CN110565529B - Sound barrier basis and case roof beam integration template of pouring - Google Patents

Sound barrier basis and case roof beam integration template of pouring Download PDF

Info

Publication number
CN110565529B
CN110565529B CN201910793725.3A CN201910793725A CN110565529B CN 110565529 B CN110565529 B CN 110565529B CN 201910793725 A CN201910793725 A CN 201910793725A CN 110565529 B CN110565529 B CN 110565529B
Authority
CN
China
Prior art keywords
sound barrier
template
foundation
angle steel
barrier foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910793725.3A
Other languages
Chinese (zh)
Other versions
CN110565529A (en
Inventor
贾晓刚
齐太山
刘振宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRRC Construction Engineering Co Ltd
Jiangsu CRRC Urban Development Co Ltd
Original Assignee
Suzhou CRRC Construction Engineering Co Ltd
CRRC Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou CRRC Construction Engineering Co Ltd, CRRC Construction Engineering Co Ltd filed Critical Suzhou CRRC Construction Engineering Co Ltd
Priority to CN201910793725.3A priority Critical patent/CN110565529B/en
Publication of CN110565529A publication Critical patent/CN110565529A/en
Application granted granted Critical
Publication of CN110565529B publication Critical patent/CN110565529B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F8/00Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic
    • E01F8/0005Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic used in a wall type arrangement
    • E01F8/0023Details, e.g. foundations
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a sound barrier foundation and box girder integrated pouring template, wherein an outer side template of the sound barrier foundation is formed by integrally extending and heightening an outer side template of the box girder upwards, an inner side template of the sound barrier foundation adopts rectangular steel plates with the same length as the outer side template of the sound barrier foundation, the outer side template of the sound barrier foundation and the inner side template of the sound barrier foundation are connected by a plurality of n-shaped connecting members arranged at equal intervals along the length direction, the n-shaped connecting members are formed by splicing oppositely arranged two strip-shaped angle steels after top surface superposition and combining bolts, the vertical surface of one strip-shaped angle steel is welded with the outer vertical surface of the outer side template of the sound barrier foundation, and the vertical surface of the other strip-shaped angle steel is welded with the outer vertical surface of. The grinding process of the outer side of the sound barrier foundation is omitted, overhead edge-facing operation is reduced, and safety risks are reduced; the number of times of template installation and concrete pouring is reduced, the construction time is saved, the labor input is reduced, and the operation efficiency and the engineering benefit are improved.

Description

Sound barrier basis and case roof beam integration template of pouring
Technical Field
The invention belongs to the technical field of bridge construction, and particularly relates to an integrated pouring template for a sound barrier foundation and a box girder.
Background
The sound barrier is widely used in municipal traffic facilities such as urban rail transit, highway and the like, can absorb sound and reduce noise, and reduces the influence of traffic noise on urban areas.
Taking a bridge as an example, the technology widely adopted at present is to bond reinforcing steel bars on the flange of a box girder after the box girder is poured and is condensed and hardened to reach a certain strength, install a sound barrier foundation template and pour a sound barrier foundation. The method has two main defects, namely, cement paste blocks are easily formed on the outer vertical face at the joint of the sound barrier foundation and the box girder due to template slurry leakage, and the safety risk of high-altitude edge-facing operation exists when the cement paste blocks on the outer vertical face are polished at the later stage; and secondly, the construction of the sound barrier foundation needs to be carried out after the construction of the box girder is finished, so that the construction procedures and the construction period are increased, the investment of time and labor is increased, and the engineering cost is increased.
Disclosure of Invention
The invention aims to save the outer side polishing process of the sound barrier foundation, reduce overhead edge-facing operation and reduce safety risks, and can reduce the times of template installation and concrete pouring, save construction time, reduce labor input and improve the operation efficiency and engineering benefits.
Therefore, the technical scheme adopted by the invention is as follows: an integral pouring template for a sound barrier foundation and a box girder comprises an outer side template of the sound barrier foundation and an inner side template of the sound barrier foundation, the outer side template of the sound barrier foundation is formed by integrally extending and heightening the outer side template of the box girder upwards, the inner side template of the sound barrier foundation adopts a rectangular steel plate with the same length as the outer side template of the sound barrier foundation, the inner side template of the sound barrier foundation and the outer side template of the sound barrier foundation are arranged in parallel, the outer side template of the sound barrier foundation and the inner side template of the sound barrier foundation are connected by a plurality of n-shaped connecting members which are arranged at equal intervals along the length direction, the n-shaped connecting member is formed by splicing two oppositely arranged strip-shaped angle steels through top surface superposition and then combining bolts, the vertical surface of one strip-shaped angle steel is welded with the outer vertical surface of the outer side template of the sound barrier foundation, and the vertical surface of the other strip-shaped angle steel is welded with the outer vertical surface of the inner side template of the sound barrier foundation.
Preferably, the stiffening member is welded on the inner side formwork of the sound barrier foundation, the stiffening member is an angle steel plate which is equal to the inner side formwork of the sound barrier foundation, the vertical surface of the angle steel plate is welded with the outer vertical surface of the inner side formwork of the sound barrier foundation, and the top of the angle steel plate is welded with the bottom surface of the strip-shaped angle steel on the corresponding side. The stiffening member plays the effect of reinforcing sound barrier foundation inboard template rigidity, welds with the inboard template of sound barrier foundation, the bar angle steel of corresponding side simultaneously, and the installation is firm reliable.
Further preferably, the top surface of bar angle steel is provided with at least three bolt via holes that set up along inside and outside direction equidistance interval, and every II type connecting elements is formed by at least two bolt concatenations to realize the adjustable installation of sound barrier basis outside template and sound barrier basis inboard template interval. The bolt via holes of selecting different splices, the connection width of adjustable II type connecting elements changes the outer template interval in the sound barrier basis to satisfy the requirement of pouring on the sound barrier basis of different design width, improve the commonality.
The invention has the beneficial effects that:
(1) the method has the advantages that the sound barrier foundation and the box girder can be integrally poured, and the steel bars are bound to install the sound barrier foundation template after the pouring of the box girder reaches a certain strength, so that the construction operation steps are simplified, the operation efficiency is improved, the construction operation period is shortened, and the economic benefit of the engineering is improved;
(2) the outer side template of the sound barrier foundation is formed by integrally extending and heightening the outer side template of the box girder upwards, so that the quality defect of the joint between the sound barrier foundation template and the box girder caused by slurry leakage of the template can be reduced and even avoided, and the attractiveness of the outer vertical surface of the bridge and the durability of the structure are improved;
(3) the traditional process for installing the sound barrier foundation formwork, particularly installing the outer side formwork of the sound barrier foundation and polishing the cement paste block of the outer vertical surface has the safety risk of high-altitude edge-facing operation, and the operation safety is high.
(4) The pouring height of the sound barrier foundation is usually about 30cm, the weight of the corresponding inner side template is small, the stress of the n-shaped connecting members is not large, the n-shaped connecting members are formed by overlapping two oppositely-arranged bar-shaped angle steels through top surfaces and then splicing the bar-shaped angle steels with bolts, the sound barrier foundation is poured between the adjacent n-shaped connecting members, the n-shaped connecting members are used for connecting the inner side template and the outer side template of the sound barrier foundation, the inner side template of the sound barrier foundation is quickly installed and detached, and then the quick formwork erection and demolding are realized; meanwhile, the dead weight of the inner side template and the lateral extrusion force of the concrete to the inner side template of the sound barrier foundation can be transmitted to the outer side template of the sound barrier foundation, and the structural design is very ingenious.
Drawings
Fig. 1 is a front view of the present invention.
Fig. 2 is a left side view of fig. 1.
Fig. 3 is a top view of fig. 1.
Detailed Description
The invention will be further illustrated by the following examples in conjunction with the accompanying drawings:
referring to fig. 1 to 3, the sound barrier foundation and box girder integrated pouring template mainly comprises a sound barrier foundation outer side template 1, a sound barrier foundation inner side template 2 and an n-shaped connecting member 3.
The outer side template 1 of the sound barrier foundation is formed by integrally extending and heightening the outer side template of the box girder upwards, the inner side template 2 of the sound barrier foundation adopts a rectangular steel plate with the same length as the outer side template 1 of the sound barrier foundation, and the inner side template 2 of the sound barrier foundation is arranged in parallel with the outer side template 1 of the sound barrier foundation. The sound barrier foundation outer side template 1 is connected with the sound barrier foundation inner side template 2 through a plurality of n-shaped connecting members 3 arranged along the length direction at equal intervals.
Pi type connecting elements 3 is formed by two relative strip angle steel 3a that set up through the top surface coincide after combining bolt 3b concatenation. The vertical surface of one strip-shaped angle steel 3a is welded with the outer vertical surface of the outer side template 1 of the sound barrier foundation, and the vertical surface of the other strip-shaped angle steel 3a is welded with the outer vertical surface of the inner side template 2 of the sound barrier foundation. The n-shaped connecting members 3 can be connected with the corresponding sections of the sound barrier foundation formwork into a whole, and can also leave sufficient construction space for installing the sound barrier foundation embedded parts and pouring and vibrating the sound barrier foundation concrete, so that the concrete pouring quality is ensured.
Preferably, the stiffening member 4 is welded on the inner side formwork 2 of the sound barrier foundation, the stiffening member 4 is a gusset plate with the same length as the inner side formwork 2 of the sound barrier foundation, the vertical face of the gusset plate is welded with the outer vertical face of the inner side formwork 2 of the sound barrier foundation, and the top of the gusset plate is welded with the bottom face of the strip-shaped angle steel 3a on the corresponding side.
In addition, the top surface of the bar angle steel 3a is provided with at least three bolt through holes 3c arranged along the inner and outer direction at equal intervals, and is not limited to three, preferably three to four. Each n-shaped connecting member 3 is formed by splicing at least two bolts 3b, so that the distance between the outer side template 1 of the sound barrier foundation and the inner side template 2 of the sound barrier foundation can be adjusted.
Preferably, the pi-shaped connecting members 3 are arranged one at an interval along the length direction 1 m-2 m, i.e. the pi-shaped connecting members 3 are arranged one at a distance of 1 m-2 m along the bridge direction.

Claims (4)

1. The utility model provides a template is pour with box girder integration to sound barrier basis which characterized in that: including sound barrier basis outside template (1) and sound barrier basis inboard template (2), sound barrier basis outside template (1) is formed by the whole increase that upwards extends of case roof beam outside template, and sound barrier basis inboard template (2) adopt the rectangle steel sheet isometric with sound barrier basis outside template (1), and sound barrier basis inboard template (2) and sound barrier basis outside template (1) parallel arrangement, sound barrier basis outside template (1) and sound barrier basis inboard template (2) are linked to each other by a plurality of II type connecting elements (3) of setting along length direction equidistance interval, II type connecting elements (3) are formed by splicing bolt (3b) after top surface coincide by two bar angle steel (3a) of relative setting, and wherein the facade of a bar angle steel (3a) welds with the facade of sound barrier basis outside template (1), the vertical surface of the other strip angle steel (3a) is welded with the outer vertical surface of the inner side template (2) of the sound barrier foundation.
2. The sound barrier foundation and box girder integrated pouring template according to claim 1, characterized in that: the welding has stiffening member (4) on the inboard template of sound barrier basis (2), stiffening member (4) adopt the angle steel board isometric with the inboard template of sound barrier basis (2), and the facade of this angle steel board welds with the outer facade of the inboard template of sound barrier basis (2), and the top of this angle steel board welds with the bottom surface of the bar angle steel (3a) of corresponding side simultaneously.
3. The sound barrier foundation and box girder integrated pouring template according to claim 1, characterized in that: the top surface of bar angle steel (3a) is provided with at least three bolt via hole (3c) that the equidistance interval set up along inside and outside direction, and every II type connecting elements (3) are formed by at least two bolts (3b) concatenation to realize the adjustable installation of sound barrier basis outside template (1) and sound barrier basis inside template (2) interval.
4. The sound barrier foundation and box girder integrated pouring template according to any one of claims 1 to 3, wherein: the n-shaped connecting members (3) are arranged at intervals along the length direction of 1 m-2 m.
CN201910793725.3A 2019-08-27 2019-08-27 Sound barrier basis and case roof beam integration template of pouring Active CN110565529B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910793725.3A CN110565529B (en) 2019-08-27 2019-08-27 Sound barrier basis and case roof beam integration template of pouring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910793725.3A CN110565529B (en) 2019-08-27 2019-08-27 Sound barrier basis and case roof beam integration template of pouring

Publications (2)

Publication Number Publication Date
CN110565529A CN110565529A (en) 2019-12-13
CN110565529B true CN110565529B (en) 2021-05-14

Family

ID=68776209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910793725.3A Active CN110565529B (en) 2019-08-27 2019-08-27 Sound barrier basis and case roof beam integration template of pouring

Country Status (1)

Country Link
CN (1) CN110565529B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113373808B (en) * 2021-06-10 2023-03-21 中铁隧道局集团建设有限公司 Steel guardrail base and bridge deck integrated prefabricated slab, prefabricated formwork and construction method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200361190Y1 (en) * 2004-06-23 2004-09-07 김길평 Soundproofing wall for bridge
CN2773156Y (en) * 2005-04-13 2006-04-19 路俊生 Integrated template of cast-in-situs concrete barrier for bridge
CN201176570Y (en) * 2008-03-21 2009-01-07 东南大学 Acoustical barrier for elevated bridge
CN102286915A (en) * 2011-08-30 2011-12-21 北京城建设计研究总院有限责任公司 Urban railway traffic continuous basin type beam
CN105755958A (en) * 2016-03-03 2016-07-13 中铁二十局集团第四工程有限公司 Special bracket for construction of whole bilateral post-poured flange plate and application method thereof
CN206591420U (en) * 2016-12-07 2017-10-27 中铁第四勘察设计院集团有限公司 Driving totally enclosed type box beam in railway box
CN108005376A (en) * 2017-11-28 2018-05-08 天津市鑫福盛新型建筑模板有限公司 Special fastening connector is used in a kind of New Type Architecture Mode support
CN207988406U (en) * 2018-01-20 2018-10-19 金粤幕墙装饰工程有限公司 A kind of Side fascia connector
CN108894133A (en) * 2018-07-13 2018-11-27 曾福英 A kind of municipal administration bridge sound insulation board mounting structure
KR20180127838A (en) * 2017-05-22 2018-11-30 민정미 Negative reaction control and displacement absorb device for noise barrier of bridges, girder using the same and construction method thereof
CN109736211A (en) * 2019-03-08 2019-05-10 中铁十九局集团第三工程有限公司 The one-piece casting template and erection method of T-type beam side walk slab and sound barrier pedestal
CN110158479A (en) * 2019-05-31 2019-08-23 陕西路桥集团有限公司 A kind of arc bracket gang form and its erection method for cast-in-situ box girder

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2653459B1 (en) * 1989-10-24 1992-01-17 Muller International Jean STATION ON A RAILWAY LINE OR OTHER LOCATED ON A VIADUCT.
AT408552B (en) * 1998-05-12 2002-01-25 Brunbauer Wolfgang Dipl Ing NOISE CONTROL DEVICE
CN201065644Y (en) * 2007-07-10 2008-05-28 宏润建设集团股份有限公司 Anti-collision wall formwork without supporting bracket
DE102011051342A1 (en) * 2011-04-11 2012-10-11 Ed. Züblin Ag Sound insulation wall installed at e.g. road, has post cap comprising molded tabs that are engaged at upper edge of the soundproofing elements
US20150376848A1 (en) * 2014-06-27 2015-12-31 M.H. Corbin, Inc. Sound Arresting Barrier Having A Spacer Bracket
CN206635662U (en) * 2017-04-07 2017-11-14 天津九为实业有限公司 A kind of cast-in-place concrete bridge flange plate mould plate supporting device
CN206987120U (en) * 2017-08-01 2018-02-09 汪风珍 A kind of integral wall form
CN109537459A (en) * 2018-11-29 2019-03-29 中铁四局集团第二工程有限公司 Cast-in-place box girder oblique web formwork integrated construction method
CN110164409A (en) * 2019-06-14 2019-08-23 苏州中车建设工程有限公司 Easy-to-detach protective sleeve of silencing module, array type silencer and mounting and dismounting method

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200361190Y1 (en) * 2004-06-23 2004-09-07 김길평 Soundproofing wall for bridge
CN2773156Y (en) * 2005-04-13 2006-04-19 路俊生 Integrated template of cast-in-situs concrete barrier for bridge
CN201176570Y (en) * 2008-03-21 2009-01-07 东南大学 Acoustical barrier for elevated bridge
CN102286915A (en) * 2011-08-30 2011-12-21 北京城建设计研究总院有限责任公司 Urban railway traffic continuous basin type beam
CN105755958A (en) * 2016-03-03 2016-07-13 中铁二十局集团第四工程有限公司 Special bracket for construction of whole bilateral post-poured flange plate and application method thereof
CN206591420U (en) * 2016-12-07 2017-10-27 中铁第四勘察设计院集团有限公司 Driving totally enclosed type box beam in railway box
KR20180127838A (en) * 2017-05-22 2018-11-30 민정미 Negative reaction control and displacement absorb device for noise barrier of bridges, girder using the same and construction method thereof
CN108005376A (en) * 2017-11-28 2018-05-08 天津市鑫福盛新型建筑模板有限公司 Special fastening connector is used in a kind of New Type Architecture Mode support
CN207988406U (en) * 2018-01-20 2018-10-19 金粤幕墙装饰工程有限公司 A kind of Side fascia connector
CN108894133A (en) * 2018-07-13 2018-11-27 曾福英 A kind of municipal administration bridge sound insulation board mounting structure
CN109736211A (en) * 2019-03-08 2019-05-10 中铁十九局集团第三工程有限公司 The one-piece casting template and erection method of T-type beam side walk slab and sound barrier pedestal
CN110158479A (en) * 2019-05-31 2019-08-23 陕西路桥集团有限公司 A kind of arc bracket gang form and its erection method for cast-in-situ box girder

Also Published As

Publication number Publication date
CN110565529A (en) 2019-12-13

Similar Documents

Publication Publication Date Title
CN107245934A (en) A kind of assembled steel profiled sheet concrete combined board small box girder
CN202131559U (en) Corrugated steel web plate prestressed concrete continuous box girder
CN102220739A (en) Corrugated steel web prestressed concrete continuous box girder and construction method thereof
CN102653931B (en) Elastic supporting vibration isolation member ballast bed
CN101280547A (en) Corrugated steel web box girder with steel-concrete combined board lower wing edges
CN104088221B (en) A kind of T-shaped plate girder precast segment unit based on steel truss and combined bridge deck
CN108222347A (en) A kind of big module welding overlapping beam slab of the assembled with plane girder temporary support
CN209854553U (en) Assembled concrete anticollision barrier based on ultrahigh performance concrete is connected
CN105484151A (en) Structure for enhancing connection among prefabricated concrete segments and construction method thereof
CN103711067A (en) Transversely assembled corrugated steel web combined box girder with small number of supports and construction method thereof
CN108301545A (en) A kind of big module overlapping contignation of the assembled with space truss temporary support
CN110565529B (en) Sound barrier basis and case roof beam integration template of pouring
CN204059179U (en) A kind of T-shaped plate girder precast segment unit based on steel truss and combined bridge deck
CN112281663B (en) Construction method for widening connection of upper structures of new and old bridges
CN202099699U (en) Elastic supporting vibration isolation component ballast bed
CN211735002U (en) Steel-concrete combined beam bridge capable of being installed quickly
CN202007380U (en) Prestressed concrete I beam of wave-shaped steel web plate
CN103669193B (en) A kind of laterally assembled Wavelike steel webplate combination T beam and construction method
CN211420740U (en) Track is assembled to well low-speed magnetic levitation girder steel
CN203795293U (en) Transverse-assembly corrugated steel web combination box beam with few supports
CN211947965U (en) Cast-in-situ continuous box girder internal mold
CN110965406B (en) Middle-low speed magnetic levitation steel beam spliced track
CN203583343U (en) Support type frame bridge
CN112458878A (en) Segmental assembling steel-concrete combined continuous beam and construction method thereof
CN106381927A (en) Steel beam structure capable of being replaced due to earthquake damage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 214104 room 301-218, block a, Xidong chuangrong building, No. 78, Danshan Road, anzhen street, Xishan District, Wuxi City, Jiangsu Province

Patentee after: Jiangsu CRRC Urban Development Co.,Ltd.

Patentee after: CRRC CONSTRUCTION ENGINEERING Co.,Ltd.

Address before: 215000 NO.115 Yinsheng Road, Shengpu Town, Suzhou Industrial Park, Jiangsu Province

Patentee before: SUZHOU CHINA VEHICLE CONSTRUCTION ENGINEERING Co.,Ltd.

Patentee before: CRRC CONSTRUCTION ENGINEERING Co.,Ltd.