CN111042841A - Tunnel water-proof and drainage construction process - Google Patents

Tunnel water-proof and drainage construction process Download PDF

Info

Publication number
CN111042841A
CN111042841A CN201910423020.2A CN201910423020A CN111042841A CN 111042841 A CN111042841 A CN 111042841A CN 201910423020 A CN201910423020 A CN 201910423020A CN 111042841 A CN111042841 A CN 111042841A
Authority
CN
China
Prior art keywords
construction
drainage
inspection well
tunnel
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910423020.2A
Other languages
Chinese (zh)
Inventor
古培峰
施正宝
李献民
陈保祥
刘伟
李永强
刘燕东
孟令辰
王薇
张建欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Civil And Agchitecural Engineering Institute Of Cccc-Fheb Ltd
CCCC First Highway Engineering Co Ltd
Original Assignee
Civil And Agchitecural Engineering Institute Of Cccc-Fheb Ltd
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Civil And Agchitecural Engineering Institute Of Cccc-Fheb Ltd, CCCC First Highway Engineering Co Ltd filed Critical Civil And Agchitecural Engineering Institute Of Cccc-Fheb Ltd
Priority to CN201910423020.2A priority Critical patent/CN111042841A/en
Publication of CN111042841A publication Critical patent/CN111042841A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a tunnel water-proof and drainage construction process, belongs to the technical field of tunnel construction, and solves the problem that a tunnel is easy to collapse in the construction process when the tunnel is subjected to water-proof and drainage construction; the technical characteristics are as follows: the method comprises the following steps: the method comprises the steps of installing the semicircular drain pipes on the surface of surrounding rock, enabling the diameter of each semicircular drain pipe to be 100cm, carrying out initial spraying on the semicircular drain pipes, enabling a primary spraying layer to be formed on the surfaces of the semicircular drain pipes, enabling the thickness of the primary spraying layer to be 2-5 cm, reserving the semicircular drain pipes after the initial spraying to the outside of a primary support, guaranteeing quick and safe discharge of accumulated water in the tunnel, guaranteeing normal operation of tunnel construction, avoiding potential safety hazards caused by water seepage in the tunnel, and being low in construction acceptance and good in waterproof effect.

Description

Tunnel water-proof and drainage construction process
Technical Field
The invention relates to the technical field of tunnel construction, in particular to a tunnel waterproof and drainage construction process.
Background
The tunnel is an engineering building buried in the stratum, the construction of highways and railways can not leave the tunnel, particularly the tunnel construction is an essential link in the process of road construction in the rugged areas such as hills, mountainous areas and the like. Compared with the construction of a flat road surface, the construction of the tunnel is more difficult, the construction period is longer, and the tunnel is always the key point and the difficulty point of one road construction.
In the tunnel construction process, how to avoid the tunnel water seepage is a technical problem, in order to avoid the condition of water seepage in the tunnel construction process, the tunnel needs to be subjected to water prevention and drainage construction in the tunnel construction process, and at the present stage, when the water prevention and drainage construction is carried out on the tunnel, hole collapse easily occurs in the tunnel in the construction process, so that the tunnel water prevention and drainage construction process is provided.
Disclosure of Invention
The invention aims to provide a tunnel water-proofing and drainage construction process, which aims to solve the problem that a tunnel is easy to collapse in the construction process when the tunnel is subjected to water-proofing and drainage construction.
In order to achieve the purpose, the invention provides the following technical scheme:
a tunnel water-proof and drainage construction process comprises the following steps:
s1, construction preparation;
s101, preparing technology, and calling address data and hydrogeological data of site construction before starting construction;
s102, taking technical performance data of the construction machinery and the corollary equipment thereof;
s103, retrieving a construction scheme of the pile foundation engineering with operability, test data of a construction process and engineering geological data;
s104, maintaining and repairing the construction mechanical equipment, and installing the construction mechanical equipment on a construction site;
s2, installing a semicircular drainage pipe on the surface of the surrounding rock, wherein the diameter of the semicircular drainage pipe is 100cm, then performing initial spraying on the semicircular drainage pipe, forming an initial spraying layer on the surface of the semicircular drainage pipe, wherein the thickness of the initial spraying layer is 2-5 cm, and reserving the semicircular drainage pipe after the initial spraying to the outside of an initial support;
s3, installing a semicircular drain pipe on the primary support surface, and installing a longitudinal drain pipe on the primary support surface after the semicircular drain pipe is safe;
s4, pre-burying a transverse drain pipe on the primary support surface, wherein a three-hole joint is arranged on the transverse drain pipe and is simultaneously communicated with a longitudinal drain pipe, and the longitudinal drain pipe and the transverse drain pipe are arranged vertically;
s5, measuring the thickness of sediments on the primary support surface, paving geotextile on the primary support surface, and paving a waterproof board after the geotextile is paved;
s6, pre-burying a transverse drainage pipe, then performing inverted arch backfill reservation, and digging a central drainage ditch at the upper part of the waterproof board;
s7, digging an inspection well and a sediment trap, sealing the central drainage ditch, and placing a central drainage ditch cover plate on the top of the central drainage ditch; then installing the inspection well and the cover of the sand sediment trap.
As a further scheme of the invention: in step S5, the waterproof board is an EVA flat waterproof board, the thickness of the waterproof board is 1.5mm, and the gram weight of the geotextile is 350g/m2
As a still further scheme of the invention: in step S6, the central drainage ditch is a rectangular drainage ditch of 60 × 60cm, the central drainage ditch is provided with sand sediment wells every 50m, each 250m is provided with an inspection well, no sand sediment well is provided at the inspection well, and both the sand sediment well and the inspection well are blind wells.
As a still further scheme of the invention: in the step S6, the inspection well is a closed-up concrete well, the inner diameter of the inspection well is 100cm, the depth of the inspection well is 250cm, the wall thickness of the inspection well is 20cm, the well body of the inspection well is made of C25 concrete, the well cover of the inspection well is made of C30 reinforced concrete, the diameter of the well cover of the inspection well is 100cm, the thickness of the well cover of the inspection well is 20cm, a single layer of reinforcing steel bars is arranged at the bottom of the well cover of the inspection well, and the thickness of the single layer of reinforcing steel bars is 5 cm.
As a still further scheme of the invention: in step S6, the sediment trap is a cylindrical concrete trap, the inner diameter of the sediment trap is 70cm, the depth of the sediment trap is 158cm, the wall thickness of the sediment trap is 20cm, the body of the sediment trap is made of C25 concrete, the cover of the sediment trap is made of C30 reinforced concrete, and the diameter of the cover of the sediment trap is 100 cm.
Compared with the prior art, the invention has the beneficial effects that: the invention ensures the rapid and safe discharge of accumulated water in the tunnel, ensures the normal operation of tunnel construction, can avoid potential safety hazard caused by water seepage in the tunnel, has low construction cost and good waterproof effect, and avoids the phenomenon of hole collapse in the tunnel.
Drawings
Fig. 1 is a flow diagram of a tunnel waterproof and drainage construction process.
Detailed Description
The technical solutions of the present invention will be described in further detail with reference to specific embodiments, and it should be apparent that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1
Referring to fig. 1, a tunnel waterproof and drainage construction process includes the following steps:
s1, construction preparation;
s101, preparing technology, and calling address data and hydrogeological data of site construction before starting construction;
s102, taking technical performance data of the construction machinery and the corollary equipment thereof;
s103, retrieving a construction scheme of the pile foundation engineering with operability, test data of a construction process and engineering geological data;
s104, maintaining and repairing the construction mechanical equipment, and installing the construction mechanical equipment on a construction site;
s2, installing a semicircular drainage pipe on the surface of the surrounding rock, wherein the diameter of the semicircular drainage pipe is 100cm, then carrying out initial spraying on the semicircular drainage pipe, forming a primary spraying layer on the surface of the semicircular drainage pipe, wherein the thickness of the primary spraying layer is 2cm, and reserving the semicircular drainage pipe after the initial spraying to the outside of the primary support;
s3, installing a semicircular drain pipe on the primary support surface, and installing a longitudinal drain pipe on the primary support surface after the semicircular drain pipe is safe;
s4, pre-burying a transverse drain pipe on the primary support surface, wherein a three-hole joint is arranged on the transverse drain pipe and is simultaneously communicated with a longitudinal drain pipe, and the longitudinal drain pipe and the transverse drain pipe are arranged vertically;
s5, measuring the thickness of sediments on the primary support surface, paving geotextile on the primary support surface, and paving a waterproof board after the geotextile is paved;
s6, pre-burying a transverse drainage pipe, then performing inverted arch backfill reservation, and digging a central drainage ditch at the upper part of the waterproof board;
s7, digging an inspection well and a sediment trap, sealing the central drainage ditch, and placing a central drainage ditch cover plate on the top of the central drainage ditch; then installing the inspection well and the cover of the sand sediment trap.
In step S5, the waterproof board is an EVA flat waterproof board, the thickness of the waterproof board is 1.5mm, and the gram weight of the geotextile is 350g/m2
In step S6, the central drainage ditch is a rectangular drainage ditch of 60 × 60cm, the central drainage ditch is provided with sand sediment wells every 50m, each 250m is provided with an inspection well, no sand sediment well is provided at the inspection well, and both the sand sediment well and the inspection well are blind wells.
In the step S6, the inspection well is a closed-up concrete well, the inner diameter of the inspection well is 100cm, the depth of the inspection well is 250cm, the wall thickness of the inspection well is 20cm, the well body of the inspection well is made of C25 concrete, the well cover of the inspection well is made of C30 reinforced concrete, the diameter of the well cover of the inspection well is 100cm, the thickness of the well cover of the inspection well is 20cm, a single layer of reinforcing steel bars is arranged at the bottom of the well cover of the inspection well, and the thickness of the single layer of reinforcing steel bars is 5 cm.
In step S6, the sediment trap is a cylindrical concrete trap, the inner diameter of the sediment trap is 70cm, the depth of the sediment trap is 158cm, the wall thickness of the sediment trap is 20cm, the body of the sediment trap is made of C25 concrete, the cover of the sediment trap is made of C30 reinforced concrete, and the diameter of the cover of the sediment trap is 100 cm.
Example 2
Referring to fig. 1, a tunnel waterproof and drainage construction process includes the following steps:
s1, construction preparation;
s101, preparing technology, and calling address data and hydrogeological data of site construction before starting construction;
s102, taking technical performance data of the construction machinery and the corollary equipment thereof;
s103, retrieving a construction scheme of the pile foundation engineering with operability, test data of a construction process and engineering geological data;
s104, maintaining and repairing the construction mechanical equipment, and installing the construction mechanical equipment on a construction site;
s2, installing a semicircular drainage pipe on the surface of the surrounding rock, wherein the diameter of the semicircular drainage pipe is 100cm, then carrying out initial spraying on the semicircular drainage pipe, forming an initial spraying layer on the surface of the semicircular drainage pipe, wherein the thickness of the initial spraying layer is 2.5cm, and reserving the semicircular drainage pipe after the initial spraying to the outside of an initial support;
s3, installing a semicircular drain pipe on the primary support surface, and installing a longitudinal drain pipe on the primary support surface after the semicircular drain pipe is safe;
s4, pre-burying a transverse drain pipe on the primary support surface, wherein a three-hole joint is arranged on the transverse drain pipe and is simultaneously communicated with a longitudinal drain pipe, and the longitudinal drain pipe and the transverse drain pipe are arranged vertically;
s5, measuring the thickness of sediments on the primary support surface, paving geotextile on the primary support surface, and paving a waterproof board after the geotextile is paved;
s6, pre-burying a transverse drainage pipe, then performing inverted arch backfill reservation, and digging a central drainage ditch at the upper part of the waterproof board;
s7, digging an inspection well and a sediment trap, sealing the central drainage ditch, and placing a central drainage ditch cover plate on the top of the central drainage ditch; then installing the inspection well and the cover of the sand sediment trap.
In step S5, the waterproof board is an EVA flat waterproof board, the thickness of the waterproof board is 1.5mm, and the gram weight of the geotextile is 350g/m2
In step S6, the central drainage ditch is a rectangular drainage ditch of 60 × 60cm, the central drainage ditch is provided with sand sediment wells every 50m, each 250m is provided with an inspection well, no sand sediment well is provided at the inspection well, and both the sand sediment well and the inspection well are blind wells.
In the step S6, the inspection well is a closed-up concrete well, the inner diameter of the inspection well is 100cm, the depth of the inspection well is 250cm, the wall thickness of the inspection well is 20cm, the well body of the inspection well is made of C25 concrete, the well cover of the inspection well is made of C30 reinforced concrete, the diameter of the well cover of the inspection well is 100cm, the thickness of the well cover of the inspection well is 20cm, a single layer of reinforcing steel bars is arranged at the bottom of the well cover of the inspection well, and the thickness of the single layer of reinforcing steel bars is 5 cm.
In step S6, the sediment trap is a cylindrical concrete trap, the inner diameter of the sediment trap is 70cm, the depth of the sediment trap is 158cm, the wall thickness of the sediment trap is 20cm, the body of the sediment trap is made of C25 concrete, the cover of the sediment trap is made of C30 reinforced concrete, and the diameter of the cover of the sediment trap is 100 cm.
Example 3
Referring to fig. 1, a tunnel waterproof and drainage construction process includes the following steps:
s1, construction preparation;
s101, preparing technology, and calling address data and hydrogeological data of site construction before starting construction;
s102, taking technical performance data of the construction machinery and the corollary equipment thereof;
s103, retrieving a construction scheme of the pile foundation engineering with operability, test data of a construction process and engineering geological data;
s104, maintaining and repairing the construction mechanical equipment, and installing the construction mechanical equipment on a construction site;
s2, installing a semicircular drainage pipe on the surface of the surrounding rock, wherein the diameter of the semicircular drainage pipe is 100cm, then carrying out initial spraying on the semicircular drainage pipe, forming a primary spraying layer on the surface of the semicircular drainage pipe, wherein the thickness of the primary spraying layer is 3cm, and reserving the semicircular drainage pipe after the initial spraying to the outside of the primary support;
s3, installing a semicircular drain pipe on the primary support surface, and installing a longitudinal drain pipe on the primary support surface after the semicircular drain pipe is safe;
s4, pre-burying a transverse drain pipe on the primary support surface, wherein a three-hole joint is arranged on the transverse drain pipe and is simultaneously communicated with a longitudinal drain pipe, and the longitudinal drain pipe and the transverse drain pipe are arranged vertically;
s5, measuring the thickness of sediments on the primary support surface, paving geotextile on the primary support surface, and paving a waterproof board after the geotextile is paved;
s6, pre-burying a transverse drainage pipe, then performing inverted arch backfill reservation, and digging a central drainage ditch at the upper part of the waterproof board;
s7, digging an inspection well and a sediment trap, sealing the central drainage ditch, and placing a central drainage ditch cover plate on the top of the central drainage ditch; then installing the inspection well and the cover of the sand sediment trap.
In step S5, the waterproof board is an EVA flat waterproof board, the thickness of the waterproof board is 1.5mm, and the gram weight of the geotextile is 350g/m2
In step S6, the central drainage ditch is a rectangular drainage ditch of 60 × 60cm, the central drainage ditch is provided with sand sediment wells every 50m, each 250m is provided with an inspection well, no sand sediment well is provided at the inspection well, and both the sand sediment well and the inspection well are blind wells.
In the step S6, the inspection well is a closed-up concrete well, the inner diameter of the inspection well is 100cm, the depth of the inspection well is 250cm, the wall thickness of the inspection well is 20cm, the well body of the inspection well is made of C25 concrete, the well cover of the inspection well is made of C30 reinforced concrete, the diameter of the well cover of the inspection well is 100cm, the thickness of the well cover of the inspection well is 20cm, a single layer of reinforcing steel bars is arranged at the bottom of the well cover of the inspection well, and the thickness of the single layer of reinforcing steel bars is 5 cm.
In step S6, the sediment trap is a cylindrical concrete trap, the inner diameter of the sediment trap is 70cm, the depth of the sediment trap is 158cm, the wall thickness of the sediment trap is 20cm, the body of the sediment trap is made of C25 concrete, the cover of the sediment trap is made of C30 reinforced concrete, and the diameter of the cover of the sediment trap is 100 cm.
Example 4
Referring to fig. 1, a tunnel waterproof and drainage construction process includes the following steps:
s1, construction preparation;
s101, preparing technology, and calling address data and hydrogeological data of site construction before starting construction;
s102, taking technical performance data of the construction machinery and the corollary equipment thereof;
s103, retrieving a construction scheme of the pile foundation engineering with operability, test data of a construction process and engineering geological data;
s104, maintaining and repairing the construction mechanical equipment, and installing the construction mechanical equipment on a construction site;
s2, installing a semicircular drainage pipe on the surface of the surrounding rock, wherein the diameter of the semicircular drainage pipe is 100cm, then carrying out initial spraying on the semicircular drainage pipe, forming a primary spraying layer on the surface of the semicircular drainage pipe, wherein the thickness of the primary spraying layer is 5cm, and reserving the semicircular drainage pipe after the initial spraying to the outside of the primary support;
s3, installing a semicircular drain pipe on the primary support surface, and installing a longitudinal drain pipe on the primary support surface after the semicircular drain pipe is safe;
s4, pre-burying a transverse drain pipe on the primary support surface, wherein a three-hole joint is arranged on the transverse drain pipe and is simultaneously communicated with a longitudinal drain pipe, and the longitudinal drain pipe and the transverse drain pipe are arranged vertically;
s5, measuring the thickness of sediments on the primary support surface, paving geotextile on the primary support surface, and paving a waterproof board after the geotextile is paved;
s6, pre-burying a transverse drainage pipe, then performing inverted arch backfill reservation, and digging a central drainage ditch at the upper part of the waterproof board;
s7, digging an inspection well and a sediment trap, sealing the central drainage ditch, and placing a central drainage ditch cover plate on the top of the central drainage ditch; then installing the inspection well and the cover of the sand sediment trap.
In step S5, the waterproof board is an EVA flat waterproof board, the thickness of the waterproof board is 1.5mm, and the gram weight of the geotextile is 350g/m2
In step S6, the central drainage ditch is a rectangular drainage ditch of 60 × 60cm, the central drainage ditch is provided with sand sediment wells every 50m, each 250m is provided with an inspection well, no sand sediment well is provided at the inspection well, and both the sand sediment well and the inspection well are blind wells.
In the step S6, the inspection well is a closed-up concrete well, the inner diameter of the inspection well is 100cm, the depth of the inspection well is 250cm, the wall thickness of the inspection well is 20cm, the well body of the inspection well is made of C25 concrete, the well cover of the inspection well is made of C30 reinforced concrete, the diameter of the well cover of the inspection well is 100cm, the thickness of the well cover of the inspection well is 20cm, a single layer of reinforcing steel bars is arranged at the bottom of the well cover of the inspection well, and the thickness of the single layer of reinforcing steel bars is 5 cm.
In step S6, the sediment trap is a cylindrical concrete trap, the inner diameter of the sediment trap is 70cm, the depth of the sediment trap is 158cm, the wall thickness of the sediment trap is 20cm, the body of the sediment trap is made of C25 concrete, the cover of the sediment trap is made of C30 reinforced concrete, and the diameter of the cover of the sediment trap is 100 cm.
The invention has the beneficial effects that: the invention ensures the rapid and safe discharge of accumulated water in the tunnel, ensures the normal operation of tunnel construction, can avoid potential safety hazard caused by water seepage in the tunnel, has low construction cost and good waterproof effect, and avoids the phenomenon of hole collapse in the tunnel.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (8)

1. A tunnel water-proof and drainage construction process is characterized by comprising the following steps:
s1, construction preparation;
s101, preparing technology, and calling address data and hydrogeological data of site construction before starting construction;
s102, taking technical performance data of the construction machinery and the corollary equipment thereof;
s103, retrieving a construction scheme of the pile foundation engineering with operability, test data of a construction process and engineering geological data;
s104, maintaining and repairing the construction mechanical equipment, and installing the construction mechanical equipment on a construction site;
s2, installing a semicircular drainage pipe on the surface of the surrounding rock, performing initial spraying on the semicircular drainage pipe, forming a primary spraying layer on the surface of the semicircular drainage pipe, and reserving the semicircular drainage pipe subjected to the initial spraying outside a primary support;
s3, installing a semicircular drain pipe on the primary support surface, and installing a longitudinal drain pipe on the primary support surface after the semicircular drain pipe is safe;
s4, pre-burying a transverse drain pipe on the primary support surface, wherein a three-hole joint is arranged on the transverse drain pipe and is simultaneously communicated with a longitudinal drain pipe, and the longitudinal drain pipe and the transverse drain pipe are arranged vertically;
s5, measuring the thickness of sediments on the primary support surface, paving geotextile on the primary support surface, and paving a waterproof board after the geotextile is paved;
s6, pre-burying a transverse drainage pipe, then performing inverted arch backfill reservation, and digging a central drainage ditch at the upper part of the waterproof board;
s7, digging an inspection well and a sediment trap, sealing the central drainage ditch, and placing a central drainage ditch cover plate on the top of the central drainage ditch; then installing the inspection well and the cover of the sand sediment trap.
2. The tunnel waterproof and drainage construction process according to claim 1, wherein in the step S2, the diameter of the semicircular drainage pipe is 100 cm.
3. The tunnel waterproof and drainage construction process according to claim 2, wherein in the step S2, the thickness of the primary spraying layer is 2-5 cm.
4. The tunnel waterproof and drainage construction process of claim 1, wherein in the step S5, the waterproof sheet is an EVA flat waterproof sheet, the thickness of the waterproof sheet is 1.5mm, and the grammage of the geotextile is 350g/m2
5. The tunnel waterproof and drainage construction process according to any one of claims 1 to 4, wherein in step S6, the central drainage ditch is a rectangular drainage ditch of 60 x 60cm, the central drainage ditch is provided with one sediment trap every 50m, the central drainage ditch is provided with one inspection well every 250m, and no sediment trap is provided at the inspection well.
6. The tunnel waterproof and drainage construction process according to claim 5, wherein the sand sediment trap and the inspection well are blind wells.
7. The tunnel waterproof and drainage construction process of claim 6, wherein in the step S6, the inspection well is a closed-end type concrete well, the inner diameter of the inspection well is 100cm, the depth of the inspection well is 250cm, the wall thickness of the inspection well is 20cm, the body of the inspection well is made of C25 concrete, the well cover of the inspection well is made of C30 reinforced concrete, the diameter of the well cover of the inspection well is 100cm, the thickness of the well cover of the inspection well is 20cm, a single layer of reinforcing steel bars is arranged at the bottom of the well cover of the inspection well, and the thickness of the single layer of reinforcing steel bars is 5 cm.
8. The tunnel waterproof and drainage construction process of claim 6, wherein in the step S6, the sand trap is a cylindrical concrete trap, the inner diameter of the sand trap is 70cm, the depth of the sand trap is 158cm, the wall thickness of the sand trap is 20cm, the sand trap body is made of C25 concrete, the sand trap cover is made of C30 reinforced concrete, and the diameter of the sand trap cover is 100 cm.
CN201910423020.2A 2019-05-21 2019-05-21 Tunnel water-proof and drainage construction process Pending CN111042841A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910423020.2A CN111042841A (en) 2019-05-21 2019-05-21 Tunnel water-proof and drainage construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910423020.2A CN111042841A (en) 2019-05-21 2019-05-21 Tunnel water-proof and drainage construction process

Publications (1)

Publication Number Publication Date
CN111042841A true CN111042841A (en) 2020-04-21

Family

ID=70231661

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910423020.2A Pending CN111042841A (en) 2019-05-21 2019-05-21 Tunnel water-proof and drainage construction process

Country Status (1)

Country Link
CN (1) CN111042841A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153379A (en) * 2021-04-27 2021-07-23 重庆永昂实业有限公司 Tunnel water-proof and drainage system and construction process

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203394584U (en) * 2013-07-31 2014-01-15 中南大学 Water drainage concealed pipe device applicable to collapsible loess tunnel
CN104806272A (en) * 2015-04-15 2015-07-29 西安科技大学 Tunnel diversion composite type waterproof and drainage system as well as construction method and use method thereof
CN207960676U (en) * 2018-03-07 2018-10-12 中南大学 One kind is for spraying pipe network drainage system in anchor single shell lining
CN208310794U (en) * 2017-12-27 2019-01-01 中铁二院工程集团有限责任公司 The tunnel-liner of haunch floor type and the drainage system of leaked oil is arranged in tunnel bottom
CN208502838U (en) * 2018-07-25 2019-02-15 中交二公局东萌工程有限公司 A kind of freeway tunnel waterproof and water drainage system
CN208564562U (en) * 2018-07-18 2019-03-01 山西省交通科学研究院 It is a kind of suitable for Han Qu and the tunnel support structure in highlight lines earthquake region
CN109441535A (en) * 2018-11-09 2019-03-08 中国十七冶集团有限公司 A kind of tunnel waterproof and water drainage system and its construction method
CN109681271A (en) * 2019-01-04 2019-04-26 交通运输部公路科学研究所 A kind of built-in type tunnel ring direction drainpipe method for arranging
CN208858401U (en) * 2018-09-03 2019-05-14 中铁二局第二工程有限公司 A kind of tunnel drainage structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203394584U (en) * 2013-07-31 2014-01-15 中南大学 Water drainage concealed pipe device applicable to collapsible loess tunnel
CN104806272A (en) * 2015-04-15 2015-07-29 西安科技大学 Tunnel diversion composite type waterproof and drainage system as well as construction method and use method thereof
CN208310794U (en) * 2017-12-27 2019-01-01 中铁二院工程集团有限责任公司 The tunnel-liner of haunch floor type and the drainage system of leaked oil is arranged in tunnel bottom
CN207960676U (en) * 2018-03-07 2018-10-12 中南大学 One kind is for spraying pipe network drainage system in anchor single shell lining
CN208564562U (en) * 2018-07-18 2019-03-01 山西省交通科学研究院 It is a kind of suitable for Han Qu and the tunnel support structure in highlight lines earthquake region
CN208502838U (en) * 2018-07-25 2019-02-15 中交二公局东萌工程有限公司 A kind of freeway tunnel waterproof and water drainage system
CN208858401U (en) * 2018-09-03 2019-05-14 中铁二局第二工程有限公司 A kind of tunnel drainage structure
CN109441535A (en) * 2018-11-09 2019-03-08 中国十七冶集团有限公司 A kind of tunnel waterproof and water drainage system and its construction method
CN109681271A (en) * 2019-01-04 2019-04-26 交通运输部公路科学研究所 A kind of built-in type tunnel ring direction drainpipe method for arranging

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153379A (en) * 2021-04-27 2021-07-23 重庆永昂实业有限公司 Tunnel water-proof and drainage system and construction process
CN113153379B (en) * 2021-04-27 2024-01-09 重庆永昂实业有限公司 Tunnel waterproof and drainage system and construction process

Similar Documents

Publication Publication Date Title
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN104110038A (en) Construction method for large-area pit support structure in deep-sludge type soft soil area
CN102943479A (en) System and method for controlling deformation of deep and large foundation pit through partition unloading
CN104532957B (en) Existing building sets up basement reversed construction method
CN107794946B (en) Underground comprehensive pipe rack structure deeply buried in soft soil and construction method thereof
CN112252336A (en) Construction method for backfilling foundation trench of premixed fluidized solidified soil
CN103911996A (en) Construction method for pulling out steel sheet piles close to existing buildings
CN212294747U (en) Pipe jacking well structure
CN201538975U (en) Seepage-proofing joint of underground continuous wall
CN101575859B (en) Anti-seepage joint of underground continuous walls and construction method thereof
CN101638898B (en) Suspension type construction method of top pipe shaft
CN112523264B (en) High-steep side slope seepage prevention system and laying method thereof
CN106320368A (en) Construction method suitable for open cut pipeline of composite stratum
KR20180096552A (en) Multi-wall construction method for construction of ports, rivers, dams, and concrete buildings that can prevent the inflow of soil and water, and building structure using the multi-wall structure
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN111042841A (en) Tunnel water-proof and drainage construction process
CN106988337A (en) Reinforcing method for reducing uneven settlement of strip-shaped shallow foundation house
CN103590424A (en) Road passage underground project construction method
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN208023600U (en) A kind of caisson structure suitable for complex environment
JP2007169927A (en) Earthquake resisting manhole structure and its manufacturing method
CN210315908U (en) Immersed tube type inspection well
CN203977434U (en) The foundation pit enclosure structure of deep In Soft Muddy Soil Region
CN103774698B (en) Drainage-free construction method for soil engineering
CN105064384A (en) Vacuum tube well precipitation system under special geological conditions

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200421

RJ01 Rejection of invention patent application after publication