CN110939065A - Method for jacking bridge by using temporary steel support auxiliary frame - Google Patents

Method for jacking bridge by using temporary steel support auxiliary frame Download PDF

Info

Publication number
CN110939065A
CN110939065A CN201911236345.6A CN201911236345A CN110939065A CN 110939065 A CN110939065 A CN 110939065A CN 201911236345 A CN201911236345 A CN 201911236345A CN 110939065 A CN110939065 A CN 110939065A
Authority
CN
China
Prior art keywords
steel
jacking
temporary
steel support
limiting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911236345.6A
Other languages
Chinese (zh)
Other versions
CN110939065B (en
Inventor
张志永
王磊
邓国庆
张明
吴涛
李贵山
林屹
杨希富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 22nd Bureau Group Co Ltd
Harbin Railway Construction Group Co Ltd of China Railway 22nd Bureau Group Co Ltd
China Railway Group Ltd CREC
Original Assignee
Harbin Railway Construction Group Co Ltd of China Railway 22nd Bureau Group Co Ltd
China Railway Group Ltd CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Railway Construction Group Co Ltd of China Railway 22nd Bureau Group Co Ltd, China Railway Group Ltd CREC filed Critical Harbin Railway Construction Group Co Ltd of China Railway 22nd Bureau Group Co Ltd
Priority to CN201911236345.6A priority Critical patent/CN110939065B/en
Publication of CN110939065A publication Critical patent/CN110939065A/en
Application granted granted Critical
Publication of CN110939065B publication Critical patent/CN110939065B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a method for jacking a bridge by utilizing an auxiliary frame of a temporary steel support, and relates to the technical field of bridge construction. The method comprises the following steps: firstly, the method comprises the following steps: the temporary steel support and a limiting device are adopted, the temporary steel support is provided with a main body formed by welding and combining two I-shaped steels, stiffening rib steel plates and top and bottom steel plates, and the limiting device is assembled and welded on site; II, secondly: installation: the temporary steel support is arranged between two transverse lifting beam I-steels below the longitudinal beam I-steel, and the limiting device is arranged on the side surface of the top end of the temporary steel support; thirdly, the method comprises the following steps: and (3) force transmission of a jacking operation steel support: before jacking operation, laying a steel sliding plate on the top of the frame bridge along the jacking direction, and coating grease on the steel sliding plate; when the frame structure bridge is jacked in, the temporary steel support is positioned on the steel sliding plate to play a role in supporting and reducing friction force. The defects of large friction force, deformation, displacement and poor integral stability generated when the sleeper pile is used for jacking are overcome.

Description

Method for jacking bridge by using temporary steel support auxiliary frame
Technical Field
The invention relates to the technical field of bridge construction, in particular to a method for reinforcing and jacking a cross beam in bridge construction, namely a method for jacking a bridge by using a temporary steel support auxiliary frame.
Background
At present, in bridge construction, a cross beam is reinforced and jacked in a process, a sleeper pile is generally adopted for supporting, and the height difference exists between the bottom of the cross beam and the top surface of a frame structure bridge. During jacking operation, the sleeper pile materials are different from those of the cross lifting beam and the frame structure bridge, so that large friction force is generated, the sleeper pile for jacking operation in the blocking points is easy to deform and displace, the overall stability is poor, and labor and operation time are consumed. Therefore, the sleeper pile is not suitable for the reinforcing and jacking operation of the transverse lifting beam.
Disclosure of Invention
The invention provides a method for assisting frame structure bridge jacking by using a temporary steel support, aiming at strengthening temporary connection between a transverse lifting beam and a frame structure bridge, overcoming the defects of large friction force, deformation, displacement and poor integral stability generated when a sleeper pile is used for jacking, and solving the problem that the sleeper pile is not suitable for being used for reinforcing the jacking operation of the transverse lifting beam.
In order to solve the problems, the invention adopts the following technical scheme: a method for jacking a temporary steel support auxiliary frame bridge comprises the following process steps:
the method comprises the following steps: the temporary steel support and a limiting device are adopted, the temporary steel support is provided with a main body formed by welding and combining two I-shaped steels, stiffening rib steel plates and top and bottom steel plates, and the limiting device is assembled and welded on site;
step two: installation: the temporary steel support is arranged between two transverse lifting beam I-steels below the longitudinal beam I-steel, and the limiting device is arranged on the side surface of the top end of the temporary steel support;
after the temporary steel support is in place, the limiting device is assembled and welded on site by an electric welder to form the temporary steel support with a fixed top end and a movable lower end; the limiting device limits the positions among the temporary steel support, the longitudinal beam I-steel and the transverse lifting beam I-steel;
step three: and (3) force transmission of a jacking operation steel support: before jacking operation, laying a steel sliding plate on the top of the frame bridge along the jacking direction, and coating grease on the steel sliding plate; when the frame structure bridge is jacked in, the temporary steel support is positioned on the steel sliding plate to play a role in supporting and reducing friction force;
step four: repeating the third step, and circularly jacking;
step five: after the jacking position passes through the second row of longitudinal beams, performing the second step, and supporting the second row of longitudinal beams by the temporary steel supports;
step six: repeating the third step, and circularly jacking;
step seven: after the jacking position passes through the third row of longitudinal beams, performing the second step, and supporting the third row of longitudinal beams by the temporary steel supports;
step eight: and repeating the third step, and circularly jacking until the jacking reaches the designed position.
Further, the method for jacking the bridge by using the temporary steel support auxiliary frame structure further has the following characteristics: the temporary steel support comprises two vertical I-shaped steels arranged side by side, stiffening rib plates and a top bottom steel plate, the edges of transverse plates of the two vertically arranged I-shaped steels are welded together, the stiffening rib plates are arranged in gaps between the two welded I-shaped steels at equal intervals along the height direction, the stiffening rib plates are welded with the I-shaped steels, and the top and the bottom of the two I-shaped steels are welded with the top bottom steel plate.
Further, the method for jacking the bridge by using the temporary steel support auxiliary frame structure further has the following characteristics: stop device includes angle steel, two right triangle's triangle steel sheet, the I shaped steel board and the II shaped steel board of rectangle, and two opposite sides of the II shaped steel board that the level set up weld with the I shaped steel board bottom limit of the angle steel right angle inboard, vertical setting respectively, and 2 hypotenuses of two triangle steel sheets are relative, right angle and angle steel lateral surface welding.
Further, the method for jacking the bridge by using the temporary steel support auxiliary frame structure further has the following characteristics: and in the second step, the I-shaped steel plate of the limiting device is respectively welded with the longitudinal beam I-shaped steel, the transverse lifting beam I-shaped steel and the temporary steel support, and the outer right-angle sides of the two triangular steel plates of the limiting device are respectively welded with the transverse lifting beam I-shaped steel at the two sides.
Compared with the prior art, the invention has the beneficial effects that:
(1) the temporary steel support is simple and convenient to manufacture, and has the advantages of high strength, high rigidity and good stability.
(2) Practice proves that under the condition that the elevation difference exists between the transverse lifting beam and the frame structure top in the transverse lifting beam reinforcing jacking operation and the temporary steel support is adopted for assisting jacking, the jacking stroke of each shift is effectively increased through the invention, and the total jacking period is shortened by three days.
(3) Construction cost is effectively reduced while construction quality is guaranteed, labor force dragging is reduced, and time is greatly saved.
Drawings
FIG. 1 is a front view of a temporary steel support;
FIG. 2 is a side view of a temporary steel support;
FIG. 3 is a top view of a temporary steel support;
FIG. 4 is a front view of the spacing device;
FIG. 5 is a top view of the spacing device;
FIG. 6 is a side view of the stop device;
FIG. 7 is a top view of the connection of the limiting device and the temporary steel support;
FIG. 8 is a side view of the stop device connected to the temporary steel support;
FIG. 9 is a front schematic view of the structures of the frame bridge, the temporary steel support, the steel slide plate and the limiting device;
FIG. 10 is a structural plan view of the frame bridge, the temporary steel support, the steel slide plate and the limiting device;
FIG. 11 is a schematic side view of the structures of the frame bridge, the temporary steel support, the steel slide plate and the limiting device;
FIG. 12 is a schematic diagram of the jacking operation of the present invention.
Description of the symbols: the temporary steel support is 1, I-shaped steel is 1-1, stiffening rib plates are 1-2, steel plates on the top and bottom surfaces are 1-3, a limiting device is 2, angle steel is 2-1, triangular steel plates are 2-2, I-shaped steel plates are 2-3, II-shaped steel plates are 2-4, longitudinal beam I-shaped steel is 3, a first row of longitudinal beams is 3-1, a first row of longitudinal beams is 3-2, a first row of longitudinal beams is 3-3, transverse lifting beam I-shaped steel is 4, a steel sliding plate 5, a concrete buttress is 6, a frame bridge 7, a frame bridge top surface is 7-1, U-shaped fittings are 8, a protective pile 9, a jacking working range is 10, and a jacking direction is.
Detailed Description
The present invention will be described in detail with reference to the following preferred embodiments.
A method for jacking a temporary steel support auxiliary frame bridge comprises the following process steps:
the method comprises the following steps: as shown in fig. 1-6, a temporary steel support and a limiting device are adopted, the temporary steel support is mainly composed of two I-shaped steels I63C, stiffening rib steel plates with the thickness of 20mm, and top and bottom steel plates through welding to form a main body, the parts of the limiting device are formed by processing the steel plates with the thickness of 10mm, and the limiting device is assembled and welded on site.
The temporary steel support 1 comprises two vertical I-shaped steels 1-1 arranged side by side, stiffening rib plates 1-2 and top and bottom surface steel plates 1-3, the edges of transverse plates of the two vertically arranged I-shaped steels 1-1 are welded together, the stiffening rib plates 1-2 are arranged in gaps between the two welded I-shaped steels 1-1 at equal intervals along the height direction, the stiffening rib plates 1-2 are welded with the I-shaped steels 1-1, and the top and bottom surfaces of the two I-shaped steels 1-1 are welded with the top and bottom surface steel plates 1-3.
The limiting device 2 comprises angle steel 2-1, two right-angled triangle-shaped triangular steel plates 2-2, rectangular I-shaped steel plates 2-3 and II-shaped steel plates 2-4, two opposite sides of the horizontally arranged II-shaped steel plates 2-4 are respectively welded with the inner sides of the right angles of the angle steel 2-1 and the bottom sides of the vertically arranged I-shaped steel plates 2-3, the oblique sides of the two triangular steel plates 2-2 are opposite, and the right angles are welded with the outer sides of the angle steel 2-1.
Step two: installation: as shown in fig. 7-9, the temporary steel support is manually installed by mechanical cooperation, the temporary steel support 1 is installed between two cross-beam I-steels 4 below a longitudinal beam I-steel 3, the limiting device 2 is installed on the side surface of the top end of the temporary steel support 1, the I-shaped steel plates 2-3 are respectively welded with the longitudinal beam I-steel 3, the cross-beam I-steel 4 and the temporary steel support 1, and the outer right-angle sides and 2-1 of two triangular steel plates 2-2 of the limiting device 2 are respectively welded with the cross-beam I-steels 4 on two sides.
After the temporary steel support is in place, the limiting device is assembled and welded on site by an electric welder to form the temporary steel support with a fixed top end and a movable lower end; the position between the temporary steel support 1, the longitudinal beam I-steel 3 and the transverse lifting beam I-steel 4 is limited by the limiting device.
Step three: and (3) force transmission of a jacking operation steel support: as shown in fig. 10-12, before the jacking operation, the steel sliding plate 5 is laid on the top of the frame bridge 7 along the jacking direction, and is coated with grease for lubricating; when the frame structure bridge is jacked in, the temporary steel support is positioned on the steel sliding plate to play a role in supporting and reducing friction force. In the step, the key point of the invention is that the steel sliding plate, the temporary steel support and the limiting device are laid, and other modes of jacking operation are the same as the existing frame structure bridge jacking technology.
Step four: and repeating the third step and circularly jacking.
Step five: and step two is carried out after the jacking position passes through the second row of longitudinal beams, and the temporary steel supports support the second row of longitudinal beams.
Step six: and repeating the third step and circularly jacking.
Step seven: and step two is carried out after the jacking position passes through the third row of longitudinal beams, and the temporary steel supports support the third row of longitudinal beams.
Step eight: and repeating the third step, and circularly jacking until the jacking reaches the designed position.

Claims (4)

1. A method for jacking a bridge by utilizing an auxiliary frame of a temporary steel support is characterized by comprising the following process steps: the method comprises the following steps: the temporary steel support and a limiting device are adopted, the temporary steel support is provided with a main body formed by welding and combining two I-shaped steels, stiffening rib steel plates and top and bottom steel plates, and the limiting device is assembled and welded on site; step two: installation: the temporary steel support is arranged between two transverse lifting beam I-steels below the longitudinal beam I-steel, and the limiting device is arranged on the side surface of the top end of the temporary steel support; after the temporary steel support is in place, the limiting device is assembled and welded on site by an electric welder to form the temporary steel support with a fixed top end and a movable lower end; the limiting device limits the positions among the temporary steel support, the longitudinal beam I-steel and the transverse lifting beam I-steel; step three: and (3) force transmission of a jacking operation steel support: before jacking operation, laying a steel sliding plate on the top of the frame bridge along the jacking direction, and coating grease on the steel sliding plate; when the frame structure bridge is jacked in, the temporary steel support is positioned on the steel sliding plate to play a role in supporting and reducing friction force; step four: repeating the third step, and circularly jacking; step five: after the jacking position passes through the second row of longitudinal beams, performing the second step, and supporting the second row of longitudinal beams by the temporary steel supports; step six: repeating the third step, and circularly jacking; step seven: after the jacking position passes through the third row of longitudinal beams, performing the second step, and supporting the third row of longitudinal beams by the temporary steel supports; step eight: and repeating the third step, and circularly jacking until the jacking reaches the designed position.
2. The method for constructing the bridge jacking by using the temporary steel support auxiliary frame as claimed in claim 1, wherein the temporary steel support comprises two I-shaped steels which are vertically arranged side by side, stiffening rib plates and top and bottom steel plates, the edges of the transverse plates of the two I-shaped steels which are vertically arranged are welded together, the stiffening rib plates are arranged in the gap between the two welded I-shaped steels at equal intervals along the height direction, the stiffening rib plates are welded with the I-shaped steels, and the top and bottom steel plates of the two I-shaped steels are welded.
3. The method for jacking up a bridge by using a temporary steel support auxiliary frame as claimed in claim 1 or 2, wherein the limiting device comprises angle steel, two triangular steel plates with right triangle, a rectangular I-shaped steel plate and a rectangular II-shaped steel plate, two opposite sides of the horizontally arranged II-shaped steel plate are respectively welded with the inner side of the right angle of the angle steel and the bottom side of the vertically arranged I-shaped steel plate, the two triangular steel plates 2 have the inclined sides opposite to each other, and the right angle is welded with the outer side of the angle steel.
4. The method for jacking the bridge by using the temporary steel support auxiliary frame as claimed in claim 3, wherein in the second step, the I-shaped steel plate of the limiting device is welded with the longitudinal beam I-shaped steel, the transverse lifting beam I-shaped steel and the temporary steel support respectively, and the outer right-angle sides of the two triangular steel plates of the limiting device are welded with the transverse lifting beam I-shaped steel at the two sides respectively.
CN201911236345.6A 2019-12-05 2019-12-05 Method for jacking bridge by using temporary steel support auxiliary frame Active CN110939065B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911236345.6A CN110939065B (en) 2019-12-05 2019-12-05 Method for jacking bridge by using temporary steel support auxiliary frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911236345.6A CN110939065B (en) 2019-12-05 2019-12-05 Method for jacking bridge by using temporary steel support auxiliary frame

Publications (2)

Publication Number Publication Date
CN110939065A true CN110939065A (en) 2020-03-31
CN110939065B CN110939065B (en) 2021-12-17

Family

ID=69909282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911236345.6A Active CN110939065B (en) 2019-12-05 2019-12-05 Method for jacking bridge by using temporary steel support auxiliary frame

Country Status (1)

Country Link
CN (1) CN110939065B (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1231063A (en) * 1984-05-17 1988-01-05 Eugene G. Crick Beaver guard for drainage culvert
ES1007509U (en) * 1988-08-26 1989-02-01 Companyia Instrumental De Mercats, S.A. Device for the construction of underpasses on roads. (Machine-translation by Google Translate, not legally binding)
CN2095220U (en) * 1991-06-22 1992-02-05 北京铁路局北京工程处石家庄工程段 Arrangement for temporarily supporting lail track, or rail or sleeper in track
KR20030008604A (en) * 2001-07-19 2003-01-29 이윤주 Construction Method of Precast Culvert using a Rolling Means
CN202164508U (en) * 2011-07-13 2012-03-14 中铁六局集团石家庄铁路建设有限公司 Liftable supporting device
CN102926299A (en) * 2012-11-19 2013-02-13 房士杰 Railway elevating and fixing device and railway bridge and culvert construction method adopting railway elevating and fixing device
CN203393606U (en) * 2013-07-22 2014-01-15 中铁十六局集团第二工程有限公司 Circuit reinforcing roller support for jacking of frame-shaped bridge
CN103726451A (en) * 2014-01-16 2014-04-16 中铁六局集团有限公司 Railway construction method of dismantling existing girder bridge and pushing frame structure in situ
CN104099872A (en) * 2014-06-30 2014-10-15 中铁四局集团第四工程有限公司 Railway-underneath-passed long-span box culvert longitudinal-picking transverse-lifting jacking construction method
CN205421025U (en) * 2016-01-26 2016-08-03 中铁二十二局集团第一工程有限公司 Top is advanced frame and is constructed roller support for bridge
CN205711790U (en) * 2016-06-14 2016-11-23 郑州铁路工程有限公司 A kind of sliding support and system
CN109505200A (en) * 2018-12-21 2019-03-22 中国建筑第七工程局有限公司 Large-span oblique crossing Frame Bridge undercrossing tunnel exempts to resist traversing anchoring wire road reinforcing construction process
CN209537958U (en) * 2018-12-21 2019-10-25 中国建筑第七工程局有限公司 Undercrossing tunnel jacking construction track strengthening assists jacking jigger

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1231063A (en) * 1984-05-17 1988-01-05 Eugene G. Crick Beaver guard for drainage culvert
ES1007509U (en) * 1988-08-26 1989-02-01 Companyia Instrumental De Mercats, S.A. Device for the construction of underpasses on roads. (Machine-translation by Google Translate, not legally binding)
CN2095220U (en) * 1991-06-22 1992-02-05 北京铁路局北京工程处石家庄工程段 Arrangement for temporarily supporting lail track, or rail or sleeper in track
KR20030008604A (en) * 2001-07-19 2003-01-29 이윤주 Construction Method of Precast Culvert using a Rolling Means
CN202164508U (en) * 2011-07-13 2012-03-14 中铁六局集团石家庄铁路建设有限公司 Liftable supporting device
CN102926299A (en) * 2012-11-19 2013-02-13 房士杰 Railway elevating and fixing device and railway bridge and culvert construction method adopting railway elevating and fixing device
CN203393606U (en) * 2013-07-22 2014-01-15 中铁十六局集团第二工程有限公司 Circuit reinforcing roller support for jacking of frame-shaped bridge
CN103726451A (en) * 2014-01-16 2014-04-16 中铁六局集团有限公司 Railway construction method of dismantling existing girder bridge and pushing frame structure in situ
CN104099872A (en) * 2014-06-30 2014-10-15 中铁四局集团第四工程有限公司 Railway-underneath-passed long-span box culvert longitudinal-picking transverse-lifting jacking construction method
CN205421025U (en) * 2016-01-26 2016-08-03 中铁二十二局集团第一工程有限公司 Top is advanced frame and is constructed roller support for bridge
CN205711790U (en) * 2016-06-14 2016-11-23 郑州铁路工程有限公司 A kind of sliding support and system
CN109505200A (en) * 2018-12-21 2019-03-22 中国建筑第七工程局有限公司 Large-span oblique crossing Frame Bridge undercrossing tunnel exempts to resist traversing anchoring wire road reinforcing construction process
CN209537958U (en) * 2018-12-21 2019-10-25 中国建筑第七工程局有限公司 Undercrossing tunnel jacking construction track strengthening assists jacking jigger

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
高印强: "顶进式框架桥施工中的线路加固检算 ", 《铁道建筑》 *

Also Published As

Publication number Publication date
CN110939065B (en) 2021-12-17

Similar Documents

Publication Publication Date Title
CN110900081A (en) Large box beam welding platform and welding method
CN110900082A (en) Large I-beam welding platform and welding method
CN206986729U (en) A kind of spacing deviation-rectifying bracket for the control of box beam pushing tow
CN111379424A (en) Anti-overturning device and method for planar structure sliding construction
CN108999427B (en) Support structure for moving load during building migration in place and construction method thereof
CN110939065B (en) Method for jacking bridge by using temporary steel support auxiliary frame
CN101839063B (en) Movable steel base for constructing prefabricated beam and standard joint thereof
CN211713700U (en) Temporary steel support structure for jacking construction of frame-structured bridge
CN106703073B (en) Super High building hoist exempts from return back to top steel beam foundation and its construction method
CN211102435U (en) Large-scale box girder welded platform
CN115492216B (en) Supporting device for pipeline to be moved to above underground station and construction method
CN110172878B (en) Ground transportation rail installation method
CN109235273B (en) Assembled prefabricated Liang Zhuangyun interlude car
CN201671063U (en) Movable steel base for construction precast beams and standard knot thereof
CN109209429B (en) Supporting trolley for preventing partition wall of multi-arch tunnel from moving laterally and construction method thereof
CN216193962U (en) Track foundation reinforcing structure of water gantry crane
CN212505679U (en) Widening and splicing roadbed structure of new and old roadbed
CN212294735U (en) Gantry crane track foundation beam
CN211285076U (en) Railway track overhead reinforcing structure
CN208592819U (en) A kind of wind-force tower planar plate members storage combination unit
CN108661238B (en) Girder and end beam structure manufacturing process
CN202913716U (en) Temporary support structure for truss integral lifting
CN213389732U (en) Supporting and limiting integrated structure for mounting steel box girder
CN215925687U (en) Steel case roof beam butt joint levelling device
CN210529733U (en) Component type cement tank foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant