CN110644521A - Offshore wind power anti-icing structure single pile reinforcement treatment method and reinforced foundation - Google Patents

Offshore wind power anti-icing structure single pile reinforcement treatment method and reinforced foundation Download PDF

Info

Publication number
CN110644521A
CN110644521A CN201910882348.0A CN201910882348A CN110644521A CN 110644521 A CN110644521 A CN 110644521A CN 201910882348 A CN201910882348 A CN 201910882348A CN 110644521 A CN110644521 A CN 110644521A
Authority
CN
China
Prior art keywords
pile
sand
foundation
compacted
sand pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910882348.0A
Other languages
Chinese (zh)
Inventor
徐海滨
高俊松
吕鹏远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges Renewables Group Co Ltd
Original Assignee
China Three Gorges Renewables Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges Renewables Group Co Ltd filed Critical China Three Gorges Renewables Group Co Ltd
Priority to CN201910882348.0A priority Critical patent/CN110644521A/en
Publication of CN110644521A publication Critical patent/CN110644521A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0017Means for protecting offshore constructions
    • E02B17/0021Means for protecting offshore constructions against ice-loads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Wind Motors (AREA)

Abstract

The invention discloses a single pile reinforcement processing method for an offshore wind power anti-icing structure, which comprises the steps of calculating the center coordinates of each compacted sand pile; sequentially sinking a plurality of sand pile sleeves, pressurizing and draining the sand pile sleeves when the sand pile sleeves are close to the mud surface, and continuously sinking to the designed bottom elevation; pouring sand into the sand pile casing; pressing the sand pile pulling sleeve, detecting the elevation of the sand surface, controlling the speed of the sand pile pulling sleeve, and preventing soft soil from entering the bottom of the sand pile pulling sleeve; continuously maintaining the pressure in the pipe to back-beat so as to compact, compact and expand the sand columns; circularly performing pipe drawing and back driving to form a whole compacted sand pile; the method is characterized in that a single pile of the wind turbine generator is used as a center, a plurality of compacted sand piles are arranged around the single pile to form a compacted sand pile array, and the single pile foundation is reinforced. The invention also discloses a single-pile reinforced foundation. According to the single-pile reinforcing treatment method, the compacted sand pile array is arranged around the single-pile foundation of the wind turbine generator, so that a new soil body around the reinforcing pile of the composite foundation is formed, and the stability of the foundation of the wind turbine generator is enhanced.

Description

Offshore wind power anti-icing structure single pile reinforcement treatment method and reinforced foundation
Technical Field
The invention belongs to the field of wind power foundation reinforcement, and particularly relates to a single pile reinforcement treatment method for an offshore wind power anti-icing structure and a reinforced foundation.
Background
At present, the offshore wind turbine foundation is 80% of single-pile type, along with the increasing power of the wind turbine, the load is also increased, the pile diameter of the single pile is increased, the pile foundation stability is difficult to meet the requirements for the deep and soft soil on the surface and the bedrock geological structure covered below, and great challenges are brought to design and construction.
Disclosure of Invention
The invention has the technical problem that the pile foundation stability of the single-pile type wind turbine generator commonly adopted by the offshore wind power is difficult to meet the requirement along with the increase of the power and the load of the offshore wind turbine generator.
The invention aims to solve the problems and provides a single pile reinforcing treatment method and a reinforcing foundation for an offshore wind power anti-icing structure.
The technical scheme of the invention is that the offshore wind power anti-icing structure single pile reinforcing treatment method utilizes compacted sand piles to replace soft soil on the surface of a seabed to reinforce the single pile foundation of an offshore wind power generation unit, and comprises the following steps,
step 1: calculating the pile center coordinate of each compacted sand pile;
step 2: positioning a construction ship to an accurate coordinate position of a compacted sand pile, sequentially and respectively sinking a plurality of sand pile sleeves, pressurizing and draining the sand pile sleeves when the sand pile sleeves are close to a mud surface, keeping the air pressure in the pipes, continuously sinking the sand pile sleeves to a designed bottom elevation, and detecting and squeezing out mud entering the end parts of the sand pile sleeves in the sinking process;
and step 3: pouring sand into the sand pile casing;
and 4, step 4: setting air pressure in the pipe according to the depth of a soil layer where the sand pile sleeve is located, pressing the sand pile sleeve, keeping sand in the pipe in the soil layer, detecting the elevation of the sand surface in the sand pile sleeve, controlling the speed of the sand pile sleeve, and avoiding soft soil from entering the bottom of the sand pile sleeve due to over-fast pipe drawing; continuously maintaining the pressure in the pipe to back-beat so as to compact, compact and expand the sand columns; circularly performing sand filling, pipe drawing and back driving to form a whole compacted sand pile;
and 5: and (5) repeating the step (2) to the step (4), wherein a single pile of the wind turbine generator is taken as a center, and a plurality of compacted sand piles are arranged around the single pile to form a compacted sand pile array so as to finish the reinforcement of the single pile foundation.
Before the step 1, carrying out underwater topography measurement by adopting a GPS non-tide method, drawing an underwater topography map and determining the elevation of the mud surface.
In step 4, circularly performing sand filling, pipe drawing and backdriving, wherein the calculation formula of the single backdriving depth and the pile forming height is as follows:
A =ΔGL ×(1-d22/D2)
H=ΔGL-A
ΔGL= GL2- GL1
wherein, the delta GL is the pipe drawing height, the A is the back driving height, the H is the pile forming height, the GL1 is the actually measured bottom elevation of the sand pile sleeve before pipe drawing, the GL2 is the actually measured bottom elevation of the sand pile sleeve after pipe drawing, the D2 is the bottom inner diameter of the sand pile sleeve, and the D is the diameter of the underwater compacted sand pile after expanding.
Step 4, detecting the elevation of the sand surface in the sand pile casing, controlling the speed of the upper sand-pulling pile casing, avoiding soft soil from entering the bottom of the sand pile casing due to over-fast pipe pulling, reducing the speed of the upper sand-pulling pile casing when the sand discharge amount in the sand pile casing is less than the theoretical application sand amount until the sand discharge amount in the sand pile casing is equal to the theoretical application sand amount,
sand discharging amount in sand pile casing
V1=π×d12(SL1-SL2)/4
In the formula, SL1 is the actually measured elevation of the sand surface in the pipe before pipe drawing, SL2 is the actually measured elevation of the sand surface in the pipe after pipe drawing, and d1 is the inner diameter of the upper part of the sand pile sleeve;
theoretical application sand amount after sand-pulling pile sleeve delta GL height
V2=π×d22(GL2-GL1)/4
ΔGL= GL2- GL1
In the formula, GL1 is actually measured bottom elevation of the sand pile casing before pipe drawing, GL2 is actually measured bottom elevation of the sand pile casing after pipe drawing, and d2 is inner diameter of the bottom of the sand pile casing.
The single-pile reinforced foundation formed by the single-pile reinforced treatment method comprises a single-pile foundation and a plurality of compacted sand piles, wherein the single-pile foundation is connected with seabed bedrock, and the compacted sand piles are arranged in a soft soil layer above the bedrock; the compaction sand pile takes the single pile foundation as the center and is arranged at intervals to form a compaction sand pile array.
Preferably, the mono-pile reinforced foundation further comprises an ice pick resistant cone mounted at the mono-pile foundation level.
Preferably, the single pile foundation is a steel pipe pile.
Preferably, the inner circle of the compacted sand pile array is a square, an equilateral triangle or a parallelogram.
Preferably, the outer ring of the compacted sand pile array is circular.
Preferably, the distance between the squeezed sand pile adjacent to the single pile foundation in the squeezed sand pile array and closest to the single pile foundation and the center of the single pile foundation is 6-10 m.
Preferably, the pitch of the compacted sand piles of the compacted sand pile array is 1.3-3.5 m.
Preferably, the pile diameter of the compacted sand pile is 1.2-2 m.
Preferably, the pile length of the compacted sand pile is 10-60 m.
Compared with the prior art, the invention has the beneficial effects that:
1) according to the single-pile reinforcement processing method, the compacted sand pile array is arranged around the single-pile foundation of the wind turbine generator, so that a new soil body around the reinforced pile of the composite foundation is formed, and the stability of the foundation of the wind turbine generator is enhanced;
2) according to the single-pile reinforcing treatment method, before each compacted sand pile is arranged, the position of the compacted sand pile is accurately positioned, so that the foundation reinforcing effect of the wind turbine generator is ensured;
3) according to the single-pile reinforcement processing method, in the process of arranging the compacted sand piles, the elevation of the sand surface is monitored, the pipe drawing speed is controlled, the compacted sand piles are effectively prevented from being clamped with mud, and the construction quality is improved;
4) the compacted sand pile display is constructed from inside to outside, so that the situation that soil mass around a single pile is excessively accumulated to be unfavorable for the laying of sand quilt and sea cable and the installation of accessory components is avoided, and the situation that the soil mass around the single pile excessively extrudes the pile body to cause the integral inclination of the pile body is avoided;
5) compared with the traditional treatment mode, the single-pile reinforcement treatment method is safer, more reliable, more economical and more efficient;
6) the ice-resistant cone of the single-pile reinforced foundation reduces the ice load of the single-pile foundation.
Drawings
The invention is further illustrated by the following figures and examples.
Fig. 1 is a flowchart of a method for reinforcing a mono-pile according to the present invention.
Fig. 2 is a schematic diagram of the pipe drawing and back driving principle of the compacted sand pile.
Fig. 3 is a schematic structural view of a single-pile reinforced foundation.
Fig. 4 is a top view of a mono pile foundation and an array of compacted sand piles.
Description of reference numerals: the steel pipe pile comprises a steel pipe pile 1, a compacted sand pile 2, an anti-ice cone 3, a sacrificial anode block 4, an overhaul platform 5, a ladder stand 6 and a cable pipe 7.
Detailed Description
As shown in figures 1-2, the offshore wind power anti-icing structure single pile reinforcing treatment method is used for reinforcing a single pile foundation of an offshore wind power generation unit, a compacted sand pile ship is used for construction, the compacted sand pile ship is positioned by a GPS measuring system and comprises a GPS base station and 2 GPS receiving stations on the ship, the single pile reinforcing treatment method comprises the following steps,
step 1: calculating the pile center coordinate of each compacted sand pile, and guiding the pile center coordinate into a GPS (global positioning system) of a compacted sand pile ship;
step 2: positioning a compacted sand pile ship to an accurate coordinate position of a compacted sand pile, sequentially and respectively sinking 3 sand pile sleeves, pressurizing and draining the sand pile sleeves when the sand pile sleeves are close to a mud surface, simultaneously keeping the air pressure in the sand pile sleeves, continuously sinking the sand pile sleeves to a designed bottom surface elevation, and detecting and squeezing out mud entering from the end part of the sand pile sleeves in the sinking process;
and step 3: pouring sand into the sand pile casing;
and 4, step 4: setting air pressure in the pipe according to the depth of a soil layer where the sand pile sleeve is located, pressing the sand pile sleeve, keeping sand in the pipe in the soil layer, detecting the elevation of the sand surface in the sand pile sleeve, controlling the speed of the sand pile sleeve, and avoiding soft soil from entering the bottom of the sand pile sleeve due to over-fast pipe drawing; continuously maintaining the pressure in the pipe to back-beat so as to compact, compact and expand the sand columns; circularly performing sand filling, pipe drawing and back driving to form a whole compacted sand pile;
and 5: and (5) repeating the step (2) to the step (4), wherein a single pile of the wind turbine generator is taken as a center, and a plurality of compacted sand piles are arranged around the single pile to form a compacted sand pile array so as to finish the reinforcement of the single pile foundation.
The sand for the compacted sand piles was transported from the banker harbor quay to the site using 2 2000t sand carriers. The pile body material of the sand compaction pile adopts coarse sand or medium sand, the maximum grain diameter is not more than 5mm, and the mud content is not more than 5%.
Before the step 1, carrying out underwater topography measurement by adopting a GPS non-tide method, drawing an underwater topography map and determining the elevation of the mud surface.
In step 2, the positioning personnel closely observe the pile position deviation displayed by the GPS system, and ensure that the pile position deviation is less than 0.2dmm, namely 320mm, when the casing is sunk. Meanwhile, in the process of sinking, the verticality of the compacted sand pile is controlled by adjusting ballast water of the underwater compacted sand pile ship, and the verticality of the sand pipe is strictly controlled within 1.5%.
And 2, when the sand pile casing pipe is sunk, observing the height of the soil plug in the sand pile casing pipe by measuring the pipe bottom elevation and the sand surface elevation in the pipe, and adjusting the air pressure in the pipe according to an observation result to keep the height of the soil plug in the sand pile casing pipe to be about 1m as much as possible.
As shown in fig. 2, in step 4, the sand make-up, pipe drawing and back-beating are performed in a circulating manner, and the calculation formula of the single back-beating depth and pile-forming height is as follows:
A =ΔGL ×(1-d22/D2)
H=ΔGL-A
ΔGL= GL2- GL1
wherein, the delta GL is the pipe drawing height, the A is the back driving height, the H is the pile forming height, the GL1 is the actually measured bottom elevation of the sand pile sleeve before pipe drawing, the GL2 is the actually measured bottom elevation of the sand pile sleeve after pipe drawing, the D2 is the bottom inner diameter of the sand pile sleeve, and the D is the diameter of the underwater compacted sand pile after expanding.
Step 4, detecting the elevation of the sand surface in the sand pile casing, controlling the speed of the upper sand-pulling pile casing, avoiding soft soil from entering the bottom of the sand pile casing due to over-fast pipe pulling, reducing the speed of the upper sand-pulling pile casing when the sand discharge amount in the sand pile casing is less than the theoretical application sand amount until the sand discharge amount in the sand pile casing is equal to the theoretical application sand amount,
sand discharging amount in sand pile casing
V1=π×d12(SL1-SL2)/4
In the formula, SL1 is the actually measured elevation of the sand surface in the pipe before pipe drawing, SL2 is the actually measured elevation of the sand surface in the pipe after pipe drawing, and d1 is the inner diameter of the upper part of the sand pile sleeve;
theoretical application sand amount after sand-pulling pile sleeve delta GL height
V2=π×d22(GL2-GL1)/4
ΔGL= GL2- GL1
In the formula, GL1 is actually measured bottom elevation of the sand pile casing before pipe drawing, GL2 is actually measured bottom elevation of the sand pile casing after pipe drawing, and d2 is inner diameter of the bottom of the sand pile casing.
And 4, automatically tracking the height of the residual sand in the sleeve by a sand surface monitor to ensure that the height is not less than 3m, immediately stopping pulling up and starting sand adding if the height is less than the value, and preventing soft soil outside the sleeve from recharging under the action of water and soil pressure in the process of exhausting and adding sand to cause mud clamping of the underwater compacted sand pile.
The top of the compacted sand pile in a partial area is shallow in soil penetration, and the surrounding soil pressure is low, so that the pressure in the pipe is reduced during backdriving, and the phenomenon that sand in the pipe is completely flushed out due to overlarge pressure is prevented, and pile breakage of the compacted sand pile is caused. Therefore, when the construction is carried out to a distance of 1-2 m from the pile top, the height of each pile should be shortened, and the compactness of the top of the compacted sand pile is improved as much as possible.
The plane deviation of the ship moving positioning is strictly controlled within +/-320 mm, and if the plane deviation is out of limit after the sand pile casing enters the mud surface, the plane deviation needs to be adjusted in time, particularly during sudden rising and falling tide. Meanwhile, the ship anchor position needs to be adjusted regularly according to the actual positioning condition so as to better control the plane deviation.
As shown in fig. 3-4, the single-pile reinforced foundation formed by the offshore wind power anti-icing structure single-pile reinforcing method comprises a steel pipe pile 1, an anti-icing cone 3 and 376 compacted sand piles 2, wherein the steel pipe pile 1 is connected with seabed bedrock, and the compacted sand piles 2 are arranged in a soft soil layer above the bedrock; the compacted sand piles 2 are arranged at intervals by taking the steel pipe pile 1 as the center to form a compacted sand pile array. And the distance between the center of the steel pipe pile 1 and the compacted sand pile 2 which is adjacent to the steel pipe pile 1 and closest to the steel pipe pile 1 in the compacted sand pile array is 9.6 m. The interval of the compacted sand piles 2 of the compacted sand pile array is 3.2 m. The pile diameter of the compacted sand pile 2 is 2 m. The pile length of the compacted sand pile 2 is 14.8 m.
The single-pile reinforced foundation further comprises a sacrificial anode block 4, an overhaul platform 5, a ladder stand 6 and a cable pipe 7. The ice-resistant cone 3 is arranged at the horizontal plane of the steel pipe pile 1. And the sacrificial anode block 4 is welded with the steel pipe pile 1 and is used for resisting corrosion of a metal part of the pile foundation. The upper end of the ladder stand 6 is connected with the maintenance platform 5, and the lower end extends to the horizontal plane. The cable pipe 7 is fixedly connected with the steel pipe pile 1, and the lower end of the cable pipe penetrates into a soft soil layer to protect a power transmission cable of the wind turbine generator.

Claims (10)

1. A single pile reinforcement processing method of an offshore wind power anti-icing structure utilizes compacted sand piles to replace soft soil on the surface of a seabed to reinforce a single pile foundation of an offshore wind power generation unit, and is characterized by comprising the following steps,
step 1: calculating the pile center coordinate of each compacted sand pile;
step 2: positioning a construction ship to an accurate coordinate position of a compacted sand pile, sequentially and respectively sinking a plurality of sand pile sleeves, pressurizing and draining the sand pile sleeves when the sand pile sleeves are close to a mud surface, keeping the air pressure in the pipes, continuously sinking the sand pile sleeves to a designed bottom elevation, and detecting and squeezing out mud entering the end parts of the sand pile sleeves in the sinking process;
and step 3: pouring sand into the sand pile casing;
and 4, step 4: setting air pressure in the pipe according to the depth of a soil layer where the sand pile sleeve is located, pressing the sand pile sleeve, keeping sand in the pipe in the soil layer, detecting the elevation of the sand surface in the sand pile sleeve, controlling the speed of the sand pile sleeve, and avoiding soft soil from entering the bottom of the sand pile sleeve due to over-fast pipe drawing; continuously maintaining the pressure in the pipe to back-beat so as to compact, compact and expand the sand columns; circularly performing sand filling, pipe drawing and back driving to form a whole compacted sand pile;
and 5: and (5) repeating the steps 2-4, taking the single pile of the wind turbine generator as a center, and arranging a plurality of compacted sand piles around the single pile from inside to outside to form a compacted sand pile array so as to finish the reinforcement of the single pile foundation.
2. The offshore wind power anti-icing structure single pile reinforcement processing method according to claim 1, characterized in that before step 1, an underwater topography is measured by a GPS tide-free method, an underwater topography map is drawn, and a mud surface elevation is determined.
3. The offshore wind power anti-icing structure single pile reinforcement processing method according to claim 1, wherein in step 4, the sand filling, pipe drawing and back driving are performed in a circulating manner, and the calculation formula of the single back driving depth and the pile forming height is as follows
A =ΔGL ×(1-d22/D2)
H=ΔGL-A
ΔGL= GL2- GL1
Wherein, the delta GL is the pipe drawing height, the A is the back driving height, the H is the pile forming height, the GL1 is the actually measured bottom elevation of the sand pile sleeve before pipe drawing, the GL2 is the actually measured bottom elevation of the sand pile sleeve after pipe drawing, the D2 is the bottom inner diameter of the sand pile sleeve, and the D is the diameter of the underwater compacted sand pile after expanding.
4. The offshore wind power anti-icing structure single pile reinforcement processing method according to claim 1, characterized in that in step 4, the sand surface elevation in the sand pile casing is detected, the speed of pulling up the sand pile casing is controlled, soft soil is prevented from entering the bottom of the sand pile casing due to too fast pipe pulling, when the sand amount discharged from the sand pile casing is smaller than the theoretical sand amount, the speed of pulling up the sand pile casing is reduced until the sand amount discharged from the sand pile casing is equal to the theoretical sand amount,
sand discharging amount in sand pile casing
V1=π×d12(SL1-SL2)/4
In the formula, SL1 is the actually measured elevation of the sand surface in the pipe before pipe drawing, SL2 is the actually measured elevation of the sand surface in the pipe after pipe drawing, and d1 is the inner diameter of the upper part of the sand pile sleeve;
theoretical application sand amount after sand-pulling pile sleeve delta GL height
V2=π×d22(GL2-GL1)/4
ΔGL= GL2- GL1
In the formula, GL1 is actually measured bottom elevation of the sand pile casing before pipe drawing, GL2 is actually measured bottom elevation of the sand pile casing after pipe drawing, and d2 is inner diameter of the bottom of the sand pile casing.
5. The single-pile reinforced foundation formed by the offshore wind power anti-icing structure single-pile reinforcing treatment method according to any one of claims 1 to 4, characterized by comprising a single-pile foundation and a plurality of compacted sand piles, wherein the single-pile foundation is connected with seabed bedrock, and the compacted sand piles are arranged in a soft soil layer above the bedrock; the compaction sand pile takes the single pile foundation as the center and is arranged at intervals to form a compaction sand pile array.
6. A mono-pile reinforced foundation as claimed in claim 5, further comprising an ice pick resistant cone mounted at the level of the mono-pile foundation.
7. The single-pile reinforced foundation of claim 5, wherein the single-pile foundation is a steel pipe pile.
8. A mono-pile reinforced foundation as claimed in claim 5, wherein the inner circle of the array of compacted sand piles is square, equilateral triangle or parallelogram.
9. A mono-pile reinforced foundation as claimed in claim 5, wherein the array of compacted sand piles has a pitch of 1.3-3.5 m.
10. The mono-pile reinforced foundation of claim 5, wherein the compacted sand pile has a pile diameter of 1.2-2 m.
CN201910882348.0A 2019-09-18 2019-09-18 Offshore wind power anti-icing structure single pile reinforcement treatment method and reinforced foundation Pending CN110644521A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910882348.0A CN110644521A (en) 2019-09-18 2019-09-18 Offshore wind power anti-icing structure single pile reinforcement treatment method and reinforced foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910882348.0A CN110644521A (en) 2019-09-18 2019-09-18 Offshore wind power anti-icing structure single pile reinforcement treatment method and reinforced foundation

Publications (1)

Publication Number Publication Date
CN110644521A true CN110644521A (en) 2020-01-03

Family

ID=68991353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910882348.0A Pending CN110644521A (en) 2019-09-18 2019-09-18 Offshore wind power anti-icing structure single pile reinforcement treatment method and reinforced foundation

Country Status (1)

Country Link
CN (1) CN110644521A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111894029A (en) * 2020-07-28 2020-11-06 中国长江三峡集团有限公司 Offshore wind power composite foundation suitable for seabed with sludge covering layer and construction method
CN112663668A (en) * 2021-01-15 2021-04-16 中国能源建设集团浙江省电力设计院有限公司 Disc type composite single-pile fan foundation suitable for soft soil seabed and construction method
CN115075283A (en) * 2021-03-16 2022-09-20 中国电建集团华东勘测设计研究院有限公司 Anti-scouring structure for single pile foundation of offshore wind turbine generator and construction method of anti-scouring structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296588A (en) * 2011-05-27 2011-12-28 中交第三航务工程局有限公司 Construction process of underwater sand compaction pile
CN108677992A (en) * 2018-05-21 2018-10-19 上海勘测设计研究院有限公司 Offshore wind turbine prestressing force gravity type foundation and its installation method
CN208472751U (en) * 2018-05-21 2019-02-05 上海勘测设计研究院有限公司 Offshore wind turbine prestressing force gravity type foundation
CN109853641A (en) * 2018-12-26 2019-06-07 中交第三航务工程局有限公司 A kind of test method of offshore wind farm sand compaction pile
CN109853608A (en) * 2018-12-25 2019-06-07 长江勘测规划设计研究有限责任公司 A kind of offshore wind turbine gravity type foundation composite foundation and its processing method
CN210827529U (en) * 2019-09-18 2020-06-23 中国三峡新能源(集团)股份有限公司 Single-pile reinforced foundation of offshore wind power anti-icing structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296588A (en) * 2011-05-27 2011-12-28 中交第三航务工程局有限公司 Construction process of underwater sand compaction pile
CN108677992A (en) * 2018-05-21 2018-10-19 上海勘测设计研究院有限公司 Offshore wind turbine prestressing force gravity type foundation and its installation method
CN208472751U (en) * 2018-05-21 2019-02-05 上海勘测设计研究院有限公司 Offshore wind turbine prestressing force gravity type foundation
CN109853608A (en) * 2018-12-25 2019-06-07 长江勘测规划设计研究有限责任公司 A kind of offshore wind turbine gravity type foundation composite foundation and its processing method
CN109853641A (en) * 2018-12-26 2019-06-07 中交第三航务工程局有限公司 A kind of test method of offshore wind farm sand compaction pile
CN210827529U (en) * 2019-09-18 2020-06-23 中国三峡新能源(集团)股份有限公司 Single-pile reinforced foundation of offshore wind power anti-icing structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蒋红晖: "《浅析海上地基处理中挤密砂桩的施工技术》", 中国水运, vol. 18, no. 2, 28 February 2018 (2018-02-28), pages 228 - 232 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111894029A (en) * 2020-07-28 2020-11-06 中国长江三峡集团有限公司 Offshore wind power composite foundation suitable for seabed with sludge covering layer and construction method
CN112663668A (en) * 2021-01-15 2021-04-16 中国能源建设集团浙江省电力设计院有限公司 Disc type composite single-pile fan foundation suitable for soft soil seabed and construction method
CN115075283A (en) * 2021-03-16 2022-09-20 中国电建集团华东勘测设计研究院有限公司 Anti-scouring structure for single pile foundation of offshore wind turbine generator and construction method of anti-scouring structure

Similar Documents

Publication Publication Date Title
CN107542101B (en) Construction method of offshore four-buoy-buoyancy tank combined foundation structure
CN110644521A (en) Offshore wind power anti-icing structure single pile reinforcement treatment method and reinforced foundation
CN108842806B (en) Construction process of offshore wind power foundation non-rock-socketed single pile
CN107653895B (en) Combined offshore six-buoy buoyancy tank foundation structure and construction method thereof
CN109780325B (en) Installation method of underwater pipeline of water taking tunnel of water plant
CN109629568A (en) The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating
CN107630461B (en) Combined offshore four-buoy buoyancy tank foundation structure and construction method thereof
CN103046553B (en) Method for carrying out deepwater laying on large-volume reinforced mud-filling tubular bags by using geotextiles-laying vessels
CN107806108A (en) Three floating drum buoyancy tank foundation structures and its construction method on a kind of combined type sea
CN109241631B (en) Shield tunnel segment floating amount calculation method
CN105908772B (en) The construction method of offshore wind turbine gravity type foundation, basic system and gravity type foundation
CN102296629B (en) Tower-drum structure suitable for ocean engineering and installation method thereof
CN107630462A (en) A kind of six floating drum buoyancy tank combined type foundation structures of sea and its construction method
CN210827529U (en) Single-pile reinforced foundation of offshore wind power anti-icing structure
CN114232689B (en) Leveling method for immersed tube tunnel full-floating foundation bed
CN114855865A (en) Tensioning type fan foundation anchored on rock-based seabed and arrangement method
CN207987950U (en) Four floating drum buoyancy tank foundation structures on a kind of combined type sea
CN102286986B (en) Five-horse foundation structure and construction method thereof
CN102704512B (en) Immersed tube bottom jack type deviation rectifying fine adjusting system and adjusting technology
CN107268649B (en) Device for improving floating water seal and negative pressure sinking stability of cylindrical foundation
CN107761751A (en) A kind of Double-Wall Steel Boxed Cofferdam and its construction method
CN110144924A (en) A kind of taper barrel marine wind turbine generator system base structure and its construction method
CN202913431U (en) Immersed tube bottom end jack type deviation-rectifying accurate adjustment system
CN115434368A (en) Offshore-crossing immersed tube construction process
CN107724414A (en) Five floating drum buoyancy tank foundation structures and its construction method on a kind of combined type sea

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination