CN110905053A - Construction method for indoor drainage pipeline penetrating through floor slab - Google Patents

Construction method for indoor drainage pipeline penetrating through floor slab Download PDF

Info

Publication number
CN110905053A
CN110905053A CN201911069913.8A CN201911069913A CN110905053A CN 110905053 A CN110905053 A CN 110905053A CN 201911069913 A CN201911069913 A CN 201911069913A CN 110905053 A CN110905053 A CN 110905053A
Authority
CN
China
Prior art keywords
hole
branch pipe
main drainage
waterproof
drainage pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911069913.8A
Other languages
Chinese (zh)
Inventor
陈汝培
邓柏声
梁建杭
何宗灼
郭文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Lianggu Construction Engineering Co Ltd
Original Assignee
Guangdong Lianggu Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Lianggu Construction Engineering Co Ltd filed Critical Guangdong Lianggu Construction Engineering Co Ltd
Priority to CN201911069913.8A priority Critical patent/CN110905053A/en
Publication of CN110905053A publication Critical patent/CN110905053A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03CDOMESTIC PLUMBING INSTALLATIONS FOR FRESH WATER OR WASTE WATER; SINKS
    • E03C1/00Domestic plumbing installations for fresh water or waste water; Sinks
    • E03C1/12Plumbing installations for waste water; Basins or fountains connected thereto; Sinks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6801Fillings therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6806Waterstops
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Health & Medical Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Sink And Installation For Waste Water (AREA)

Abstract

The invention relates to the technical field of indoor pipelines, and particularly discloses a construction method for an indoor drainage pipeline to penetrate through a floor slab, which is characterized by comprising the following steps of: s1, installing a main drainage pipe and plugging holes; s2, constructing the ground of the functional area; s3, forming a through hole in the main drainage pipe, wherein the position of the hole in the main drainage pipe is higher than the ground of the functional area constructed in the step S2, the through hole is formed by positioning and forming a hole through a branch pipe connection piece, the branch pipe connection piece comprises a fixing plate, a communication positioning hole is formed in the fixing plate, a branch pipe joint is formed by extending outwards along the communication positioning hole, the fixing plate is covered on the main drainage pipe in the through hole forming process, the communication positioning hole is positioned at the position where the through hole needs to be formed, and a portable hole drilling machine is inserted into the branch pipe and cuts the hole along the edge of the communication positioning hole; s4, attaching the branch pipe connecting piece to the main drainage pipe; effectively avoid current branch pipe connection piece to suffer destruction easily in building or fitment to and suffer to destroy the problem that the back needs to chisel out the entrance to a cave and change.

Description

Construction method for indoor drainage pipeline penetrating through floor slab
Technical Field
The invention relates to the technical field of indoor pipelines, in particular to a construction method for an indoor drainage pipeline to penetrate through a floor slab.
Background
The indoor drainage pipeline often involves and needs to pass the floor, need reserve the hole slightly bigger than the pipeline on the floor in the building or in the decoration process, sewage pipe, waste pipe, downspout etc. drainage main pipe of indoor installation all construct through combining the waterproof steel sleeve pipe that is pre-buried in the hole at present, and to the functional area that requires higher waterproof nature, such as bathroom, kitchen, as shown in figure 5, its branch pipe connection piece is pre-buried together with the major structure usually, or after the connection installation is accomplished, carry on the entrance to a cave shutoff (seal the clearance between hole and the pipeline) immediately, carry on waterproof operation simultaneously. However, during actual on-site construction, different construction operations are often performed by a plurality of construction teams at the same construction position, the branch pipe connectors are frequently damaged, the conventional repair method usually comprises the steps of removing the waterproof layer on the surface and the plugged hole, replacing the branch pipe connectors, repeating the hole plugging and waterproof operations again, and the like, so that a large amount of labor and time are consumed, and leakage is easily caused between the waterproof layer newly laid near the hole and the waterproof layer on the original integral ground, therefore, the conventional construction method for penetrating the floor slab of the indoor drainage pipeline has the defect that the construction method particularly relates to functional areas such as toilets and kitchens.
Disclosure of Invention
The invention aims to provide a construction method for indoor drainage pipeline to penetrate through a floor slab, aiming at the existing technical situation, and effectively solving the problems that the existing branch pipe connector is easy to damage in building or decoration and a hole needs to be removed for replacement after the existing branch pipe connector is damaged.
In order to achieve the purpose, the invention adopts the following technical scheme:
a construction method for penetrating a floor slab through an indoor drainage pipeline is characterized by comprising the following steps:
s1, installing a main drainage pipe in a hole reserved in a floor slab, and plugging the hole;
s2, constructing the ground of the functional area;
s3, forming a through hole in the main drainage pipe, wherein the position of the through hole in the main drainage pipe is higher than the ground of the functional area constructed in the step S2, the through hole is formed by positioning and opening through a branch pipe connection piece, the branch pipe connection piece comprises a fixing plate for fixing the branch pipe connection piece on the main drainage pipe, the surface, which is attached to the main drainage pipe, of the fixing plate is of an arc-shaped surface structure protruding outwards, a communication positioning hole is formed in the fixing plate, a branch pipe joint for connecting with the branch pipe is formed by extending outwards along the communication positioning hole, the fixing plate is covered on the main drainage pipe in the through hole forming process, the communication positioning hole is positioned at the position where the through hole needs to be formed, and the portable hole drilling machine is inserted into the branch pipe and cuts and opens the hole along;
s4, coating an adhesive on the inner wall of the fixing plate, attaching the branch pipe connecting piece to the main drainage pipe, and enabling the communicating positioning hole to coincide with the through hole in the main drainage pipe;
s5, connecting the branch pipe on the branch pipe joint.
Preferably, the plugging in step S1 includes the following steps:
1) uniformly mixing the expansive cement and the fine stone to form mixed slurry, arranging a bottom die in the hole, and pouring the mixed slurry until the mixed slurry is filled to the thickness of two thirds of the thickness of the floor slab;
2) brushing two waterproof coatings;
3) after the water test, no water seepage phenomenon exists, and the mixed slurry is poured until the mixed slurry is 2-3cm higher than the floor slab.
Preferably, the functional area ground construction described in step S2 includes the steps of:
1) local waterproof treatment: coating waterproof paint on a waterproof weak part in the functional area, wherein the waterproof weak part comprises a joint of a main drainage pipe and the ground of the functional area, a floor drain and a male and female corner;
2) integral waterproof treatment: laying two coating waterproof layers on the functional area ground, after water test, no water seepage phenomenon exists, and then laying a waterproof mortar protective layer;
3) backfilling;
4) and laying a finishing coat.
The invention has the beneficial effects that:
according to the invention, the branch pipe connection piece for connecting the branch pipe is installed after hole plugging and functional area ground construction, so that the problem that a branch pipe connection port is damaged in the hole plugging and functional area ground construction process is effectively avoided, meanwhile, the branch pipe connection piece is installed at a position higher than the constructed functional area ground without adopting an installation mode of being pre-embedded in the hole, and if the branch pipe connection piece needs to be replaced in the later period, the plugging structure of the hole and the functional area ground structure do not need to be damaged, so that the replacement is simple and rapid, and the repair construction time is effectively shortened.
Drawings
FIG. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic structural view of the present invention in a state where the branch pipe connector is not installed.
Fig. 3 is a schematic structural view of the branch pipe connector.
Fig. 4 is a schematic view of the inner side structure of the branch pipe connector.
FIG. 5 is a prior art floor penetrating installation structure of indoor drainage pipeline.
Detailed Description
The invention is further illustrated by the following examples in conjunction with the accompanying drawings:
referring to fig. 1-4, the present invention discloses a construction method for indoor drainage pipeline to pass through a floor slab 3, which comprises the following steps:
s1, install the drainage in the hole of reserving in floor 3 and be responsible for 1 (big pipe diameter straight tube), the installation that the drainage was responsible for 1 can refer to current technology, if combine the waterproof sleeve pipe (not marked in the picture) of reservation to carry out the shutoff to the hole, wherein, the shutoff includes following step:
1) uniformly mixing the expansive cement and the fine stone to form mixed slurry, cleaning the peripheral wall of the hole, arranging a bottom die in the hole, enabling the bottom die to be tightly attached to the bottom of the floor slab 3, and pouring the mixed slurry until the mixed slurry is filled to the thickness of two thirds of the thickness of the floor slab 3;
2) brushing two waterproof coatings;
3) and after the waterproof coating is dried, carrying out a water test for 48 hours, pouring the mixed slurry if no water seepage phenomenon exists, until the mixed slurry is 32-3cm higher than the floor slab, and removing the bottom die after the mixed slurry is condensed.
According to the invention, the hole plugging structure of the first slurry condensation layer 41, the double-layer waterproof coating 42 and the second slurry condensation layer 43 is sequentially formed by hole plugging, the waterproof and leak-proof performance of the hole plugging is effectively improved by combining the secondary slurry condensation layer with the double waterproof coating, the second slurry condensation layer 43 is higher than the floor slab 3, the combination of the hole plugging structure and the subsequent functional area ground construction structure layer is facilitated, and the waterproof and leak-proof performance of the whole structure is further enhanced.
S2, construction of the functional area on the ground:
in the present invention, the functional area refers to an indoor area having a high waterproof requirement, such as a kitchen and a toilet.
1) Local waterproof treatment: coating waterproof paint on a waterproof weak part in the functional area, wherein the waterproof weak part comprises a joint of the main drainage pipe 1 and the ground of the functional area, a floor drain and a male and female corner; the waterproof and leakage-proof performance of the whole structure is effectively enhanced by carrying out local waterproof treatment on the waterproof weak part;
2) integral waterproof treatment: laying two coating waterproof layers on the ground of the functional area, testing water for 48 hours, then laying a waterproof mortar protective layer 52, wherein the waterproof mortar protective layer has no water seepage phenomenon;
3) backfilling: and paving the backfill material on the ground of the functional area so as to raise the ground of the functional area to be slightly lower than the ground of other indoor floors, wherein the backfill material can be waste brick residues, cement precast slabs or pearl wool ceramsite.
4) A finishing layer 54 is laid.
In this application, the construction of functional area ground forms double-deck coating waterproof layer 51, waterproof mortar protective layer 52, backfill layer 53 and finish coat 54 in proper order, through multilayer waterproof layer structure, strengthens the waterproof leak protection effect on the whole ground in functional area.
S3, a through hole 11 is formed in the main drainage pipe 1, the position of the hole of the main drainage pipe 1 is higher than the ground of the functional area constructed in the step S2, the through hole 11 is positioned and holed through the branch pipe connector 2, the branch pipe connector 2 can be prefabricated and processed in a factory in a unified way, in the embodiment, the branch pipe connector 2 and the main drainage pipe 1 are made of PVC materials, as shown in figures 3 to 4, the branch pipe connector 2 comprises a fixing plate 21 used for fixing the branch pipe connector 2 on the main drainage pipe 1, the joint surface of the fixing plate 21 and the main drainage pipe 1 is an arc surface structure protruding outwards, preferably, the corresponding diameter of the arc surface of the fixing plate 21 is the same as or similar to that of the main drainage pipe 1, the pipe wall of the fixing plate 21 and the main drainage pipe 1 can be better jointed, a communication positioning hole 22 is formed in the fixing plate 21, and a branch pipe joint 23 used for being connected with the branch pipe is formed by extending outwards along, in the process of opening the through hole 11, the fixing plate 21 is externally covered on the drainage main pipe 1, the communicating positioning hole 22 plays a role in positioning and assisting in opening the hole when the drainage main pipe 1 opens the through hole 11, plays a role in communicating the branch pipe with the drainage main pipe 1 in subsequent branch pipe connection, positions the communicating positioning hole 22 at the position where the through hole 11 needs to be opened, and a portable hole drilling machine is inserted into the branch pipe and performs cutting and opening along the edge of the communicating positioning hole 22;
s4, coating an adhesive on the inner wall of the fixing plate 21, attaching the branch pipe connector 2 to the main drainage pipe 1, and enabling the communication positioning hole 22 to coincide with the through hole 11 in the main drainage pipe 1;
s5, connecting the branch pipe on the branch pipe joint 23.
In the invention, the branch pipe connecting piece 2 for connecting the branch pipe is installed after the hole plugging and the functional area ground construction, so that the problem that the branch pipe connecting port is damaged in the hole plugging and functional area ground construction process is effectively avoided, meanwhile, the branch pipe connecting piece 2 is not embedded in the hole, but is installed at the position higher than the functional area ground after the construction, and if the branch pipe connecting piece 2 needs to be replaced in the later period, the plugging structure of the hole and the functional area ground structure do not need to be damaged, the replacement is simple and rapid, and the repair construction time is effectively shortened.
It should be understood that the above-mentioned drawings are merely illustrative of the preferred embodiments of the present invention, and that the scope of the invention is not limited thereto.

Claims (3)

1. A construction method for penetrating a floor slab through an indoor drainage pipeline is characterized by comprising the following steps:
s1, installing a main drainage pipe in a hole reserved in a floor slab, and plugging the hole;
s2, constructing the ground of the functional area;
s3, forming a through hole in the main drainage pipe, wherein the position of the through hole in the main drainage pipe is higher than the ground of the functional area constructed in the step S2, the through hole is formed by positioning and opening through a branch pipe connection piece, the branch pipe connection piece comprises a fixing plate for fixing the branch pipe connection piece on the main drainage pipe, the surface, which is attached to the main drainage pipe, of the fixing plate is of an arc-shaped surface structure protruding outwards, a communication positioning hole is formed in the fixing plate, a branch pipe joint for connecting with the branch pipe is formed by extending outwards along the communication positioning hole, the fixing plate is covered on the main drainage pipe in the through hole forming process, the communication positioning hole is positioned at the position where the through hole needs to be formed, and the portable hole drilling machine is inserted into the branch pipe and cuts and opens the hole along;
s4, coating an adhesive on the inner wall of the fixing plate, attaching the branch pipe connecting piece to the main drainage pipe, and enabling the communicating positioning hole to coincide with the through hole in the main drainage pipe;
s5, connecting the branch pipe on the branch pipe joint.
2. The indoor drainage pipeline floor penetrating construction method according to claim 1, wherein the plugging in the step S1 comprises the following steps:
1) uniformly mixing the expansive cement and the fine stone to form mixed slurry, arranging a bottom die in the hole, and pouring the mixed slurry until the mixed slurry is filled to the thickness of two thirds of the thickness of the floor slab;
2) brushing two waterproof coatings;
3) after the water test, no water seepage phenomenon exists, and the mixed slurry is poured until the mixed slurry is 2-3cm higher than the floor slab.
3. The indoor drainage pipeline floor-penetrating construction method as claimed in claim 1, wherein the functional area floor construction in the step S2 includes the steps of:
1) local waterproof treatment: coating waterproof paint on a waterproof weak part in the functional area, wherein the waterproof weak part comprises a joint of a main drainage pipe and the ground of the functional area, a floor drain and a male and female corner;
2) integral waterproof treatment: laying two coating waterproof layers on the functional area ground, after water test, no water seepage phenomenon exists, and then laying a waterproof mortar protective layer;
3) backfilling;
4) and laying a finishing coat.
CN201911069913.8A 2019-11-04 2019-11-04 Construction method for indoor drainage pipeline penetrating through floor slab Pending CN110905053A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911069913.8A CN110905053A (en) 2019-11-04 2019-11-04 Construction method for indoor drainage pipeline penetrating through floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911069913.8A CN110905053A (en) 2019-11-04 2019-11-04 Construction method for indoor drainage pipeline penetrating through floor slab

Publications (1)

Publication Number Publication Date
CN110905053A true CN110905053A (en) 2020-03-24

Family

ID=69816375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911069913.8A Pending CN110905053A (en) 2019-11-04 2019-11-04 Construction method for indoor drainage pipeline penetrating through floor slab

Country Status (1)

Country Link
CN (1) CN110905053A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111945901A (en) * 2020-07-27 2020-11-17 北京天恒建设集团有限公司 Waterproof construction method for floor penetrating drainage main pipe hole of toilet in old community
CN112344091A (en) * 2020-10-27 2021-02-09 中建三局安装工程有限公司 Hanging-hole-free drainage pipeline installation method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103089014A (en) * 2013-02-05 2013-05-08 浙江新东阳建设集团有限公司 Construction method of through floor pipe
CN203258205U (en) * 2013-05-14 2013-10-30 中国建筑第八工程局有限公司 Anti-leakage structure of floor-penetrating pipeline without sleeve
CN205148473U (en) * 2015-11-03 2016-04-13 浙江中财管道科技股份有限公司 Saddle tee bend integration forming device for drain line
CN208380085U (en) * 2018-06-25 2019-01-15 成都惟尚建筑设计有限公司 The draining pipe-through floor slab structure of a kind of ground leak
CN208668951U (en) * 2018-06-25 2019-03-29 成都惟尚建筑设计有限公司 A kind of sanitary ware draining pipe-through floor slab structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103089014A (en) * 2013-02-05 2013-05-08 浙江新东阳建设集团有限公司 Construction method of through floor pipe
CN203258205U (en) * 2013-05-14 2013-10-30 中国建筑第八工程局有限公司 Anti-leakage structure of floor-penetrating pipeline without sleeve
CN205148473U (en) * 2015-11-03 2016-04-13 浙江中财管道科技股份有限公司 Saddle tee bend integration forming device for drain line
CN208380085U (en) * 2018-06-25 2019-01-15 成都惟尚建筑设计有限公司 The draining pipe-through floor slab structure of a kind of ground leak
CN208668951U (en) * 2018-06-25 2019-03-29 成都惟尚建筑设计有限公司 A kind of sanitary ware draining pipe-through floor slab structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111945901A (en) * 2020-07-27 2020-11-17 北京天恒建设集团有限公司 Waterproof construction method for floor penetrating drainage main pipe hole of toilet in old community
CN112344091A (en) * 2020-10-27 2021-02-09 中建三局安装工程有限公司 Hanging-hole-free drainage pipeline installation method
CN112344091B (en) * 2020-10-27 2022-08-05 中建三局安装工程有限公司 Hanging-hole-free drainage pipeline installation method

Similar Documents

Publication Publication Date Title
CN106836516B (en) A kind of integrated water-proof chassis of toilet pipeline
CN110905053A (en) Construction method for indoor drainage pipeline penetrating through floor slab
CN203947772U (en) A kind of kitchen and toilet draining main riser service sleeve
CN105239729B (en) It has constructed the construction method of poling reparation of punching after roofing
CN103410318B (en) Washroom pipe well water-leakage construction method
CN105442861A (en) Method for restoring water leakage air face of toilet drainage pipeline
KR100592115B1 (en) The drainage for the tolit water lakage prevention of the residence and the construction method
CN203307978U (en) Double-floor-drain seepage prevention structure
JP2001254414A (en) Remodeling method for drain pipe penetrating concrete building frame
TWM638668U (en) Water guide wall structure of basement interior wall
WO2023039745A1 (en) Drainage and anti-seepage device and method for assembled prefabricated sandwich thermal-insulation external wallboard
CN104775484A (en) Water supply and drainage system of water supply and drainage integrated module and building
CN114045880A (en) Basement post-cast strip treatment process
CN205024824U (en) Bathroom mounting structure
CN211081020U (en) Indoor drainage pipe floor construction structures of wearing
CN206554180U (en) A kind of integrated water-proof chassis of toilet pipeline
CN221052888U (en) Little maintenance structure of tearing open of bathroom infiltration
CN104975623A (en) Non-excavation leaking inspection well repairing method and repairing structure
TW451019B (en) Water-proof and damp-proof method for basement side wall
CN215802143U (en) Secondary drainage stagnant water structure
CN214575373U (en) Indoor waterproof construction for architectural design
CN206859375U (en) A kind of apparatus structure for solving kitchen and toilet floor drain off normal
CN221118813U (en) Toilet caisson water-proof structure
CN216234080U (en) Water receiving bucket for building sewer leakage
CN215166653U (en) Leakage-proof structure for root of pipeline

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200324

RJ01 Rejection of invention patent application after publication