CN110904860A - Large-span flexible steel beam pushing construction method based on stay cable assistance - Google Patents

Large-span flexible steel beam pushing construction method based on stay cable assistance Download PDF

Info

Publication number
CN110904860A
CN110904860A CN201911082876.4A CN201911082876A CN110904860A CN 110904860 A CN110904860 A CN 110904860A CN 201911082876 A CN201911082876 A CN 201911082876A CN 110904860 A CN110904860 A CN 110904860A
Authority
CN
China
Prior art keywords
span
stay cable
steel beam
tower
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911082876.4A
Other languages
Chinese (zh)
Other versions
CN110904860B (en
Inventor
夏学军
李智勇
张锐鹏
周功建
侯守飞
孟庆科
杨庆
闫斌
徐春旺
孙强强
牛伟峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
1st Engineering Co Ltd of MBEC
Original Assignee
No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No1 Engineering Co Ltd Zhongtie Bridge Bureau Group filed Critical No1 Engineering Co Ltd Zhongtie Bridge Bureau Group
Priority to CN201911082876.4A priority Critical patent/CN110904860B/en
Publication of CN110904860A publication Critical patent/CN110904860A/en
Application granted granted Critical
Publication of CN110904860B publication Critical patent/CN110904860B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a large-span flexible steel beam pushing construction method based on stay cable assistance, which relates to the technical field of bridge construction and comprises the steps of arranging an assembling platform and a plurality of temporary buttresses in a bridge construction area, and installing walking type pushing equipment on each temporary buttress; assembling a guide beam, a steel beam and a tower frame on the assembling platform in sections, hanging and tensioning a stay cable, and pre-deflecting the top of the tower frame to a certain angle backwards through different initial tensions of a front cable and a rear cable; starting the walking type pushing equipment to push the steel beam and the guide beam forwards until the front end of the guide beam spans the maximum span and is positioned on the front temporary buttress, and then releasing and tensioning the stay cable, wherein the tower does not enter the maximum span; continuously assembling and jacking the steel beam, and dismantling the cable-buckled tower at a preset position; and continuously assembling and jacking the steel beam, dismantling the guide beam in sections after the steel beam reaches the design position, and dropping the beam in place. The invention reduces the stress of the steel beam and the guide beam and the deflection of the front end of the guide beam in the maximum cantilever state.

Description

Large-span flexible steel beam pushing construction method based on stay cable assistance
Technical Field
The invention relates to the technical field of bridge construction, in particular to a large-span flexible steel beam pushing construction method based on stay cable assistance.
Background
At present, bridge pushing construction is more and more widely applied to projects crossing existing railways, highways and navigation channels because of the advantage that the bridge pushing construction does not need to interrupt traffic under a bridge.
In the pushing construction process of municipal bridges spanning urban cutting such as railway marshalling stations, the pushing span is large due to the fact that the temporary buttress cannot be arranged in the middle of the marshalling station, the large pushing span exceeds the span limit of a steel beam, particularly the steel beam in a steel-concrete composite beam, and the stress of the steel beam and a guide beam and the deflection of the front end of the guide beam can not meet the requirement easily under the condition.
Disclosure of Invention
Aiming at the difficulties in the prior art, the invention provides a large-span flexible steel beam pushing construction method based on stay cable assistance, which reduces the stress of a steel beam and a guide beam and the deflection of the front end of the guide beam in the maximum cantilever state.
In order to achieve the above purposes, the technical scheme adopted by the invention is as follows:
the large-span flexible steel beam pushing construction method based on stay cable assistance specifically comprises the following steps:
arranging an assembling platform and a plurality of temporary buttresses in a bridge construction area, and installing walking type pushing equipment on each temporary buttress;
assembling a guide beam, a steel beam and a tower frame on the assembling platform in sections, installing and tensioning stay cables on the front side and the rear side of the steel beam, and adjusting the front stay cable and the rear stay cable to different initial tensions so as to enable the top of the tower frame to be pre-deflected backwards by a certain angle;
starting the walking type pushing equipment to push a system consisting of a guide beam, a steel beam, a tower frame and a stay cable forwards and span a plurality of large spans, and after the walking type pushing equipment is started to push the system forwards for a certain distance, assembling the steel beams in sections;
when the front end of the guide beam spans one large span and is supported on a first temporary buttress after the large span, a stay cable is stretched, and when the tower spans one large span and is supported on the first temporary buttress after the large span, the stay cable is stretched;
when the tower spans the last large span, the stay cable and the tower are dismantled at a preset position;
and the walking type pushing equipment continuously pushes the system forwards, and after the walking type pushing equipment pushes the system forwards to a designed position, the guide beam is dismantled in sections, and the beam falls into place.
On the basis of the technical scheme, after the stay cable is tensioned, the stay cable force of the tower in the advancing direction is smaller than that of the stay cable on the other side.
On the basis of the technical scheme, when the front end of the guide beam is about to span a larger span and is positioned on the first temporary buttress after the larger span, the difference between the stay cable force in the advancing direction of the tower and the stay cable force on the other side of the tower is not more than 10%.
On the basis of the technical scheme, when the front end span of the guide beam is larger and is supported on the first temporary buttress spanning the large span, the tower does not enter the large span currently.
On the basis of the technical scheme, an anchor beam is arranged at the top of the tower along the bridge direction, two pairs of stay cables are arranged on two sides of the tower respectively, the upper ends of the stay cables are anchored on the anchor beam through anchor seats, and the lower ends of the stay cables are connected with the steel beam or the guide beam through pin shafts through anchor boxes.
On the basis of the technical scheme, when the stay cable is tensioned, the tower is located in a safe area, and the guide beam is not located in a large span.
Compared with the prior art, the invention has the advantages that:
according to the construction method for pushing the large-span flexible steel beam based on the stay cable assistance, the tower and the stay cable are used as auxiliary measures, so that the stress and deflection of the steel beam and the guide beam are improved, the pushing span of the steel beam is increased, and the problem that the bridge with large span is difficult to push due to the fact that the temporary buttress cannot be arranged is solved; the tower and the steel beam are fixedly connected, the top of the tower is pre-deflected to a certain angle backwards through the tension of the stay cables on the front side and the rear side, the stress of the stay cables, the tower, the steel beam and the guide beam in the maximum cantilever state is improved, the change of the stay cable force is small in the pushing process, the cable force is in an allowable range, the stay cable force does not need to be adjusted in the pushing process, the construction process is reduced, the construction risk of a business line is reduced, and the operation time is shortened.
Drawings
FIG. 1 is a schematic structural view of a tower frame and a stay cable after being installed and tensioned;
FIG. 2 is a schematic structural diagram of an embodiment of the present invention when a nose girder is about to complete a maximum span;
FIG. 3 is a schematic structural diagram of a stay cable that is stretched and extended when the tower enters the maximum span in the embodiment of the present invention;
FIG. 4 is a schematic structural diagram of the tower and the stay cables removed after the tower spans the maximum span according to the embodiment of the present invention;
in the figure: 1-splicing platform, 2-temporary buttress, 3-walking pushing equipment, 4-guide beam, 5-steel beam, 6-tower and 7-stay cable.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples.
Referring to fig. 1 to 4, an embodiment of the present invention provides a large-span flexible steel beam pushing construction method based on stay cable assistance, which specifically includes the following steps:
the construction method comprises the following steps that an assembling platform 1 and a plurality of temporary buttresses 2 are arranged in a bridge construction area, further, the temporary buttresses 2 are also arranged in the middle of the assembling platform 1, walking type pushing equipment 3 is installed on each temporary buttress 2, and main pier 8 along the line is also used as a temporary buttress to reduce temporary structural investment;
assembling a guide beam 4 and a steel beam 5 on an assembling platform 1 in sections, welding a base of a tower 6 and a lower anchor point ear plate of a stay cable 7 on the steel beam 5 and the guide beam 4 in the process of assembling the steel beam 5 and the guide beam 4, and starting a walking type pushing device 3 to push the guide beam 4 and the steel beam 5 forwards;
after the guide beam 4 and the steel beam 5 reach a preset assembling position of the tower frame 6, assembling the tower frame 6 on the steel beam 5 in sections, installing and tensioning stay cables 7 on the front side and the rear side of the steel beam 5, adjusting the front stay cables 7 and the rear stay cables 7 to different initial tensions to enable the top of the tower frame 6 to be pre-deflected backwards by a certain angle, connecting the lower end of the tower frame 6 with a base on the steel beam 5 through bolts, and respectively connecting the lower ends of the front stay cables 7 and the rear stay cables 7 with lower anchor point lug plates on the guide beam 4 and the steel beam 5 through anchor boxes by pin shafts;
starting the walking type pushing equipment 3 to push a system consisting of a guide beam 4, a steel beam 5, a tower 6 and a stay cable 7 forwards and span a plurality of large spans, and starting the walking type pushing equipment 3 to push the system forwards for a certain distance each time, assembling the steel beam 5 in sections;
when the front end of the guide beam 4 spans one large span and is supported on the first temporary buttress 2 after the large span, the stay cable 7 is stretched, and when the tower 6 spans one large span and is supported on the first temporary buttress 2 after the large span, the stay cable 7 is stretched;
after the tower 6 spans the last large span, the stay cable 7 and the tower 6 are dismantled at a preset position, preferably, the preset position of the tower 6 is a position where the tower 6 exceeds the large span and is convenient for a crane to operate;
the walking type pushing equipment 3 continuously pushes the system forwards, and after the walking type pushing equipment 3 pushes the system forwards to a designed position, the guide beam 4 is dismantled in sections, and the beam falls into place;
referring to fig. 2 to 3, when the front end span of the guide beam 4 is larger and is supported on the first front temporary pier 2 after the large span, the stay cable 7 is stretched, and the stay cable 7 is used as a wind cable of the tower 6, so that the stability of the tower 6 in the jacking process of the steel beam 5 is improved.
By using the tower 6 and the stay cables 7 as auxiliary measures, the stress and deflection of the steel beam 5 are improved, so that the pushing span of the steel beam 5 is increased, and the problem of difficult bridge pushing due to large span caused by incapability of arranging the temporary buttress 2 is solved; after the tower 6 is assembled, the top of the tower 6 is pre-deflected backward by a certain angle by adjusting the tension of the stay cables 7 on the front side and the rear side of the tower 6, so that the stress of the stay cables 7, the tower 6, the steel beam 5 and the guide beam 4 under the maximum cantilever state at the front end of the guide beam 4 is improved, the change of the stay cables 7 on the cable force is small in the pushing process, the cable force is in an allowable range, the cable force of the stay cables 7 does not need to be adjusted in the pushing process, the construction process is reduced, the construction risk of a business line is reduced, and the operation time is shortened.
When the stay cable 7 is tensioned, the tower 6 is positioned in a safe area, and the guide beam 4 is not positioned in a large span, so that the safety of personnel for tensioning the stay cable 7 can be ensured, and meanwhile, when the stay cable 7 is tensioned, the guide beam 4 is not downwarped, wherein after the stay cable 7 is tensioned, the cable force of the stay cable 7 in the advancing direction of the tower 6 is smaller than that of the stay cable 7 on the other side of the stay cable, and the cable force of the stay cable 7 in the advancing direction is smaller than that of the stay cable 7 on the other side after the stay cable 7 is tensioned, so that the large body 6 is pre-deflected by a certain angle in the opposite direction of the advancing direction;
when the front end of the guide beam 4 is about to span a larger span and is positioned on the first temporary buttress 2 after the larger span (the guide beam 4 is positioned in the large span and in the maximum cantilever state), the difference between the cable force of the stay cable 7 in the advancing direction of the tower 6 and the cable force of the stay cable 7 on the other side of the tower is not more than 10%, and the stress of the steel beam and the guide beam and the deflection of the front end of the guide beam can meet the preset requirements when the guide beam 4 is about to span the maximum span and is positioned on the first temporary buttress 2 after the maximum span, namely the stress of the steel beam and the guide beam and the deflection of the front end of the guide beam meet the preset requirements in the maximum cantilever state.
The top of the tower frame 6 is provided with an anchor beam along the bridge direction, two pairs of stay cables 7 are arranged on two sides of the tower frame 6 respectively, the upper ends of the stay cables 7 are anchored on the anchor beam through anchor seats, and the lower ends of the stay cables 7 are connected with the steel beam 5 or the guide beam 4 through anchor boxes by pin shafts, so that the stay cables 7 can adapt to the change of the relative angle between the top of the tower frame 6 and the steel beam 5 as well as the change of the relative angle between the top of the tower frame and the guide beam 4, the stay cables 7 are prevented from bearing the action of transverse force, and the safety.
When the front end of the guide beam 4 spans a larger span and is supported on the first front temporary buttress 2 after the large span is spanned, the tower 6 does not enter the current large span, so that the tower 6 can be prevented from transmitting excessive concentrated force to the steel beam 5, and the condition that the steel beam 5 is damaged in the pushing process is prevented.
The walking type pushing equipment 3 comprises a three-way jack, can push the steel beam 5 forwards, and can adjust the vertical and horizontal line shapes of the steel beam 5 according to the requirement; meanwhile, the walking type pushing equipment 3 is uniformly controlled through the controller, so that the stability of the jacking process of the steel beam 5 is ensured, the structural shaking in the jacking process is avoided, and the structural safety is improved.
The tension sensor is arranged on the stay cable 7, the stress sensor is arranged at the bottom of the tower frame 6, the displacement sensor is arranged at the top of the tower frame 6, the actual state monitoring of the stay cable 7 and the tower frame 6 in the jacking process can be completed through the tension sensor, the stress sensor and the displacement sensor, parameters detected by the tension sensor, the stress sensor and the displacement sensor are compared with theoretical calculation data, if the detected parameters exceed a safe controllable range, the vertical jacking height and the jacking force of each walking jacking device 3 are adjusted, the indexes are ensured to be in the safe controllable range, the construction safety is ensured, constructors can be adjusted and maintained aiming at corresponding parts, and the safety performance in the jacking process is improved.
The present invention is not limited to the above-described embodiments, and it will be apparent to those skilled in the art that various modifications and improvements can be made without departing from the principle of the present invention, and such modifications and improvements are also considered to be within the scope of the present invention. Those not described in detail in this specification are within the skill of the art.

Claims (6)

1. A large-span flexible steel beam pushing construction method based on stay cable assistance is characterized by comprising the following steps:
arranging an assembling platform (1) and a plurality of temporary buttresses (2) in a bridge construction area, and installing a walking type pushing device (3) on each temporary buttress (2);
assembling a guide beam (4), a steel beam (5) and a tower frame (6) on the assembling platform (1) in sections, installing and tensioning stay cables (7) on the front side and the rear side of the steel beam (5), and adjusting the front stay cable and the rear stay cable (7) to different initial tensions so as to enable the top of the tower frame (6) to be pre-deflected backwards by a certain angle;
starting the walking type pushing equipment (3) to push a system consisting of a guide beam (4), a steel beam (5), a tower frame (6) and a stay cable (7) forwards and span a plurality of large spans, and starting the walking type pushing equipment (3) to push the system forwards for a certain distance each time, splicing the steel beam (5) in sections;
when the front end of the guide beam (4) spans one large span and is supported on the first temporary buttress (2) after the large span, a stay cable (7) is stretched, and when the tower (6) spans one large span and is supported on the first temporary buttress (2) after the large span, the stay cable (7) is stretched;
after the tower (6) spans the last large span, dismantling the stay cable (7) and the tower (6) at a preset position;
and the walking pushing equipment (3) continuously pushes the system forward, and after the walking pushing equipment (3) pushes the system forward to a designed position, the guide beam (4) is dismantled in sections and falls into place.
2. The stay cable assisted large-span flexible steel beam pushing construction method according to claim 1, characterized in that: and after the stay cable (7) is tensioned, the cable force of the stay cable (7) in the advancing direction of the tower (6) is smaller than that of the stay cable (7) on the other side.
3. The stay cable assisted large-span flexible steel beam pushing construction method according to claim 1, characterized in that: when the front end of the guide beam (4) is about to span a larger span and is positioned on the first temporary buttress (2) after the larger span, the difference between the cable force of the stay cable (7) in the advancing direction of the tower (6) and the cable force of the stay cable (7) on the other side is not more than 10%.
4. The stay cable assisted large-span flexible steel beam pushing construction method according to claim 1, characterized in that: when the front end span of the guide beam (4) is large and is supported on the first temporary buttress (2) spanning the large span, the tower (6) does not enter the large span.
5. The stay cable assisted large-span flexible steel beam pushing construction method according to claim 1, characterized in that: the top of the tower frame (6) is provided with an anchor beam along the bridge direction, two pairs of stay cables (7) are arranged on two sides of the tower frame (6), the upper ends of the stay cables (7) are anchored on the anchor beam through anchor seats, and the lower ends of the stay cables (7) are connected with the steel beam (5) or the guide beam (4) through pin shafts through anchor boxes.
6. The stay cable assisted large-span flexible steel beam pushing construction method according to claim 1, characterized in that: when the stay cable (7) is tensioned, the tower (6) is located in a safe area, and the guide beam (4) is not located in a large span.
CN201911082876.4A 2019-11-07 2019-11-07 Large-span flexible steel beam pushing construction method based on stay cable assistance Active CN110904860B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911082876.4A CN110904860B (en) 2019-11-07 2019-11-07 Large-span flexible steel beam pushing construction method based on stay cable assistance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911082876.4A CN110904860B (en) 2019-11-07 2019-11-07 Large-span flexible steel beam pushing construction method based on stay cable assistance

Publications (2)

Publication Number Publication Date
CN110904860A true CN110904860A (en) 2020-03-24
CN110904860B CN110904860B (en) 2022-02-01

Family

ID=69816671

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911082876.4A Active CN110904860B (en) 2019-11-07 2019-11-07 Large-span flexible steel beam pushing construction method based on stay cable assistance

Country Status (1)

Country Link
CN (1) CN110904860B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576252A (en) * 2020-06-17 2020-08-25 广西交科集团有限公司 Real-time adjusting device and adjusting method for main beam line type in bridge pushing process
CN113322813A (en) * 2021-04-30 2021-08-31 中铁上海工程局集团第五工程有限公司 Method for solving synchronous pushing of large-span steel concrete composite beam by using cable-stayed tower
CN113356081A (en) * 2021-07-15 2021-09-07 中交一公局集团有限公司 Bridge incremental launching construction method and bridge precast beam structure
CN113756209A (en) * 2021-10-18 2021-12-07 湖南省通盛工程有限公司 Diagonal pulling and pushing construction method for large-span steel beam
CN115418969A (en) * 2022-09-30 2022-12-02 中冶(上海)钢结构科技有限公司 Construction method for high-position beam falling of large-span through tied steel arch bridge
CN115506265A (en) * 2022-11-24 2022-12-23 湖南省通盛工程有限公司 Multipoint walking pushing equipment and pushing process for large-section I-shaped steel beam

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001193016A (en) * 2000-01-17 2001-07-17 Sumitomo Heavy Ind Ltd Launching machine for erecting bridge
CN101139821A (en) * 2007-10-16 2008-03-12 中铁大桥局集团第四工程有限公司 Method and system for erecting steel trusses by stay cable auxiliary complete cantilever
CN101200876A (en) * 2007-12-03 2008-06-18 中铁大桥局集团第四工程有限公司 Erection of second hole large-span steel girder by rear anchorage cable method
CN201106155Y (en) * 2007-10-16 2008-08-27 中铁大桥局集团第四工程有限公司 Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN101525866A (en) * 2009-04-17 2009-09-09 中铁大桥局股份有限公司 Multiple girder steel beam compel closure technique using deviation of temporary rest pier
CN102094389A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Separable large-section truss girder hydraulic lifting device
CN102383378A (en) * 2011-11-28 2012-03-21 中铁大桥局股份有限公司 Successive launching method for high temporary piers
CN103821075A (en) * 2013-12-23 2014-05-28 浙江省交通科学研究院 Large-span cable-stayed highway steel bridge
JP2014118724A (en) * 2012-12-14 2014-06-30 Ihi Infrastructure Systems Co Ltd Erection method for bridge
CN106968178A (en) * 2017-04-07 2017-07-21 中交第二公路勘察设计研究院有限公司 A kind of cable-stayed type suspension bridge main girder construction method
CN107489103A (en) * 2017-08-08 2017-12-19 云南公投建设集团第六工程有限公司 Large-span Steel Box Beam tower with suspended cable aids in push construction method
CN207032062U (en) * 2017-08-08 2018-02-23 云南公投建设集团第六工程有限公司 Tower with suspended cable available for Large-span Steel Box Beam construction
CN208009265U (en) * 2018-02-28 2018-10-26 中国水利水电第五工程局有限公司 A kind of combined I-shaped steel girder erection device
CN108951434A (en) * 2018-10-10 2018-12-07 河北工业大学 Curve lightweight I-beam beam bridge hauling construction cantilever end control device and control method
CN208917704U (en) * 2018-10-10 2019-05-31 河北工业大学 Curve lightweight I-beam beam bridge hauling construction cantilever end control device
CN209368697U (en) * 2018-11-28 2019-09-10 中铁上海工程局集团有限公司 A kind of tensioning pylon

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001193016A (en) * 2000-01-17 2001-07-17 Sumitomo Heavy Ind Ltd Launching machine for erecting bridge
CN101139821A (en) * 2007-10-16 2008-03-12 中铁大桥局集团第四工程有限公司 Method and system for erecting steel trusses by stay cable auxiliary complete cantilever
CN201106155Y (en) * 2007-10-16 2008-08-27 中铁大桥局集团第四工程有限公司 Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN101200876A (en) * 2007-12-03 2008-06-18 中铁大桥局集团第四工程有限公司 Erection of second hole large-span steel girder by rear anchorage cable method
CN101525866A (en) * 2009-04-17 2009-09-09 中铁大桥局股份有限公司 Multiple girder steel beam compel closure technique using deviation of temporary rest pier
CN102094389A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Separable large-section truss girder hydraulic lifting device
CN102383378A (en) * 2011-11-28 2012-03-21 中铁大桥局股份有限公司 Successive launching method for high temporary piers
JP2014118724A (en) * 2012-12-14 2014-06-30 Ihi Infrastructure Systems Co Ltd Erection method for bridge
CN103821075A (en) * 2013-12-23 2014-05-28 浙江省交通科学研究院 Large-span cable-stayed highway steel bridge
CN106968178A (en) * 2017-04-07 2017-07-21 中交第二公路勘察设计研究院有限公司 A kind of cable-stayed type suspension bridge main girder construction method
CN107489103A (en) * 2017-08-08 2017-12-19 云南公投建设集团第六工程有限公司 Large-span Steel Box Beam tower with suspended cable aids in push construction method
CN207032062U (en) * 2017-08-08 2018-02-23 云南公投建设集团第六工程有限公司 Tower with suspended cable available for Large-span Steel Box Beam construction
CN208009265U (en) * 2018-02-28 2018-10-26 中国水利水电第五工程局有限公司 A kind of combined I-shaped steel girder erection device
CN108951434A (en) * 2018-10-10 2018-12-07 河北工业大学 Curve lightweight I-beam beam bridge hauling construction cantilever end control device and control method
CN208917704U (en) * 2018-10-10 2019-05-31 河北工业大学 Curve lightweight I-beam beam bridge hauling construction cantilever end control device
CN209368697U (en) * 2018-11-28 2019-09-10 中铁上海工程局集团有限公司 A kind of tensioning pylon

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
同济大学等: "《建筑索结构技术标准》", 30 April 2019, 同济大学出版社 *
彭孝旺: "波形钢腹板小箱梁结构设计及顶推施工技术研究", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 *
曹迎春: "《大跨度建筑施工技术手册》", 31 July 2003, 当代中国音像出版社 *
牛远志: "通惠河北路立交匝道桥设计简介", 《桥梁建设》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576252A (en) * 2020-06-17 2020-08-25 广西交科集团有限公司 Real-time adjusting device and adjusting method for main beam line type in bridge pushing process
CN113322813A (en) * 2021-04-30 2021-08-31 中铁上海工程局集团第五工程有限公司 Method for solving synchronous pushing of large-span steel concrete composite beam by using cable-stayed tower
CN113356081A (en) * 2021-07-15 2021-09-07 中交一公局集团有限公司 Bridge incremental launching construction method and bridge precast beam structure
CN113756209A (en) * 2021-10-18 2021-12-07 湖南省通盛工程有限公司 Diagonal pulling and pushing construction method for large-span steel beam
CN115418969A (en) * 2022-09-30 2022-12-02 中冶(上海)钢结构科技有限公司 Construction method for high-position beam falling of large-span through tied steel arch bridge
CN115506265A (en) * 2022-11-24 2022-12-23 湖南省通盛工程有限公司 Multipoint walking pushing equipment and pushing process for large-section I-shaped steel beam

Also Published As

Publication number Publication date
CN110904860B (en) 2022-02-01

Similar Documents

Publication Publication Date Title
CN110904860B (en) Large-span flexible steel beam pushing construction method based on stay cable assistance
CN110761201B (en) Steel approach bridge pushing equipment and construction method adopting same
CN101560752A (en) Construction method for erecting steel truss girder on uplift pushing tow
CN103510475A (en) Long-distance pushing construction method of thee-main-truss steel truss beam in single-connection and double-span modes without guide beam
CN108385539B (en) Long-distance pushing construction method for steel-concrete combined beam span arch ring of deck arch bridge
CN112900282A (en) Bidirectional quick pushing equipment system for large-span main beam and construction method
CN103147405B (en) Method for erecting steel girder of cable-stayed bridge with diagonal main trusses
CN114438905A (en) Walking type sliding and pushing construction method and device for bridge construction
CN105401527B (en) Construction method for anchoring catwalk and catwalk anchoring device
CN110939071A (en) Non-buttress construction method for assembled steel-concrete I-shaped composite beam bridge
CN110396943B (en) Steel arch segmental moving and hoisting system and method for upper bearing arch bridge construction
CN101892634B (en) Top pushing mechanism of steel box girder of single longitudinal clapboard on wide bridge deck and top pushing method
CN116949946A (en) Construction method for bridge bridging of small-radius curve bridge
CN111119068A (en) Closure system for main beam of arch-tower cable-stayed bridge and construction method thereof
KR20020074130A (en) Methodology in one united body for pre-fabrication upper part of bridge using lifting System with push pull mechanism.
CN114250716A (en) Long cantilever upper pier structure for medium-long span steel beam incremental launching construction and method thereof
CN216193962U (en) Track foundation reinforcing structure of water gantry crane
CN215482398U (en) Two-way quick top of large-span girder pushes away equipment system
CN212533727U (en) Bridge bottom maintenance platform
CN210368664U (en) Wide-body bridge girder erection machine
CN115404786B (en) Pushing construction method for steel-concrete composite beam
CN108221639B (en) Three tower suspension bridge girder installation construction structures
CN207933870U (en) A kind of asymmetric assembled steel cable-stayed bridge
CN107815968B (en) Large-beam combined steel plate beam bridge deck cast-in-place construction sliding formwork system and application thereof
CN215164796U (en) A nose girder mounting structure for steel box girder top pushes away construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant