrene board, and when the heat insulation layer 4 is laid, the polystyrene foam polystyrene board can be prefabricated outside the hole according to the size of the cavity, and the size is generally 1m multiplied by 1m or 1m multiplied by 1.5 m. In addition, when the polystyrene foam polystyrene board is laid, the polystyrene foam polystyrene board with good flexibility is selected, and the polystyrene foam polystyrene board is bonded with the polystyrene foam polystyrene board by using a polystyrene bonding material.
CPU polyurethane waterproof paint is required to be sprayed on the base surface of the heat insulation layer 4 after the paving is finished, the thickness is 1-2mm, and the purpose is to prevent the heat insulation layer 4 from being damaged and increase the waterproof performance of the structure during the construction of the mold concrete lining.
After the laying quality of the waterproof protective layer is checked, in order to enable the concrete lining to be tightly attached to the waterproof protective layer, a common concrete lining is poured by a mould building method, the concrete label is C25, the thickness is 40cm, and finally, a heat-insulation high-temperature-resistant structure suitable for the diversion tunnel in the high-ground-temperature area is formed.
In order to avoid the damage of the tunnel to the inner-layer composite heat insulation lining caused by the extrusion stress of the tunnel along the length direction caused by the additional temperature stress generated by ventilation construction under the condition of high temperature, expansion joints are arranged at every 50 meters, the width of each expansion joint is 3cm, and flexible compressible materials are filled in the expansion joints, such as: polyurethane sealing paste, flexible resin and the like. When the outer layer combined support in the tunnel heat-insulation high-temperature-resistant structure is used, the adopted construction sequence of spraying, anchoring and spraying is suitable for surrounding rocks with short self-stabilization time.
Compared with C25 common concrete, the C25 fiber concrete used for outer layer combined support has larger conductivity coefficient, and aims to reduce the temperature difference inside and outside a sprayed layer, reduce temperature stress, improve tensile strength and prevent the sprayed layer from tensile damage. The polystyrene foam polystyrene plate adopted in the inner layer composite heat insulation lining has the thickness of 10cm, and is reasonably selected by combining with economic conditions within the high-efficiency performance range obtained by finite element software simulation.
The invention can also change the fiber concrete spray layer into steel fiber concrete spray layer, and for the surrounding rock with higher hardness, the self strength of the spray layer meets the requirement, and the anchor rod can be eliminated.
The principle and the implementation mode of the invention are explained by applying a specific example, and the description of the embodiment is only used for helping to understand the method and the core idea of the invention; meanwhile, for a person skilled in the art, according to the idea of the present invention, the specific embodiments and the application range may be changed. In view of the above, the present disclosure should not be construed as limiting the invention.

Claims (8)

1. The utility model provides a thermal-insulated high temperature resistant structure of high ground temperature diversion tunnel which characterized in that: comprises a combined supporting structure; the combined supporting structure comprises an anchor rod, a fiber concrete layer and a mesh-hanging reinforcing steel layer which are sequentially laid from the hole wall to the center along the hole diameter, a composite heat-insulating lining is laid in the mesh-hanging reinforcing steel layer, and the composite heat-insulating lining comprises a heat-insulating layer, a waterproof protective layer and a molded concrete layer which are sequentially arranged.
2. The high-geothermal diversion tunnel heat-insulating high-temperature-resistant structure according to claim 1, characterized in that: the anchor rods are arranged in a quincunx structure, the length of each anchor rod is 3m, the diameter of each anchor rod is 25mm, and the spacing is 2m x 2 m.
3. The high-geothermal diversion tunnel heat-insulating high-temperature-resistant structure according to claim 1, characterized in that: the fiber concrete layer has a thickness of 10cm and a impermeability rating of at least W8.
4. The high-geothermal diversion tunnel heat-insulating high-temperature-resistant structure according to claim 3, characterized in that: the diameter of the steel bar of the mesh hanging steel bar layer is 8mm, and the mesh interval is 200mm x 200 mm.
5. The high-geothermal diversion tunnel heat-insulating high-temperature-resistant structure according to claim 1, characterized in that: the heat insulation layer is formed by laying polystyrene foam polystyrene boards with the thickness of 10 cm.
6. The high-geothermal diversion tunnel heat-insulating high-temperature-resistant structure according to claim 1, characterized in that: the waterproof protective layer is a CPU polyurethane waterproof coating layer, and the thickness of the waterproof protective layer is 1-2 mm.
7. The high-geothermal diversion tunnel heat-insulating high-temperature-resistant structure according to claim 2, characterized in that: the thickness of the molded concrete layer is 40 cm.
8. A construction method of a heat-insulating high-temperature-resistant structure of a high-ground-temperature diversion tunnel is characterized by comprising the following steps of: the method comprises the following steps:
step one; checking the size of the opened section, cleaning the sprayed section, spraying 5cm thick fiber concrete for the first time, adding a high-efficiency setting accelerator, drilling holes, washing with cold water, applying a cement explosive roll anchor rod as an anchor rod immediately, laying a steel bar net layer, cleaning dust and spraying 5cm thick fiber concrete again;
step two; laying a heat insulation layer, prefabricating a polystyrene foam polystyrene board outside the hole according to the size of the cavity, and bonding the boards by using a polystyrene bonding material;
step three; spraying a CPU polyurethane waterproof coating on the base surface of the laid heat insulation layer, wherein the thickness of the CPU polyurethane waterproof coating is 1-2 mm;
step four; after the laying quality of the waterproof protective layer is checked, pouring a common concrete lining by adopting a molding method, wherein the concrete is marked as C25 and the thickness is 40 cm;
step five; expansion joints are arranged every 50 meters, the width of each joint is 3cm, and the joints are filled with flexible and compressible materials.
CN202010122438.2A 2020-02-27 2020-02-27 Heat-insulation high-temperature-resistant structure of high-ground-temperature diversion tunnel and construction method thereof Pending CN111173543A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010122438.2A CN111173543A (en) 2020-02-27 2020-02-27 Heat-insulation high-temperature-resistant structure of high-ground-temperature diversion tunnel and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010122438.2A CN111173543A (en) 2020-02-27 2020-02-27 Heat-insulation high-temperature-resistant structure of high-ground-temperature diversion tunnel and construction method thereof

Publications (1)

Publication Number Publication Date
CN111173543A true CN111173543A (en) 2020-05-19

Family

ID=70656893

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010122438.2A Pending CN111173543A (en) 2020-02-27 2020-02-27 Heat-insulation high-temperature-resistant structure of high-ground-temperature diversion tunnel and construction method thereof

Country Status (1)

Country Link
CN (1) CN111173543A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101985882A (en) * 2010-08-10 2011-03-16 中铁二十局集团有限公司 Construction method of rigid primary support of mould-building concrete of plateau permafrost tunnel
JP2011167510A (en) * 2010-01-21 2011-09-01 Furukawa Electric Co Ltd:The Piping structure for tunnel fire extinguisher, branch structure of pipe for tunnel fire extinguisher, heat insulation structure of pipe for tunnel fire extinguisher, and method of preventing reduction in strength of pipe for tunnel fire extinguisher
CN102230385A (en) * 2011-06-03 2011-11-02 中铁二院工程集团有限责任公司 Heat-resistant lining structure of tunnel with high ground temperature
CN202073573U (en) * 2011-06-03 2011-12-14 中铁二院工程集团有限责任公司 High-ground-temperature heat-resistant and heat-proof tunnel lining structure
CN104695980A (en) * 2015-03-11 2015-06-10 中水北方勘测设计研究有限责任公司 Hydropower diversion tunnel lining structure applied to rock burst regions with high burial depth, high ground temperature and high ground stress
CN204511468U (en) * 2015-03-02 2015-07-29 成都理工大学 A kind of High-geotemperature tunnel heat insulation and dissipation liner structure
CN106320296A (en) * 2016-11-02 2017-01-11 广西大学 Basalt fiber grid reinforced lining structure for high ground temperature high-pressure hydraulic tunnel
CN207245730U (en) * 2017-06-02 2018-04-17 安徽理工大学 A kind of deep High-geotemperature tunnel heat-insulation liner structure
CN211777496U (en) * 2020-02-27 2020-10-27 石河子大学 Heat-insulating high-temperature-resistant structure of high-ground-temperature diversion tunnel

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011167510A (en) * 2010-01-21 2011-09-01 Furukawa Electric Co Ltd:The Piping structure for tunnel fire extinguisher, branch structure of pipe for tunnel fire extinguisher, heat insulation structure of pipe for tunnel fire extinguisher, and method of preventing reduction in strength of pipe for tunnel fire extinguisher
CN101985882A (en) * 2010-08-10 2011-03-16 中铁二十局集团有限公司 Construction method of rigid primary support of mould-building concrete of plateau permafrost tunnel
CN102230385A (en) * 2011-06-03 2011-11-02 中铁二院工程集团有限责任公司 Heat-resistant lining structure of tunnel with high ground temperature
CN202073573U (en) * 2011-06-03 2011-12-14 中铁二院工程集团有限责任公司 High-ground-temperature heat-resistant and heat-proof tunnel lining structure
CN204511468U (en) * 2015-03-02 2015-07-29 成都理工大学 A kind of High-geotemperature tunnel heat insulation and dissipation liner structure
CN104695980A (en) * 2015-03-11 2015-06-10 中水北方勘测设计研究有限责任公司 Hydropower diversion tunnel lining structure applied to rock burst regions with high burial depth, high ground temperature and high ground stress
CN106320296A (en) * 2016-11-02 2017-01-11 广西大学 Basalt fiber grid reinforced lining structure for high ground temperature high-pressure hydraulic tunnel
CN207245730U (en) * 2017-06-02 2018-04-17 安徽理工大学 A kind of deep High-geotemperature tunnel heat-insulation liner structure
CN211777496U (en) * 2020-02-27 2020-10-27 石河子大学 Heat-insulating high-temperature-resistant structure of high-ground-temperature diversion tunnel

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
"隧道工程", vol. 1, 30 September 2013, 成都:西南交通大学出版社, pages: 211 - 212 *
袁培国: "超高地温条件下引水隧洞施工关键技术探讨", 水利水电技术, vol. 45, no. 4, 20 April 2014 (2014-04-20), pages 101 - 106 *

Similar Documents

Publication Publication Date Title
Ansell Investigation of shrinkage cracking in shotcrete on tunnel drains
CN101985882B (en) Construction method of rigid primary support of mould-building concrete of plateau permafrost tunnel
CN110617067B (en) Low-risk construction method for full-section boundary advanced pipe shed of extremely-soft surrounding rock tunnel
CN108301531A (en) Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node
CN105003020A (en) Ceramsite concrete metal net rack light wallboard and splicing structure thereof
CN113107525A (en) Support system for extruded large-deformation tunnel, construction method and application
CN211777496U (en) Heat-insulating high-temperature-resistant structure of high-ground-temperature diversion tunnel
CN206467824U (en) A kind of assembly concrete frame wall filled with masonry
Xu et al. Application of fabricated corrugated steel plate in subway tunnel supporting structure
US11821316B1 (en) System and construction method of single-layer lining tunnel structure based on mine-tunnelling method
CN102587329B (en) Arched combined faceplate for earth-rock dam and construction method thereof
CN111173543A (en) Heat-insulation high-temperature-resistant structure of high-ground-temperature diversion tunnel and construction method thereof
CN102433930A (en) Overground-underground bidirectional ultra-long concrete seamless design method
Yang et al. Closed cavity thin-wall components design for prefabricated underground subway structures
CN109404019B (en) Cave surrounding rock pre-supporting system and cave structure
CN214785202U (en) Building pipe shaft floor structure
Tong Research on application of multi-factor surrounding rock pressure calculation theory in engineering
CN103758256A (en) Decorative heat preservation composite wall and manufacturing method thereof
CN112012761A (en) Construction method of anti-disturbance double-arch tunnel structure
CN103924616A (en) Super-deep underground continuous wall pre-buried shear-force groove manufacturing and installing construction method
CN109440820A (en) It is a kind of to fill out sea or the internal immersed tube for being filled with construction waste of bridge
Fan et al. Key issues in rock mechanics of the Three Gorges Project in China
CN204715313U (en) A kind of underground workshop be arranged in solid rock
CN219691552U (en) Large-span underground cavern roof arch surrounding rock stability control device
CN218991620U (en) Lining structure for open TBM construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination