CN110886202A - Socket joint type node connection structure and construction method for prefabricated reinforced concrete hollow pier - Google Patents

Socket joint type node connection structure and construction method for prefabricated reinforced concrete hollow pier Download PDF

Info

Publication number
CN110886202A
CN110886202A CN201911176790.8A CN201911176790A CN110886202A CN 110886202 A CN110886202 A CN 110886202A CN 201911176790 A CN201911176790 A CN 201911176790A CN 110886202 A CN110886202 A CN 110886202A
Authority
CN
China
Prior art keywords
component
bearing platform
pier
steel
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911176790.8A
Other languages
Chinese (zh)
Inventor
韩强
刘腾飞
贾振雷
陈龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Technology
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201911176790.8A priority Critical patent/CN110886202A/en
Publication of CN110886202A publication Critical patent/CN110886202A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a socket joint type joint connection structure of a prefabricated reinforced concrete hollow pier and a manufacturing method thereof. Meanwhile, interface ripples are arranged on the surfaces of the pier column and the bearing platform, connection and shearing resistance are improved, gaps between the pier column and the bearing platform are subjected to crack pouring by adopting UHPC (ultra high performance concrete), socket connection quality is greatly met, and meanwhile, the early strength is high, and the performance of rapid construction can be achieved. And the operation is simple and convenient, the construction is easy, and the quality is controllable.

Description

Socket joint type node connection structure and construction method for prefabricated reinforced concrete hollow pier
Technical Field
The invention relates to the technical field of bridge engineering, in particular to a socket joint type joint connection structure of a prefabricated reinforced concrete hollow pier and a manufacturing method thereof.
Background
At present, the bridge construction is mainly based on cast-in-place concrete, and the cast-in-place construction of the concrete has the disadvantages of large quantity of required field labor force and high casualty risk; the working procedures are multiple, and the waste of site resources is much; with the reduction of the Chinese population dividend in the last decade, the population aging is serious, and the labor cost is increased; environmental pollution, noise pollution and other adverse social and economic influences in field construction.
The economic quantity is rapidly increased, the site is limited, and the urban construction and operation face huge traffic pressure, so that the construction of three-dimensional traffic is imperative, but the construction of the conventional cast-in-place structure is long in time consumption, traffic jam around the urban construction site is serious in environmental pollution, and the construction method can not adapt to urban development more and more. The novel prefabricated structure can be used for greatly improving the construction efficiency.
Compared with the conventional cast-in-place concrete structure, the hollow pier has the advantages that the moment of inertia is obviously increased, the bending resistance is increased, the dead weight is obviously reduced, and the construction cost, the transportation cost and the hoisting cost are saved under the condition of the same mass. At present, the joint connection mode of the prefabricated pier mainly comprises sleeve steel bar connection, grouting corrugated pipe connection, cast-in-place wet joint connection and conventional socket joint type connection. The sleeve steel bar connection and grouting corrugated pipe connection construction difficulty is large, the sleeve steel bar connection and grouting corrugated pipe connection construction method is generally only used in regions with seismic fortification intensity below 7 degrees, and a connection mode of a prefabrication assembly technology adopted in a high-intensity region needs to be further developed. The work load of the connection of the cast-in-place wet joint and the cast-in-place is large, and the improvement of the construction speed is limited. The stress performance of the joint of the conventional socket joint type connection prefabricated pier stud and the foundation is undefined, the connection is weak, and the thickness of a required bearing platform is large. The invention aims at the problems of a prefabricated bridge, and discloses a socket type prefabricated reinforced concrete hollow pier connecting structure and a manufacturing method.
Disclosure of Invention
The invention aims to provide a socket joint type joint connecting structure of a prefabricated reinforced concrete hollow pier and a manufacturing method thereof. The construction time of the pier connection form of the cast-in-place structure is long, the field requirement labor force is large, and the environment is easily polluted. The grouting sleeve is high in precision requirement, not beneficial to construction and not easy to guarantee quality. The socket splicing between the hollow pier stud and the bearing platform has the advantages of reliable connection, quick construction of the prefabricated pier, easy construction and controllable quality. From the mechanical point of view, the bearing capacity is basically the same as that of a cast-in-place structure, the stress is reasonable, and the bending resistance and torsion resistance are excellent. From the technical implementation perspective, this type of structure is easily prefabricated at the mill, saves the labour, and the quality is easily guaranteed, can save the cost simultaneously at the reasonable scope of distance to transport. And in the field implementation stage, the structure is convenient to splice on the field, has a self-locking function and is easy to accurately position. The pouring of the UHPC is convenient, the strength and the durability meet the requirements, and particularly, under the action of fatigue load, the UHPC can effectively reduce the development of tiny cracks at the crack pouring position.
The technical scheme for solving the technical problems is as follows:
a prefabricated reinforced concrete hollow pier socket joint type connecting node structure is characterized in that a prefabricated hollow pier column (a second component) is composed of a hollow pier solid part 1, cast-in-place core filling concrete 2, pier column and bearing platform interface spiral ripples 3, a pier column and bearing platform steel wedge 4, a pier bottom steel plate hole 7 and a pier lower steel plate 8. The prefabricated bearing platform (component I) is composed of a pier stud and a bearing platform steel wedge 4, a cast-in-place bearing platform solid part 5, a crack pouring UHPC6 and a mortar sitting UHPC 9. And (3) extending anchoring steel bars 10 in the prefabricated bearing platform, anchoring the lower part of the prefabricated bearing platform in the prefabricated bearing platform (component I), inserting the upper part of the prefabricated bearing platform into the prefabricated hollow pier stud (component II) through a steel plate hole 7 at the bottom of the prefabricated hollow pier stud (component II), and embedding the upper part of the extending anchoring steel bars 10 in the prefabricated bearing platform (component I) in the cast-in-situ core filling concrete 2. And the pier lower steel plate 8 of the prefabricated hollow pier column (component II) is connected with the prefabricated hollow pier column (component II) through an anchoring steel bar (not shown). The bottom of the prefabricated hollow pier column (component II) is connected with the prefabricated bearing platform (component I) through a mortar UHPC9, the side surface of the prefabricated hollow pier column (component II) is aligned and self-locked with the bearing platform steel wedge 4 through the pier column and a crack pouring UHPC6, and the hollow part of the prefabricated hollow pier column (component II) is connected with the prefabricated bearing platform (component I) through the anchoring steel bar 10 extending out of the prefabricated bearing platform and the cast-in-situ core filling concrete 2.
The first component is a prefabricated bearing platform, a socket space and a socket position are reserved before pouring, the interface corrugation 3 is considered to be arranged, the effect of a shear key is achieved, the shear force is effectively transmitted, the interface connection performance of concrete and UHPC is improved, and meanwhile, the phenomenon that the UHPC generates debonding due to repeated action of load when the structure is in a normal use state can be reduced.
The lower end of an anchoring steel bar 10 extending out of the prefabricated bearing platform is anchored in the prefabricated bearing platform concrete, the end part of the lower end of the anchoring steel bar is welded with the prefabricated bearing platform steel bar, and when the prefabricated hollow pier stud is inserted, the anchoring steel bar can extend out of a long round hole of a steel plate at the lower part of the prefabricated hollow pier stud, enters the hollow part of the prefabricated hollow pier stud and then is bent.
And the second component is a prefabricated hollow pier column, a steel plate 8 at the lower part of the pier is positioned at the end part of the hollow pier to seal the hollow pier, but the surface of the second component is provided with steel plate holes 7 to facilitate the extension of anchoring steel bars 10, and then the second component is bent to play a role in locally reinforcing and separating the cast-in-situ C40 core filling concrete 2 and the grout UHPC 9.
The prefabricated bearing platform (component I) and the prefabricated hollow pier stud (component II) are both provided with steel wedges 4, the steel wedges 4 are in a spatial hexahedron, when the pier stud is in socket construction, corresponding positions are staggered firstly, and when the designed position is reached, the pier stud is rotated, so that the steel wedges 4 are aligned up and down and reach the designed corresponding positions. When the pier stud steel wedge is arranged, the pier stud steel wedge is arranged on the lower side of the bearing platform steel wedge, the lower two pairs of steel wedges 4 are arranged, and the pier stud steel wedge is arranged on the upper side of the bearing platform steel wedge. Therefore, the steel wedges can be used as positioning and limiting measures in space, meanwhile, the steel wedges 4 limit the movement of the pier stud in all directions, the temporary reinforcing effect can be achieved, redundant temporary reinforcing measures can be omitted, the engineering quantity of engineering is greatly reduced, the construction period is shortened, and meanwhile, construction is facilitated.
When the prefabricated hollow pier stud (the second component) is used for rotationally positioning the steel wedge 4, a certain space is required for the steel plate hole 7 at the lower part of the pier stud corresponding to the anchoring steel bar 10, so that the steel plate hole 7 is arranged to be a long round hole, and the rotation angle of the pier stud can be provided.
In order to improve the connection performance of the hollow pier stud and the prefabricated bearing platform, UHPC mortar is adopted for the bottom of the hollow pier stud and the prefabricated bearing platform, and the compact mark during construction is that UHPC slurry flows out from a steel plate hole 7 at the lower part of the hollow pier stud.
When the prefabricated bearing platform (the first component) and the prefabricated hollow pier stud (the second component) rotate to the position, and after the prefabricated bearing platform and the prefabricated hollow pier stud (the second component) are installed, pouring is carried out by using the pouring UHPC6, so that the structure is integrated. The pouring adopts a one-point pouring and self-leveling mode, so that the compactness can be ensured, and auxiliary vibration measures are not needed.
And finally, in order to meet the anti-collision requirement of the pier stud and provide enough anchoring space for the anchoring reinforcing steel bar 10, the core filling concrete 2 is cast in the hollow position of the hollow pier in situ.
Compared with the conventional prefabricated assembled and cast-in-place pier, the invention has the following advantages and effects:
1) the grouting sleeve is high in connection construction precision requirement, small in grouting clearance, difficult in guarantee of compactness, difficult in grouting detection, sudden change of section rigidity of a sleeve region, stress concentration and easy to damage in the sleeve region. The long general scope of metal bellows connecting reinforcement anchor length is 7 ~ 10 times and indulges the muscle diameter, and reinforcing bar figure is too much, and the installation is difficult, and the transportation is inconvenient, and the grout space is little, and the closely knit degree of quality is difficult to guarantee, detects the difficulty equally, has the joint failure risk. The scheme has no steel bar anchoring problem, the grouting space is large and is formed in one step, and the quality is easy to guarantee and detect. The invention has reliable connection, easy installation, high construction fault tolerance rate, easy quality detection and good stress transfer.
2) The method has the characteristics of scale and industrialization, and has great advantages in a reasonable distance range.
Drawings
Fig. 1 is an overall schematic diagram of a prefabricated socket assembling hollow pier.
Fig. 2 is a schematic diagram of a prefabricated socket assembling hollow pier bearing platform (a first component).
Fig. 3 is a schematic diagram of a prefabricated socket assembling hollow pier column (component II).
FIG. 4 is a schematic cross-sectional view of a prefabricated socket assembling hollow pier A-A.
FIG. 5 is a schematic cross-sectional view of a prefabricated socket assembling hollow pier B-B.
FIG. 6 is a schematic cross-sectional view of a prefabricated socket assembling hollow pier C-C.
FIG. 7 is a schematic cross-sectional view of a prefabricated socket assembling hollow pier D-D.
Fig. 8 is a big picture of a prefabricated socket assembling hollow pier component 4.
Fig. 9 is a flow chart of assembling a prefabricated socket assembling hollow pier.
In the figure: a bearing platform (a first component); a pier stud (second component); 1-solid part of hollow pier; 2-cast-in-situ C40 core filling concrete; 3-the interface of the pier stud and the bearing platform is spirally corrugated; 4, steel wedge between pier stud and bearing platform; 5, casting a solid part of a bearing platform in situ; 6-crack pouring UHPC; 7-steel plate holes at the lower part of the bridge pier; 8, a lower steel plate of the pier; 9-sitting plasm UHPC; 10, extending anchoring steel bars in the bearing platform.
Detailed Description
The following detailed description of the embodiments of the invention refers to the accompanying drawings.
The utility model provides a prefabricated reinforced concrete hollow pier socket joint formula connected node structure, includes: the hollow pier comprises a hollow pier solid part 1, cast-in-situ core filling concrete 2, pier column and bearing platform interface spiral ripples 3, pier column and bearing platform steel wedges 4, a cast-in-situ bearing platform solid part 5, a crack pouring UHPC6, pier bottom steel plate holes 7, pier lower steel plates 8, mortar pouring UHPC9 and anchoring steel bars 10 extending out of the bearing platform. The construction comprises two members; the first component is a prefabricated bearing platform, and the second component is a prefabricated hollow pier stud; the first component and the second component are connected through socket joint, and a gap between the first component and the second component is filled with UHPC; the bottom of the second component is provided with a steel plate, and a steel plate hole is arranged at the corresponding position; the bottom of the first component is provided with an anchoring steel bar, the lower end of the first component is welded with the steel bar in the bearing platform, and the upper end of the first component extends into the hollow part of the second component through the long pore of the steel plate at the bottom of the second component and then is bent; the second component is poured with core filling concrete, the height of the core filling concrete exceeds the exposed length of the anchoring reinforcing steel bar, and the core filling concrete meets the anti-collision requirement;
the hollow pier splicing structure based on the prefabricated socket joint and the manufacturing method thereof comprise the following steps:
1) the prefabrication work of the bearing platform (the first component) and the hollow pier stud (the second component) is completed in a prefabrication factory,
2) before the bearing platform (component I) is poured, the anchoring steel bars 10 are welded with steel bars inside the bearing platform, meanwhile, the upper ends of the anchoring steel bars extend out for a certain distance, the steel wedges 4 on the upper portion and the lower portion of the bearing platform are welded with the steel bars of the bearing platform before pouring, and then concrete is poured and maintained.
3) Before the pier column (component II) is poured, the steel plate 8 at the lower part of the pier is connected with the pier column steel bar. The upper and lower steel wedges 4 of the pier stud are welded with the steel bars of the pier stud before pouring. Meanwhile, the steel plate 8 at the lower part of the pier is provided with steel plate holes 7 at corresponding positions, so that the anchoring steel bars 10 can conveniently stretch into and rotate with the pier stud, and then concrete is poured and maintained.
4) After the component is transported to the site, the spigot and socket part is cleaned and wetted by water, so that the strength of the UHPC is prevented from being affected due to water loss.
5) UHPC sitting slurry is firstly paved at the bottom of the bell socket of the bearing platform (the first component) as shown in figure 9, the pier stud (the second component) is inserted into the bell socket, and when the pier stud reaches a designed position, the hollow pier is slowly rotated to enable the pier stud and the steel wedge 4 of the bearing platform to align and self-lock, so that temporary supporting and fixing effects are achieved, and the process is finished before UHPC is initially set.
6) The bearing platform (the first component) and the hollow pier stud (the second component) rotate to the position, then the UHPC is used for pouring joints as shown in figure 9, a funnel is used for pouring from one point, a self-leveling mode is adopted, the strength and compactness can be ensured, and other auxiliary vibration facilities can not be used.
7) The concrete pouring of the core filling of the hollow pier is carried out as shown in fig. 9, the concrete volume is strictly considered during pouring, and the anchoring steel bars 10 are ensured to extend out of the bearing platform and meet the anti-collision requirement.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the present invention. It will be apparent to those skilled in the art that various modifications and adaptations can be made without departing from the principles of the invention and these are intended to be within the scope of the invention.

Claims (5)

1. The utility model provides a prefabricated reinforced concrete hollow pier socket joint formula nodal connection structure which characterized in that: the construction comprises two members; the first component is a prefabricated bearing platform, and the second component is a prefabricated hollow pier stud; the first component and the second component are connected through socket joint, and a gap between the first component and the second component is filled with UHPC; the bottom of the second component is provided with a steel plate, and a steel plate hole is arranged at the corresponding position; the bottom of the first component is provided with an anchoring steel bar, the lower end of the first component is welded with the steel bar in the bearing platform, and the upper end of the first component extends into the hollow part of the second component through the long pore of the steel plate at the bottom of the second component and then is bent; and the second component is poured with core filling concrete, the height of the core filling concrete exceeds the exposed length of the anchoring reinforcing steel bar, and the anti-collision requirement is met.
2. The socket joint type joint connection structure of the prefabricated reinforced concrete hollow pier is characterized in that the surfaces of socket joints of the first member and the second member are provided with interface spiral corrugations, the interface corrugations of the first member and the second member are symmetrically distributed, and after assembly is completed, UHPC grouting material is poured to form a plurality of small shear keys.
3. The socket joint type joint connection structure of the precast reinforced concrete hollow pier as claimed in claim 1, wherein the upper part and the lower part of the socket joint of the first member and the second member are both provided with oblique steel wedges, the second member is constructed and placed in place, and is rotated to form self-locking without temporary support.
4. The socket joint type joint connection structure of the prefabricated reinforced concrete hollow pier, according to claim 1, is characterized in that UHPC sitting slurry is adopted at the socket bottoms of the first member and the second member, the thickness of the sitting slurry can be limited by a steel block, and UHPC grouting is adopted at the gap.
5. A socket joint type joint connection method for a prefabricated reinforced concrete hollow pier, which is characterized in that,
1) the prefabrication work of the bearing platform and the hollow pier stud is completed in a prefabrication factory,
2) before the bearing platform is poured, the anchoring steel bars are welded with the steel bars inside the bearing platform, meanwhile, the upper end of the anchoring steel bars extends out for a certain distance, the steel wedges on the upper portion and the lower portion of the bearing platform are welded with the steel bars of the bearing platform before pouring, and then concrete is poured and cured;
3) before pouring the pier stud, connecting a steel plate at the lower part of the pier with a pier stud steel bar; the steel wedges at the upper and lower parts of the pier column are welded with the steel bars of the pier column before pouring; meanwhile, steel plate holes are arranged at corresponding positions of the steel plates at the lower part of the pier, so that anchoring steel bars can conveniently extend into the steel plates and the pier stud can conveniently rotate, and then concrete is poured and cured;
4) after the component is transported to the site, the spigot and socket part is cleaned and wetted by water, so that the strength of the UHPC is prevented from being affected due to water loss;
5) the method comprises the following steps that UHPC sitting slurry is laid at the bottom of a bell socket of a bearing platform, a pier stud is inserted into the bell socket, when the hollow pier stud reaches a designed position, a hollow pier is slowly rotated, the pier stud and a steel wedge of the bearing platform are aligned and self-locked, a temporary supporting and fixing effect is achieved, and the process is finished before initial setting of the UHPC;
6) the bearing platform and the hollow pier stud rotate to the position, then the UHPC is used for pouring joints as shown in figure 9, a funnel is used for pouring from one point, a self-leveling mode is adopted, the strength and compactness can be ensured, and other auxiliary vibration facilities can not be used;
7) and (4) carrying out core filling concrete pouring on the hollow pier, and strictly considering the concrete volume during pouring to ensure that the anchoring reinforcing steel bars extend out of the bearing platform and meet the anti-collision requirement.
CN201911176790.8A 2019-11-26 2019-11-26 Socket joint type node connection structure and construction method for prefabricated reinforced concrete hollow pier Pending CN110886202A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911176790.8A CN110886202A (en) 2019-11-26 2019-11-26 Socket joint type node connection structure and construction method for prefabricated reinforced concrete hollow pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911176790.8A CN110886202A (en) 2019-11-26 2019-11-26 Socket joint type node connection structure and construction method for prefabricated reinforced concrete hollow pier

Publications (1)

Publication Number Publication Date
CN110886202A true CN110886202A (en) 2020-03-17

Family

ID=69748905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911176790.8A Pending CN110886202A (en) 2019-11-26 2019-11-26 Socket joint type node connection structure and construction method for prefabricated reinforced concrete hollow pier

Country Status (1)

Country Link
CN (1) CN110886202A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576196A (en) * 2020-04-29 2020-08-25 中铁四局集团第二工程有限公司 On-site splicing pouring construction process for prefabricated pier column segment shell and bent cap
CN112030724A (en) * 2020-08-10 2020-12-04 山东高速建设管理集团有限公司 Bidirectional socket type prefabricated assembly type pier and construction method thereof
CN112176886A (en) * 2020-11-16 2021-01-05 山东高速建设管理集团有限公司 Double-steel sleeve socket connection structure of prefabricated bridge pier and construction method thereof
CN112761176A (en) * 2020-12-26 2021-05-07 北京工业大学 Socket and embedded steel bar combined prefabricated hollow pier-bearing platform connection method and structure
CN113356037A (en) * 2021-05-31 2021-09-07 郑州大学 Cast-in-place UHPC-NC combination formula antidetonation pier in outer assembly
CN113481834A (en) * 2021-08-12 2021-10-08 上海应用技术大学 Novel prefabricated assembled pier and construction method thereof
CN113565120A (en) * 2021-07-22 2021-10-29 国网甘肃省电力公司经济技术研究院 Composite iron tower bearing platform suitable for frost heaving area and construction method
CN114263093A (en) * 2022-01-22 2022-04-01 郑州大学 Fully-prefabricated assembled bridge and construction method
CN114592423A (en) * 2022-04-01 2022-06-07 中国十九冶集团有限公司 Wet joint connection construction method of prefabricated pier stud and bearing platform
CN114635349A (en) * 2021-12-06 2022-06-17 中交第二公路勘察设计研究院有限公司 Light-duty assembled pier suitable for non-violent earthquake district
CN114855651A (en) * 2022-05-25 2022-08-05 北京市政路桥管理养护集团有限公司 Concrete pier column reinforcing structure and reinforcing method
WO2022227177A1 (en) * 2021-04-28 2022-11-03 福州大学 Connection structure capable of achieving accurate positioning of multi-limb concrete-filled steel tube spatial structure and bearing platform, and construction method therefor
CN116201003A (en) * 2023-03-23 2023-06-02 天津大学 Novel high-strength steel bar UHPC-high-strength concrete combined hollow pier

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120107183A (en) * 2011-03-21 2012-10-02 김서지 One touch binder for a precast construction and a precast construction applied with the same
CN105421223A (en) * 2015-12-21 2016-03-23 上海市城市建设设计研究总院 Prefabricated pier upright column, cushion cap spigot and insertion groove combined connection structure and splicing method
CN107227685A (en) * 2017-08-07 2017-10-03 上海应用技术大学 A kind of spliced bridge pier structure of rotary buckle and corresponding joining method
CN107882051A (en) * 2017-10-29 2018-04-06 北京工业大学 A kind of conical pipe anchor bar connecting structure for precast assembly structure
CN108547216A (en) * 2018-06-12 2018-09-18 北京市市政工程设计研究总院有限公司 Bridge prefabrication performance of concrete column confined and bridge foundation alligator bell and spigot frame and construction method
CN108547217A (en) * 2018-06-12 2018-09-18 北京市市政工程设计研究总院有限公司 Unit construction bridge formed precast concrete pier stud and bent cap bell and spigot frame and construction method
CN108951404A (en) * 2018-08-10 2018-12-07 苏交科集团股份有限公司 Cross connection structure and connection method for segment prefabricated pier stud
KR20190012039A (en) * 2017-07-26 2019-02-08 주식회사 동성엔지니어링 Pier protector
CN110468694A (en) * 2019-09-06 2019-11-19 郑州大学 Spigot-and-socket Self-resetting multi-segmental precast pier and its assembly method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120107183A (en) * 2011-03-21 2012-10-02 김서지 One touch binder for a precast construction and a precast construction applied with the same
CN105421223A (en) * 2015-12-21 2016-03-23 上海市城市建设设计研究总院 Prefabricated pier upright column, cushion cap spigot and insertion groove combined connection structure and splicing method
KR20190012039A (en) * 2017-07-26 2019-02-08 주식회사 동성엔지니어링 Pier protector
CN107227685A (en) * 2017-08-07 2017-10-03 上海应用技术大学 A kind of spliced bridge pier structure of rotary buckle and corresponding joining method
CN107882051A (en) * 2017-10-29 2018-04-06 北京工业大学 A kind of conical pipe anchor bar connecting structure for precast assembly structure
CN108547216A (en) * 2018-06-12 2018-09-18 北京市市政工程设计研究总院有限公司 Bridge prefabrication performance of concrete column confined and bridge foundation alligator bell and spigot frame and construction method
CN108547217A (en) * 2018-06-12 2018-09-18 北京市市政工程设计研究总院有限公司 Unit construction bridge formed precast concrete pier stud and bent cap bell and spigot frame and construction method
CN108951404A (en) * 2018-08-10 2018-12-07 苏交科集团股份有限公司 Cross connection structure and connection method for segment prefabricated pier stud
CN110468694A (en) * 2019-09-06 2019-11-19 郑州大学 Spigot-and-socket Self-resetting multi-segmental precast pier and its assembly method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
马会天: "《装配式桥梁预制空心桥墩安装施工工艺》", 《工程与建设》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576196A (en) * 2020-04-29 2020-08-25 中铁四局集团第二工程有限公司 On-site splicing pouring construction process for prefabricated pier column segment shell and bent cap
CN112030724A (en) * 2020-08-10 2020-12-04 山东高速建设管理集团有限公司 Bidirectional socket type prefabricated assembly type pier and construction method thereof
CN112176886A (en) * 2020-11-16 2021-01-05 山东高速建设管理集团有限公司 Double-steel sleeve socket connection structure of prefabricated bridge pier and construction method thereof
CN112761176A (en) * 2020-12-26 2021-05-07 北京工业大学 Socket and embedded steel bar combined prefabricated hollow pier-bearing platform connection method and structure
WO2022227177A1 (en) * 2021-04-28 2022-11-03 福州大学 Connection structure capable of achieving accurate positioning of multi-limb concrete-filled steel tube spatial structure and bearing platform, and construction method therefor
CN113356037A (en) * 2021-05-31 2021-09-07 郑州大学 Cast-in-place UHPC-NC combination formula antidetonation pier in outer assembly
CN113565120A (en) * 2021-07-22 2021-10-29 国网甘肃省电力公司经济技术研究院 Composite iron tower bearing platform suitable for frost heaving area and construction method
CN113481834A (en) * 2021-08-12 2021-10-08 上海应用技术大学 Novel prefabricated assembled pier and construction method thereof
CN114635349A (en) * 2021-12-06 2022-06-17 中交第二公路勘察设计研究院有限公司 Light-duty assembled pier suitable for non-violent earthquake district
CN114263093A (en) * 2022-01-22 2022-04-01 郑州大学 Fully-prefabricated assembled bridge and construction method
CN114592423A (en) * 2022-04-01 2022-06-07 中国十九冶集团有限公司 Wet joint connection construction method of prefabricated pier stud and bearing platform
CN114592423B (en) * 2022-04-01 2024-01-30 中国十九冶集团有限公司 Wet joint connection construction method for prefabricated pier column and bearing platform
CN114855651A (en) * 2022-05-25 2022-08-05 北京市政路桥管理养护集团有限公司 Concrete pier column reinforcing structure and reinforcing method
CN116201003A (en) * 2023-03-23 2023-06-02 天津大学 Novel high-strength steel bar UHPC-high-strength concrete combined hollow pier

Similar Documents

Publication Publication Date Title
CN110886202A (en) Socket joint type node connection structure and construction method for prefabricated reinforced concrete hollow pier
CN107190635B (en) Dumbbell type steel pipe concrete combined bridge pier and connecting structure and method of dumbbell type steel pipe concrete combined bridge pier and bearing platform
US8474080B2 (en) Construction method of steel composition girder bridge
CN113216484B (en) Steel-concrete composite beam connection structure and design calculation method
CN110777661B (en) Flange connection prefabricated assembly pier structure and construction method thereof
CN109252727B (en) Shock insulation layer rubber support, column, beam and plate system integrated assembly node and method
CN211036679U (en) Socket joint connection structure of prefabricated pier stud of assembled bridge and cushion cap
CN108179806B (en) Fully assembled reinforced concrete frame structure system
CN110258362B (en) Deformation control method for urban underground engineering to pass through existing bridge
CN211113140U (en) Equal cast-in-place assembly type hollow pier system
CN113216409A (en) Connecting structure of precast concrete tubular pile column with diagonal bracing and hollow floor or flat floor
CN111364355A (en) Assembled reinforced concrete side anti-collision guardrail for connecting bridges and construction method
CN212200051U (en) Assembled reinforced concrete side anti-collision guardrail for connecting bridge
CN115045181A (en) Socket joint type node connection method and structure for prefabricated pier column and bearing platform in middle and high intensity region
CN114319977B (en) Steel pipe concrete row column type connection precast shear wall structure and construction method
CN111364356A (en) Assembled reinforced concrete side anti-collision guardrail for connecting bridge
CN108265744B (en) Connection structure of overhead transmission line PHC tubular pile foundation pile and cushion cap
CN109972512B (en) Cast-in-place construction method of profiled steel sheet-concrete combined bridge deck slab
CN219219334U (en) Prefabricated assembled ultra-high performance concrete T type roof beam
CN216664531U (en) Take precast concrete board of layer board wet joint structure
CN114016380A (en) Prefabricated assembled concrete trestle and construction method thereof
CN113737636A (en) Steel-concrete combined connecting structure suitable for assembly type pier stud and construction method thereof
CN112064824A (en) Combined-connection prefabricated shear wall system
CN220643676U (en) Pile-board connection node of pile-board road bridge structure
CN220724829U (en) Double-sided overlapped assembled bridge pier suitable for construction of high and cold and earthquake active areas

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200317