CN110777854A - High-rise building basement roof structure, waterproof coiled material and construction method for protecting layer to survive in one step - Google Patents

High-rise building basement roof structure, waterproof coiled material and construction method for protecting layer to survive in one step Download PDF

Info

Publication number
CN110777854A
CN110777854A CN201910973532.6A CN201910973532A CN110777854A CN 110777854 A CN110777854 A CN 110777854A CN 201910973532 A CN201910973532 A CN 201910973532A CN 110777854 A CN110777854 A CN 110777854A
Authority
CN
China
Prior art keywords
concrete
construction
waterproof
coiled material
protective layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910973532.6A
Other languages
Chinese (zh)
Inventor
秦加龙
谭国良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201910973532.6A priority Critical patent/CN110777854A/en
Publication of CN110777854A publication Critical patent/CN110777854A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a construction method for one-step survival of a basement roof structure, a waterproof coiled material and a protective layer of a high-rise building, which comprises the following steps of vibrating and compacting concrete in the concrete pouring process of the basement roof structure, and leveling, compacting, finishing and maintaining primary pulp; when the structural concrete has the strength of 3-5 days, cleaning and drying, brushing the binder, and making the coiled material waterproof; binding an anti-crack reinforcing mesh on the waterproof layer of the coil material which is qualified after acceptance, and pouring a fine aggregate concrete protective layer after acceptance; the method has the advantages that large temporary facilities are arranged, earthwork in an open roof area is backfilled, superstructure construction is carried out, and overall outdoor construction is alternated.

Description

High-rise building basement roof structure, waterproof coiled material and construction method for protecting layer to survive in one step
Technical Field
The invention belongs to a construction technical method which relates to a basement top plate structure of a high-rise building, waterproof coiled material and a fine stone concrete protective layer which can survive in one step. More particularly, the construction method relates to a construction method for pouring the fine stone concrete protective layer in time after the concrete reaches the strength of 3-5 days after leveling, compacting and finishing the primary pulp and the concrete is made into a waterproof coiled material and qualified by inspection and acceptance in the process of pouring the concrete of the top plate structure of the basement of the high-rise building.
Background
At present, in the long-term practice of basement construction of high-rise buildings, the habitual method is as follows: and often, after the structure of the basement roof is constructed, earth around the basement foundation pit is backfilled. Directly setting up a steel bar processing and manufacturing field on a basement roof plate structure, planning a template square timber stacking warehouse, laying sand, stone and cement storage yards, installing a mortar stirrer and the like. Meanwhile, the construction of the superstructure of the high-rise building is carried out immediately after the construction, and when the superstructure is constructed to about ten floors, the construction of the brick wall is inserted, and the construction of the secondary structure is carried out. After the high-rise structure is capped, finishing the secondary structure immediately after capping, checking and accepting the structure, and after the structure is qualified, completely spreading the interior and exterior decoration construction of the building. When finishing almost waiting for the decoration, clear away and move all and face the facility again, clear up basement roof structure, carry out roof structure cement mortar and level, compaction, receive the light back, do the waterproof and fine aggregate concrete protective layer of coiled material, backfill earthwork, do outdoor totality. In summary, the following steps: a large number of repeated processes and repeated labor are generated, and huge workload and engineering cost are increased. The construction period is delayed, and great economic loss is caused.
Therefore, only one construction technical method which simplifies the construction process flow and strives for one-step survival is invented, so that the repeated investment and the repeated labor are avoided, the working procedures are reduced, the workload is reduced, the construction period is shortened, the economic benefit is improved, and the engineering construction quality is ensured and improved.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the method aims at the defects and shortcomings of the conventional construction technical method which is directly erected on the basement roof structure and is used for a long time, so that the construction technical method which is adopted for forming the concrete of the basement roof structure, paving and pasting the coiled material in a waterproof way and pouring the fine stone concrete protective layer comprehensively considers the survival in one step, repeated labor investment is avoided, the working procedures are reduced, the workload is reduced, the cost is reduced, the construction period is shortened, the economic benefit is improved, and the engineering construction quality is ensured and improved.
In order to solve the technical problems, the inventor obtains the technical scheme of the invention through practice and summary, and the invention discloses a construction method for forming a roof structure, a waterproof coiled material and a protective layer of a high-rise building basement in one step, which comprises the following steps:
the method comprises the following steps: in the process of pouring concrete of the basement roof structure, after the concrete is vibrated to be compact, primary pulp is leveled, compacted, smoothed and maintained;
step two: when the structural concrete has the strength of 3-5 days, cleaning and drying, brushing the binder, and making the coiled material waterproof;
step three: binding an anti-crack reinforcing mesh on the waterproof layer of the coil material which is qualified after acceptance, and pouring a fine aggregate concrete protective layer after acceptance;
step four: laying and facing the facility greatly, backfilling the earthwork of the open roof area, carrying out superstructure construction, and alternating outdoor overall construction.
Preferably, in the second step, concrete of the top plate structure is poured into one block gradually.
Preferably, in the third step, the waterproof layer of the coiled material is finished one by one, and the fine stone is concreted one by one until the top plate is finished.
Compared with the prior art, the invention can obtain the following technical effects:
1. the invention avoids repeated investment and repeated labor, reduces working procedures, workload and cost, shortens construction period, improves economic benefit, and ensures and improves engineering quality.
2. The invention solves the technical problems in the construction of basement top plate structure, coiled material water-proof and fine stone concrete protective layer of high-rise building in one air survival: the method is a challenge for the traditional method, a construction process technical method is innovated, and the sinking and long construction chain of the conventional construction process technical method is cut off. After the previous process is completed, the next process is implemented following the previous process, the concrete pouring of the top plate structure living in one step is compacted by vibration, primary pulp is leveled, compacted and collected, all construction contents of waterproof paving of the coiled material and pouring of the fine stone concrete protective layer are achieved, continuity between the processes is achieved, repeated investment is avoided, secondary leveling, compaction and collection of the top plate structure are avoided, engineering materials and labor cost are saved, the construction period is shortened, soil is filled in 6-8 months in advance, and the necessary conditions for outdoor overall construction in advance are achieved. Meanwhile, the cost is reduced, and the economic benefit and the construction quality level are improved.
3. The invention utilizes the primary concrete pulp of the basement roof structure to level, compact and collect the light, avoids the procedures of secondary structure surface cleaning and cement mortar leveling, compacting and collecting the light, and simultaneously, a coiled material waterproof layer and a fine stone concrete protective layer are manufactured immediately after the procedures. The construction period chain is compressed, the repeated investment is avoided, the workload is reduced, the cost is reduced, the engineering quality level is improved, and good economic benefit and social benefit are obtained.
Drawings
In order to more clearly illustrate the embodiments or technical solutions in the prior art of the present invention, the drawings used in the description of the embodiments or prior art will be briefly described below, and it is obvious for those skilled in the art that other drawings can be obtained based on these drawings without creative efforts.
FIG. 1 is a schematic of the present invention.
In the figure: 1. 2, leveling, compacting and light collecting of primary pulp of a top plate surface, 3, cleaning and brushing of a binder, 4, a coiled material waterproof layer, 5, 8, 200 x 200 steel mesh sheets, 6, a fine stone concrete protective layer, 7, backfilling earthwork and 8, a large temporary facility.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to the following embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
The application of the principles of the present invention will be further described with reference to the accompanying drawings and specific embodiments.
Example 1
As shown in fig. 1: the method comprises the following steps: from the drawings, it is known that: in the concrete pouring process of the basement top plate structure 1, primary pulp is leveled, compacted and smoothed 2, and maintenance measures are taken.
Step two: after waiting for basement roof 1 to have 3-5 days intensity, clearance brush binder 3 does coiled material waterproof layer 4, and step by step, roof concrete 1 pours one, just does coiled material waterproof layer 4. And (4) the waterproof layer 4 of the coiled material is qualified after acceptance, namely, the next procedure is carried out.
Step three: binding anti-crack steel bar mesh 5 of phi 8 @ 200 × 200 on the qualified roll waterproof layer 4, pouring fine-stone concrete 6 after 5 is qualified, and gradually pouring the fine-stone concrete 6 until the fine-stone concrete 6 of the top plate protective layer of the basement is completely poured.
Step four: laying a large temporary facility 8, backfilling earthwork 7 in an open roof area, performing upper building structure construction, and alternating outdoor overall construction to achieve the purpose of shortening the construction period.
In the process of pouring concrete in the top plate structure of basement, after leveling, compacting and finishing the raw stock, the raw stock is used as a waterproof layer of coiled material when the intensity reaches 3-5 days, a phi 8 @ 200 x 200 steel bar net sheet is bound, a fine stone concrete protective layer is poured, and the raw stock survives at one time, thereby avoiding repeated investment and repeated labor, compressing the working procedures, reducing the workload, shortening the construction period, improving the economic benefit, and ensuring and improving the engineering quality level.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (3)

1. The construction method for the top plate structure of the basement of the high-rise building, the waterproof coiled material and the protective layer to survive in one step is characterized in that: the method comprises the following steps:
the method comprises the following steps: in the process of pouring concrete of the basement roof structure, after the concrete is vibrated to be compact, primary pulp is leveled, compacted, smoothed and maintained;
step two: when the structural concrete has the strength of 3-5 days, cleaning and drying, brushing the binder, and making the coiled material waterproof;
step three: binding an anti-crack reinforcing mesh on the waterproof layer of the coil material which is qualified after acceptance, and pouring a fine aggregate concrete protective layer after acceptance;
step four: laying and facing the facility greatly, backfilling the earthwork of the open roof area, carrying out superstructure construction, and alternating outdoor overall construction.
2. The construction method for the roof structure, the waterproof roll and the protective layer of the high-rise building basement to survive in one atmosphere according to claim 1, wherein the construction method comprises the following steps: and step two, sequentially pouring concrete of the top plate structure into the concrete blocks.
3. The construction method for the roof structure, the waterproof roll and the protective layer of the high-rise building basement to survive in one atmosphere according to claim 1, wherein the construction method comprises the following steps: and in the third step, the waterproof layer of the coiled material is finished one by one, and the fine stone is concreted one by one until the top plate is finished.
CN201910973532.6A 2019-10-14 2019-10-14 High-rise building basement roof structure, waterproof coiled material and construction method for protecting layer to survive in one step Pending CN110777854A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910973532.6A CN110777854A (en) 2019-10-14 2019-10-14 High-rise building basement roof structure, waterproof coiled material and construction method for protecting layer to survive in one step

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910973532.6A CN110777854A (en) 2019-10-14 2019-10-14 High-rise building basement roof structure, waterproof coiled material and construction method for protecting layer to survive in one step

Publications (1)

Publication Number Publication Date
CN110777854A true CN110777854A (en) 2020-02-11

Family

ID=69385390

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910973532.6A Pending CN110777854A (en) 2019-10-14 2019-10-14 High-rise building basement roof structure, waterproof coiled material and construction method for protecting layer to survive in one step

Country Status (1)

Country Link
CN (1) CN110777854A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111779013A (en) * 2020-08-18 2020-10-16 中国十七冶集团有限公司 Method for backfilling below terrace of upper layer of basement roof of high-rise building in advance
CN116950403A (en) * 2023-07-05 2023-10-27 广东省六建工程总承包有限公司 Construction method for reducing cracks of basement roof structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203008243U (en) * 2012-03-23 2013-06-19 上海市电力公司 Roof plantation roofing system for underground substation
CN108643230A (en) * 2018-06-12 2018-10-12 五冶集团上海有限公司 A kind of outer waterproof construction of underground pipe gallery and construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203008243U (en) * 2012-03-23 2013-06-19 上海市电力公司 Roof plantation roofing system for underground substation
CN108643230A (en) * 2018-06-12 2018-10-12 五冶集团上海有限公司 A kind of outer waterproof construction of underground pipe gallery and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
付海强: "高层住宅小区建筑施工综合管理研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111779013A (en) * 2020-08-18 2020-10-16 中国十七冶集团有限公司 Method for backfilling below terrace of upper layer of basement roof of high-rise building in advance
CN116950403A (en) * 2023-07-05 2023-10-27 广东省六建工程总承包有限公司 Construction method for reducing cracks of basement roof structure

Similar Documents

Publication Publication Date Title
CN107653894A (en) A kind of construction technology that foundation platform is made by precast concrete
CN211646494U (en) Waterproof construction of underground garage foundation slab
CN104711974B (en) A kind of steel tube regeneration concrete complex carrier stake and preparation method thereof
CN110306595B (en) Co-building structure of electric power pipe gallery and flood control wall and construction method thereof
CN110777854A (en) High-rise building basement roof structure, waterproof coiled material and construction method for protecting layer to survive in one step
CN106812219A (en) Filling wall top stuff up a crack construction method
CN110792200A (en) Masonry construction method without post-picking and pipe wrapping structure thereof
CN103215950B (en) Pile foundation extension construction method in backfilling area
CN105780992A (en) Construction method of orthogonal and ortho-laid steel concrete vierendeel sandwich plate floor
CN104328790A (en) Cast-in-situ sprayed concrete hidden bearing platform and hidden ground beam molding bed
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN210117716U (en) Trapezoidal foundation ditch lateral wall concrete typical forms of elevartor shaft
CN107882050A (en) The manufacture method of the side plate of cap mold and cap mold
CN208023601U (en) A kind of prefabricated pile foundation support table side form of mutual buckle type
CN101929245A (en) Thin webbed girder vertical construction method
CN210288465U (en) Assembled retaining wall post-cast strip plugging member
CN204418229U (en) Poured band of outer wall of basement concrete draw-in groove
CN218322884U (en) Waterproof structure of basement bottom plate of pre-paved anti-sticking waterproof roll
CN109944265A (en) The method for carrying out foundation construction using concrete light scutum
CN213115347U (en) Dampproof ground
CN111576658B (en) Construction method of post-cast strip protection wall of assembled basement outer wall
CN209923944U (en) Novel backfill soil geotechnique reinforcement
CN109667278B (en) Anti-cracking and anti-seepage construction method for arranging tower crane foundation under independent foundation of underground garage
CN112681373A (en) Backfill reverse construction method for basement cantilever slab
CN111042047A (en) Construction process for lower cross beam of platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200211