CN111173017A - Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well - Google Patents

Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well Download PDF

Info

Publication number
CN111173017A
CN111173017A CN202010196518.2A CN202010196518A CN111173017A CN 111173017 A CN111173017 A CN 111173017A CN 202010196518 A CN202010196518 A CN 202010196518A CN 111173017 A CN111173017 A CN 111173017A
Authority
CN
China
Prior art keywords
water
water seepage
pipe
seepage pipe
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010196518.2A
Other languages
Chinese (zh)
Inventor
陈耀武
姚志宝
郭庆海
曲德文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202010196518.2A priority Critical patent/CN111173017A/en
Publication of CN111173017A publication Critical patent/CN111173017A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/22Lining sumps in trenches or other foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention relates to the field of underground water control of reverse operation construction of ultra-deep foundation pits, in particular to a water stopping device for concrete pouring at the bottom of a reverse operation well of a cyclone well, which comprises a water collecting pit, a water seepage pipe and a submersible pump, wherein the water seepage pipe is arranged in the water collecting pit, water seepage holes are formed in the periphery of the pipe wall of the water seepage pipe, a manhole flange is arranged at the upper part of the water seepage pipe, and a water stopping ring is arranged on the water seepage pipe; the submersible pump is arranged in the water seepage pipe. The invention can effectively control the water under the cushion layer and the bottom plate concrete, report the anti-permeability quality of the concrete and reduce the construction cost.

Description

Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well
Technical Field
The invention relates to the field of underground water control of reverse operation construction of ultra-deep foundation pits, in particular to a water stopping device and a water stopping method for concrete pouring at the bottom of a reverse operation pit of a cyclone well.
Background
When the earthwork below the cyclone well is excavated, groundwater can overflow due to various geological factors, according to the current engineering characteristics, for the construction of an ultra-deep foundation pit, the construction quality is often ensured at the end of the foundation pit construction, the current common pouring of the concrete at the bottom of the well is mostly carried out after the groundwater level is reduced to the depth of 3-5 m below a concrete bottom plate cushion layer by adopting a deep foundation pit dewatering mode, the cost is not obviously increased under the high-quality geological condition, when the geological condition has rock strata or springs, the dewatering cost is sharply increased, and the dewatering effect and the concrete pouring quality are also difficult to guarantee. The special situation is that devices like 'pouring jacket bottom plate underwater plugging' and the like are adopted, although the devices successfully carry out bottom sealing operation on concrete, the cost is doubled, and the device is not an optimal engineering solution.
Disclosure of Invention
In order to solve the technical problems, the invention adopts the water stopping device and the water stopping method for concrete pouring at the bottom of the reverse operation well of the cyclone well, and aims to improve the working efficiency and reduce the construction cost while ensuring the construction quality.
The invention adopts the following preferred scheme:
a water stopping device for concrete pouring at the bottom of a reverse operation well of a cyclone well comprises a water collecting pit, a water seepage pipe and a submersible pump, wherein the water seepage pipe is arranged in the water collecting pit, water seepage holes are formed in the periphery of the pipe wall of the water seepage pipe, a manhole flange is arranged at the upper part of the water seepage pipe, and a water stopping ring is arranged on the water seepage pipe; the submersible pump is arranged in the water seepage pipe.
Compared with the prior art, the device has the beneficial effects that:
the device utilizes the mode of mechanical plugging of the perforated steel pipe welding manhole flange to control underground water under the cushion layer and the bottom plate concrete, so that the reinforcement and the concrete pouring are carried out in an anhydrous environment, the construction quality and the construction efficiency are improved, the anti-permeability quality of the concrete can be effectively ensured, and the construction cost is reduced.
Further, the preferred scheme adopted is as follows:
the periphery of the water seepage pipe is provided with steel wire mesh sheets.
The diameter of the sump is phi 800mm, and the depth is h =1000 mm.
The water seepage pipe is a steel pipe with the length of 4000mm and phi 630 multiplied by 10mm, and the periphery of the water seepage pipe is provided with holes phi 10mm @ 100.
A water stopping method for concrete pouring at the bottom of a reverse operation well of a cyclone well comprises the following steps:
A. deeply digging a water collecting pit with the diameter phi of 800mm and the depth h =1000mm at the vacant position before pouring the bottom plate concrete cushion layer;
B. taking a steel pipe which is 4000mm long and phi 630 multiplied by 10mm as a water seepage pipe, and opening holes phi 10mm @100 on the periphery of the water seepage pipe;
C. fixing the periphery of the drilled water seepage pipe by using a steel wire mesh sheet;
D. welding a flange with a manhole at the upper part of the water seepage pipe;
E. welding a water stop ring outside the water seepage pipe;
F. inserting the processed water seepage pipe into the water collecting pit;
G. opening a manhole flange, putting the submersible pump into the water seepage pipe, and continuously dewatering the pipe;
H. performing subsequent work such as concrete cushion layer pouring, bottom plate steel bar binding, concrete pouring and the like in time;
I. when the pumping of the water pump is basically completed, the submersible pump is withdrawn, the manhole of the flange is screwed down, underground water overflowing in the process of withdrawing the submersible pump is timely cleaned, and anti-corrosion treatment is carried out.
Compared with the prior art, the method has the beneficial effects that:
the method utilizes the steel pipe with the hole as the water seepage pipe and fixes the steel pipe by the steel wire mesh sheet, thereby preventing the soil body from collapsing and the submersible pump from being blocked on the premise that the steel pipe has the water seepage function, ensuring the submersible pump to pump water smoothly and improving the working efficiency of the submersible pump; the concrete pouring of the cushion layer and the bottom plate is timely carried out after short-term water inhibition is carried out by adopting the water seepage pipe, so that the construction operation is completed in an anhydrous environment, the construction speed is accelerated, the construction quality is ensured, and the construction cost is reduced.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is an enlarged view of portion A of FIG. 1;
in the figure: a sump 1; a water seepage pipe 2; water seepage holes 201; a submersible pump 3; a water stop ring 4; a manhole flange 5; a steel mesh sheet 6.
Detailed Description
The invention is further described below with reference to the accompanying drawings and specific embodiments.
A water stopping device for concrete pouring at the bottom of a reverse operation well of a cyclone well comprises a water collecting pit 1, a water seepage pipe 2 and a submersible pump 3, wherein the submersible pump 3 is arranged in the water seepage pipe 2.
Before pouring a bottom plate concrete cushion layer, deeply digging a water collecting pit 1 at an empty position near the pouring, wherein the diameter of the water collecting pit 1 is 800mm, and the depth of the water collecting pit 1 is 1000 mm; the water seepage pipe 2 is a steel pipe with the length of 4000mm and phi 630 multiplied by 10mm, water seepage holes 201 are formed in the periphery of the steel pipe within the range of 1000mm from bottom to top, and the size of each water seepage hole 201 is phi 10@100 (namely the distance between every two adjacent water seepage holes 201 is 100 mm); the periphery of the hole part of the water seepage pipe 2 is fixed by a steel wire mesh sheet 6, so that soil collapse and blockage of the submersible pump 3 in the water seepage process are prevented; the upper portion cover of infiltration pipe 2 is equipped with seal ring 4, and seal ring 4 is arranged in the top of sump 1 in, and the top welding of infiltration pipe 2 has manhole flange 5.
And excavating the water collecting pit 1, dredging underground water pressure and reasonably draining the water into the water collecting pit 1, and selecting a specific vacant position to combine the use functions of different cyclone pools to reduce the influence of the finally exposed manhole as much as possible.
The pipe wall of the water seepage pipe 2 is provided with holes, and the steel wire mesh sheets 6 are added, so that the water seepage pipe 2 has the functions of water seepage and water collection and can prevent soil body collapse and blockage of the submersible pump 3; the top welding manhole flange 5 of infiltration pipe 2 opens and puts into infiltration pipe 2 with powerful immersible pump 3 after the manhole in, can in time withdraw from immersible pump 3 smoothly when immersible pump 3 draws water and accomplish basically. The water stop ring 4 above the water collection pit 1 can achieve the effect of a rigid waterproof sleeve when the bottom plate is poured with concrete, and underground water is prevented from leaking from the side wall of the water seepage pipe.
The control of ground water level can only transient suppression, can not stop water completely, after the short-term restraines water in infiltration pipe 2, in time accomplish the bed course concrete placement, make this part reserve reinforcement speed accelerate and in time carry out bottom plate concrete placement, after whole process in time accomplished, make whole whirl well bottom of the pool and lateral wall and external soil body and water pressure form a balanced state, accomplish the bottom of the pool stagnant water effect promptly.
A water stopping method for concrete pouring at the bottom of a reverse operation well of a cyclone well comprises the following steps:
A. before pouring the bottom plate concrete cushion layer, a water collecting pit 1 with the diameter phi 800mm and the depth h =1000mm is dug deeply at an empty position near the pouring position.
B. A steel pipe with the length of 4000mm and the diameter of 630 multiplied by 10mm is used as a water seepage pipe 2, water seepage holes 201 are formed around the position 1000mm from bottom to top of the water seepage pipe 2, and the size of the water seepage holes 201 is the diameter of 10mm @ 100.
C. After the drilling of the water seepage pipe 2 is completed, the periphery of the position of the opening of the water seepage pipe 2 is fixed by the steel wire mesh sheets 6.
D. And a manhole flange 5 is welded at the top of the water seepage pipe 2.
E. And a water stop ring 4 is welded on the outer side of the upper part of the water seepage pipe 2, and the water stop ring 4 is arranged in the bottom plate concrete.
F. And inserting the processed water seepage pipe 2 into the water collecting pit 1.
G. And (3) opening the manhole flange 5, putting the submersible pump 3 into the water seepage pipe 2 and continuously carrying out precipitation treatment on the underground water in the seepage pipe 2.
H. The immersible pump 3 in the sump pit 1 is after the short-term restraines water, in time carries out follow-up work such as bed course concrete placement, reinforcement bottom plate, concrete placement.
I. After the bottom plate concrete pouring is finished, the strength reaches about 90%, when the submersible pump 3 pumps water basically, the submersible pump 3 is withdrawn and the manhole of the flange is screwed down, underground water which possibly overflows in the process of withdrawing the submersible pump 3 is timely cleaned, and the underground water is subjected to corrosion prevention treatment.
The above description is only for the specific embodiment of the present invention, but the protection of the present invention is not limited thereto, and all equivalent changes or substitutions to the technical features of the present invention that can be made by those skilled in the art are included in the protection scope of the present invention.

Claims (5)

1. The utility model provides a stagnant water device that contrary operation well bottom concrete placement of whirl well, includes sump pit, infiltration pipe and immersible pump, its characterized in that: the water seepage pipe is arranged in the water collecting pit, water seepage holes are formed in the periphery of the pipe wall of the water seepage pipe, a manhole flange is arranged at the upper part of the water seepage pipe, and a water stop ring is arranged on the water seepage pipe; the submersible pump is arranged in the water seepage pipe.
2. The water stopping device for concrete pouring at the bottom of the cyclone well reverse operation well according to claim 1, is characterized in that: the periphery of the water seepage pipe is provided with steel wire mesh sheets.
3. The water stopping device for concrete pouring at the bottom of the cyclone well reverse operation well according to claim 1, is characterized in that: the diameter of the sump is phi 800mm, and the depth is h =1000 mm.
4. The water stopping device for concrete pouring at the bottom of the cyclone well reverse operation well according to claim 1, is characterized in that: the water seepage pipe is a steel pipe with the length of 4000mm and phi 630 multiplied by 10mm, and the periphery of the water seepage pipe is provided with holes phi 10mm @ 100.
5. A water stopping device and a water stopping method for concrete pouring at the bottom of a reverse operation well of a cyclone well are characterized by comprising the following steps of:
A. deeply digging a water collecting pit with the diameter phi of 800mm and the depth h =1000mm at the vacant position before pouring the bottom plate concrete cushion layer;
B. taking a steel pipe which is 4000mm long and phi 630 multiplied by 10mm as a water seepage pipe, and opening holes phi 10mm @100 on the periphery of the water seepage pipe;
C. fixing the periphery of the drilled water seepage pipe by using a steel wire mesh sheet;
D. welding a flange with a manhole at the upper part of the water seepage pipe;
E. welding a water stop ring outside the water seepage pipe;
F. inserting the processed water seepage pipe into the water collecting pit;
G. opening a manhole flange, putting the submersible pump into the water seepage pipe, and continuously dewatering the pipe;
H. performing subsequent work such as concrete cushion layer pouring, bottom plate steel bar binding, concrete pouring and the like in time;
I. when the pumping of the water pump is basically completed, the submersible pump is withdrawn, the manhole of the flange is screwed down, underground water overflowing in the process of withdrawing the submersible pump is timely cleaned, and anti-corrosion treatment is carried out.
CN202010196518.2A 2020-03-19 2020-03-19 Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well Withdrawn CN111173017A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010196518.2A CN111173017A (en) 2020-03-19 2020-03-19 Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010196518.2A CN111173017A (en) 2020-03-19 2020-03-19 Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well

Publications (1)

Publication Number Publication Date
CN111173017A true CN111173017A (en) 2020-05-19

Family

ID=70647267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010196518.2A Withdrawn CN111173017A (en) 2020-03-19 2020-03-19 Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well

Country Status (1)

Country Link
CN (1) CN111173017A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112196076A (en) * 2020-09-23 2021-01-08 贵州建工集团第一建筑工程有限责任公司 Shallow formula job site drainage device that buries of case permeates water
CN114263201A (en) * 2021-12-23 2022-04-01 中建八局第二建设有限公司 Finished product self-flowing dewatering deep well pipe and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112196076A (en) * 2020-09-23 2021-01-08 贵州建工集团第一建筑工程有限责任公司 Shallow formula job site drainage device that buries of case permeates water
CN114263201A (en) * 2021-12-23 2022-04-01 中建八局第二建设有限公司 Finished product self-flowing dewatering deep well pipe and construction method thereof

Similar Documents

Publication Publication Date Title
CN105002913B (en) A kind of highly permeable stratum deep basal pit back cover water sealing structure and its construction method
CN104711994A (en) Foundation pit deep well rainfall and plugging construction method
CN111173017A (en) Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well
CN112761644A (en) Suspension sinking vertical shaft well completion process
CN202194149U (en) Water-proof curtain
CN112695803A (en) Supporting and water-stopping construction method for pipe-jacking working well and pipe ditch on beach
CN113279421A (en) Vacuum dewatering process for deep foundation pit
CN106480891B (en) A kind of shaft construction method
CN110409420B (en) Underground continuous wall with pit facing surface and precipitation function
CN212506349U (en) Water-logging well sealing device for water-lowering zone of ultra-deep foundation pit pipe well
CN212641468U (en) Pit-in-pit rapid construction structure
CN210341957U (en) Precipitation structure suitable for caisson
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN211898488U (en) Water stopping device for concrete pouring at bottom of reverse operation well of cyclone well
CN110670613B (en) Foundation pit elevator shaft water seepage prevention structure and construction method thereof
CN111733839A (en) Method for reinforcing receiving end of deep-buried shield water-rich sand layer next to excavation foundation pit
CN106498951A (en) A kind of shaft excavation construction method
CN206956731U (en) One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer
CN104846837A (en) Construction method for ultra-deep well pit in surface drainage foundation pit
CN211898587U (en) Rear-mounted thin-wall steel pipe water draining device for large bottom plate anti-floating
CN113605380A (en) Construction method of cast-in-situ bored pile
JP4011209B2 (en) Construction method of shaft
CN111042212A (en) Rear-mounted thin-wall steel pipe water draining device and method for large bottom plate anti-floating
CN217679207U (en) Underground structure Cheng Jiangshui wellhead plugging structure
CN218324953U (en) Shaft type vacuum underground laboratory supporting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20200519