CN110778323A - Construction method for pulling and passing buried pipeline - Google Patents
Construction method for pulling and passing buried pipeline Download PDFInfo
- Publication number
- CN110778323A CN110778323A CN201910839041.2A CN201910839041A CN110778323A CN 110778323 A CN110778323 A CN 110778323A CN 201910839041 A CN201910839041 A CN 201910839041A CN 110778323 A CN110778323 A CN 110778323A
- Authority
- CN
- China
- Prior art keywords
- drilling
- pipeline
- drill bit
- reaming
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 60
- 238000005553 drilling Methods 0.000 claims abstract description 126
- 238000000034 method Methods 0.000 claims abstract description 24
- 238000013461 design Methods 0.000 claims abstract description 17
- 230000008569 process Effects 0.000 claims abstract description 17
- 238000011835 investigation Methods 0.000 claims abstract description 4
- 239000002689 soil Substances 0.000 claims description 49
- 239000002002 slurry Substances 0.000 claims description 42
- 230000009471 action Effects 0.000 claims description 14
- 238000005520 cutting process Methods 0.000 claims description 13
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- CDBYLPFSWZWCQE-UHFFFAOYSA-L Sodium Carbonate Chemical compound [Na+].[Na+].[O-]C([O-])=O CDBYLPFSWZWCQE-UHFFFAOYSA-L 0.000 claims description 8
- 238000007599 discharging Methods 0.000 claims description 8
- 239000000314 lubricant Substances 0.000 claims description 7
- 239000004927 clay Substances 0.000 claims description 6
- 238000012546 transfer Methods 0.000 claims description 6
- 238000003466 welding Methods 0.000 claims description 6
- 230000003628 erosive effect Effects 0.000 claims description 5
- 239000000843 powder Substances 0.000 claims description 5
- 239000000700 radioactive tracer Substances 0.000 claims description 5
- 239000000440 bentonite Substances 0.000 claims description 4
- 229910000278 bentonite Inorganic materials 0.000 claims description 4
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 claims description 4
- 229920001222 biopolymer Polymers 0.000 claims description 4
- 229910003460 diamond Inorganic materials 0.000 claims description 4
- 239000010432 diamond Substances 0.000 claims description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 229910000029 sodium carbonate Inorganic materials 0.000 claims description 4
- 235000017550 sodium carbonate Nutrition 0.000 claims description 4
- 239000002562 thickening agent Substances 0.000 claims description 4
- 241001536352 Fraxinus americana Species 0.000 claims description 3
- 238000013459 approach Methods 0.000 claims description 3
- 238000002347 injection Methods 0.000 claims description 3
- 239000007924 injection Substances 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 238000005259 measurement Methods 0.000 claims description 3
- 238000009659 non-destructive testing Methods 0.000 claims description 3
- 239000003973 paint Substances 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 claims description 3
- 239000003550 marker Substances 0.000 claims description 2
- 238000004321 preservation Methods 0.000 claims description 2
- 238000009331 sowing Methods 0.000 claims description 2
- 238000012937 correction Methods 0.000 claims 1
- 238000009933 burial Methods 0.000 abstract description 3
- 238000009826 distribution Methods 0.000 abstract description 2
- 238000009412 basement excavation Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 230000007797 corrosion Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 238000010438 heat treatment Methods 0.000 description 2
- 230000001050 lubricating effect Effects 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 239000000243 solution Substances 0.000 description 2
- 238000005507 spraying Methods 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 244000208734 Pisonia aculeata Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000001816 cooling Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000003912 environmental pollution Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000005461 lubrication Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 238000003892 spreading Methods 0.000 description 1
- 230000007480 spreading Effects 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000003756 stirring Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/10—Making by using boring or cutting machines
- E21D9/1066—Making by using boring or cutting machines with fluid jets
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/04—Directional drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/28—Enlarging drilled holes, e.g. by counterboring
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
- F16L1/036—Laying or reclaiming pipes on land, e.g. above the ground in the ground the pipes being composed of sections of short length
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Fluid Mechanics (AREA)
- Mechanical Engineering (AREA)
- Earth Drilling (AREA)
Abstract
The invention discloses a construction method for pulling and passing through a buried pipeline, and belongs to the field of pipeline construction. The construction method for pulling and crossing the buried pipeline mainly comprises the following steps: s1, determining an earth entry point and an earth exit point according to a design drawing and actual investigation; s2, designing according to the drilling track of the design drawing, and preparing a pipeline with the required length; s3, drilling a guide hole by adopting drill bit jet flow for assisting drilling, and the method is well suitable for different design depths of laid pipelines and different construction site conditions; the pipe dragging track is accurate, the precision is high, and the design requirement is met; in the whole construction process, the position and the burial depth of the pipeline can be determined on the ground at any time, the requirement of the working safety of the pipeline is met, the drilling design track is smooth, the curve section is smooth, the method is suitable for underground pipeline traction crossing construction of underground pipe networks in complicated distribution sections, the success of pipeline construction is ensured, and the method is also suitable for complicated geological structures such as riprap, backfill and the like.
Description
Technical Field
The invention relates to the technical field of pipeline construction, in particular to a construction method for pulling and passing through a buried pipeline.
Background
In recent years, due to social development, old city reconstruction, new rural construction and the like, the requirements on heat supply quantity and heat supply quality are continuously improved, so that municipal heat supply pipe networks are continuously expanded and reconstructed; the buried heat supply pipe network can certainly cross roads or rivers, if traditional road excavation is adopted, the construction of the overhead mode above the rivers not only influences the traffic, still needs a large amount of manpower and material resources to find out the concrete position of the existing pipeline on both sides of the road, so both time and energy are wasted, and the control of the time limit for a project is not facilitated.
In the prior art, application number 99115006.6 discloses a drilling traction casing crossing construction method in 2003-07-23, which belongs to the technical field of underground casing laying construction methods, and aims to solve the technical problem of providing a construction method adopting rotary drilling and casing traction, and the technical scheme for solving the technical problem is as follows: the method comprises four processes of digging an operation pit and a receiving pit, drilling a guide hole to the receiving pit by a drilling machine arranged in the operation pit, reaming a hole to be a traction hole by a reamer arranged on a drilling tool along the guide hole from the receiving pit to the operation pit and pulling back a traction steel wire rope, and pulling the traction steel wire rope by a tractor arranged in the receiving pit to draw a laid sleeve from the operation pit to the receiving pit along the traction hole, wherein the four processes are adopted; the improvement is still needed, for the complex geological structures such as riprap, backfill, underwater and the like, underground water precaution and soft soil layer reinforcement measures are needed, underground pipelines of underground pipe network distribution complex sections are inconvenient to construct, and the overall construction difficulty is high.
Disclosure of Invention
The invention aims to solve the problems in the prior art and provides a construction method for pulling and passing through a buried pipeline.
In order to achieve the purpose, the invention adopts the following technical scheme:
the construction method for pulling and crossing the buried pipeline mainly comprises the following steps:
s1, determining an earth entry point and an earth exit point according to a design drawing and actual investigation;
s2, designing according to the drilling track of the design drawing, and preparing a pipeline with the required length;
s3 drilling guide holes
Adopt drill bit efflux to assist and creep into, specifically do: adopting high-pressure slurry jet flow erosion crushing rotary cutting of a drill bit to form a guide hole, and controlling the drilling direction by using a 15-degree inclined-plane drill bit;
drilling at the soil-entering point, wherein the drill bit is driven by the drilling machine to rotate under the action of the thrust of the drilling machine and the pressure of slurry, and the soil layer is cut and the ruler is continuously advanced;
if the rotation and the feeding are carried out simultaneously in the drilling process, the guided drilling is linear drilling;
if the drill bit is fed and does not rotate, the deflecting drilling is implemented under the action of the 15-degree inclined plane reaction force of the drill bit, and the accurate position and state of the drill bit and the direction of the inclined plane drill bit are determined and determined according to a signal transmitter and a ground positioning tracer in a drill bit cavity;
measuring the drill bit once each drill rod is drilled, and directing an operator of the drilling machine to adjust drill bit parameters according to the measured parameters and adjust the drilling direction of the drill bit in time so as to control the drill bit to drill according to a designed track, ensure the finished pilot hole until the preset position of the drill bit is unearthed and finish the drilling work of the whole pilot hole;
s4, reaming
Combining a drill rod, a reamer, a transfer case and the drill rod into a pre-reaming drilling tool, jetting a soil layer by using high-pressure slurry to loosen the soil layer, extruding the soil layer to form a hole by using a conical drill bit of the reaming drilling tool under the action of rotation and tension, simultaneously jetting a large amount of slurry into a back reaming hole, conveying cut soil scraps to the ground to play a reaming role and forming a track hole;
the mud is mixed with a lubricant, soda ash, a diamond thickener and a biopolymer;
s5, drawing through pipeline
After reaming, a reamer, a universal rotary joint and a U-shaped ring are installed by a hoisting machine in a matching way, the reamer with the diameter being 1.5 times of that of the pipeline is firmly connected with a steel pipe with the diameter being 1 time of that of the pipeline by a transfer case, and then the pipeline in the step S2 is dragged into the track hole formed in the step S4 under the matching of the hoisting machine and the rotary traction of the drilling machine until the pipeline is pulled to a pre-laying position at the side of the drilling machine;
and S6, welding and butting the traction pipeline with the pipelines at two sides after the traction pipeline is in place, and finishing pipeline traction.
Preferably, when the hole expanding is performed in step S4, two pre-hole expanding operations are performed for the steel pipe with the laid outer diameter Φ 426 mm:
reaming for the first time: connecting a phi 300mm reamer to the rear end of a drilling machine, then rotationally pulling back the reamer by the drilling machine for reaming, unloading one drill rod on one side of an earth entering point after each drill rod is reamed, installing one drill on one side of an earth discharging point, and repeating the steps until the phi 300mm reamer is reamed; injecting slurry while reaming;
and (5) reaming for the second time: and (4) unloading the phi 300mm reamer, replacing the phi 600mm reamer for back expansion, and simultaneously injecting mud.
Preferably, in the drilling process of the drilling machine in the step S4 and the step S5, if the drilling is stopped, a proper amount of slurry is still injected, so as to ensure that positive pressure is always present in the hole, and the cuttings in the hole are conveyed out.
Preferably, the mud is mainly bentonite, and the lubricant agent mixed in the mud is natural clay fine powder.
Preferably, after the soil entry point and the soil exit point are determined in step S1, the elevation and the horizontal distance of the soil entry point, the soil exit point and the elevation of the construction site are retested, and the elevation is measured pile by arranging the red paint sprayed marker piles on the ground surface of the center line, the horizontal length position of the center line which is calibrated according to the length and the inclination of each drill rod, and the soil entry point and the soil exit point.
Preferably, after the elevation is measured pile by pile, discharging side line piles of a drilling work area, an approach road, a work pit of a pipeline soil-entry point and a drilling machine installation position, and spraying a gray line as an obvious range mark; and (3) discharging side line piles at one end of the unearthed point according to the central line of the pipeline, the occupied land width and length, the length and width of a working pit of the unearthed point of the pipeline and the length and width of the discharge ditch, then sowing white ash along the edge to form a side line, marking an unearthed point operation area, and completing measurement preparation work before construction.
Preferably, in step S2, the reinforcing ribs are welded to the pipe according to the size of the pipe orifice.
Preferably, before drilling in step S3, a working pit is mechanically excavated at the earth entry and exit points for placing mud.
Preferably, before the drilling in the step S3, the drilling machine performs trial injection of the drilling mud, and the drilling machine performs trial drilling on 2-3 drill rods.
Preferably, after the butt welding in step S6 is completed, nondestructive testing is performed, and corrosion-resistant and heat-insulating treatment is performed.
Compared with the prior art, the invention provides a construction method for pulling and crossing buried pipelines, which has the following beneficial effects:
1. the construction method for the traction crossing of the buried pipeline comprises the following steps of measuring and determining the accurate position and state of a drill bit and the direction of an inclined plane drill bit according to a signal transmitter and a ground positioning tracer in a drill bit cavity in the traction crossing process; measuring a drill bit once each drill rod is drilled, and directing an operator of the drilling machine to adjust drill bit parameters according to the measured parameters and adjust the drilling direction of the drill bit in time so as to control the drill bit to drill according to a designed track, ensure the finished guide hole and control the drilling track, thereby better adapting to different pipeline laying design depths and different construction site conditions; the pipe dragging track is accurate, the precision is high, and the design requirement is met; during the whole construction process, the position and the burial depth of the pipeline can be determined on the ground at any time; adopt drill bit efflux to assist and creep into, specifically do: adopting high-pressure slurry jet flow erosion crushing rotary cutting of a drill bit to form a guide hole, and controlling the drilling direction by using a 15-degree inclined-plane drill bit; drilling at the soil-entering point, wherein the drill bit is driven by the drilling machine to rotate under the action of the thrust of the drilling machine and the pressure of slurry, and the soil layer is cut and the ruler is continuously advanced; if the rotation and the feeding are carried out simultaneously in the drilling process, the guided drilling is linear drilling; if the drill bit is fed without rotation, a curve section and a straight section of a drilling track can be formed under the action of the reaction force of a 15-degree inclined plane of the drill bit, the curve section is used as a part of drilling, the requirement of the working safety of a pipeline is met, the drilling design track is smooth, the curve section is smooth, the drill bit is suitable for underground pipeline traction crossing construction of underground pipelines of underground pipe networks distributed in complex sections, the success of pipeline construction is ensured, and the drill bit is also suitable for complex geological structures such as riprap, backfill and the like.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
A construction method for pulling and crossing buried pipelines mainly comprises the following steps:
s1, determining an earth entry point and an earth exit point according to a design drawing and actual investigation;
s2, designing according to the drilling track of the design drawing, and preparing a pipeline with the required length;
s3 drilling guide holes
Adopt drill bit efflux to assist and creep into, specifically do: adopting high-pressure slurry jet flow erosion crushing rotary cutting of a drill bit to form a guide hole, and controlling the drilling direction by using a 15-degree inclined-plane drill bit;
drilling at the soil-entering point, wherein the drill bit is driven by the drilling machine to rotate under the action of the thrust of the drilling machine and the pressure of slurry, and the soil layer is cut and the ruler is continuously advanced;
if the rotation and the feeding are carried out simultaneously in the drilling process, the guided drilling is linear drilling;
if the drill bit is fed and does not rotate, the deflecting drilling is implemented under the action of the 15-degree inclined plane reaction force of the drill bit, and the accurate position and state of the drill bit and the direction of the inclined plane drill bit are determined and determined according to a signal transmitter and a ground positioning tracer in a drill bit cavity;
measuring the drill bit once each drill rod is drilled, and directing an operator of the drilling machine to adjust drill bit parameters according to the measured parameters and adjust the drilling direction of the drill bit in time so as to control the drill bit to drill according to a designed track, ensure the finished pilot hole until the preset position of the drill bit is unearthed and finish the drilling work of the whole pilot hole;
s4, reaming
Combining a drill rod, a reamer, a transfer case and the drill rod into a pre-reaming drilling tool, jetting a soil layer by using high-pressure slurry to loosen the soil layer, extruding the soil layer to form a hole by using a conical drill bit of the reaming drilling tool under the action of rotation and tension, simultaneously jetting a large amount of slurry into a back reaming hole, conveying cut soil scraps to the ground to play a reaming role and forming a track hole;
the slurry is mixed with a lubricant, soda ash, a diamond thickener and a biopolymer;
s5, drawing through pipeline
After reaming, a reamer, a universal rotary joint and a U-shaped ring are installed by a hoisting machine in a matching way, the reamer with the diameter being 1.5 times of that of the pipeline is firmly connected with a steel pipe with the diameter being 1 time of that of the pipeline by a transfer case, and then the pipeline in the step S2 is dragged into the track hole formed in the step S4 under the matching of the hoisting machine and the rotary traction of the drilling machine until the pipeline is pulled to a pre-laying position at the side of the drilling machine;
and S6, welding and butting the traction pipeline with the pipelines at two sides after the traction pipeline is in place, and finishing pipeline traction.
In the method, in the traction crossing process, the accurate position and state of a drill bit and the direction of an inclined plane drill bit are determined and determined according to a signal transmitter in a drill bit cavity and a ground positioning tracer; measuring a drill bit once each drill rod is drilled, and directing an operator of the drilling machine to adjust drill bit parameters according to the measured parameters and adjust the drilling direction of the drill bit in time so as to control the drill bit to drill according to a designed track, ensure the finished guide hole and control the drilling track, thereby better adapting to different pipeline laying design depths and different construction site conditions; the pipe dragging track is accurate, the precision is high, and the design requirement is met; during the whole construction process, the position and the burial depth of the pipeline can be determined on the ground at any time; adopt drill bit efflux to assist and creep into, specifically do: adopting high-pressure slurry jet flow erosion crushing rotary cutting of a drill bit to form a guide hole, and controlling the drilling direction by using a 15-degree inclined-plane drill bit; drilling at the soil-entering point, wherein the drill bit is driven by the drilling machine to rotate under the action of the thrust of the drilling machine and the pressure of slurry, and the soil layer is cut and the ruler is continuously advanced; if the rotation and the feeding are carried out simultaneously in the drilling process, the guided drilling is linear drilling; if the drill bit is fed without rotation, a curve section and a straight section of a drilling track can be formed under the action of the reaction force of a 15-degree inclined plane of the drill bit, the curve section is used as a part of drilling, the requirement of the working safety of a pipeline is met, the drilling design track is smooth, the curve section is smooth, the drill bit is suitable for underground pipeline traction crossing construction of underground pipelines of underground pipe networks distributed in complex sections, the success of pipeline construction is ensured, and the drill bit is also suitable for complex geological structures such as riprap, backfill and the like.
The construction method has the advantages that traffic is not obstructed, the environment is not polluted, no damage is caused to the road surface and the river channel in the traction crossing construction process, the original soil structure is basically not damaged, underground water precaution and soft soil layer reinforcement measures are not needed, and the stress damage to the pipeline in the soil settling process is avoided.
The construction method greatly reduces the construction difficulty of laying the pipeline across the road or river, has high pipe laying speed and short construction period, is a pipeline with the same length and pipe diameter, has construction time of 1/2 of the construction time of a common jacking pipe, and ensures the construction period and the engineering quality.
In step S4, the high-pressure slurry is sprayed to the soil layer to loosen the soil layer, the conical drill bit extrudes the soil layer to form a hole under the action of rotation and tension, the hole wall of the formed hole is complete, compact and smooth, meanwhile, a large amount of slurry is injected into the return reaming hole to ensure the integrity of the return reaming hole, the cutting soil chips are carried back to the ground without collapse, and the hole-expanding effect is achieved; in addition, the slurry sprayed by the high-pressure slurry is mixed with pollution-free natural clay fine powder as a lubricant, so that the wall of a pore channel can be stabilized and has a lubricating effect, the friction force during pipe pulling is reduced to the minimum, and the slurry forms a circle of dry clay-coated pipeline in the future; in addition, in order to improve the performance of the slurry, soda ash is added into the slurry, the slurry can be tackified and the static shearing force can be increased, the diamond thickener can increase the lubrication in the hole and has good pore-forming performance, the biopolymer can improve the soil chip carrying capacity of the slurry, the soil chips in the hole are taken out, the slurry forms a mud skin on the wall of the hole, the seepage inside and outside the hole is isolated, the slurry leakage is avoided, the rotation torque and the pull-back force during pipe dragging are reduced, the friction coefficient of the steel pipe and the wall of the hole is reduced, and the lubricating effect is; the sprayed slurry can be used for hydraulic cutting, cooling the drill bit, reducing torque and guiding thrust during guiding and playing a guiding auxiliary role; the effect of the back expansion torque and the pulling force is reduced during back expansion; in order to ensure the smooth operation of the crossing engineering, the success of the crossing of the pipeline can be ensured only by practically ensuring the performance of the slurry.
When the hole expanding is performed in step S4, two pre-hole expanding operations are performed for the steel pipe having the outer diameter Φ 426mm laid:
reaming for the first time: connecting a phi 300mm reamer to the rear end of a drilling machine, then rotationally pulling back the reamer by the drilling machine for reaming, unloading one drill rod on one side of an earth entering point after each drill rod is reamed, installing one drill on one side of an earth discharging point, and repeating the steps until the phi 300mm reamer is reamed; injecting slurry while reaming;
and (5) reaming for the second time: and (3) unloading the phi 300mm reamer, replacing the phi 600mm reamer for back expansion, and simultaneously injecting slurry to ensure the reaming effect and the reaming integrity.
In the drilling process of the drilling machine in the steps S4 and S5, if the drilling is stopped, a proper amount of slurry is still injected, so that positive pressure is always present in the hole, the cuttings in the hole are conveyed out, and the cuttings are prevented from being deposited in the hole.
The mud is mainly bentonite, the lubricant agent mixed in the mud adopts natural clay fine powder, high-quality bentonite is used, the natural clay fine powder is stirred by a stirring system to form mud, the mud is injected into a hole, the mud is a key factor of guiding drilling, the mud can remove drilling soil cuttings, can suspend and carry the drilling soil cuttings to the ground surface, reduces corrosion, stabilizes and protects the hole wall, balances formation pressure, and plays a role in fixing the hole and protecting the pipe.
After the soil entry point and the soil exit point are determined in the step S1, the elevation and the horizontal distance of the soil entry point and the soil exit point of the construction site are retested, a whole position instrument is used for traversing the horizontal length position on the ground surface of the central line after being corrected according to the length and the inclination of each section of drill rod, and red paint sprayed mark piles are respectively arranged on the soil entry point and the soil exit point, and the elevation is measured pile by pile; after the elevation is measured pile by pile, discharging side line piles of a drilling working area, an approach road, a working pit of a pipeline soil-entering point and a drilling machine installation position, and spraying a gray line as an obvious range mark; and (3) discharging side line piles at one end of the unearthed point according to the central line of the pipeline, the occupied area width and the length of the pipeline, the length and the width of a working pit of the unearthed point of the pipeline and the length and the width of the discharge ditch, then spreading white ash along the edge to form a side line, marking an unearthed point operation area, completing measurement preparation work before construction, accurately finding an unearthed point and an unearthed point, and facilitating accurate construction.
In step S2, a reinforcing rib is welded to the pipe according to the diameter of the pipe opening to perform a stabilizing and reinforcing function.
Before the drilling in the step S3 is carried out, a working pit is excavated at the soil outlet and the soil inlet by a machine for placing slurry, so that the environmental pollution is avoided.
And before the step S3 of drilling, performing trial injection on the slurry of the drilling machine, and drilling 2-3 sections of drill rods by the drilling machine in a trial manner to ensure the normal work of the drilling machine.
And after the butt welding is finished in the step S6, performing nondestructive testing and anticorrosion and heat preservation treatment to ensure the quality of the pipeline.
The construction method is implemented by combining the centralized heating and capacity expansion of the Lijin county and city district as follows:
taking the second standard section of the construction of the centralized heating capacity expansion reconstruction project in the Rijin county district as an example, in the project, the DN800 pipeline needs to cross three main roads in the county city in total, the construction is carried out by adopting the traditional excavation mode, the cost is about 63 ten thousand yuan from the road surface excavation to the road surface recovery, the directional drilling traction crossing construction is adopted, the equipment lease cost is only 60 ten thousand yuan, the cost is saved by 3 ten thousand yuan, the construction time is shortened by about 9 days compared with the excavation, and the purposes of saving time, labor and money are achieved.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.
Claims (10)
1. The construction method for pulling and crossing the buried pipeline is characterized by mainly comprising the following steps:
s1, determining an earth entry point and an earth exit point according to a design drawing and actual investigation;
s2, designing according to the drilling track of the design drawing, and preparing a pipeline with the required length;
s3 drilling guide holes
Adopt drill bit efflux to assist and creep into, specifically do: adopting high-pressure slurry jet flow erosion crushing rotary cutting of a drill bit to form a guide hole, and controlling the drilling direction by using a 15-degree inclined-plane drill bit;
drilling at the soil-entering point, wherein the drill bit is driven by the drilling machine to rotate under the action of the thrust of the drilling machine and the pressure of slurry, and the soil layer is cut and the ruler is continuously advanced;
if the rotation and the feeding are carried out simultaneously in the drilling process, the guided drilling is linear drilling;
if the drill bit is fed and does not rotate, the deflecting drilling is implemented under the action of the 15-degree inclined plane reaction force of the drill bit, and the accurate position and state of the drill bit and the direction of the inclined plane drill bit are determined and determined according to a signal transmitter and a ground positioning tracer in a drill bit cavity;
measuring the drill bit once each drill rod is drilled, and directing an operator of the drilling machine to adjust drill bit parameters according to the measured parameters and adjust the drilling direction of the drill bit in time so as to control the drill bit to drill according to a designed track, ensure the finished pilot hole until the preset position of the drill bit is unearthed and finish the drilling work of the whole pilot hole;
s4, reaming
Combining a drill rod, a reamer, a transfer case and the drill rod into a pre-reaming drilling tool, jetting a soil layer by using high-pressure slurry to loosen the soil layer, extruding the soil layer to form a hole by using a conical drill bit of the reaming drilling tool under the action of rotation and tension, simultaneously jetting a large amount of slurry into a back reaming hole, conveying cut soil scraps to the ground to play a reaming role and forming a track hole;
the mud is mixed with a lubricant, soda ash, a diamond thickener and a biopolymer;
s5, drawing through pipeline
After reaming, a reamer, a universal rotary joint and a U-shaped ring are installed by a hoisting machine in a matching way, the reamer with the diameter being 1.5 times of that of the pipeline is firmly connected with a steel pipe with the diameter being 1 time of that of the pipeline by a transfer case, and then the pipeline in the step S2 is dragged into the track hole formed in the step S4 under the matching of the hoisting machine and the rotary traction of the drilling machine until the pipeline is pulled to a pre-laying position at the side of the drilling machine;
and S6, welding and butting the traction pipeline with the pipelines at two sides after the traction pipeline is in place, and finishing pipeline traction.
2. The underground pipeline traction crossing construction method according to claim 1, wherein when reaming is performed in step S4, two pre-reaming operations are performed for laying a steel pipe with an outer diameter Φ 426 mm:
reaming for the first time: connecting a phi 300mm reamer to the rear end of a drilling machine, then rotationally pulling back the reamer by the drilling machine for reaming, unloading one drill rod on one side of an earth entering point after each drill rod is reamed, installing one drill on one side of an earth discharging point, and repeating the steps until the phi 300mm reamer is reamed; injecting slurry while reaming;
and (5) reaming for the second time: and (4) unloading the phi 300mm reamer, replacing the phi 600mm reamer for back expansion, and simultaneously injecting mud.
3. The underground pipeline traction crossing construction method as claimed in claim 2, wherein in the drilling process of the drilling machine in the steps S4 and S5, if the drilling is stopped, a proper amount of slurry is still injected, so that positive pressure is always present in the hole, and cuttings in the hole are conveyed out.
4. The construction method for pulling and passing through the buried pipeline according to claim 1, wherein the slurry is mainly bentonite, and the lubricant agent mixed in the slurry is natural clay fine powder.
5. The underground pipeline traction crossing construction method as claimed in any one of claims 1 to 4, wherein after the soil entry point and the soil exit point are determined in step S1, the elevation and the horizontal distance of the soil entry point and the soil exit point at the construction site are retested, and a level gauge is used to cross the horizontal length position on the ground surface of the central line after the correction according to the length and the inclination of each drill rod, and the soil entry point and the soil exit point are respectively provided with a marker pile sprayed with red paint, and the elevation is measured pile by pile.
6. The construction method for pulling and passing through the buried pipeline according to claim 5, wherein after the elevation is measured pile by pile, the side line piles of the working area, the approach road, the working pit of the pipeline soil-entering point and the installation position of the drilling machine are discharged, and the gray line is sprayed as an obvious range mark; and (3) discharging side line piles at one end of the unearthed point according to the central line of the pipeline, the occupied land width and length, the length and width of a working pit of the unearthed point of the pipeline and the length and width of the discharge ditch, then sowing white ash along the edge to form a side line, marking an unearthed point operation area, and completing measurement preparation work before construction.
7. A method of buried pipeline pull through construction according to any one of claims 1 to 4 wherein in step S2 reinforcing bars are welded to the pipeline according to the size of the pipe orifice.
8. A method of buried pipeline pull through construction according to any one of claims 1 to 4 wherein a working pit is mechanically excavated at the point of entry and exit for the placement of slurry before drilling at step S3.
9. A buried pipeline traction crossing construction method according to any one of claims 1 to 4, wherein before drilling in step S3, trial injection of drilling rig mud is carried out, and the drilling rig drills 2-3 drill rods in trial.
10. The buried pipeline traction crossing construction method as claimed in any one of claims 1 to 4, wherein after the butt welding of the step S6 is completed, nondestructive testing is performed and anticorrosion and heat preservation treatment is performed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910839041.2A CN110778323A (en) | 2019-09-05 | 2019-09-05 | Construction method for pulling and passing buried pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910839041.2A CN110778323A (en) | 2019-09-05 | 2019-09-05 | Construction method for pulling and passing buried pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110778323A true CN110778323A (en) | 2020-02-11 |
Family
ID=69383383
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910839041.2A Pending CN110778323A (en) | 2019-09-05 | 2019-09-05 | Construction method for pulling and passing buried pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110778323A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112324333A (en) * | 2020-10-22 | 2021-02-05 | 河北省水利工程局 | Construction method for horizontal directional crossing of complex pebble-gravel stratum by underground pipeline |
CN112944033A (en) * | 2021-02-02 | 2021-06-11 | 中建七局第一建筑有限公司 | Construction method of horizontal directional drilling pipeline |
CN113007611A (en) * | 2021-02-18 | 2021-06-22 | 呼和浩特中燃城市燃气发展有限公司 | Monitoring system for gas pipeline crossing river bottom |
CN113090187A (en) * | 2021-03-30 | 2021-07-09 | 苏州凌云建设有限公司 | Pipeline traction construction method |
CN113958265A (en) * | 2021-09-23 | 2022-01-21 | 中国化学工程第六建设有限公司 | Oil pipeline long-distance directional drilling construction method |
CN114109422A (en) * | 2020-08-26 | 2022-03-01 | 中国石油天然气集团有限公司 | Guide type push pipe installation construction method |
CN115653498A (en) * | 2022-10-17 | 2023-01-31 | 中交第三公路工程局有限公司 | Construction method of horizontal directional drilling drag pipe |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020114671A1 (en) * | 2001-01-22 | 2002-08-22 | Wentworth Steven W. | Pipe replacement method and rotary impact mechanism for pipe bursting |
JP2004293142A (en) * | 2003-03-26 | 2004-10-21 | Komatsu Ltd | Pipe burying method |
CN101457853A (en) * | 2008-11-20 | 2009-06-17 | 江苏广宇建设集团有限公司 | Non-digging tube-pulling construction method |
CN101575860A (en) * | 2009-06-01 | 2009-11-11 | 上海市第二市政工程有限公司 | Construction method for embedding inclinometer tube |
CN102953683A (en) * | 2012-11-27 | 2013-03-06 | 福建省泷澄建设集团有限公司 | Pipe pulling construction method through horizontal directional drilling |
-
2019
- 2019-09-05 CN CN201910839041.2A patent/CN110778323A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020114671A1 (en) * | 2001-01-22 | 2002-08-22 | Wentworth Steven W. | Pipe replacement method and rotary impact mechanism for pipe bursting |
JP2004293142A (en) * | 2003-03-26 | 2004-10-21 | Komatsu Ltd | Pipe burying method |
CN101457853A (en) * | 2008-11-20 | 2009-06-17 | 江苏广宇建设集团有限公司 | Non-digging tube-pulling construction method |
CN101575860A (en) * | 2009-06-01 | 2009-11-11 | 上海市第二市政工程有限公司 | Construction method for embedding inclinometer tube |
CN102953683A (en) * | 2012-11-27 | 2013-03-06 | 福建省泷澄建设集团有限公司 | Pipe pulling construction method through horizontal directional drilling |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114109422A (en) * | 2020-08-26 | 2022-03-01 | 中国石油天然气集团有限公司 | Guide type push pipe installation construction method |
CN114109422B (en) * | 2020-08-26 | 2024-03-26 | 中国石油天然气集团有限公司 | Guide type push pipe installation construction method |
CN112324333A (en) * | 2020-10-22 | 2021-02-05 | 河北省水利工程局 | Construction method for horizontal directional crossing of complex pebble-gravel stratum by underground pipeline |
CN112324333B (en) * | 2020-10-22 | 2022-08-02 | 河北省水利工程局 | Construction method for horizontal directional crossing of complex pebble-gravel stratum by underground pipeline |
CN112944033A (en) * | 2021-02-02 | 2021-06-11 | 中建七局第一建筑有限公司 | Construction method of horizontal directional drilling pipeline |
CN113007611A (en) * | 2021-02-18 | 2021-06-22 | 呼和浩特中燃城市燃气发展有限公司 | Monitoring system for gas pipeline crossing river bottom |
CN113090187A (en) * | 2021-03-30 | 2021-07-09 | 苏州凌云建设有限公司 | Pipeline traction construction method |
CN113958265A (en) * | 2021-09-23 | 2022-01-21 | 中国化学工程第六建设有限公司 | Oil pipeline long-distance directional drilling construction method |
CN115653498A (en) * | 2022-10-17 | 2023-01-31 | 中交第三公路工程局有限公司 | Construction method of horizontal directional drilling drag pipe |
CN115653498B (en) * | 2022-10-17 | 2023-11-07 | 中交第三公路工程局有限公司 | Construction method of horizontal directional drilling drag pipe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110778323A (en) | Construction method for pulling and passing buried pipeline | |
CN101737060B (en) | Beneath-soil through-tunnel superlarge diameter pipe curtain construction method | |
CN107060796B (en) | It is a kind of to use Slurry Balanced Pipe Jacking Construction technique | |
CN100410485C (en) | Construction method for push pipe by cooperation of horizontal auger driller and horizontal directional driller | |
CN101761083B (en) | Underground continuous wall obstacle clearing construction method for traversing ultra-thick obstacle | |
CN101457853B (en) | Non-digging tube-pulling construction method | |
CN108678130A (en) | A kind of non-digging drag pipe construction method | |
CN205172598U (en) | Pipe curtain spouts a supporting construction soon | |
CN111287653A (en) | Large-caliber forward reaming construction method for horizontal directional drilling of hard rock | |
CN110005442A (en) | Under wear existing building Urban Underground mining sectbn surrounding rock consolidation technique | |
CN102953683A (en) | Pipe pulling construction method through horizontal directional drilling | |
CN101962949A (en) | Long spiral double-pipe high-pressure stir-jet grouting pile construction method and device | |
CN106088099B (en) | A kind of subway foundation pit anchor cable processing method | |
CN116006080A (en) | Quick-replacement back-reaming device and reaming method | |
CN108661650A (en) | A kind of rich water magmatic body area depth pozo shaft construction method | |
CN108590706A (en) | One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain | |
CN110080789A (en) | A kind of shield sky, which pushes away, spells section of jurisdiction construction | |
CN112252973A (en) | Non-excavation directional drilling construction method for pipeline buried channel | |
CN112664221A (en) | Pipe jacking construction method for complex geological formation | |
CN106758759B (en) | A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed | |
CN110274088A (en) | A kind of road construction non-excavation type inspection shaft pipeline construction method | |
KR101867598B1 (en) | ahead reaming method of drilling method | |
KR101867599B1 (en) | reaming device for drilling and reaming process | |
CN205296194U (en) | Rich irrigated land layer undercut tunnel interlock pipe curtain | |
CN108590668A (en) | A kind of Station overlength pipe shed trombone slide method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20200211 |