CN110886238A - Post-tensioning simply supported box girder prestress tensioning trolley - Google Patents

Post-tensioning simply supported box girder prestress tensioning trolley Download PDF

Info

Publication number
CN110886238A
CN110886238A CN201911366479.XA CN201911366479A CN110886238A CN 110886238 A CN110886238 A CN 110886238A CN 201911366479 A CN201911366479 A CN 201911366479A CN 110886238 A CN110886238 A CN 110886238A
Authority
CN
China
Prior art keywords
base
sliding rail
fixed
tensioning
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911366479.XA
Other languages
Chinese (zh)
Inventor
韩广雁
范存丽
王杰
卢孟凡
安明明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN201911366479.XA priority Critical patent/CN110886238A/en
Publication of CN110886238A publication Critical patent/CN110886238A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A post-tensioning simple-supported box girder prestress tensioning trolley relates to the field of trolleys. The jack is mainly designed for solving the problems that the existing jack for tensioning is not easy to move and easily causes injury to people and objects in the tensioning construction process. The walking wheel device comprises a base, wherein a bottom plate is fixed on the base, the walking wheel is installed on the base through a shaft, and a connecting arm is connected to the left end of the base through a shaft. The four support rods are respectively in threaded connection with nuts of the base; the frame is fixed on the base, and the top of the frame is fixed with a front transverse sliding rail and a rear transverse sliding rail; pulleys at the bottoms of the left longitudinal slide rail and the right longitudinal slide rail are matched with the two transverse slide rails; the front longitudinal slide rail and the rear longitudinal slide rail are both provided with a pulley, the pulley is provided with a hanging ring, the electric hoist is hung in the hanging ring, and the lower end of the electric hoist chain is provided with a jack; the rear side surface of the frame is provided with a protective net. The advantages are convenient movement and effective prevention of casualty accidents.

Description

Post-tensioning simply supported box girder prestress tensioning trolley
The technical field is as follows:
the invention relates to the field of trolleys, in particular to a post-tensioning simple-supported box girder prestress tensioning trolley.
Background art:
in the post-tensioning prestressed concrete simply-supported box girder construction process, the prestressed construction is a key process. The box girder which reaches the requirements of strength, age and elastic modulus after pouring needs to be subjected to tensioning construction, so that the jack is required to be lifted, and the tensioning position needs to be changed continuously in the tensioning process, so that the position of the jack needs to be changed in time. The existing jack for tensioning is very heavy and is not easy to move. The accidents of hurting people and objects can be caused by the conditions of sliding, breaking, flying out of clamping pieces and the like in the tensioning construction process.
The invention content is as follows:
the invention aims to solve the technical problem of providing a post-tensioning method simple-supported box girder prestress tensioning trolley which is convenient to move and can not generate the conditions of wire sliding, wire breaking, clip flying and the like in the tensioning process.
The above object is achieved by: the walking wheel comprises a base, a bottom plate is fixed on the base, the walking wheel is installed on the base through a shaft, the right ends of two connecting arms are connected with two corners of the left end of the base through the shaft, the left ends of the two connecting arms are provided with holes, and the walking wheel is connected with an upper tractor through the connecting arms, so that the walking wheel can be very conveniently transferred.
Nuts are fixed at four corners of the base, and four support rods made of finish-rolled deformed steel bars are respectively in threaded connection with the nuts at the four corners of the base;
the frame is fixed on the base, and the top of the frame is fixed with a front transverse sliding rail and a rear transverse sliding rail;
the left longitudinal slide rail and the right longitudinal slide rail are arranged above the two transverse slide rails, pulleys are arranged at the positions, corresponding to the front transverse slide rail and the rear transverse slide rail, of the bottoms of the left longitudinal slide rail and the right longitudinal slide rail, and the pulleys at the bottoms of the left longitudinal slide rail and the right longitudinal slide rail are installed with the two transverse slide rails in a matched mode; the left longitudinal slide rail and the right longitudinal slide rail can move left and right on the two transverse slide rails;
pulleys are mounted on the front longitudinal slide rail and the rear longitudinal slide rail, each pulley is fixedly provided with a hanging ring, a hook of the electric hoist is hung in the hanging ring, and a jack is hung at the lower end of a chain of the electric hoist; the jack can move back and forth through the pulley;
a protective net is fixed at the left end of the rear side of the frame, a protective net is also fixed at the right end of the rear side of the frame, the lengths and the heights of the protective nets at the two positions are the same, and the lengths of the two protective nets are both one fourth of the length of the frame; the lower half part of the rear side of the frame between the two protective nets is fixed with the protective net; the protective net is composed of a steel wire mesh, a rubber pad and a steel plate which are fixed together.
The middle part of the frame is provided with a pedal.
The invention has the advantages that: when the device is used for tensioning the box girder, the box girder can be moved freely in a girder yard construction site by means of a tractor, and the electric hoist can be used for connecting the upper jack to realize free movement of the jack. Convenient and fast, labour saving and time saving has saved engineering cost greatly for the construction progress, and the protection network can effectually prevent the casualties accident that leads to such as smooth silk, disconnected silk, clamping piece departure among the tensioning process, effectively guarantees the security quality among the box girder tensioning work progress.
Description of the drawings:
FIG. 1 is a schematic front view of the present invention;
FIG. 2 is a schematic diagram of the right-hand side view of the present invention;
fig. 3 is a schematic top view of the base of the present invention.
The specific implementation mode is as follows:
the invention is further illustrated with reference to fig. 1-3;
it includes base 1, is fixed with bottom plate 2 on the base, and the walking wheel 3 is installed on the base through the axle, and the right-hand member of two linking arms 4 passes through two bights of hub connection at the base left end, and the left end of two linking arms is porose, connects the tractor through the linking arm, can be very convenient shift.
Nuts are fixed at four corners of the base, and four support rods 5 made of finish-rolled deformed steel bars are respectively in threaded connection with the nuts at the four corners of the base;
the frame 6 is fixed on the base, and the top of the frame is fixed with a front transverse slide rail 7 and a rear transverse slide rail 8;
the left longitudinal slide rail and the right longitudinal slide rail are both arranged above the two transverse slide rails, pulleys are arranged at the positions, corresponding to the front transverse slide rail and the rear transverse slide rail, of the bottoms of the left longitudinal slide rail and the right longitudinal slide rail, and the pulleys at the bottoms of the left longitudinal slide rail and the right longitudinal slide rail are installed with the two transverse slide rails in a matched mode; the left longitudinal slide rail and the right longitudinal slide rail can move left and right on the two transverse slide rails;
the front longitudinal slide rail and the rear longitudinal slide rail are both provided with pulleys 11, each pulley is fixed with a hanging ring, a hook of an electric hoist 12 is hung in the hanging ring, and the lower end of a chain of the electric hoist is hung with a jack 13; the jack can move back and forth through the pulley;
a protective net 14 is fixed at the left end of the rear side of the frame, a protective net is also fixed at the right end of the rear side of the frame, the lengths and the heights of the protective nets at the two positions are the same, and the lengths of the two protective nets are both one fourth of the length of the frame; the lower half part of the rear side of the frame between the two protective nets is fixed with the protective net; the protective net is composed of a steel wire mesh, a rubber pad and a steel plate which are fixed together.
The middle part of the frame is provided with a pedal 15.

Claims (3)

1. The utility model provides a post-tensioned method simple box girder prestressing force stretch-draw platform truck, includes base (1), is fixed with bottom plate (2) on the base, and walking wheel (3) are installed on the base through the axle, characterized by: the right ends of the two connecting arms (4) are connected with two corners of the left end of the base through shafts, and the left ends of the two connecting arms are provided with holes;
nuts are fixed at four corners of the base, and four support rods (5) made of finish-rolled deformed steel bars are respectively in threaded connection with the nuts at the four corners of the base;
the frame (6) is fixed on the base, and the top of the frame is fixed with a front transverse sliding rail (7) and a rear transverse sliding rail (8);
the sliding device is characterized by further comprising a left longitudinal sliding rail (9) and a right longitudinal sliding rail (10), wherein the left longitudinal sliding rail and the right longitudinal sliding rail are arranged above the two transverse sliding rails, pulleys are arranged at the positions, corresponding to the front transverse sliding rail and the rear transverse sliding rail, of the bottoms of the left longitudinal sliding rail and the right longitudinal sliding rail, and the pulleys at the bottoms of the left longitudinal sliding rail and the right longitudinal sliding rail are installed in a matched mode with the two transverse sliding rails; the left longitudinal slide rail and the right longitudinal slide rail can move left and right on the two transverse slide rails;
pulleys (11) are mounted on the front longitudinal slide rail and the rear longitudinal slide rail, each pulley is fixedly provided with a hanging ring, a hook of an electric hoist (12) is hung in the hanging ring, and a jack (13) is hung at the lower end of a chain of the electric hoist;
a protective net (14) is fixed at the left end of the rear side of the frame, a protective net is also fixed at the right end of the rear side of the frame, the lengths and the heights of the protective nets at the two positions are the same, and the lengths of the two protective nets are one fourth of the length of the frame; the lower half part of the rear side surface of the frame between the two protective nets is fixed with the protective net.
2. The post-tensioning simple supported box girder prestress tensioning trolley according to claim 1, which is characterized in that: the middle part of the frame is provided with a pedal (15).
3. The post-tensioning simple supported box girder prestress tensioning trolley according to claim 1, which is characterized in that: the protective net is composed of a steel wire mesh, a rubber pad and a steel plate which are fixed together.
CN201911366479.XA 2019-12-26 2019-12-26 Post-tensioning simply supported box girder prestress tensioning trolley Pending CN110886238A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911366479.XA CN110886238A (en) 2019-12-26 2019-12-26 Post-tensioning simply supported box girder prestress tensioning trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911366479.XA CN110886238A (en) 2019-12-26 2019-12-26 Post-tensioning simply supported box girder prestress tensioning trolley

Publications (1)

Publication Number Publication Date
CN110886238A true CN110886238A (en) 2020-03-17

Family

ID=69753240

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911366479.XA Pending CN110886238A (en) 2019-12-26 2019-12-26 Post-tensioning simply supported box girder prestress tensioning trolley

Country Status (1)

Country Link
CN (1) CN110886238A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201560587U (en) * 2009-09-28 2010-08-25 中国建筑土木建设有限公司 Box girder tensioning frame adopting post-tensioning method
CN204249072U (en) * 2014-11-28 2015-04-08 中国建筑第六工程局有限公司 For stretch-draw and the baffle plate integrating device of precast beam stretch-draw
CN204826678U (en) * 2015-07-25 2015-12-02 中铁十九局集团第二工程有限公司 Prestressing force is platform truck for steel strand stretching
CN208328712U (en) * 2018-05-31 2019-01-04 宁夏路桥工程股份有限公司 Composite multifunction tensioning platform
CN208543625U (en) * 2018-07-04 2019-02-26 湖南联智智能科技有限公司 A kind of precast beam production line tensioning trolley
CN211665589U (en) * 2019-12-26 2020-10-13 中铁十九局集团第一工程有限公司 Post-tensioning simply supported box girder prestress tensioning trolley

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201560587U (en) * 2009-09-28 2010-08-25 中国建筑土木建设有限公司 Box girder tensioning frame adopting post-tensioning method
CN204249072U (en) * 2014-11-28 2015-04-08 中国建筑第六工程局有限公司 For stretch-draw and the baffle plate integrating device of precast beam stretch-draw
CN204826678U (en) * 2015-07-25 2015-12-02 中铁十九局集团第二工程有限公司 Prestressing force is platform truck for steel strand stretching
CN208328712U (en) * 2018-05-31 2019-01-04 宁夏路桥工程股份有限公司 Composite multifunction tensioning platform
CN208543625U (en) * 2018-07-04 2019-02-26 湖南联智智能科技有限公司 A kind of precast beam production line tensioning trolley
CN211665589U (en) * 2019-12-26 2020-10-13 中铁十九局集团第一工程有限公司 Post-tensioning simply supported box girder prestress tensioning trolley

Similar Documents

Publication Publication Date Title
CN204249072U (en) For stretch-draw and the baffle plate integrating device of precast beam stretch-draw
CN213865240U (en) Two stacker that stretch of double-column
CN204780488U (en) Portable hanger rail frame
CN211665589U (en) Post-tensioning simply supported box girder prestress tensioning trolley
CN102191731A (en) Gantry crane for auxiliary rail
CN110886238A (en) Post-tensioning simply supported box girder prestress tensioning trolley
CN2235961Y (en) Lifter
CN211037745U (en) Road engineering installation crane
CN203199883U (en) Scissor type lifting tool for steel rail lifting
CN103663236A (en) Heavy-type cover plate lifting device
CN216471869U (en) Bridge crane damping device
CN211198537U (en) Device for opening electric working well cover plate
CN214087406U (en) Fine quality rod hoisting equipment
CN204778565U (en) Well lid handling device
CN213950340U (en) Simple hoisting device for lifting lug-free ditch cover plate
CN211444787U (en) Span-adjustable beam lifting machine
CN211519531U (en) Curb handling tool
CN109403167B (en) Rail bending trolley for rail welding recovery engineering
CN203593962U (en) Movable transversally-tensioning device of T-shaped beam bridge floor system
CN207062782U (en) A kind of cast-in-situ box girder prestressed stretch-draw support
CN207657838U (en) A kind of carrying cart for heavy articles
CN112252195A (en) Assembly type continuous beam prestressed steel strand whole-bundle tensioning operation trolley and use method thereof
CN209353221U (en) A kind of packaged type cantilever job platform for the construction of side guardrail
CN217556694U (en) Prestressed reinforcement tensioning platform
CN214187766U (en) A precast beam tensioning equipment for construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination