CN110714772A - Construction process of saturated loess 12m large-span small-clear-distance tunnel - Google Patents

Construction process of saturated loess 12m large-span small-clear-distance tunnel Download PDF

Info

Publication number
CN110714772A
CN110714772A CN201911203260.8A CN201911203260A CN110714772A CN 110714772 A CN110714772 A CN 110714772A CN 201911203260 A CN201911203260 A CN 201911203260A CN 110714772 A CN110714772 A CN 110714772A
Authority
CN
China
Prior art keywords
tunnel
hole
construction
geotextile
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911203260.8A
Other languages
Chinese (zh)
Inventor
马天昌
徐少平
饶胜斌
苏春生
何十美
朴占华
郭建强
郝玉峰
卫守峰
赵辉
石先火
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA REILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP NO6 ENGINEERING Co Ltd
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Sixth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
5th Engineering Co Ltd of MBEC
Original Assignee
CHINA REILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP NO6 ENGINEERING Co Ltd
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA REILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP NO6 ENGINEERING Co Ltd, China Railway Construction Bridge Engineering Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical CHINA REILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP NO6 ENGINEERING Co Ltd
Priority to CN201911203260.8A priority Critical patent/CN110714772A/en
Publication of CN110714772A publication Critical patent/CN110714772A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction process of a saturated loess 12m large-span small-clear-distance tunnel, which comprises the following steps of: s1) precipitation before construction; s2) forepoling construction; s3) tunnel excavation and primary lining support are carried out; s4) waterproof layer and secondary lining support; wherein, precipitation before construction in S1) is realized by a precipitation well and a water collection pool; the water collecting tank is arranged far away from the tunnel excavation site and is communicated with the dewatering well; and the excavation site of the water collecting tank and the tunnel is not less than 2 km. The construction process of the large-span small-clear-distance tunnel with saturated loess of 12m disclosed by the invention adopts the water collecting tank and the precipitation well which are used simultaneously, so that the precipitation in the construction area before excavation is well controlled, and the influence of underground water seepage or water immersion on the tunnel construction is avoided.

Description

Construction process of saturated loess 12m large-span small-clear-distance tunnel
Technical Field
The invention relates to the technical field of construction processes of large-collapse small-clear-distance tunnels, in particular to a construction process of a large-span small-clear-distance tunnel saturated with loess 12 m.
Background
Due to the influences of factors such as the showing difficulty and the large occupied area caused by the limitation of terrain and geological conditions and the tunnel construction, the structural form of the small-clear-distance tunnel is increasingly selected in the urban tunnel engineering construction. Compared with a multi-arch tunnel, the small clear distance tunnel has the advantages of simple construction process and low construction cost; compared with the common separated tunnel, the method can increase the degree of freedom of route wiring, reduce the scale of the separated roadbed, reduce the excavation work amount of the tunnel portal and is beneficial to environmental protection. Therefore, the small clear distance tunnel has great practical significance for improving the traffic efficiency, protecting and utilizing the natural environment, accelerating the development of economic construction and the like.
Loess is a special soil which is rich in pores and developed in joints, and has its collapsible property due to changes in pore structure caused by water immersion, and research on the collapsible property of loess has been conducted for years internationally. Tunneling in loess poses many risks and challenges, including large deformation of the formation due to the collapsible property and erosion of the formation due to seepage of groundwater, which severely impact the safety of tunnel construction and surrounding environment.
Disclosure of Invention
Aiming at the prior art, the invention provides a construction process of a large-span small-clear-distance tunnel saturated with loess 12 m.
The invention is realized by the following technical scheme: the construction process of the saturated loess 12m large-span small-clear-distance tunnel comprises the following steps:
s1) precipitation before construction;
s2) forepoling construction;
s3) tunnel excavation and primary lining support are carried out;
s4) waterproof layer and secondary lining support;
wherein, precipitation before construction in S1) is realized by a precipitation well and a water collection pool; the water collecting tank is arranged far away from the tunnel excavation site and is communicated with the dewatering well; and the excavation site of the water collecting tank and the tunnel is not less than 2 km.
Further, the construction step of S1) is:
s11) positioning and clearly identifying the precipitation well and the water collecting pool according to the design scheme and the actual site;
s12) adopting impact drilling to form a hole, wherein the aperture meets the requirement of placing a submersible pump in a water pumping pipe; then adopting slurry to protect the wall;
s13) cleaning the hole immediately after the hole is formed, and mounting a well pipe, wherein a filter pipe part of the well pipe is placed at the position of the permeable layer as far as possible;
s14) before the water pump is installed, washing the well by an air compression method;
s15), installing a water pump, checking, and then performing trial water pumping to check whether water pumping equipment and a water pumping and draining system can meet precipitation requirements;
s16) excavating a water collecting pool according to the positioning, wherein the capacity of the water collecting pool is larger than the product of the capacity of a precipitation well communicated with the water collecting pool and the local average monthly precipitation; then adopting slurry to protect the wall;
s17), immediately cleaning the water pipe after the excavation is finished, and then communicating the water pipe with the water outlet of the water pump.
Further, in step S13), after the well pipe is put in, the space between the well pipe and the hole wall is backfilled with a filter material to prevent collapse, and the well point is backfilled to be dense within a range of 50-100cm below the ground surface with clay.
Further, the S2) specifically includes the following steps:
s21) preparing a small catheter; pouring concrete into the small guide pipe, and vibrating, compacting and finally setting to obtain the small guide pipe for pouring concrete;
s22) supporting construction of a supporting frame; installing and fixing a support frame in the tunnel; measuring and positioning the tunnel at the position of the support frame, determining a small guide pipe construction hole position and drilling, wherein the drilling direction and the tunnel direction form an acute angle;
s23) installing a small concrete injection guide pipe; and (4) driving the small concrete-injected guide pipes into each drilling hole position, and fixedly connecting each small concrete-injected guide pipe with the support frame respectively.
Furthermore, the small guide pipe passes through a seamless steel pipe with one end being conical, and the aggregate grain size of the poured concrete does not exceed 1/5 of the inner diameter of the small guide pipe.
Further, the step S3) includes dividing the tunnel into an upper left hole, a middle left hole, a lower left hole, an upper right hole, a middle right hole, and a lower right hole, and includes the following steps:
s31) grouting above the upper left hole, and then excavating the upper left hole; excavating a rear vertical grid steel frame, driving a foot locking anchor rod, and then spraying concrete; completing primary lining support of the upper left hole;
s32) after the left upper hole is excavated for 3m, grouting above the right upper hole, beginning to excavate the right upper hole, erecting a grid steel frame, and spraying concrete to complete primary lining support of the right upper hole;
s33) lagging behind the upper right hole by 6m, and then excavating a left middle hole; excavating a rear vertical grid steel frame, driving a foot locking anchor rod, and then spraying concrete; completing primary lining support of the left middle hole;
s34) after the distance lags behind the left middle hole by 3m, excavating the right middle hole, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; completing primary lining support of the right middle hole;
s35) after 6m of the right middle hole, excavating a left lower hole, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; completing primary lining support of the left lower hole;
s36) excavating a right lower hole after lagging behind the right middle hole by 3m, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; and finishing primary lining support of the lower right hole.
Further, the S4) includes the following specific steps:
s41) waterproof layer construction;
s42) second lining construction;
the construction of the waterproof layer comprises the following steps:
s411) hanging the geotextile: loading the geotextile on a bracket of the waterproof board laying trolley, pulling out the geotextile, feeding the geotextile into the center of a reel of the waterproof board laying trolley, keeping the axis of the geotextile vertical to the reel of the waterproof board laying trolley, and clamping the geotextile; starting a 'geotextile rolling' mode of the waterproof board laying trolley, and rolling the geotextile from a bracket of the waterproof board laying trolley onto a reel of a crawling trolley of the waterproof board laying trolley; the geotextiles on the reel of the crawling trolley are symmetrically distributed; starting a crawling trolley of the waterproof board laying trolley, laying geotextile, and starting a jacking system of the waterproof board laying trolley to jack the geotextile to the primary support surface; and fixing the geotextile on the surface of the primary support by using the hot-melt gasket to finish the laying of the geotextile ring.
S412) laying, fixing and welding the waterproof board; firstly, correctly marking a longitudinal central line of a tunnel on a geotextile buffer layer at the top of a tunnel arch, then enabling the central line of a waterproof board to coincide with the central line of the tunnel, laying the waterproof board from the arch top to two sides like geotextile, performing hot-melt welding on the edge laying side and a round gasket, and performing hot-melt welding on the waterproof board and the round gasket; the waterproof board is laid along the circumferential direction of the tunnel, and the laying length of the waterproof board is the same as that of the geotextile;
s413) waterproof treatment of construction joints: the annular construction joint is sealed by adopting an externally-attached rubber water stop and a middle-embedded rubber water stop, and the longitudinal construction joint is sealed by a middle-embedded steel-edge water stop and a water-swelling rubber water stop.
Further, the S42) secondary lining construction is carried out, and an integral hydraulic lining trolley is adopted for construction; the method comprises the following specific steps:
s421) binding reinforcing steel bars in the tunnel to form a plurality of reinforcing steel bar bundles, binding to form reinforcing steel bar net sheets, lifting the reinforcing steel bar net sheets to installation positions through the integral hydraulic lining trolley, binding adjacent reinforcing steel bar net sheets to form longitudinal and transverse reinforcing steel bars to be connected into a whole, and forming the reinforcing steel bar net
S422) pumping and stirring the initially-solidified concrete to side wall bodies on two sides of the tunnel until the concrete is flush with half of the width of the waterproof steel strip to form a two-lining main body structure.
Detailed Description
The present invention will be described in further detail with reference to examples, but the embodiments of the present invention are not limited thereto.
The invention discloses a construction process of a saturated loess 12m large-span small-clear-distance tunnel, which comprises the following steps of:
s1) precipitation before construction;
s11) positioning and clearly identifying the precipitation well and the water collecting pool according to the design scheme and the actual site;
s12) adopting impact drilling to form a hole, wherein the aperture meets the requirement of placing a submersible pump in a water pumping pipe; then adopting slurry to protect the wall;
s13) cleaning the hole immediately after the hole is formed, and mounting a well pipe, wherein a filter pipe part of the well pipe is placed at the position of the permeable layer as far as possible;
s14) before the water pump is installed, washing the well by an air compression method;
s15), installing a water pump, checking, and then performing trial water pumping to check whether water pumping equipment and a water pumping and draining system can meet precipitation requirements;
s16) excavating a water collecting pool according to the positioning, wherein the capacity of the water collecting pool is larger than the product of the capacity of a precipitation well communicated with the water collecting pool and the local average monthly precipitation; then adopting slurry to protect the wall;
s17), after the excavation is finished, immediately cleaning, and then communicating with a water outlet of a water pump through a water pumping pipe;
s2) forepoling construction;
s21) preparing a small catheter; pouring concrete into the small guide pipe, and vibrating, compacting and finally setting to obtain the small guide pipe for pouring concrete;
s22) supporting construction of a supporting frame; installing and fixing a support frame in the tunnel; measuring and positioning the tunnel at the position of the support frame, determining a small guide pipe construction hole position and drilling, wherein the drilling direction and the tunnel direction form an acute angle;
s23) installing a small concrete injection guide pipe; and (4) driving the small concrete-injected guide pipes into each drilling hole position, and fixedly connecting each small concrete-injected guide pipe with the support frame respectively.
S3) tunnel excavation and primary lining support are carried out;
the step S3) includes the steps of dividing the tunnel into a left upper hole, a left middle hole, a left lower hole, a right upper hole, a right middle hole and a right lower hole:
s31) grouting above the upper left hole, and then excavating the upper left hole; excavating a rear vertical grid steel frame, driving a foot locking anchor rod, and then spraying concrete; completing primary lining support of the upper left hole;
s32) after the left upper hole is excavated for 3m, grouting above the right upper hole, beginning to excavate the right upper hole, erecting a grid steel frame, and spraying concrete to complete primary lining support of the right upper hole;
s33) lagging behind the upper right hole by 6m, and then excavating a left middle hole; excavating a rear vertical grid steel frame, driving a foot locking anchor rod, and then spraying concrete; completing primary lining support of the left middle hole;
s34) after the distance lags behind the left middle hole by 3m, excavating the right middle hole, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; completing primary lining support of the right middle hole;
s35) after 6m of the right middle hole, excavating a left lower hole, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; completing primary lining support of the left lower hole;
s36) excavating a right lower hole after lagging behind the right middle hole by 3m, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; primary lining support for completing right lower hole
S4) waterproof layer and secondary lining support;
s41) waterproof layer construction;
s42) second lining construction;
the construction of the waterproof layer comprises the following steps:
s411) hanging the geotextile: loading the geotextile on a bracket of the waterproof board laying trolley, pulling out the geotextile, feeding the geotextile into the center of a reel of the waterproof board laying trolley, keeping the axis of the geotextile vertical to the reel of the waterproof board laying trolley, and clamping the geotextile; starting a 'geotextile rolling' mode of the waterproof board laying trolley, and rolling the geotextile from a bracket of the waterproof board laying trolley onto a reel of a crawling trolley of the waterproof board laying trolley; the geotextiles on the reel of the crawling trolley are symmetrically distributed; starting a crawling trolley of the waterproof board laying trolley, laying geotextile, and starting a jacking system of the waterproof board laying trolley to jack the geotextile to the primary support surface; and fixing the geotextile on the surface of the primary support by using the hot-melt gasket to finish the laying of the geotextile ring.
S412) laying, fixing and welding the waterproof board; firstly, correctly marking a longitudinal central line of a tunnel on a geotextile buffer layer at the top of a tunnel arch, then enabling the central line of a waterproof board to coincide with the central line of the tunnel, laying the waterproof board from the arch top to two sides like geotextile, performing hot-melt welding on the edge laying side and a round gasket, and performing hot-melt welding on the waterproof board and the round gasket; the waterproof board is laid along the circumferential direction of the tunnel, and the laying length of the waterproof board is the same as that of the geotextile;
s413) waterproof treatment of construction joints: the annular construction joint is sealed by adopting an externally-attached rubber water stop and a middle-embedded rubber water stop, and the longitudinal construction joint is sealed by a middle-embedded steel-edge water stop and a water-swelling rubber water stop.
Further, the S42) secondary lining construction is carried out, and an integral hydraulic lining trolley is adopted for construction; the method comprises the following specific steps:
s421) binding reinforcing steel bars in the tunnel to form a plurality of reinforcing steel bar bundles, binding to form reinforcing steel bar net sheets, lifting the reinforcing steel bar net sheets to installation positions through the integral hydraulic lining trolley, binding adjacent reinforcing steel bar net sheets to form longitudinal and transverse reinforcing steel bars to be connected into a whole, and forming the reinforcing steel bar net
S422) pumping and stirring the initially-solidified concrete to side wall bodies on two sides of the tunnel until the concrete is flush with half of the width of the waterproof steel strip to form a two-lining main body structure.
Wherein, precipitation before construction in S1) is realized by a precipitation well and a water collection pool; the water collecting tank is arranged far away from the tunnel excavation site and is communicated with the dewatering well; and the excavation site of the water collecting tank and the tunnel is not less than 2 km.
Wherein, in the step S13), after the well pipe is put in, the space between the well pipe and the hole wall is backfilled by using filter materials to prevent collapse, and the well point is backfilled and compacted by using clay within the range of 50-100cm below the ground.
The small guide pipe passes through a seamless steel pipe with one conical end, and the aggregate particle size of the poured concrete does not exceed 1/5 of the inner diameter of the small guide pipe.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention in any way, and all simple modifications and equivalent variations of the above embodiments according to the technical spirit of the present invention are included in the scope of the present invention.

Claims (8)

1. Saturated loess 12m large-span small-clear-distance tunnel construction technology is characterized by comprising the following steps of:
s1) precipitation before construction;
s2) forepoling construction;
s3) tunnel excavation and primary lining support are carried out;
s4) waterproof layer and secondary lining support;
wherein, precipitation before construction in S1) is realized by a precipitation well and a water collection pool; the water collecting tank is arranged far away from the tunnel excavation site and is communicated with the dewatering well; and the excavation site of the water collecting tank and the tunnel is not less than 2 km.
2. The saturated loess 12m large-span small-clear-distance tunnel construction process as claimed in claim 1, wherein: the construction step of S1) is as follows:
s11) positioning and clearly identifying the precipitation well and the water collecting pool according to the design scheme and the actual site;
s12) adopting impact drilling to form a hole, wherein the aperture meets the requirement of placing a submersible pump in a water pumping pipe; then adopting slurry to protect the wall;
s13) cleaning the hole immediately after the hole is formed, and mounting a well pipe, wherein a filter pipe part of the well pipe is placed at the position of the permeable layer as far as possible;
s14) before the water pump is installed, washing the well by an air compression method;
s15), installing a water pump, checking, and then performing trial water pumping to check whether water pumping equipment and a water pumping and draining system can meet precipitation requirements;
s16) excavating a water collecting pool according to the positioning, wherein the capacity of the water collecting pool is larger than the product of the capacity of a precipitation well communicated with the water collecting pool and the local average monthly precipitation; then adopting slurry to protect the wall;
s17), immediately cleaning the water pipe after the excavation is finished, and then communicating the water pipe with the water outlet of the water pump.
3. The saturated loess 12m large-span small-clear-distance tunnel construction process as claimed in claim 2, wherein: in step S13), after the well pipe is put in, the space between the well pipe and the hole wall is backfilled by using filter materials to prevent collapse, and the well point is backfilled to be compact in a range of 50-100cm below the ground by using clay.
4. The saturated loess 12m large-span small-clear-distance tunnel construction process as claimed in any one of claims 1 ~ 3, wherein the S2) comprises the following steps:
s21) preparing a small catheter; pouring concrete into the small guide pipe, and vibrating, compacting and finally setting to obtain the small guide pipe for pouring concrete;
s22) supporting construction of a supporting frame; installing and fixing a support frame in the tunnel; measuring and positioning the tunnel at the position of the support frame, determining a small guide pipe construction hole position and drilling, wherein the drilling direction and the tunnel direction form an acute angle;
s23) installing a small concrete injection guide pipe; and (4) driving the small concrete-injected guide pipes into each drilling hole position, and fixedly connecting each small concrete-injected guide pipe with the support frame respectively.
5. The saturated loess 12m large-span small-clear-distance tunnel construction process as claimed in claim 4, wherein: the small guide pipe passes through a seamless steel pipe with one conical end, and the aggregate particle size of the poured concrete does not exceed 1/5 of the inner diameter of the small guide pipe.
6. The construction process of the saturated loess 12m large-span small-clear-distance tunnel according to any one of claims 1 ~ 3 and 4, wherein the S3) comprises the following steps of:
s31) grouting above the upper left hole, and then excavating the upper left hole; excavating a rear vertical grid steel frame, driving a foot locking anchor rod, and then spraying concrete; completing primary lining support of the upper left hole;
s32) after the left upper hole is excavated for 3m, grouting above the right upper hole, beginning to excavate the right upper hole, erecting a grid steel frame, and spraying concrete to complete primary lining support of the right upper hole;
s33) lagging behind the upper right hole by 6m, and then excavating a left middle hole; excavating a rear vertical grid steel frame, driving a foot locking anchor rod, and then spraying concrete; completing primary lining support of the left middle hole;
s34) after the distance lags behind the left middle hole by 3m, excavating the right middle hole, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; completing primary lining support of the right middle hole;
s35) after 6m of the right middle hole, excavating a left lower hole, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; completing primary lining support of the left lower hole;
s36) excavating a right lower hole after lagging behind the right middle hole by 3m, erecting a grid steel frame, driving a foot locking anchor rod, and spraying concrete; and finishing primary lining support of the lower right hole.
7. The construction process of the saturated loess 12m large-span small-clear-distance tunnel as claimed in any one of claims 1 ~ 3 and 4, wherein the S4) comprises the following steps:
s41) waterproof layer construction;
s42) second lining construction;
the construction of the waterproof layer comprises the following steps:
s411) hanging the geotextile: loading the geotextile on a bracket of the waterproof board laying trolley, pulling out the geotextile, feeding the geotextile into the center of a reel of the waterproof board laying trolley, keeping the axis of the geotextile vertical to the reel of the waterproof board laying trolley, and clamping the geotextile; starting a 'geotextile rolling' mode of the waterproof board laying trolley, and rolling the geotextile from a bracket of the waterproof board laying trolley onto a reel of a crawling trolley of the waterproof board laying trolley; the geotextiles on the reel of the crawling trolley are symmetrically distributed; starting a crawling trolley of the waterproof board laying trolley, laying geotextile, and starting a jacking system of the waterproof board laying trolley to jack the geotextile to the primary support surface; fixing the geotextile on the surface of the primary support by using a hot-melt gasket to finish the laying of a ring of geotextile;
s412) laying, fixing and welding the waterproof board; firstly, correctly marking a longitudinal central line of a tunnel on a geotextile buffer layer at the top of a tunnel arch, then enabling the central line of a waterproof board to coincide with the central line of the tunnel, laying the waterproof board from the arch top to two sides like geotextile, performing hot-melt welding on the edge laying side and a round gasket, and performing hot-melt welding on the waterproof board and the round gasket; the waterproof board is laid along the circumferential direction of the tunnel, and the laying length of the waterproof board is the same as that of the geotextile;
s413) waterproof treatment of construction joints: the annular construction joint is sealed by adopting an externally-attached rubber water stop and a middle-embedded rubber water stop, and the longitudinal construction joint is sealed by a middle-embedded steel-edge water stop and a water-swelling rubber water stop.
8. The saturated loess 12m large-span small-clear-distance tunnel construction process as claimed in claim 7, wherein: s42), secondary lining construction, namely, construction by adopting an integral hydraulic lining trolley; the method comprises the following specific steps:
s421) binding reinforcing steel bars in the tunnel to form a plurality of reinforcing steel bar bundles, binding to form reinforcing steel bar net sheets, lifting the reinforcing steel bar net sheets to installation positions through the integral hydraulic lining trolley, binding adjacent reinforcing steel bar net sheets to form longitudinal and transverse reinforcing steel bars to be connected into a whole, and forming the reinforcing steel bar net
S422) pumping and stirring the initially-solidified concrete to side wall bodies on two sides of the tunnel until the concrete is flush with half of the width of the waterproof steel strip to form a two-lining main body structure.
CN201911203260.8A 2019-11-29 2019-11-29 Construction process of saturated loess 12m large-span small-clear-distance tunnel Pending CN110714772A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911203260.8A CN110714772A (en) 2019-11-29 2019-11-29 Construction process of saturated loess 12m large-span small-clear-distance tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911203260.8A CN110714772A (en) 2019-11-29 2019-11-29 Construction process of saturated loess 12m large-span small-clear-distance tunnel

Publications (1)

Publication Number Publication Date
CN110714772A true CN110714772A (en) 2020-01-21

Family

ID=69215635

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911203260.8A Pending CN110714772A (en) 2019-11-29 2019-11-29 Construction process of saturated loess 12m large-span small-clear-distance tunnel

Country Status (1)

Country Link
CN (1) CN110714772A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510959A (en) * 2013-09-13 2014-01-15 北京交通大学 Excavation technique for shallow-buried large-span small-spacing loess tunnel
CN105507337A (en) * 2015-12-09 2016-04-20 中铁建大桥工程局集团第五工程有限公司 Construction process combining high-pressure jet grouting pile with precipitation construction interconnecting channel
CN105863648A (en) * 2016-04-06 2016-08-17 中铁二十三局集团第二工程有限公司 Underground-excavation shallow-covering large-cross-section tunnel construction method
CN106050266A (en) * 2016-07-22 2016-10-26 中铁建大桥工程局集团第五工程有限公司 Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel
CN108194136A (en) * 2017-12-31 2018-06-22 中铁十九局集团第二工程有限公司 Lining construction method
CN109653749A (en) * 2018-11-30 2019-04-19 中铁二局第五工程有限公司 A kind of loose slide rock rubble soil section tunnel excavation construction method of high altitude localities shallow embedding

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510959A (en) * 2013-09-13 2014-01-15 北京交通大学 Excavation technique for shallow-buried large-span small-spacing loess tunnel
CN105507337A (en) * 2015-12-09 2016-04-20 中铁建大桥工程局集团第五工程有限公司 Construction process combining high-pressure jet grouting pile with precipitation construction interconnecting channel
CN105863648A (en) * 2016-04-06 2016-08-17 中铁二十三局集团第二工程有限公司 Underground-excavation shallow-covering large-cross-section tunnel construction method
CN106050266A (en) * 2016-07-22 2016-10-26 中铁建大桥工程局集团第五工程有限公司 Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel
CN108194136A (en) * 2017-12-31 2018-06-22 中铁十九局集团第二工程有限公司 Lining construction method
CN109653749A (en) * 2018-11-30 2019-04-19 中铁二局第五工程有限公司 A kind of loose slide rock rubble soil section tunnel excavation construction method of high altitude localities shallow embedding

Similar Documents

Publication Publication Date Title
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN111075454B (en) Double-arch tunnel five-hole excavation method
CN106907159B (en) Shallow-buried underground excavation subway station separated open type structure and construction method thereof
CN101864960B (en) Carst region double-arch road tunnel construction method
CN102322064A (en) Construction method for underground diaphragm wall of deep foundation pit for subway station in collapsible loess areas
CN103741714A (en) Full-cover excavation top-down construction method for underground engineering
CN113847050B (en) Construction method of ultra-long highway tunnel in lava mountain area
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN112031814B (en) Cave-entering construction method for crossing shallow-layer high-load highway
CN105464074A (en) Manual hole digging pile high polymer grouting protection structure and construction method thereof
CN111734425A (en) Construction method of underground excavation tunnel for downwards passing through airport terminal building
CN105133581A (en) Three-in-one construction method for uplift pile, lattice column and precipitation well in supporting structure
CN110847929B (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
CN110700860B (en) Construction method of soil-stone boundary tunnel crossing loess valley
CN110985003B (en) Tunnel construction method for penetrating through earth-rock boundary stratum
CN110821500B (en) Large-section tunnel excavation and support construction method for penetrating through earth-rock boundary stratum
CN211258631U (en) Loess tunnel basement reinforcement construction structure based on high pressure jet grouting pile
CN105926642B (en) A kind of Urban Underground pipe gallery pattern foundation pit supporting structure and underground structure external mold integral structure and construction method
CN110735641B (en) Construction method of transfer passage of underpass pipeline
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN112983461A (en) Construction method for bias tunnel portal in slope volume
CN110762286B (en) Drainage pipe network artificial pipe jacking construction process
CN108252307A (en) A kind of foundation pit construction method for underground tunnel upper
CN111560959A (en) Excavation and supporting method for shield starting well foundation pit adjacent to subway
CN108978709B (en) Urban comprehensive pipe gallery branch construction method in space-limited environment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Ma Tianchang

Inventor after: Zhao Hui

Inventor after: Shi Xianhuo

Inventor after: Hao Yufeng

Inventor after: Wei Shoufeng

Inventor after: Su Chunsheng

Inventor after: He Shimei

Inventor after: Pu Zhanhua

Inventor after: Guo Jianqiang

Inventor after: Xu Shaoping

Inventor after: Rao Shengbin

Inventor before: Ma Tianchang

Inventor before: Zhao Hui

Inventor before: Shi Xianhuo

Inventor before: Xu Shaoping

Inventor before: Rao Shengbin

Inventor before: Su Chunsheng

Inventor before: He Shimei

Inventor before: Pu Zhanhua

Inventor before: Guo Jianqiang

Inventor before: Hao Yufeng

Inventor before: Wei Shoufeng

CB03 Change of inventor or designer information
RJ01 Rejection of invention patent application after publication

Application publication date: 20200121

RJ01 Rejection of invention patent application after publication