CN110930124A - Method, device and equipment for determining construction progress - Google Patents

Method, device and equipment for determining construction progress Download PDF

Info

Publication number
CN110930124A
CN110930124A CN201911203501.9A CN201911203501A CN110930124A CN 110930124 A CN110930124 A CN 110930124A CN 201911203501 A CN201911203501 A CN 201911203501A CN 110930124 A CN110930124 A CN 110930124A
Authority
CN
China
Prior art keywords
target
weight
floor
construction progress
determining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911203501.9A
Other languages
Chinese (zh)
Inventor
梁新伟
陈哲诗
宋明
伊辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Jizhi Digital Technology Co Ltd
Original Assignee
Shenzhen Jizhi Digital Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Jizhi Digital Technology Co Ltd filed Critical Shenzhen Jizhi Digital Technology Co Ltd
Priority to CN201911203501.9A priority Critical patent/CN110930124A/en
Publication of CN110930124A publication Critical patent/CN110930124A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application discloses a method, a device and equipment for determining construction progress, which comprise the following steps: acquiring operation data of hoisting equipment; determining an operation floor according to the target operation height in the operation data, and determining a target building weight corresponding to the operation floor, wherein the target building weight is the weight of building materials required for building the operation floor; and determining the construction progress corresponding to the operation floor according to the actual carrying weight of the operation floor and the target building weight corresponding to the operation floor, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor. The current construction progress of the current building floor can be obtained through analysis of the operation data of the hoisting equipment, and therefore the construction progress does not need to be obtained through manual statistics, the efficiency of the construction progress can be improved, the labor cost is reduced, and the accuracy of the finally determined construction progress is improved.

Description

Method, device and equipment for determining construction progress
Technical Field
The present disclosure relates to the field of construction progress determination technologies, and in particular, to a method, an apparatus, and a device for determining a construction progress.
Background
During the project implementation process, it is usually necessary to follow up the construction progress of the current working surface in the project regularly (e.g., every day, every week, etc.). Taking a building as an example, it is usually necessary to arrange a specific schedule of a current floor of a building, which is counted by a specific technician every day, so as to adjust a later-stage operation schedule, planning, and the like in time according to a current construction schedule.
At present, the construction progress of reporting and establishing the current working face is usually that a specific technician is arranged to perform manual statistics on a construction site, and the data that the technician needs to perform statistics is more (for example, the data of multiple aspects of the current building floor needs to be counted), so that the technician needs to spend longer time to perform data statistics and further analyze the construction progress of the current building floor according to the counted data, and therefore, the method not only enables the efficiency of reporting and establishing the construction progress to be low, but also enables the required labor cost to be higher. In addition, the accuracy of the statistical data depends on the professional degree of the technical staff, and if the professional degree of the technical staff is insufficient, the accuracy of the data and the accuracy of the reported construction progress cannot be guaranteed, so that the monitoring of the project implementation process is not facilitated.
Disclosure of Invention
The embodiment of the application provides a method, a device and equipment for determining construction progress, so that the efficiency and the accuracy of reporting the construction progress are improved, and the required labor cost is reduced.
In a first aspect, an embodiment of the present application provides a method for determining a construction progress, where the method includes:
acquiring operation data of hoisting equipment, wherein the operation data comprises a target operation height of the hoisting equipment at an operation end point and a carrying weight of the hoisting equipment at the target operation height;
determining an operation floor according to the target operation height, and determining a target building weight corresponding to the operation floor, wherein the target building weight is the weight of building materials required for building the operation floor;
and determining the construction progress of the operation floor according to the actual carrying weight of the operation floor and the target building weight, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor.
In one possible embodiment, the work end point is determined by judging that the reduction amount of the load weight is larger than a predetermined threshold value.
In one possible embodiment, the method further comprises:
and adding a timestamp for the determined construction progress, wherein the timestamp represents the time for the operation floor to reach the construction progress.
In a possible embodiment, the carrying weight of the hoisting device at the target working height, in particular the carrying weight of the hoisting device at the target working height in one working cycle, is greater than a preset value at the start of the working cycle, and is less than the preset value at the end of the working cycle.
In a possible embodiment, the acquiring operation data of the hoisting device includes:
acquiring initial operation data of the hoisting equipment;
and merging the initial operation data to obtain the operation data of the hoisting equipment.
In a second aspect, an embodiment of the present application further provides a device for determining a construction progress, where the device and the method include:
the system comprises an acquisition module, a control module and a control module, wherein the acquisition module is used for acquiring operation data of the hoisting equipment, and the operation data comprises a target operation height of the hoisting equipment at an operation end point and a carrying weight of the hoisting equipment under the target operation height;
the first determining module is used for determining an operation floor according to the target operation height and determining a target building weight corresponding to the operation floor, wherein the target building weight is the weight of building materials required for building the operation floor;
and the second determination module is used for determining the construction progress of the operation floor according to the actual carrying weight of the operation floor and the target building weight, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor.
In one possible embodiment, the work end point is determined by judging that the reduction amount of the load weight is larger than a predetermined threshold value.
In a possible embodiment, the apparatus further comprises:
and the adding module is used for adding a timestamp for the determined construction progress, and the timestamp represents the time for the operation floor to reach the construction progress.
In a possible embodiment, the carrying weight of the hoisting device at the target working height, in particular the carrying weight of the hoisting device at the target working height in one working cycle, is greater than a preset value at the start of the working cycle, and is less than the preset value at the end of the working cycle.
In a possible implementation, the obtaining module includes:
the acquiring unit is used for acquiring initial operation data of the hoisting equipment;
and the merging unit is used for merging the initial operation data to obtain the operation data of the hoisting equipment.
In a third aspect, an embodiment of the present application further provides an apparatus, where the apparatus includes a processor and a memory:
the memory is to store program instructions;
the processor is configured to call the program instructions in the memory to execute the method for determining construction progress described in any of the embodiments of the first aspect.
In a fourth aspect, an embodiment of the present application further provides a computer-readable storage medium, where the computer-readable storage medium is used for storing program codes, and the program codes, when executed by a processor, implement the method for determining a construction progress, described in any one of the embodiments of the first aspect above.
In the foregoing implementation manner of the embodiment of the present application, the operation data of the hoisting device may be obtained, where the operation data includes a target operation height of the hoisting device at an operation end point and a carrying weight of the hoisting device at the target operation height; then, an operation floor can be determined according to the target operation height, and a target building weight corresponding to the operation floor can be further determined, wherein the target building weight is the weight of building materials required for building the operation floor; then, the construction progress corresponding to the operation floor can be determined according to the actual carrying weight of the operation floor and the target building weight corresponding to the operation floor, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor. It can be understood that there is close relevance in the construction progress of the operation state of hoisting equipment and current building floor when the operation, consequently, can the analysis obtain the current construction progress of this current building floor through the operation data that acquire hoisting equipment to need not to acquire the construction progress through artifical statistical mode, not only can improve the efficiency of statistics construction progress, reduce the human cost, and moreover, because the data that acquire are actual operation data, not by the data that artifical statistics obtained, consequently, the accuracy of the construction progress that finally confirms has also been improved.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings needed to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments described in the present application, and other drawings can be obtained by those skilled in the art according to the drawings.
Fig. 1 is a schematic diagram of a network system framework involved in an application scenario in an embodiment of the present application;
FIG. 2 is a schematic flow chart illustrating a method for determining a construction progress according to an embodiment of the present disclosure;
FIG. 3 is a schematic structural diagram of an apparatus for determining a construction progress in an embodiment of the present application;
fig. 4 is a schematic hardware structure diagram of an apparatus in an embodiment of the present application.
Detailed Description
At present, when following up the construction progress of a project, the construction progress of the current building floor is usually determined in a manual statistics and evaluation mode, so that the efficiency of reporting the construction progress is low, the data obtained by statistics depend on the professional degree of a statistic person, and the accuracy of the construction progress reported by the statistic person cannot be guaranteed.
Based on this, the embodiment of the application provides a method for determining a construction progress, and aims to improve the efficiency and accuracy of reporting the construction progress of the current building floor. Specifically, the operation data of the hoisting equipment can be acquired, and the operation data comprises a target operation height of the hoisting equipment at an operation end point and a carrying weight of the hoisting equipment at the target operation height; then, an operation floor can be determined according to the target operation height, and a target building weight corresponding to the operation floor can be further determined, wherein the target building weight is the weight of building materials required for building the operation floor; then, the construction progress corresponding to the operation floor can be determined according to the actual carrying weight of the operation floor and the target building weight corresponding to the operation floor, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor. It can be understood that there is close relevance in the construction progress of the operation state of hoisting equipment and current building floor when the operation, consequently, can the analysis obtain the current construction progress of this current building floor through the operation data that acquire hoisting equipment to need not to acquire the construction progress through artifical statistical mode, not only can improve the efficiency of statistics construction progress, reduce the human cost, and moreover, because the data that acquire are actual operation data, not by the data that artifical statistics obtained, consequently, the accuracy of the construction progress that finally confirms has also been improved.
As an example, the embodiment of the present application may be applied to an exemplary application scenario as shown in fig. 1. In this scenario, the hoisting device may be specifically a tower crane terminal 102 as illustrated in fig. 1. The user terminal 101 can be connected with the tower crane terminal 102 and obtain operation data of the tower crane terminal 102, wherein the operation data at least comprises a target operation height of the tower crane terminal 102 at an operation end point and a carrying weight of the tower crane terminal 102 at the target operation height; then, the user terminal 101 may determine an operation floor of the tower crane terminal 102 during operation according to the target operation height, and determine a target building weight corresponding to the operation floor, where the target building weight is a weight of building materials required for building the operation floor; then, the user terminal 101 may determine the construction progress of the current operation floor according to the actual carrying weight of the operation floor and the target building weight, where the actual carrying weight is the sum of the carrying weights of the tower crane terminal 102 at the target operation height corresponding to the operation floor; finally, the user terminal 102 may present the construction progress to a supervisor of the project, and the supervisor performs corresponding planning and adjustment according to the construction progress of the current operation floor.
It is to be understood that the above scenario is only one example of a scenario provided in the embodiment of the present application, and the embodiment of the present application is not limited to this scenario. For example, in other possible application scenarios, the hoisting device may also be other devices besides the tower crane terminal. In summary, the embodiments of the present application can be applied to any applicable application scenario, and are not limited to the scenario examples described above.
In order to make the aforementioned objects, features and advantages of the present application more comprehensible, various non-limiting embodiments accompanying the present application examples are described below with reference to the accompanying drawings. It is to be understood that the embodiments described are only a few embodiments of the present application and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
Referring to fig. 2, fig. 2 is a schematic flow chart of a method for determining a construction progress in an embodiment of the present application, where the method specifically may include:
s201: acquiring operation data of the hoisting equipment, wherein the operation data at least comprises a target operation height of the hoisting equipment at an operation end point and a carrying weight of the hoisting equipment at the target operation height.
The inventor finds that the construction progress of the current working floor is closely related to the working data of the hoisting equipment. For example, in the process of building a high-rise building, if the current building reaches the 4 th floor, the hoisting device such as a tower crane will usually carry the building material to the 4 th floor, so that the constructor can use the carried building material to construct the 4 th floor, that is, the operation end point of the hoisting device is usually closely related to the floor of the current building, and the building material carried by the hoisting device for the 4 th floor directly represents the construction progress of the floor, therefore, the construction progress of the current operation floor can be determined by analyzing the operation data of the hoisting device.
Based on this, in this embodiment, the operation data of the hoisting device may be obtained, and the operation data may include a target operation height of the hoisting device at the operation end point, so that the floor currently being operated may be determined according to the target operation height. Wherein the reduced load weight of the hoisting device at the end of the operation is greater than a preset threshold. It will be appreciated that in practice, the lifting device will usually carry the construction material of the current floor from the work starting point, which is usually the site where the construction material is deposited on the construction site, to the work ending point, which is the destination to which the construction material is to be transported, usually the floor of the current building. As an example, it may be that the work end is determined by judging that the reduction amount of the load weight is larger than a predetermined threshold. Therefore, during the operation of the hoisting equipment, if the carrying weight of the hoisting equipment is increased from 0 ton to 0.01 ton or more, the current operation position of the hoisting equipment can be considered as the operation starting point, and if the carrying weight of the hoisting equipment which is reduced in a short time is larger than a preset threshold value, for example, the carrying weight is reduced from 0.01 ton or more to 0 ton, the current operation position of the hoisting equipment can be considered as the operation ending point. It should be noted that the preset threshold may be a fixed threshold, such as 0.5 ton, etc., that is, when the load weight decreased in a short time is greater than 0.5 ton, it indicates that the hoisting apparatus is unloading the load at the operation end; or may be a value calculated each time the object is carried by the lifting device (i.e. may be a non-fixed threshold), for example, the preset threshold may be calculated by subtracting 0.1 ton from the current carrying weight, and the preset threshold may be 1.19 ton (i.e. 1.2 ton-0.01 ton) assuming that the current carrying weight is 1.2 ton.
The acquired operating data may also include the load weight of the lifting device at the target operating height. It will be appreciated that the total amount of building material required to construct each work floor may be predetermined and that the predetermined total amount of building material will typically be required to be carried by the lifting device. Therefore, the weight of the building material carried by the hoisting device for the operation floor can reflect the construction progress of the operation floor to a certain extent, so that the carrying weight of the hoisting device at the target operation height can be obtained in this embodiment, that is, the weight of the building material carried by the operation floor corresponding to the target operation height by the hoisting device is obtained.
It should be noted that the hoisting device may be interfered by the outside during the actual operation, so that the operation data of the hoisting device may fluctuate, for example, during the process of carrying 0.1 ton of building material from the operation starting point to the operation ending point by the hoisting device, the carrying weight continuously returned by the hoisting device may change to 0.101 ton or 0.102 ton due to the influence of the external wind force, humidity and other environmental factors. Accordingly, the work of the hoisting device can be correspondingly combined, for example, it is combined into the initial carrying weight of 0.1 ton of the hoisting device. In an exemplary embodiment, the initial operation data of the hoisting device may be obtained, and data fluctuation may exist in the initial operation data, for this reason, the initial operation data may be further merged, and the merged data may be used as the operation data of the hoisting device.
S202: and determining an operation floor according to the target operation height, and determining a target building weight corresponding to the operation floor, wherein the target building weight is the weight of the building materials required for building the operation floor.
It can be understood that in practical applications, the hoisting device carries the building material to the operation terminal, which is usually convenient for a constructor to construct a floor based on the building material carried by the hoisting device, and therefore, the height of the operation terminal is usually the height of the current operation floor, so that the operation floor can be determined based on the target operation height corresponding to the operation terminal. For example, when the target working height is 7.85 meters, it may be determined that the working floor may be a third floor corresponding to a height of 7.85 meters.
In a specific implementation, each working floor may have a working height corresponding thereto, for example, it may correspond to a working height of 0 to 4 meters for a first-floor working floor, a working height of 4 to 7.3 meters for a second-floor working floor, a working height of 7.3 to 10.6 meters for a third-floor working floor, and the like. Therefore, after the target operation height of the hoisting equipment is determined, the target operation height can be matched with the operation height corresponding to each operation floor, and the operation floor which is successfully matched is the operation floor corresponding to the operation height. For example, when the target working height is 7.85 meters, since it is located within a working height range of 7.3 meters to 10.6 meters corresponding to the third-floor working floor, it may be determined that the hoisting device is currently carrying the construction material to the third-floor construction floor.
Meanwhile, the total amount of the building material corresponding to each working floor may be predetermined, for example, the total amount of the building material required for each building floor may be planned in advance. Therefore, after the operation floor is determined according to the target operation height, a target building weight required for building the operation floor can be further determined according to the operation floor, wherein the target building weight is the weight of the building materials required for building the operation floor, so that the current construction progress of the operation floor can be measured based on the target building weight.
S203: and determining the construction progress of the operation floor according to the determined actual carrying weight of the operation floor and the target building weight, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor.
In an exemplary embodiment, after determining the actual carrying weight and the target building weight corresponding to the current operation floor, a ratio between the actual carrying weight and the target building weight may be calculated, and the ratio may be used as the construction progress of the operation floor. For example, assuming that the actual carrying weight of the current working floor is 35 tons and the target building weight of the working floor is 50 tons, the ratio between 35 tons and 50 tons can be calculated to be 70%, and the construction progress of the working floor can be determined to be 70%.
And the actual carrying weight of the floor operation is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor. It will be appreciated that in practice the lifting device will typically carry a portion of the building material required to build the current working floor to that working floor, so that in calculating how much weight of building material the lifting device has actually carried for that working floor, the sum of the carried weights of building material the lifting device carries at that target working height can be calculated.
Of course, in further possible embodiments, the ratio between the actual carrying weight and the target building weight may also be adapted. For example, in the actual construction process, a constructor needs a certain time to utilize the building floor of the building material, so the influence of the ratio and the building delay on the construction progress can be comprehensively considered, and the construction progress corresponding to the current operation floor is finally determined.
In practical applications, in order to facilitate tracing back the construction progress of the operation floor, in a further embodiment, time information may be added to the construction progress corresponding to the operation floor. As an example, specifically, when the construction progress corresponding to the operation floor is calculated each time, a corresponding timestamp is added to the construction progress. Therefore, the time point of the construction progress of each working floor in the implementation process of the whole project can be known based on the time stamp corresponding to each construction progress.
In other possible embodiments, the weight carried by the hoisting device in one working cycle may be obtained each time the carried weight of the hoisting device at the target working height is obtained. The starting time of the operation period is that the carrying weight of the hoisting equipment is larger than a preset value, and the ending time of the operation period is that the carrying weight of the hoisting equipment is smaller than the preset value. For example, when the carrying weight of the hoisting device is increased from 0 ton to 0.01 ton or more (the preset value is 0.01 ton), the operation cycle of the hoisting device may be considered to be started, and when the carrying weight of the device is decreased from 0.01 ton or more to 0 ton, the operation cycle of the hoisting device may be considered to be ended. Therefore, when the construction progress of the current operation floor is determined, the operation data of the hoisting equipment carries the operation period information of the operation data, so that the calculated construction progress also has corresponding time information, and the time point corresponding to each construction progress of each operation floor can be determined based on the time information.
In this embodiment, the operation data of the hoisting device may be obtained, where the operation data includes a target operation height of the hoisting device at an operation end point and a carrying weight of the hoisting device at the target operation height; then, an operation floor can be determined according to the target operation height, and a target building weight corresponding to the operation floor can be further determined, wherein the target building weight is the weight of building materials required for building the operation floor; then, the construction progress corresponding to the operation floor can be determined according to the actual carrying weight of the operation floor and the target building weight corresponding to the operation floor, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor. It can be understood that there is close relevance in the construction progress of the operation state of hoisting equipment and current building floor when the operation, consequently, can the analysis obtain the current construction progress of this current building floor through the operation data that acquire hoisting equipment to need not to acquire the construction progress through artifical statistical mode, not only can improve the efficiency of statistics construction progress, reduce the human cost, and moreover, because the data that acquire are actual operation data, not by the data that artifical statistics obtained, consequently, the accuracy of the construction progress that finally confirms has also been improved.
In addition, the embodiment of the application also provides a device for determining the construction progress. Referring to fig. 3, fig. 3 is a schematic structural diagram illustrating an apparatus for determining a construction progress in an embodiment of the present application, where the apparatus 300 may specifically include:
an obtaining module 301, configured to obtain operation data of a hoisting device, where the operation data includes a target operation height of the hoisting device at an operation end point and a carrying weight of the hoisting device at the target operation height;
a first determining module 302, configured to determine an operation floor according to the target operation height, and determine a target building weight corresponding to the operation floor, where the target building weight is a weight of a building material required for building the operation floor;
a second determining module 303, configured to determine the construction progress of the operation floor according to the actual carrying weight of the operation floor and the target building weight, where the actual carrying weight is a sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor.
In one possible embodiment, the work end point is determined by judging that the reduction amount of the load weight is larger than a predetermined threshold value.
In a possible implementation, the apparatus 300 further comprises:
and the adding module is used for adding a timestamp for the determined construction progress, and the timestamp represents the time for the operation floor to reach the construction progress.
In a possible embodiment, the carrying weight of the hoisting device at the target working height, in particular the carrying weight of the hoisting device at the target working height in one working cycle, is greater than a preset value at the start of the working cycle, and is less than the preset value at the end of the working cycle.
In a possible implementation, the obtaining module 301 includes:
the acquiring unit is used for acquiring initial operation data of the hoisting equipment;
and the merging unit is used for merging the initial operation data to obtain the operation data of the hoisting equipment.
It should be noted that, for the contents of information interaction, execution process, and the like between the modules and units of the apparatus, since the same concept is based on the method embodiment in the embodiment of the present application, the technical effect brought by the contents is the same as that of the method embodiment in the embodiment of the present application, and specific contents may refer to the description in the foregoing method embodiment in the embodiment of the present application, and are not described herein again.
In addition, the embodiment of the application also provides equipment. Referring to fig. 4, fig. 4 shows a hardware structure diagram of a device in an embodiment of the present application, the device 400 may be connected to the hoisting device, and the device 400 may include a processor 401 and a memory 402.
Wherein the memory 402 is used for storing a computer program;
the processor 401 is configured to execute the following steps according to the computer program:
acquiring operation data of hoisting equipment, wherein the operation data comprises a target operation height of the hoisting equipment at an operation end point and a carrying weight of the hoisting equipment at the target operation height;
determining an operation floor according to the target operation height, and determining a target building weight corresponding to the operation floor, wherein the target building weight is the weight of building materials required for building the operation floor;
and determining the construction progress of the operation floor according to the actual carrying weight of the operation floor and the target building weight, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor.
In some possible embodiments, the work end point is determined by judging that the reduction amount of the load weight is larger than a predetermined threshold.
In some possible embodiments, the processor 401 is further configured to perform the following steps according to the computer program:
and adding a timestamp for the determined construction progress, wherein the timestamp represents the time for the operation floor to reach the construction progress.
In some possible embodiments, the carrying weight of the hoisting device at the target working height, specifically the carrying weight of the hoisting device at the target working height in one working cycle, is greater than a preset value at the start time of the working cycle, and is less than the preset value at the end time of the working cycle.
In some possible embodiments, the processor 401 is specifically configured to execute the following steps according to the computer program:
acquiring initial operation data of the hoisting equipment;
and merging the initial operation data to obtain the operation data of the hoisting equipment.
In addition, an embodiment of the present application further provides a computer-readable storage medium, where the computer-readable storage medium is used for storing program codes, and the program codes, when executed by a processor, implement the method for determining a construction progress in the foregoing method embodiment.
The "first" in the names of the "first determination module", etc., mentioned in the embodiments of the present application is only used for name identification, and does not represent the first in order. The rule applies equally to "second", etc.
It is clear to those skilled in the art that, for convenience and brevity of description, the specific working processes of the above-described systems, apparatuses and units may refer to the corresponding processes in the foregoing method embodiments, and are not described herein again.
In the several embodiments provided in the present application, it should be understood that the disclosed system, apparatus and method may be implemented in other manners. For example, the above-described apparatus embodiments are merely illustrative, and for example, the division of the units is only one logical division, and other divisions may be realized in practice, for example, a plurality of units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, devices or units, and may be in an electrical, mechanical or other form.
The units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of the embodiment.
In addition, functional units in the embodiments of the present application may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The integrated unit can be realized in a form of hardware, and can also be realized in a form of a software functional unit.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present application may be substantially implemented or contributed to by the prior art, or all or part of the technical solution may be embodied in a software product, which is stored in a storage medium and includes instructions for causing a computer device (which may be a personal computer, a server, or a network device) to execute all or part of the steps of the method according to the embodiments of the present application. And the aforementioned storage medium includes: a U-disk, a removable hard disk, a Read-only Memory (ROM), a Random Access Memory (RAM), a magnetic disk or an optical disk, and other various media capable of storing program codes.
The above embodiments are only used for illustrating the technical solutions of the present application, and not for limiting the same; although the present application has been described in detail with reference to the foregoing embodiments, it should be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions in the embodiments of the present application.

Claims (12)

1. A method of determining a construction progress, the method comprising:
acquiring operation data of hoisting equipment, wherein the operation data comprises a target operation height of the hoisting equipment at an operation end point and a carrying weight of the hoisting equipment at the target operation height;
determining an operation floor according to the target operation height, and determining a target building weight corresponding to the operation floor, wherein the target building weight is the weight of building materials required for building the operation floor;
and determining the construction progress of the operation floor according to the actual carrying weight of the operation floor and the target building weight, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor.
2. The method of claim 1, wherein the job endpoint is determined by determining that an amount of reduction in payload is greater than a predetermined threshold.
3. The method of claim 1, further comprising:
and adding a timestamp for the determined construction progress, wherein the timestamp represents the time for the operation floor to reach the construction progress.
4. The method according to claim 1, wherein the load carrying capacity of the hoisting device at the target working height, in particular the load carrying capacity of the hoisting device at the target working height during a working cycle, is greater than a predetermined value at the start of the working cycle and less than the predetermined value at the end of the working cycle.
5. The method of any one of claims 1 to 4, wherein the obtaining operational data of the lifting device comprises:
acquiring initial operation data of the hoisting equipment;
and merging the initial operation data to obtain the operation data of the hoisting equipment.
6. A device for determining construction progress is characterized in that the device method comprises the following steps:
the system comprises an acquisition module, a control module and a control module, wherein the acquisition module is used for acquiring operation data of the hoisting equipment, and the operation data comprises a target operation height of the hoisting equipment at an operation end point and a carrying weight of the hoisting equipment under the target operation height;
the first determining module is used for determining an operation floor according to the target operation height and determining a target building weight corresponding to the operation floor, wherein the target building weight is the weight of building materials required for building the operation floor;
and the second determination module is used for determining the construction progress of the operation floor according to the actual carrying weight of the operation floor and the target building weight, wherein the actual carrying weight is the sum of the carrying weights of the hoisting equipment at the target operation height corresponding to the operation floor.
7. The apparatus of claim 6, wherein the job end point is determined by determining that a reduction in the payload weight is greater than a predetermined threshold.
8. The apparatus of claim 6, further comprising:
and the adding module is used for adding a timestamp for the determined construction progress, and the timestamp represents the time for the operation floor to reach the construction progress.
9. The apparatus according to claim 6, wherein the carrying weight of the hoisting device at the target working height, in particular the carrying weight of the hoisting device at the target working height within one working cycle, is greater than a preset value at the start of the working cycle and is less than the preset value at the end of the working cycle.
10. The apparatus according to any one of claims 6 to 9, wherein the obtaining module comprises:
the acquiring unit is used for acquiring initial operation data of the hoisting equipment;
and the merging unit is used for merging the initial operation data to obtain the operation data of the hoisting equipment.
11. An apparatus, comprising a processor and a memory:
the memory is to store program instructions;
the processor is configured to invoke the program instructions in the memory to perform the method of determining construction progress according to any one of claims 1 to 5.
12. A computer-readable storage medium for storing program code, which when executed by a processor implements a method of determining construction progress according to any one of claims 1 to 5.
CN201911203501.9A 2019-11-29 2019-11-29 Method, device and equipment for determining construction progress Pending CN110930124A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911203501.9A CN110930124A (en) 2019-11-29 2019-11-29 Method, device and equipment for determining construction progress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911203501.9A CN110930124A (en) 2019-11-29 2019-11-29 Method, device and equipment for determining construction progress

Publications (1)

Publication Number Publication Date
CN110930124A true CN110930124A (en) 2020-03-27

Family

ID=69847851

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911203501.9A Pending CN110930124A (en) 2019-11-29 2019-11-29 Method, device and equipment for determining construction progress

Country Status (1)

Country Link
CN (1) CN110930124A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112561487A (en) * 2020-12-21 2021-03-26 广联达科技股份有限公司 Method, device and equipment for calculating construction progress and readable storage medium
CN112630793A (en) * 2020-11-30 2021-04-09 深圳集智数字科技有限公司 Method and related device for determining plane abnormal point
CN113971781A (en) * 2021-12-03 2022-01-25 上海建工四建集团有限公司 Building structure construction progress identification method and device, client and storage medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107150933A (en) * 2017-06-26 2017-09-12 上海与德科技有限公司 Determination method, device, server and the storage medium of elevator floor
CN108985714A (en) * 2018-07-04 2018-12-11 江苏南通三建集团股份有限公司 A kind of construction site wisdom control integrated system
CN109284928A (en) * 2018-09-27 2019-01-29 广东开放大学(广东理工职业学院) A kind of construction monitoring method and system based on unmanned air vehicle technique
CN109559006A (en) * 2018-09-19 2019-04-02 中建科技有限公司深圳分公司 A kind of monitoring method, device and the terminal device of the construction site based on unmanned plane
CN110232740A (en) * 2019-06-17 2019-09-13 重庆建工第九建设有限公司 Control system and method based on BIM Building Information Model
CN110287519A (en) * 2019-05-14 2019-09-27 深圳大学 A kind of the building engineering construction progress monitoring method and system of integrated BIM

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107150933A (en) * 2017-06-26 2017-09-12 上海与德科技有限公司 Determination method, device, server and the storage medium of elevator floor
CN108985714A (en) * 2018-07-04 2018-12-11 江苏南通三建集团股份有限公司 A kind of construction site wisdom control integrated system
CN109559006A (en) * 2018-09-19 2019-04-02 中建科技有限公司深圳分公司 A kind of monitoring method, device and the terminal device of the construction site based on unmanned plane
CN109284928A (en) * 2018-09-27 2019-01-29 广东开放大学(广东理工职业学院) A kind of construction monitoring method and system based on unmanned air vehicle technique
CN110287519A (en) * 2019-05-14 2019-09-27 深圳大学 A kind of the building engineering construction progress monitoring method and system of integrated BIM
CN110232740A (en) * 2019-06-17 2019-09-13 重庆建工第九建设有限公司 Control system and method based on BIM Building Information Model

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112630793A (en) * 2020-11-30 2021-04-09 深圳集智数字科技有限公司 Method and related device for determining plane abnormal point
CN112630793B (en) * 2020-11-30 2024-05-17 深圳集智数字科技有限公司 Method and related device for determining plane abnormal point
CN112561487A (en) * 2020-12-21 2021-03-26 广联达科技股份有限公司 Method, device and equipment for calculating construction progress and readable storage medium
CN112561487B (en) * 2020-12-21 2024-01-23 广联达科技股份有限公司 Method, device and equipment for calculating construction progress and readable storage medium
CN113971781A (en) * 2021-12-03 2022-01-25 上海建工四建集团有限公司 Building structure construction progress identification method and device, client and storage medium

Similar Documents

Publication Publication Date Title
CN110930124A (en) Method, device and equipment for determining construction progress
CN108959934A (en) Safety risk estimating method, device, computer equipment and storage medium
CN109446041B (en) Server pressure early warning method and system and terminal equipment
CN113310650B (en) Arch bridge sling damage identification method based on beam deflection, terminal and storage medium
EP3499331A1 (en) Monitoring system, learning apparatus, learning method, monitoring apparatus, and monitoring method
CN110659130A (en) CPU utilization rate self-adaptive adjusting method, device, terminal and storage medium
US20210067593A1 (en) Service deployment control system, service deployment control method, and storage medium
CN105491079A (en) Method and device for adjusting resources needed by application in cloud computing environment
CN111289277A (en) Load weight detection method and device, computer equipment and storage medium
Smith CONCRETE PLACING ANALYSIS USING DISCRETE-EVENT SIMULATION.
CN110647437B (en) Method, device, terminal and medium for adjusting CPU utilization rate based on PID controller
US20230192456A1 (en) Working equipment system, and a method of the working equipment system
CN116630082A (en) Method and device for allocating production resources, electronic equipment and storage medium
CN108124442B (en) Elevator element parameter calibration method, device, equipment and storage medium
CN111047098A (en) Construction progress and cost management system, computer equipment and computer readable storage medium
Mandell et al. Quantity choice in unit price contract procurements
CN109019336A (en) A kind of grab bucket crane control system and method based on material detection
US10871759B2 (en) Machining time prediction device for predicting an execution time for tool change
CN114861495A (en) Remaining life determining method and device and working machine
CN107678911B (en) Method and device for monitoring abnormal event processing efficiency
CN112288246B (en) Resource allocation method, terminal and storage medium
RU162895U1 (en) AUTOMATED RISK ASSESSMENT DEVICE
CN112286998B (en) Crane work cycle analysis method and device, terminal equipment and readable storage medium
CN113958107B (en) Climbing frame control method, electric box, server and storage medium
CN115973872B (en) Method and device for correcting abnormal working hours of construction lifter

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200327