CN110528770A - A kind of blue bricks furred ceiling base layer structure and its construction method - Google Patents

A kind of blue bricks furred ceiling base layer structure and its construction method Download PDF

Info

Publication number
CN110528770A
CN110528770A CN201910902183.9A CN201910902183A CN110528770A CN 110528770 A CN110528770 A CN 110528770A CN 201910902183 A CN201910902183 A CN 201910902183A CN 110528770 A CN110528770 A CN 110528770A
Authority
CN
China
Prior art keywords
blue bricks
angle steel
furred ceiling
retarded
base layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910902183.9A
Other languages
Chinese (zh)
Inventor
车涛涛
袁学勇
王世鑫
徐学艇
陈令明
黄计想
赵飞
韩伟虎
陈汉伟
陈向峰
徐娜
梁猛
司博
刘聪
王淑婷
于洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Original Assignee
Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gold Mantis Fine Decoration Technology Suzhou Co Ltd filed Critical Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Priority to CN201910902183.9A priority Critical patent/CN110528770A/en
Publication of CN110528770A publication Critical patent/CN110528770A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/04Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/04Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like
    • E04B9/045Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like being laminated
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/22Connection of slabs, panels, sheets or the like to the supporting construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The invention discloses a kind of blue bricks furred ceiling base layer structures, it include: lateral long angle steel, lateral angle clip, vertical angle steel and multi-layer fire-retarded plate, the long angle steel of transverse direction is connect with described vertical angle steel one end, the vertical angle steel other end is connect with the lateral angle clip, the transverse direction angle clip is set to above the multi-layer fire-retarded plate, and the vertical angle steel and the multi-layer fire-retarded plate corner junction are equipped with and reinforce fastener;Base layer structure is stablized in this way, improves the construction efficiency of blue bricks furred ceiling, has saved a large amount of man power and material and has carried out antirust treatment, has effectively reduced construction cost.

Description

A kind of blue bricks furred ceiling base layer structure and its construction method
Technical field
The present invention relates to construction and decoration technical field of construction, and in particular to a kind of blue bricks furred ceiling base layer structure and its construction party Method.
Background technique
At present in building ceiling construction field, furred ceiling surface layer generallys use brushing gypsum emulsion paint way, such surface layer To the of less demanding of base, general lightgage steel joist, but while using blue bricks as furred ceiling surface layer, wants high to basic level requirement certainly Very much, it falls off if then may cause not secured enough the large area of base layer structure with general steel joist suspended ceiling, causes not drawing The loss returned.
It would therefore be highly desirable to the appearance of a kind of blue bricks furred ceiling base layer structure and its construction method, such base layer structure is stablized, and improves The efficiency of blue bricks furred ceiling has saved a large amount of man power and material and has carried out antirust treatment, effectively reduced construction cost.
Summary of the invention
In order to solve the above-mentioned technical problem, the invention proposes a kind of blue bricks furred ceiling base layer structure and its construction method, this Sample base layer structure is stablized, and the construction efficiency of blue bricks furred ceiling is improved, and has saved a large amount of man power and material and has carried out antirust treatment, has had Effect reduces construction cost.
In order to achieve the above object, technical scheme is as follows:
A kind of blue bricks furred ceiling base layer structure, comprising: laterally long angle steel, lateral angle clip, vertical angle steel and multi-layer fire-retarded plate, The long angle steel of transverse direction is connect with described vertical angle steel one end, and the vertical angle steel other end is connect with the lateral angle clip, The transverse direction angle clip is set to above the multi-layer fire-retarded plate, the vertical angle steel and the multi-layer fire-retarded plate corner junction Equipped with reinforcing fastener.
A kind of blue bricks furred ceiling base layer structure provided by the invention and its construction method, base layer structure are stablized, and blue bricks is improved The construction efficiency of furred ceiling has saved a large amount of man power and material and has carried out antirust treatment, effectively reduced construction cost.
Based on the above technical solution, following improvement can also be done:
As a preferred option, the long angle steel of the transverse direction, the lateral angle clip and the vertical angle steel interconnection group At dies.
As a preferred option, the reinforcing fastener is L-shaped.
As a preferred option, blue bricks furred ceiling base layer structure, comprising: dry hanging article and fixing piece, the upper end of the dry hanging article It is connect by the fixing piece with the lateral angle clip.
As a preferred option, blue bricks furred ceiling base layer structure, comprising: the lower end of stabilization and reinforcement fastener, the dry hanging article is logical The stabilization and reinforcement fastener is crossed to connect with the multi-layer fire-retarded plate.
As a preferred option, blue bricks furred ceiling base layer structure, comprising: blue bricks, the blue bricks are connected by structure glue In on the multi-layer fire-retarded plate.
As a preferred option, the multi-layer fire-retarded plate includes: that multi-layer fire-retarded plate right angle short side, multi-layer fire-retarded plate right angle are long Side and multi-layer fire-retarded plate bevel edge, the multi-layer fire-retarded plate right angle short side, the multi-layer fire-retarded plate right angle long side and multilayer resistance It fires plate bevel edge and is connected with each other composition triangular structure of right angle.
As a preferred option, the multi-layer fire-retarded plate right angle long side extends simultaneously along the longitudinal direction of the vertical angle steel With the vertical Bolted angle connection.
As a preferred option, the multi-layer fire-retarded plate right angle short side prolongs along the opposite direction of multi-layer fire-retarded plate bevel edge It stretches.
As a preferred option, a kind of blue bricks furred ceiling base layer structure construction method, comprising the following steps:
1) according to design drawing, check that facade flatness determines keel and wall cylindrical surface drilling point in top surface surveying setting-out Position;
2) vertical angle steel is fixed on the lateral long angle steel in top by connection fixture, the spacing of vertical angle steel is according to existing The size of field blue bricks typesetting determines;
3) vertical angle steel is equipped with reinforcing fastener with multi-layer fire-retarded plate corner junction and is reinforced, and the upper end of dry hanging article passes through Fixing piece is connect with lateral angle clip, and the lower end of dry hanging article is connect by stabilization and reinforcement fastener with multi-layer fire-retarded plate;
4) it checks whether each components of blue bricks furred ceiling base layer structure connect fastening, is used on multi-layer fire-retarded plate basal plate Structure glue blue bricks.
Detailed description of the invention
Fig. 1 is a kind of structure chart of blue bricks furred ceiling base layer structure provided in an embodiment of the present invention;
Wherein: 1. dry hanging articles, 2. reinforce fasteners, 3. lateral long angle steel, 4. fixing pieces, 5. lateral angle clips, 6. stablize plus Gu fastener, 7. vertical angle steel, 8. multi-layer fire-retarded plates, 9. multi-layer fire-retarded plate right angle short sides, 10. multi-layer fire-retarded plate right angle long sides, 11. Multi-layer fire-retarded plate bevel edge.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without creative efforts belongs to the model that the present invention protects It encloses.
The preferred embodiment that the invention will now be described in detail with reference to the accompanying drawings.
In order to reach the purpose of the present invention, as shown in Figure 1, the blue bricks furred ceiling base layer structure in the present embodiment, comprising: laterally Long angle steel 3, lateral angle clip 5, vertical angle steel 7 and multi-layer fire-retarded plate 8, the long angle steel 3 of transverse direction and described vertical 7 one end of angle steel Connection, vertical 7 other end of angle steel are connect with the lateral angle clip 5, and the transverse direction angle clip 5 is set to the multilayer resistance 9 top of plate is fired, the vertical angle steel 7 is equipped with the multi-layer fire-retarded 8 corner junction of plate reinforces fastener 2.
A kind of blue bricks furred ceiling base layer structure provided by the invention and its construction method, such base layer structure are stablized, are improved The construction efficiency of blue bricks furred ceiling has saved a large amount of man power and material and has carried out antirust treatment, effectively reduced construction cost.
In some embodiments, the long angle steel 3 of the transverse direction, the lateral angle clip 5 and the vertical angle steel 7 are connected with each other Form dies.
Using above-described embodiment, structure is simple, easy to operate, keeps base more steady in such a way that " work " word connects Gu.
In some embodiments, the reinforcing fastener 2 is L-shaped.
Using above-described embodiment, structure is simple, easy to operate, sets in vertical angle steel and multi-layer fire-retarded plate corner junction There is reinforcing fastener, ensure that the absolute stability of blue bricks furred ceiling base layer structure.
In some embodiments, blue bricks furred ceiling base layer structure, comprising: dry hanging article 1 and fixing piece 4, the dry hanging article 1 Upper end is connect by the fixing piece 4 with the lateral angle clip 5.
Using above-described embodiment, structure is simple, easy to operate, ensure that base layer structure is stablized, improves blue bricks furred ceiling Construction efficiency.
In some embodiments, blue bricks furred ceiling base layer structure, comprising: stabilization and reinforcement fastener 6, the lower end of the dry hanging article 1 It is connect by the stabilization and reinforcement fastener 6 with the multi-layer fire-retarded plate 8.
Using above-described embodiment, structure is simple, easy to operate, multi-layer fire-retarded being connected by stainless steel dry hanging article Plate ensure that the performance of blue bricks furred ceiling base layer structure fire retardant anticorrosion.
In some embodiments, blue bricks furred ceiling base layer structure, comprising: blue bricks (not shown), the blue bricks (not shown) are logical The stickup of structure glue (not shown) is crossed to be connected on the multi-layer fire-retarded plate 8.
Using above-described embodiment, structure is simple, easy to operate, ensure that base layer structure is stablized, improves blue bricks paving Construction efficiency.
In some embodiments, the multi-layer fire-retarded plate 8 includes: that multi-layer fire-retarded plate right angle short side 9, multi-layer fire-retarded plate are straight Angular length side 10 and multi-layer fire-retarded plate bevel edge 11, the multi-layer fire-retarded plate right angle short side 9,10 and of multi-layer fire-retarded plate right angle long side The multi-layer fire-retarded plate bevel edge 11 is connected with each other composition triangular structure of right angle.
Using above-described embodiment, structure is simple, easy to operate, ensure that base layer structure is stablized, improves blue bricks furred ceiling Construction efficiency.
In some embodiments, the multi-layer fire-retarded plate right angle long side 10 is prolonged along the longitudinal direction of the vertical angle steel 7 It stretches and is connect with the vertical angle steel 7.
Using above-described embodiment, structure is simple, easy to operate, ensure that base layer structure is stablized, improves blue bricks furred ceiling Construction efficiency.
In some embodiments, the multi-layer fire-retarded plate right angle short side 9 along multi-layer fire-retarded plate bevel edge 11 opposite direction Extend.
Using above-described embodiment, structure is simple, easy to operate, ensure that base layer structure is stablized, improves blue bricks furred ceiling Construction efficiency.
In some embodiments, a kind of blue bricks furred ceiling base layer structure construction method, comprising the following steps:
1) according to design drawing, check that facade flatness determines keel and wall cylindrical surface drilling point in top surface surveying setting-out Position;
2) vertical angle steel 7 is fixed on the lateral long angle steel 3 in top by connection fixture, the spacing root of vertical angle steel 7 It is determined according to the size of live blue bricks typesetting;
3) vertical angle steel 7 is equipped with reinforcing fastener 2 with multi-layer fire-retarded 8 corner junction of plate and is reinforced, the upper end of dry hanging article 1 It is connect by fixing piece 4 with lateral angle clip 5, the lower end of dry hanging article 1 is connected by stabilization and reinforcement fastener 6 and multi-layer fire-retarded plate 8 It connects;
4) it checks whether each components of blue bricks furred ceiling base layer structure connect fastening, makes on multi-layer fire-retarded 8 basal plate of plate With structure glue blue bricks.
Using above-described embodiment, such base layer structure is stablized, and the construction efficiency of blue bricks furred ceiling is improved, and has saved a large amount of Man power and material carries out antirust treatment, effectively reduces construction cost.
Using blue bricks as the furred ceiling base layer structure of surface layer, comprising: stainless steel dry hanging article 1, thick 304 stainless steels of customization 5mm are reinforced The components such as fastener 2 and the long angle steel 3 of zinc-plated transverse direction, reversed support is done with the long angle steel 3 of the zinc-plated transverse direction of 50*50 in top, according to blue bricks The vertical angle steel 7 of 50*50 is vertically welded on the zinc-plated long angle steel 3 of transverse direction in top, at the end of vertical angle steel 7 again by trend Lateral angle clip 5 forms a dies in welding, in addition, zinc-plated 7 lower end of vertical angle steel and the multi-layer fire-retarded plate in bottom 8 corner junctions reinforce fastener 2 equipped with the stainless steel of 50*50 and are reinforced.The preferred galvanized bolt of fixing piece 4, reuses 304 Stainless steel dry hanging article 1 is connected on lateral angle clip 5 plus matched galvanized bolt 4, the clipping room of dry hanging article 1 away from for 300mm is stablized in the bottom of dry hanging article 1 and thick multi-layer fire-retarded 8 junction of plate 12mm using 304 stainless steels of the 5mm thickness of customization Reinforce fastener 6 to connect, guarantee the stabilization of the thick multi-layer fire-retarded plate 8 of 12mm, later period base complete by the way of structure glue Blue bricks is pasted on multi-layer fire-retarded 8 basal plate of plate.
The processing and construction method of the present embodiment are as follows:
1) it according to design drawing, checks facade flatness, selects suitable combination, in top surface surveying setting-out, determine The position of keel and wall cylindrical surface drilling point out;
2) vertical angle steel 7 is fixed on laterally long angle steel 3 by connection fixture, the spacing of vertical angle steel 7 is according to existing The size of blue bricks typesetting determines, the preferred expansion bolt of the connection fixture or chemical anchor bolts;
3) vertical angle steel 7 is equipped with reinforcing fastener 2 with multi-layer fire-retarded 8 corner junction of plate and is reinforced, the upper end of dry hanging article 1 It is connect by fixing piece 4 with lateral angle clip 5, the lower end of dry hanging article 1 is connected by stabilization and reinforcement fastener 6 and multi-layer fire-retarded plate 8 It connects;
4) it checks that each components of blue bricks furred ceiling base layer structure connect fastening, top surface base is connected by design requirement, In Structure glue blue bricks is used on multi-layer fire-retarded plate 8.
Blue bricks furred ceiling base layer structure, comprising: angle steel (3,5 and 7), stainless steel dry hanging article 1, customization stainless steel reinforce connector The components such as (2 and 6), multi-layer fire-retarded plate 8 and fixing piece 4, the angle steel keep base more firm in such a way that " work " word connects Gu ensure that fire retardant anticorrosion connecting multi-layer fire-retarded plate 8 by stainless steel dry hanging article, in vertical angle steel 7 and multi-layer fire-retarded plate 8 corner junctions, which are equipped with, reinforces fastener 2, ensure that the absolute stabilization of blue bricks furred ceiling base layer structure.
The present invention provides a kind of blue bricks furred ceiling base layer structure and its construction method, has the advantages that
1) present invention improves the efficiency of blue bricks furred ceiling using blue bricks as the furred ceiling base layer structure and its construction method of surface layer, It has saved a large amount of man power and material and has carried out antirust treatment, cost of labor is lower, and does not need professional's operation, popular Construction, improves speed of application, is conducive to standardized work.
2) present invention is using blue bricks as the furred ceiling base layer structure and its construction method of surface layer, when encountering designer to facing typesetting When size adjusts, it need to only adjust corresponding blue bricks and paste at once, greatly shorten change duration timeliness, reduce consumables cost.
3) for the present invention using blue bricks as the furred ceiling base layer structure and its construction method of surface layer, welding position is less, reduces and applies The work with torches of work scene eliminates Partial security hidden danger.
4) present invention is using blue bricks as the furred ceiling base layer structure and its construction method of surface layer, wherein used material is all made of The zinc-plated one-step die casting of hot rolling, perception is beautiful, durable, securely and reliably.
The above are merely the preferred embodiment of the present invention, it is noted that for those of ordinary skill in the art, Without departing from the concept of the premise of the invention, various modifications and improvements can be made, these belong to guarantor of the invention Protect range.

Claims (10)

1. a kind of blue bricks furred ceiling base layer structure characterized by comprising laterally long angle steel, lateral angle clip, vertical angle steel and more Layer flame-retardant board, the long angle steel of transverse direction are connect with described vertical angle steel one end, and the vertical angle steel other end and the transverse direction are short Bolted angle connection, the transverse direction angle clip are set to above the multi-layer fire-retarded plate, the vertical angle steel and the multi-layer fire-retarded plate Corner junction, which is equipped with, reinforces fastener.
2. blue bricks furred ceiling base layer structure according to claim 1, which is characterized in that the long angle steel of the transverse direction, the transverse direction Angle clip and the vertical angle steel are connected with each other composition dies.
3. blue bricks furred ceiling base layer structure according to claim 2, which is characterized in that the reinforcing fastener is L-shaped.
4. blue bricks furred ceiling base layer structure according to claim 3 characterized by comprising dry hanging article and fixing piece, it is described The upper end of dry hanging article is connect by the fixing piece with the lateral angle clip.
5. blue bricks furred ceiling base layer structure according to claim 4 characterized by comprising stabilization and reinforcement fastener, it is described dry The lower end of pendant is connect by the stabilization and reinforcement fastener with the multi-layer fire-retarded plate.
6. blue bricks furred ceiling base layer structure according to claim 5 characterized by comprising blue bricks, the blue bricks pass through knot Structure glue is connected on the multi-layer fire-retarded plate.
7. blue bricks furred ceiling base layer structure according to claim 6, which is characterized in that the multi-layer fire-retarded plate includes: multilayer Flame-retardant board right angle short side, multi-layer fire-retarded plate right angle long side and multi-layer fire-retarded plate bevel edge, it is the multi-layer fire-retarded plate right angle short side, described Multi-layer fire-retarded plate right angle long side and the multi-layer fire-retarded plate bevel edge are connected with each other composition triangular structure of right angle.
8. blue bricks furred ceiling base layer structure according to claim 7, which is characterized in that the multi-layer fire-retarded long edge in plate right angle The vertical angle steel longitudinal direction extend and with the vertical Bolted angle connection.
9. blue bricks furred ceiling base layer structure according to claim 8, which is characterized in that the multi-layer fire-retarded plate right angle short side edge Multi-layer fire-retarded plate bevel edge opposite direction extend.
10. a kind of blue bricks furred ceiling base layer structure construction method, which comprises the following steps:
1) according to design drawing, check that facade flatness determines the position of keel and wall cylindrical surface drilling point in top surface surveying setting-out It sets;
2) vertical angle steel is fixed on the lateral long angle steel in top by connection fixture, the spacing of vertical angle steel is according to live green The size of brick typesetting determines;
3) vertical angle steel is equipped with reinforcing fastener with multi-layer fire-retarded plate corner junction and is reinforced, and the upper end of dry hanging article passes through fixation Part is connect with lateral angle clip, and the lower end of dry hanging article is connect by stabilization and reinforcement fastener with multi-layer fire-retarded plate;
4) it checks whether each components of blue bricks furred ceiling base layer structure connect fastening, structure is used on multi-layer fire-retarded plate basal plate Glue blue bricks.
CN201910902183.9A 2019-09-24 2019-09-24 A kind of blue bricks furred ceiling base layer structure and its construction method Pending CN110528770A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910902183.9A CN110528770A (en) 2019-09-24 2019-09-24 A kind of blue bricks furred ceiling base layer structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910902183.9A CN110528770A (en) 2019-09-24 2019-09-24 A kind of blue bricks furred ceiling base layer structure and its construction method

Publications (1)

Publication Number Publication Date
CN110528770A true CN110528770A (en) 2019-12-03

Family

ID=68669716

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910902183.9A Pending CN110528770A (en) 2019-09-24 2019-09-24 A kind of blue bricks furred ceiling base layer structure and its construction method

Country Status (1)

Country Link
CN (1) CN110528770A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201507056U (en) * 2009-09-09 2010-06-16 中建三局东方装饰设计工程有限公司 Composite stone suspended ceiling system
WO2013023383A1 (en) * 2011-08-18 2013-02-21 惠州维岛美建材有限公司 Building composite board, wall and building with composite board structure
CN103669671A (en) * 2013-12-29 2014-03-26 中国建筑第七工程局有限公司 Stone honeycomb composite board suspended ceiling system
CN204738435U (en) * 2015-06-16 2015-11-04 上海沈飞新型幕墙工程有限公司 Decorate furred ceiling structure of brick wall outward
CN205688642U (en) * 2016-06-18 2016-11-16 青岛海川建设集团有限公司 A kind of large space ceiling decoration supporting construction
CN206888321U (en) * 2017-05-08 2018-01-16 苏州广林建设有限责任公司 A kind of lightgage steel joist Thistle board furred ceiling
CN207739492U (en) * 2018-01-05 2018-08-17 深圳市华诚通建筑工程有限公司 A kind of environment-friendly type building construction Integral ceiling
CN209082797U (en) * 2018-05-11 2019-07-09 四川蜀美建筑装饰工程有限公司 A kind of ceiling system of light trough lines
CN211114334U (en) * 2019-09-24 2020-07-28 金螳螂精装科技(苏州)有限公司 Blue or green brick furred ceiling basic unit structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201507056U (en) * 2009-09-09 2010-06-16 中建三局东方装饰设计工程有限公司 Composite stone suspended ceiling system
WO2013023383A1 (en) * 2011-08-18 2013-02-21 惠州维岛美建材有限公司 Building composite board, wall and building with composite board structure
CN103669671A (en) * 2013-12-29 2014-03-26 中国建筑第七工程局有限公司 Stone honeycomb composite board suspended ceiling system
CN204738435U (en) * 2015-06-16 2015-11-04 上海沈飞新型幕墙工程有限公司 Decorate furred ceiling structure of brick wall outward
CN205688642U (en) * 2016-06-18 2016-11-16 青岛海川建设集团有限公司 A kind of large space ceiling decoration supporting construction
CN206888321U (en) * 2017-05-08 2018-01-16 苏州广林建设有限责任公司 A kind of lightgage steel joist Thistle board furred ceiling
CN207739492U (en) * 2018-01-05 2018-08-17 深圳市华诚通建筑工程有限公司 A kind of environment-friendly type building construction Integral ceiling
CN209082797U (en) * 2018-05-11 2019-07-09 四川蜀美建筑装饰工程有限公司 A kind of ceiling system of light trough lines
CN211114334U (en) * 2019-09-24 2020-07-28 金螳螂精装科技(苏州)有限公司 Blue or green brick furred ceiling basic unit structure

Similar Documents

Publication Publication Date Title
CN105040944A (en) Integrally-installed wallboard
CN110847534B (en) Stone toilet wall assembly and mounting method thereof
CN106368368B (en) Based on T-shaped and Z-type pendant stone material aluminium honeycomb composite plate ceiling construction method
CN205677192U (en) Wood facing cassette mounting structure
CN110469075A (en) A kind of metope pottery aluminium core abatvoix system and its construction method
CN207700492U (en) A kind of furred ceiling crack resistence structure
CN109356296A (en) A kind of water-proof heat-preserving integrated plate of external wall and construction method
CN110528770A (en) A kind of blue bricks furred ceiling base layer structure and its construction method
CN208777622U (en) A kind of nodal wood type indoor wall facing panel cladding system
CN205025027U (en) Wallboard of getting ready
CN109610717A (en) A kind of installation method of W font furred ceiling keelson
CN207228439U (en) A kind of viscous anchor combination ceramic thin plate decoration wall
CN204139418U (en) Corrugation PLASTIC LAMINATED suspended ceiling mounting structure
CN203684562U (en) Anti-crack suspended ceiling structure
CN105401680A (en) House roof system
CN211114334U (en) Blue or green brick furred ceiling basic unit structure
CN213774051U (en) Light steel keel thistle board furred ceiling
CN111962791B (en) Wall surface hanging external corner system
CN212224366U (en) Special-shaped keel ceiling lamp groove
CN205224367U (en) House roof system
CN201011080Y (en) Suspending board and its mounting structure used for architectural ornament
CN210828154U (en) Wallboard connecting structure
CN210685085U (en) External wall board made of diamond wood for light steel villa
CN208934149U (en) Metope expansion joint lightgage steel joist sliding system
CN101886453B (en) Method for fixing thermal insulation decorative board and X-type and J-type fixing devices

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination