CN110552499A - Transversely pre-buried fixed creeping formwork support body auxiliary stay structure - Google Patents

Transversely pre-buried fixed creeping formwork support body auxiliary stay structure Download PDF

Info

Publication number
CN110552499A
CN110552499A CN201910822363.6A CN201910822363A CN110552499A CN 110552499 A CN110552499 A CN 110552499A CN 201910822363 A CN201910822363 A CN 201910822363A CN 110552499 A CN110552499 A CN 110552499A
Authority
CN
China
Prior art keywords
plate
steel column
auxiliary supporting
bolt
seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910822363.6A
Other languages
Chinese (zh)
Inventor
任海波
焦惟
庞天舒
李桐
李海生
蒋逸霄
李冬冬
张海峰
刘福生
苏贝
杨剑伯
孟磊
张惠茹
金维
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Building Construction Research Institute Co Ltd
Original Assignee
Beijing Building Construction Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Building Construction Research Institute Co Ltd filed Critical Beijing Building Construction Research Institute Co Ltd
Priority to CN201910822363.6A priority Critical patent/CN110552499A/en
Publication of CN110552499A publication Critical patent/CN110552499A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model provides a fixed creeping formwork support body auxiliary stay structure of horizontal pre-buried, includes auxiliary stay steel column, connecting seat, pre-buried bolt, adjusting bolt, U type bolt, layer height control seat, variable cross section backing plate, attaches the wall seat. The auxiliary supporting steel column and the connecting seat are fixedly connected with the core barrel structural beam through the embedded bolts, the auxiliary supporting steel column is connected with the connecting seat through the U-shaped bolts, the adjusting bolts are used for adjusting the gap between the auxiliary supporting steel column and the connecting seat and the installation and construction errors, the layer height adjusting seat is used for heightening the auxiliary supporting steel column when the layer height changes, and the variable cross-section base plate is installed between the connecting plate of the auxiliary supporting steel column and the beam when the beam thickness and the position change. The beneficial effect of this patent is: the wall attaching device can solve the problem of installation of a wall attaching device when meeting an opening in hydraulic creeping formwork construction, is adaptive to layer height, beam thickness and position change, is simple in structure, convenient and fast, can be repeatedly utilized and saves construction cost, and the structural design of a prokaryotic core barrel is not changed in construction.

Description

Transversely pre-buried fixed creeping formwork support body auxiliary stay structure
Technical Field
The invention relates to the field of constructional engineering, in particular to an auxiliary supporting structure for a core tube structural beam in a hydraulic creeping formwork construction process.
Background
Along with the needs of social development and people's life, land resources are limited, people are large in population, usable area is small and the like, super high-rise buildings are more and more appeared in modern buildings, and hydraulic climbing formwork technology is generally adopted in super high-rise construction. The hydraulic climbing formwork frame body is used for penetrating a fixing bolt of the frame body wall-attaching device through a pre-buried hole in a structural wall body. Holes are often distributed on the combination surface of the core barrel design and the creeping formwork frame body of the building body, and some holes can not be avoided according to comprehensive consideration of construction.
for the hole which cannot be avoided, the concrete support column is poured at the hole, and the concrete support column is removed after construction. The method firstly requires the consent of a design unit, secondly consumes a large amount of manpower and material resources in the construction process, has poor economy, generates more construction waste and has great influence on the environment.
Disclosure of Invention
In order to solve the problem, this patent has proposed a fixed creeping formwork support body auxiliary stay structure of horizontal pre-buried, adopts the steel structural support, and the installation is simple swift to but reuse. The method does not change the main structure design of the building body, meets the construction requirement, is economical and efficient, and saves the construction cost.
The purpose of this patent is so realized:
The utility model provides a fixed creeping formwork support body auxiliary stay structure of horizontal pre-buried, includes auxiliary stay steel column, connecting seat, pre-buried bolt, adjusting bolt, U type bolt, layer height control seat, variable cross section backing plate, attaches the wall seat.
The auxiliary supporting steel column and the connecting seat are connected to the core barrel structural beam through the embedded bolt;
The auxiliary supporting steel column is connected with the floor height adjusting seat into a whole through standard parts such as bolts, nuts, gaskets and the like, and is connected with the connecting seat through a U-shaped bolt;
The gap between the auxiliary support steel column and the connecting seat is adjusted through an adjusting bolt;
A bolt hole is reserved at a designated position of the core tube structural beam in the transverse direction, and a pre-buried bolt horizontally penetrates in the installation process;
The main structure of the auxiliary supporting steel column is formed by welding two channel steel back-to-back middle connection channel steel and welding a top plate at the top. The front top of the auxiliary support steel column is welded with a connecting plate of embedded bolts, the connecting plate is provided with holes, the number of the holes is determined according to the number of the embedded bolts, and the connecting plate is welded with a wall attaching seat of the creeping formwork support body. The auxiliary supporting steel column bottom plate is provided with a connecting hole for connecting the layer height adjusting seat;
The lower part of the auxiliary support steel column is provided with a support plate for supporting the top wall supporting leg of the creeping formwork frame body, a channel steel at the position of the support plate is welded with a rib plate, and the support plate and the channel steel rib plate are welded with a reinforcing rib plate, so that the strength of the support plate is enhanced, and the top wall supporting leg of the creeping formwork frame body is prevented from deforming;
The front end of the connecting seat is welded with a connecting plate of the embedded bolt, the connecting plate is provided with holes, and the number of the holes is determined according to the number of the embedded bolts; the connecting seat is provided with a bearing plate in the horizontal direction and the vertical direction, the bearing plate is provided with a through hole with the diameter larger than that of the adjusting bolt, and the position of the through hole is welded with a nut matched with the adjusting bolt. The vertical bearing plate of the connecting seat is provided with a hole for fixing the U-shaped bolt;
The layer height adjusting seat is formed by welding two channel steel back-to-back in the middle, welding top plates at two ends, and a connecting hole for connecting an auxiliary supporting steel column is formed in one top plate.
The end part of the bolt of the adjusting bolt is propped against the bottom plate of the auxiliary support steel column or the top plate of the floor height adjusting seat, the bolt rod is screwed on the nut of the force bearing plate of the connecting seat, and the structural error of the core barrel and the installation error of the auxiliary support structure are eliminated through the adjusting bolt;
The variable cross-section base plate is of a frame structure formed by buckling, welding and assembling channel steel, holes for penetrating embedded bolts are formed in the variable cross-section base plate, and the variable cross-section base plate is used for being installed between a connecting plate of the embedded bolts of the auxiliary supporting steel column and the core tube structure beam when the wall thickness changes.
The beneficial part of this patent is can satisfy the requirement to attaching the wall device under meeting the entrance to a cave condition in the hydraulic pressure creeping formwork construction, installation in service problem when solution layer height, roof beam thickness and position change that moreover can be fine, simple structure, the construction does not change prokaryotic core section of thick bamboo structural design, convenient and fast, but reuse.
Drawings
the patent is further described with reference to the figures and examples.
Fig. 1 is a schematic view of an embodiment of the present patent.
in the figure: 1-auxiliary supporting steel columns; 2-a connecting seat; 3, embedding bolts; 4-adjusting the bolt; 5-U-shaped bolt; 6-layer height adjusting seat; 7-a variable cross-section base plate; 8-attaching a wall base.
FIG. 2 is a front and left side view of the auxiliary support steel column;
FIG. 3 is a cross-sectional view of the support plate for the support of the legs of the top wall of the steel column;
FIG. 4 is a front and left side view of the connecting socket;
FIG. 5 is a schematic view of a floor height adjusting seat
FIG. 6 is a schematic view of a variable cross-section shim plate
Detailed Description
referring to fig. 1, an auxiliary support structure of a climbing formwork frame body which is transversely pre-embedded and fixed comprises an auxiliary support steel column 1, a connecting seat 2, pre-embedded bolts 3, adjusting bolts 4, U-shaped bolts 5, a layer height adjusting seat 6, a variable cross-section base plate 7 and an attached wall seat 8; the auxiliary supporting steel column 1 and the connecting seat 2 are connected to the core tube structural beam through 2 embedded bolts 3 respectively at the upper part and the lower part; the auxiliary supporting steel column 1 is fixedly connected with the connecting seat 2 through a U-shaped bolt 5; the gap between the auxiliary support steel column 1 and the connecting seat 2 is adjusted through the adjusting bolt 4, and installation errors and construction errors of the core tube structure beam are eliminated.
See fig. 1, reserve the bolt hole in the horizontal direction assigned position department of core section of thick bamboo structure roof beam, embedded bolt 3 level penetrates, fixed auxiliary stay steel column 1 and connecting seat 2.
See fig. 1, the core barrel layer height changes, uses layer height to adjust seat 6, and connecting hole on the roof of layer height adjustment seat 6 passes through bolted connection with connecting hole on the 1 bottom plate of auxiliary stay steel column, and at this moment, U type bolt 5 is fixed on layer height adjustment seat 6, with 4 bolt tip tops of adjusting bolt on layer height adjustment seat 6 roof, under the normal conditions, 4 bolt tip tops of adjusting bolt are on 1 bottom plate of auxiliary stay steel column, and the shank of bolt is twisted on the nut of 2 bearing plates of connecting seat.
Referring to fig. 2, the main structure of the auxiliary support steel column 1 is formed by welding two channel steel back-to-back middle connection channel steel and welding a top plate at the top. The connecting plate of the embedded bolt 3 is welded at the top end in front of the auxiliary support steel column 1, two holes are formed in the horizontal direction of the connecting plate, and a wall attaching seat 8 of the creeping formwork support body is welded on the connecting plate. And a connecting hole for connecting the layer height adjusting seat 6 is formed in the bottom plate of the auxiliary supporting steel column 1. The lower part of the auxiliary supporting steel column 1 is provided with a supporting plate for supporting the top wall supporting leg of the climbing formwork frame body.
According to the drawing 3, the channel steel of the supporting plate position of the auxiliary supporting steel column 1 is welded with the rib plates, and the reinforcing rib plates are welded at the supporting plate and the channel steel rib plates, so that the strength of the supporting plate is enhanced, and the top wall supporting leg of the creeping formwork support body is prevented from deforming.
See fig. 4, the connecting plate of the embedded bolt 3 is welded at the front end of the connecting seat 2, and the connecting plate is provided with a hole. The connecting seat 2 is provided with a bearing plate in the horizontal direction and the vertical direction, the bearing plate is respectively provided with 2 round holes, the diameter of each round hole is larger than the diameter of the adjusting bolt 4, and the hole positions are welded with nuts matched with the adjusting bolts 4. The vertical bearing plate of the connecting seat 2 is provided with a hole for fixing the U-shaped bolt 5.
Referring to fig. 5, the layer height adjusting seat 6 is formed by welding two channel steel back-to-back middle connecting channel steel, and two ends of the channel steel are welded with a top plate, wherein a connecting hole for connecting with the auxiliary supporting steel column 1 is formed in the top plate at one end.
Referring to fig. 6, the variable cross-section base plate 7 is a frame structure formed by welding and splicing 8 equal-length channel steels in a pairwise buckling manner, holes for penetrating the embedded bolts 3 are formed in the variable cross-section base plate, and the variable cross-section base plate is installed between a connecting plate of the auxiliary support steel column 1 and a core tube structure beam when the thickness or the position of the beam changes.
Referring to fig. 2-6, the connecting holes are all oblong holes, which is convenient for installation and position adjustment.
The above-mentioned embodiments are only for describing the preferred embodiments of the patent, and do not limit the scope of the patent, and various changes and modifications of the technical solution of the patent made by those skilled in the art without departing from the design idea of the patent should fall within the protection scope defined by the claims of the patent.

Claims (9)

1. a transverse pre-buried fixed creeping formwork support body auxiliary supporting structure comprises an auxiliary supporting steel column (1), a connecting seat (2), pre-buried bolts (3), adjusting bolts (4), U-shaped bolts (5), a layer height adjusting seat (6), a variable cross-section base plate (7) and a wall attaching seat (8); the method is characterized in that: the auxiliary support steel column (1) and the connecting seat (2) are connected to the core tube structural beam through the embedded bolt (3); the auxiliary supporting steel column (1) is connected with the floor height adjusting seat (6) into a whole through standard parts such as bolts, nuts, gaskets and the like, and is connected with the connecting seat (2) through a U-shaped bolt (5); the gap between the auxiliary support steel column (1) and the connecting seat (2) is adjusted through an adjusting bolt (4), and the variable cross-section base plate (7) is installed between a connecting plate of an embedded bolt (3) of the auxiliary support steel column (1) and the core tube structure beam.
2. The transverse embedded and fixed creeping formwork support body auxiliary supporting structure of claim 1, characterized in that: the main structure of the auxiliary supporting steel column (1) is formed by welding two channel steel back-to-back middle connection channel steel and welding a top plate at the top.
3. The transverse embedded and fixed creeping formwork support body auxiliary supporting structure of claim 1, characterized in that: the top end of the front surface of the auxiliary support steel column (1) is welded with a connecting plate of the embedded bolt (3), and the connecting plate is provided with a hole; the embedded bolt (3) is fixedly connected with the connecting plate of the auxiliary support steel column (1) in the horizontal direction; and an attached wall base (8) of the creeping formwork frame body is welded on the connecting plate, and a connecting hole for connecting the layer height adjusting base (6) is arranged on the bottom panel of the auxiliary supporting steel column (1).
4. The transverse embedded and fixed creeping formwork support body auxiliary supporting structure of claim 1, characterized in that: the lower part of the auxiliary support steel column (1) is provided with a support plate for supporting a top wall supporting leg of the creeping formwork support body, a channel steel welding rib plate is arranged at the position of the support plate, and a reinforcing rib plate is welded at the position of the support plate and the channel steel rib plate.
5. The transverse embedded and fixed creeping formwork support body auxiliary supporting structure of claim 1, characterized in that: the front end of the connecting seat (2) is welded with a connecting plate of the embedded bolt (3), and the connecting plate is provided with a hole.
6. The transverse embedded and fixed creeping formwork support body auxiliary supporting structure of claim 1, characterized in that: the connecting seat (2) is provided with a bearing plate in the horizontal direction and the vertical direction, a through hole with the diameter larger than that of the adjusting bolt (4) is arranged on the bearing plate, a nut matched with the adjusting bolt (4) is welded at the position of the through hole, and a hole for fixing the U-shaped bolt (5) is arranged on the vertical bearing plate.
7. The transverse embedded and fixed creeping formwork support body auxiliary supporting structure of claim 1, characterized in that: the layer height adjusting seat (6) is formed by welding two channel steel back-to-back middle connecting channel steel, two ends of the layer height adjusting seat are welded with a top plate, and a connecting hole for connecting with the auxiliary supporting steel column (1) is formed in one end of the top plate.
8. The transverse embedded and fixed creeping formwork support body auxiliary supporting structure of claim 1, characterized in that: the end part of the bolt of the adjusting bolt (4) is propped against the bottom plate of the auxiliary supporting steel column (1) or the top plate of the layer height adjusting seat (6), and the bolt rod is connected with the nut on the bearing plate of the connecting seat (2) in a matching way.
9. the transverse embedded and fixed creeping formwork support body auxiliary supporting structure of claim 1, characterized in that: the variable cross-section base plate (7) is a channel steel butt-joint, a frame structure is formed by welding and assembling, and holes for penetrating the embedded bolts (3) are formed in the variable cross-section base plate.
CN201910822363.6A 2019-09-02 2019-09-02 Transversely pre-buried fixed creeping formwork support body auxiliary stay structure Pending CN110552499A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910822363.6A CN110552499A (en) 2019-09-02 2019-09-02 Transversely pre-buried fixed creeping formwork support body auxiliary stay structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910822363.6A CN110552499A (en) 2019-09-02 2019-09-02 Transversely pre-buried fixed creeping formwork support body auxiliary stay structure

Publications (1)

Publication Number Publication Date
CN110552499A true CN110552499A (en) 2019-12-10

Family

ID=68738812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910822363.6A Pending CN110552499A (en) 2019-09-02 2019-09-02 Transversely pre-buried fixed creeping formwork support body auxiliary stay structure

Country Status (1)

Country Link
CN (1) CN110552499A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111350346A (en) * 2020-03-23 2020-06-30 北京市建筑工程研究院有限责任公司 Creeping formwork attachment device for doubly-linked beam
CN111364756A (en) * 2020-03-23 2020-07-03 北京市建筑工程研究院有限责任公司 Support type creeping formwork adhesion device
CN115467506A (en) * 2022-09-05 2022-12-13 中国建筑第八工程局有限公司 Variable cross-section backing plate and creeping formwork support body

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1091433A (en) * 1964-07-17 1967-11-15 Mills Scaffold Co Ltd Improved adjustable yoke for use in sliding formwork
JP2008150778A (en) * 2006-12-14 2008-07-03 Tohoku Regional Bureau Ministry Of Land Infrastructure & Transport Anchor bolt and traveling type form construction method by use of this anchor bolt
CN103967277A (en) * 2014-05-21 2014-08-06 中国建筑第八工程局有限公司 Construction method of super-high-rise core tube inclined shear wall
CN104164968A (en) * 2013-08-20 2014-11-26 北京市建筑工程研究院有限责任公司 Novel shiftable through-wall (or embedded) type double-point adhering device
CN205088950U (en) * 2015-09-29 2016-03-16 中国建筑第八工程局有限公司 Instrument formula creeping formwork anchorage device
CN107268987A (en) * 2017-06-30 2017-10-20 上海建工集团股份有限公司 Across formula adjustable climb seat in the plane reaction frame and its construction method
CN207277828U (en) * 2017-08-31 2018-04-27 中国建筑第八工程局有限公司 Nonstandard interlayer is used for the attaching structure that climbs of creeping formwork frame body
CN207620365U (en) * 2017-10-18 2018-07-17 中国建筑第八工程局有限公司 Temporary support structure
CN109025259A (en) * 2018-09-19 2018-12-18 中建三局第二建设工程有限责任公司 One kind can turnover type hydraulic climbing formwork wall-attaching equipment
CN109162447A (en) * 2018-10-11 2019-01-08 上海建工建集团有限公司 Steel platform of climbing support device and its application method
CN211499776U (en) * 2019-09-02 2020-09-15 北京市建筑工程研究院有限责任公司 Transversely pre-buried fixed creeping formwork support body auxiliary stay structure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1091433A (en) * 1964-07-17 1967-11-15 Mills Scaffold Co Ltd Improved adjustable yoke for use in sliding formwork
JP2008150778A (en) * 2006-12-14 2008-07-03 Tohoku Regional Bureau Ministry Of Land Infrastructure & Transport Anchor bolt and traveling type form construction method by use of this anchor bolt
CN104164968A (en) * 2013-08-20 2014-11-26 北京市建筑工程研究院有限责任公司 Novel shiftable through-wall (or embedded) type double-point adhering device
CN103967277A (en) * 2014-05-21 2014-08-06 中国建筑第八工程局有限公司 Construction method of super-high-rise core tube inclined shear wall
CN205088950U (en) * 2015-09-29 2016-03-16 中国建筑第八工程局有限公司 Instrument formula creeping formwork anchorage device
CN107268987A (en) * 2017-06-30 2017-10-20 上海建工集团股份有限公司 Across formula adjustable climb seat in the plane reaction frame and its construction method
CN207277828U (en) * 2017-08-31 2018-04-27 中国建筑第八工程局有限公司 Nonstandard interlayer is used for the attaching structure that climbs of creeping formwork frame body
CN207620365U (en) * 2017-10-18 2018-07-17 中国建筑第八工程局有限公司 Temporary support structure
CN109025259A (en) * 2018-09-19 2018-12-18 中建三局第二建设工程有限责任公司 One kind can turnover type hydraulic climbing formwork wall-attaching equipment
CN109162447A (en) * 2018-10-11 2019-01-08 上海建工建集团有限公司 Steel platform of climbing support device and its application method
CN211499776U (en) * 2019-09-02 2020-09-15 北京市建筑工程研究院有限责任公司 Transversely pre-buried fixed creeping formwork support body auxiliary stay structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111350346A (en) * 2020-03-23 2020-06-30 北京市建筑工程研究院有限责任公司 Creeping formwork attachment device for doubly-linked beam
CN111364756A (en) * 2020-03-23 2020-07-03 北京市建筑工程研究院有限责任公司 Support type creeping formwork adhesion device
CN115467506A (en) * 2022-09-05 2022-12-13 中国建筑第八工程局有限公司 Variable cross-section backing plate and creeping formwork support body

Similar Documents

Publication Publication Date Title
CN110552499A (en) Transversely pre-buried fixed creeping formwork support body auxiliary stay structure
CN111206675B (en) Steel structure corridor structure and hoisting construction method
CN107313540B (en) Fireproof and buckling-restrained fabricated composite beam and construction method
CN108894430B (en) Construction method for reinforcing steel structure beam or column
CN111335466A (en) Fabricated concrete self-resetting beam-column joint connecting structure and assembling method
CN211499776U (en) Transversely pre-buried fixed creeping formwork support body auxiliary stay structure
CN209942050U (en) Adjustable interim reinforcing bar split heads that can have enough to meet need of high strength for big cross-section roof beam
CN107313508B (en) Prefabricated assembly type main and secondary beam installation structure and installation method
CN212376021U (en) Steel corbel and support-free installation connecting node comprising same
CN212129455U (en) Self-resetting node connecting structure for beam column of assembled concrete frame
CN211499775U (en) Vertical pre-buried fixed creeping formwork support body auxiliary stay structure
CN212078674U (en) Creeping formwork attachment device for doubly-linked beam
CN212026596U (en) Hinged connection node of H-shaped steel beam and shear wall built-in cross-shaped steel column
CN212129456U (en) Assembled concrete is from restoring to throne beam column node connection structure
CN214783307U (en) Cast-in-place support of case roof beam
CN211621988U (en) Wall type shear damper embedded part
CN203113908U (en) Full assembly structure with enclosing wall and advertising board integrated
CN113279565A (en) Tool type supporting structure for reinforcing ultra-thick inner wall and construction method
CN207597580U (en) A kind of Steel corridor
CN110552498A (en) Vertical pre-buried fixed creeping formwork support body auxiliary stay structure
CN217352582U (en) Tower machine basis auxiliary stay device
CN219826270U (en) Additional reinforcing device for existing steel beam
CN212376020U (en) Steel corbel and support-free installation connecting node comprising same
CN210127036U (en) Adduction building tower crane attachment device
CN218757991U (en) Connecting structure of precast beam and precast column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination