CN110525582A - One kind large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method - Google Patents
One kind large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method Download PDFInfo
- Publication number
- CN110525582A CN110525582A CN201910666262.4A CN201910666262A CN110525582A CN 110525582 A CN110525582 A CN 110525582A CN 201910666262 A CN201910666262 A CN 201910666262A CN 110525582 A CN110525582 A CN 110525582A
- Authority
- CN
- China
- Prior art keywords
- pedestal
- point
- block
- control method
- prepackage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
The invention discloses a kind of large-scale pedestals peculiar to vessel always to organize prepackage accuracy control method, which includes: that larboard segmentation is formed the first block with starboard block assembly;Block axial line is marked on the first block;First rib bit line, the second rib bit line are marked in larboard segmentation and/or starboard segmentation;It determines on first rib bit line at first point, so that be separated by first distance with block axial line, second point is determined on the second rib bit line at first point, so that second point and block axial line are separated by second distance;Mark segmentation axial line according to and second point at first point;Pedestal is lifted to position to be installed;Adjustment pedestal is overlapped the punching of the center ocean on pedestal point with segmentation axial line, the apparent height of pedestal and described first point or second point are equal to predetermined altitude.Beneficial effects of the present invention are that can effectively discharge crane resources, promote the control precision and efficiency of carrying, shorten the ship building dock phase, save the cost, practicability with higher.
Description
Technical field
The invention belongs to shipbuilding technical fields, and in particular to one kind large-scale pedestal peculiar to vessel always organizes prepackage precision controlling side
Method.
Background technique
Ship crane in building course builds resource as core and plays the important and pivotal role.If can build
Crane resources are discharged during making as far as possible, so that it may promote efficiency of construction.Traditional pedestal installation is carried in dock
Stage carries out, and dock portal jib crane is used when lifting, and use cost is high, while seriously affecting other work while carrying out, and
It takes this method to can reduce the frequency of use of crane, reduces cost.
On the other hand large-scale pedestal carries out after being mounted on dock segment carrying, process lag, influence to carry lift into
Degree delays the depressed place phase, increases cost.And take this method that pedestal can be improved and always organize prepackage precision quality, shorten the depressed place phase, raising is taken
Carry production efficiency.
Summary of the invention
Aiming at the problems existing in the prior art, the present invention provides one kind large-scale pedestal peculiar to vessel and always organizes prepackage precision controlling side
Method, the present invention can save crane resources, improve efficiency of construction, and process shifts to an earlier date, and shorten the ship building dock phase, improve total group of pedestal
Pre-install precision quality.
To achieve the above object, the invention adopts the following technical scheme:
One kind large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method, which includes:
Larboard segmentation is formed into the first block with starboard block assembly;
Block axial line is marked on the first block;
First rib bit line, the second rib bit line are marked in larboard segmentation and/or starboard segmentation;
Determine on first rib bit line at first point, so that be separated by first distance with block axial line, in the second rib bit line at first point
Upper determining second point, so that second point and block axial line are separated by second distance;
Mark segmentation axial line according to and second point at first point;
Pedestal is lifted to position to be installed;
Adjustment pedestal is overlapped the punching of the center ocean on pedestal point with segmentation axial line, the apparent height of pedestal and described first point
Either second point is equal to predetermined altitude, the preset lines on pedestal and first rib bit line or the second rib bit line predetermined distance;
Pedestal is welded and fixed.
The adjustment pedestal includes:
Freeze guide pad on first total section surface at left and right sides of pedestal, enables pedestal sliding on segmentation direction of axis line
It is dynamic.
The adjustment pedestal includes:
Freeze bracket on first total section surface of pedestal front and rear sides, oil cylinder is set up on bracket, the piston of oil cylinder is against base
Seat, for providing thrust.
Described pedestal is welded and fixed include:
Balanced welding is carried out in pedestal periphery quadrangle;
By the peripheral board welding equipment of pedestal;
By the internal framework welding equipment of pedestal.
It is described by the peripheral board welding equipment of pedestal, the internal framework welding equipment by pedestal, after including: welding equipment, by complete
Instrument of standing measures pedestal installation position data, overproof if there is data, readjusts welding.
It is described mark first rib bit line, the second rib bit line determines the first rib bit line, the second rib by total station
The position of bit line.
The control method further include:
After pedestal is welded and fixed, the overall data of the first block is measured and recorded.
The control method further include:
After pedestal is welded and fixed, the seam two sides between the first block and its adjacent block are arranged to zygonema.
The control method further include:
After pedestal is welded and fixed, several monitoring points are set, simultaneously to the relative distance DATA REASONING of the first block and external object
Record, several monitoring points are not all coplanar.
The preset lines are angle square line.
Compared with prior art, the invention has the benefit that
1, ensure pedestal can with block integral hoisting, meanwhile, also effectively promote the promotion in sectional construction period;
2, the pedestal set-up time can be greatlyd save by the method, it is effective to improve depressed place rate under block integrality, while being great
Technical basis and basis have been established in the propulsion of installation of project technology lead, so that the development of ship precision has been striden forward one big
Step;
3, have and save crane resources, positioning states can easily be accommodated, the easily controllable effect of later period construction precision.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
It obtains other drawings based on these drawings.
Fig. 1 is the schematic diagram that block axial line is determined on the first block.
Fig. 2 is the schematic diagram for determining segmentation axial line.
Fig. 3 is the schematic diagram for determining pedestal front-rear position.
Fig. 4 is the drafting schematic diagram to zygonema.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other under that premise of not paying creative labor
Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that, term " longitudinal direction ", " transverse direction ", "upper", "lower", "front", "rear",
The orientation or positional relationship of the instructions such as "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside" is based on attached drawing institute
The orientation or positional relationship shown, is merely for convenience of description of the present invention and simplification of the description, rather than the dress of indication or suggestion meaning
It sets or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as to limit of the invention
System.
As shown in Figs 1-4, the present embodiment provides a kind of large-scale pedestals peculiar to vessel always to organize prepackage accuracy control method, the controlling party
Method includes:
By larboard segmentation 10, always group forms the first block 70 with starboard segmentation 20;
Block axial line 100 is marked on the first block;
First rib bit line 200, the second rib bit line 300 are marked in larboard segmentation 10 and/or starboard segmentation 20;
1: 1 is determined on first rib bit line 200, so that 1: 1 is separated by first distance with block axial line 100, the
Second point 2 is determined on two rib bit lines 300, so that second point 2 and block axial line 100 are separated by second distance;
Segmentation axial line 400 is marked according to 1: 1 and second point 2;
Pedestal 30 is lifted to position to be installed;
Adjustment pedestal 30 make the center ocean on pedestal 30 punching point with segmentation axial line 400 be overlapped, the apparent height of pedestal 30 and
Described 1: 1 or second point 2 be equal to predetermined altitude, the preset lines on pedestal 30 and first rib bit line 200 or the second rib
300 predetermined distance of bit line;
Pedestal 30 is welded and fixed.
Preferably, adjustment pedestal 30 described in the present embodiment includes:
Freeze guide pad 40 on first total section surface of 30 left and right sides of pedestal, enables pedestal 30 in segmentation axial line
400 side's upward slidings.
As further preferred, adjustment pedestal 30 described in the present embodiment includes:
Freeze bracket 50 on first total section surface of 30 front and rear sides of pedestal, and oil cylinder, the piston of oil cylinder are set up on bracket 50
Against pedestal 30, for providing thrust.
As further preferred, pedestal 30 is welded and fixed described in the present embodiment includes:
Balanced welding is carried out in the peripheral quadrangle of pedestal 30;
By the peripheral board welding equipment of pedestal 30;
By the internal framework welding equipment of pedestal 30.
As further preferred, by the peripheral board welding equipment of pedestal 30, the inside structure by pedestal 30 described in the present embodiment
Rack-mounted weldering, it is overproof if there is data by 30 installation position data of total station survey pedestal after including: welding equipment, it adjusts again
Whole welding.
As further preferred, first rib bit line 200 is marked described in the present embodiment, the second rib bit line 300 passes through whole station
Instrument determines the position of the first rib bit line 200, the second rib bit line 300.
As further preferred, the present embodiment control method further include:
After pedestal 30 is welded and fixed, the overall data of the first block is measured and recorded.
As further preferred, the present embodiment control method further include:
After pedestal 30 is welded and fixed, the seam two sides between the first block and its adjacent block 80 are arranged to zygonema 500.
As further preferred, the present embodiment control method further include:
After pedestal 30 is welded and fixed, several monitoring points are set, to the relative distance DATA REASONING of the first block and external object
And record, several monitoring points are not all coplanar.
The preset lines are angle square line 600.
Specifically, the installation for Double gear box pedestal includes the following steps:
1, the total packet size of block is adjusted within the scope of precision controlling
EBZ02 block ensures the high level of synchronization of port and starboard FR42# rib position, and the gear cage base pit levelness of two sides of a ship when always organizing
It is adjusted within the scope of precision controlling, corresponding region is resized to meet gear-box base according to the data on total group positioning figure
Seat positioning requirements;
2, segmentation axial line is marked
Two segmentation axial lines are marked on EB02P/S inner bottom plating according to EBZ02 axial line scribing line figure, by port and starboard FR42# with
Axial line intersection point, which is refuted, on FR36# rib position marks as basis on location:
3, block installation positioning is carried out to Double gear box with segmentation axial line
Gear cage base is lifted into installation site, setting segmentation axial line on cabin inner bottom plating using total station, will as reference line
The ocean punching point of gear cage base is aligned with segmentation axial line.Confirm pedestal levelness and height, if need to cut surplus.Use whole station
Instrument sets FR42# rib bit line and determines gear-box front-rear position.The burned guide pad of pedestal left and right side, the burned cylinder bracket of front-rear position,
For adjusting pedestal front-rear position.Ensure that Double gear box pedestal meets 2.4 ° of shafting lateral slopes.
4, the assembly of Double gear box pedestal, welding process monitoring
It has been adjusted within the scope of precision controlling before the assembly of Double gear box pedestal, welding, pedestal is subjected to constraint tack welding
It connects, takes balanced welding in peripheral quadrangle, total station repetition measurement pedestal data are used after peripheral board welding equipment is good, it is overproof if any dimension data
Phenomenon stops being adjusted at once, and pending data continues welding equipment internal framework after being adjusted in place, and carries out again after the completion of electric welding primary detailed
Thin repetition measurement ensures that pedestal meets required precision.Data record is carried out simultaneously, the construction reference frame as the subsequent ship of offer.
5, Double gear box pedestal welding equipment overall process carries out tracking measurement data
It all arranges special messenger to carry out tracking measurement to the welding equipment process of pedestal in every morning, afternoon to proofread in time.
6, it resets and makees to zygonema and monitoring coordinate points after Double gear box pedestal segmentation coating
Another critical stage of the project is that be applied that will be segmented feeding after Double gear box pedestal and cabin segmentation welding equipment
Whole sand washing coating is carried out between entrucking, that requires secondary reset positioning states for the first time must be put in segmentation and pedestal.It is logical
It crosses and block entirety measurement data is collected, draws 100M.K to three insurance methods of zygonema and setting 3 D monitoring point to complete to apply
Reset work after dress.
Above-mentioned steps have the following beneficial effects:
1. later process is done in advance
The project implementation substantially increases the efficiency of hull construction, originally considers the positioning accuracy control of diclinic shafting gear cage base
The difficulty of system is larger, so just positioning Double gear box pedestal after waiting sterns cabin segment carrying, not only site work environment is poor,
And need to expend a large amount of working hour and go to complete base stand location welding equipment, in addition relevant stowed on deck segmentation can also be affected by it nothing
Method is carried in advance, can not shorten entire construction period.
2. precision controlling Whole plot
The Whole plot that precision controlling process has been reacted in the project implementation is carried out, and Double gear box pedestal is installed on block, i.e.,
Guarantee that 2.4 ° of shafting slopes meet block size, also ensures that its block carries and meet whole shafting requirement.
3. Promoting Standardized shipbuilding technology
The propulsion of the project may conform to the building technology Standardization Practice under present shipbuilding new model, the construction to similar type ship
Production standard is provided, it is horizontal to promote company's shipbuilding.
Although above-described embodiment makes specific descriptions to the present invention, come for those of ordinary skill in the art
It says, it is understood that can be modified within spirit and scope of the invention based on present disclosure not departing from
Or improve, these modification and improvement are all within spirit and scope of the invention.
Claims (10)
1. a kind of large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method, which is characterized in that the control method includes:
By larboard segmentation (10) and starboard segmentation (20), always group forms the first block;
Block axial line (100) are marked on the first block;
First rib bit line (200), the second rib bit line (300) are marked in larboard segmentation (10) and/or starboard segmentation (20);
On first rib bit line (200) determine first point (1) so that first point (1) with block axial line (100) be separated by first away from
From, determine second point (2) on the second rib bit line (300) so that second point (2) and block axial line (100) be separated by second away from
From;
Mark segmentation axial line (400) according to (1) and second point (2) at first point;
Lift pedestal (30) to position to be installed;
Adjustment pedestal (30) make the center ocean on pedestal (30) punching point be segmented axial line (400) be overlapped, the table of pedestal (30)
Face height and first point (1) or second point (2) are equal to predetermined altitude, the preset lines on pedestal (30) and first rib bit line
(200) or second rib bit line (300) predetermined distance;
Pedestal (30) is welded and fixed.
2. large-scale pedestal peculiar to vessel according to claim 1 always organizes prepackage accuracy control method, which is characterized in that the adjustment
Pedestal (30) includes:
It freezes on first total section surface at left and right sides of pedestal (30) guide pad (40), so that pedestal (30) can be in segmentation axis
Heart line (400) side upward sliding.
3. large-scale pedestal peculiar to vessel according to claim 2 always organizes prepackage accuracy control method, which is characterized in that the adjustment
Pedestal (30) includes:
It freezes on first total section surface of pedestal (30) front and rear sides bracket (50), sets up oil cylinder, oil cylinder on bracket (50)
Piston against pedestal (30), for providing thrust.
4. large-scale pedestal peculiar to vessel according to claim 1 always organizes prepackage accuracy control method, which is characterized in that described by base
Seat (30), which is welded and fixed, includes:
Balanced welding is carried out in the peripheral quadrangle of pedestal (30);
By the peripheral board welding equipment of pedestal (30);
By the internal framework welding equipment of pedestal (30).
5. large-scale pedestal peculiar to vessel according to claim 4 always organizes prepackage accuracy control method, which is characterized in that described by base
Peripheral board welding equipment, the internal framework welding equipment by pedestal (30) of seat (30), include: to pass through total station survey after welding equipment
Pedestal (30) installation position data, it is overproof if there is data, readjust welding.
6. large-scale pedestal peculiar to vessel according to claim 1 always organizes prepackage accuracy control method, which is characterized in that described to mark
First rib bit line (200), the second rib bit line (300) determine the first rib bit line (200), the second rib position by total station
The position of line (300).
7. large-scale pedestal peculiar to vessel according to claim 1 always organizes prepackage accuracy control method, which is characterized in that the controlling party
Method further include:
After pedestal (30) is welded and fixed, the overall data of the first block is measured and recorded.
8. large-scale pedestal peculiar to vessel according to claim 1 always organizes prepackage accuracy control method, which is characterized in that the controlling party
Method further include:
After pedestal (30) is welded and fixed, the seam two sides between the first block and its adjacent block are arranged to zygonema
(500).
9. large-scale pedestal peculiar to vessel according to claim 1 always organizes prepackage accuracy control method, which is characterized in that the controlling party
Method further include:
After pedestal (30) is welded and fixed, several monitoring points are set, the relative distance data of the first block and external object are surveyed
It measures and records, several monitoring points are not all coplanar.
10. large-scale pedestal peculiar to vessel according to claim 1 always organizes prepackage accuracy control method, which is characterized in that described pre-
Alignment is angle square line (600).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910666262.4A CN110525582A (en) | 2019-07-23 | 2019-07-23 | One kind large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910666262.4A CN110525582A (en) | 2019-07-23 | 2019-07-23 | One kind large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110525582A true CN110525582A (en) | 2019-12-03 |
Family
ID=68661829
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910666262.4A Pending CN110525582A (en) | 2019-07-23 | 2019-07-23 | One kind large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110525582A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113401308A (en) * | 2021-05-21 | 2021-09-17 | 沪东中华造船(集团)有限公司 | Ship large-line type subsection total assembly precision control method |
CN114179994A (en) * | 2021-11-08 | 2022-03-15 | 上海江南长兴造船有限责任公司 | Ship building piping installation precision control method |
CN114348204A (en) * | 2021-12-13 | 2022-04-15 | 上海江南长兴造船有限责任公司 | General assembly and carrying method for bottom layer block of LNG ship engine room and bottom layer block of LNG ship engine room |
CN114701618A (en) * | 2022-03-10 | 2022-07-05 | 江南造船(集团)有限责任公司 | Ship precision control method based on block construction |
CN116039871A (en) * | 2022-11-25 | 2023-05-02 | 沪东中华造船(集团)有限公司 | LNG ship double-stern-shaft total section assembly, carrying method and double-stern-shaft total section |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101058335A (en) * | 2007-05-23 | 2007-10-24 | 沪东中华造船(集团)有限公司 | Method of positioning and mounting mainframe base and gearbox base in ship complete cross section manufacture |
CN107323610A (en) * | 2017-06-30 | 2017-11-07 | 广船国际有限公司 | Main engine bed, the installation method in gear block block stage |
CN108974250A (en) * | 2018-06-15 | 2018-12-11 | 沪东中华造船(集团)有限公司 | A method of location and installation precision of the control special equipment pedestal on block |
-
2019
- 2019-07-23 CN CN201910666262.4A patent/CN110525582A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101058335A (en) * | 2007-05-23 | 2007-10-24 | 沪东中华造船(集团)有限公司 | Method of positioning and mounting mainframe base and gearbox base in ship complete cross section manufacture |
CN107323610A (en) * | 2017-06-30 | 2017-11-07 | 广船国际有限公司 | Main engine bed, the installation method in gear block block stage |
CN108974250A (en) * | 2018-06-15 | 2018-12-11 | 沪东中华造船(集团)有限公司 | A method of location and installation precision of the control special equipment pedestal on block |
Non-Patent Citations (2)
Title |
---|
林坤 等;: "LNG船齿轮箱基座预装工艺的优化", 《船舶工程》 * |
熊飞 等;: "双轴系推进***基座总段安装工艺研究", 《广船国际》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113401308A (en) * | 2021-05-21 | 2021-09-17 | 沪东中华造船(集团)有限公司 | Ship large-line type subsection total assembly precision control method |
CN114179994A (en) * | 2021-11-08 | 2022-03-15 | 上海江南长兴造船有限责任公司 | Ship building piping installation precision control method |
CN114179994B (en) * | 2021-11-08 | 2023-12-26 | 上海江南长兴造船有限责任公司 | Ship building piping installation accuracy control method |
CN114348204A (en) * | 2021-12-13 | 2022-04-15 | 上海江南长兴造船有限责任公司 | General assembly and carrying method for bottom layer block of LNG ship engine room and bottom layer block of LNG ship engine room |
CN114701618A (en) * | 2022-03-10 | 2022-07-05 | 江南造船(集团)有限责任公司 | Ship precision control method based on block construction |
CN116039871A (en) * | 2022-11-25 | 2023-05-02 | 沪东中华造船(集团)有限公司 | LNG ship double-stern-shaft total section assembly, carrying method and double-stern-shaft total section |
CN116039871B (en) * | 2022-11-25 | 2024-06-18 | 沪东中华造船(集团)有限公司 | LNG ship double-stern-shaft total section assembly, carrying method and double-stern-shaft total section |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110525582A (en) | One kind large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method | |
CN102358413B (en) | Installation method of full-revolving rudder propeller device with special angle | |
CN102490003B (en) | Method for installing telescopic full-rotating rudder propeller device | |
CN107284603B (en) | LNG liquid vault segment is the same as tire manufacture, stage by stage folding method | |
CN109606542A (en) | A method of location and installation precision of the control special equipment pedestal on block | |
CN107600314B (en) | Integral hoisting method is built in thin plate multilayer | |
CN107323610A (en) | Main engine bed, the installation method in gear block block stage | |
CN110525576A (en) | A kind of ship deck base construction and ship deck base construction installation method | |
CN103979073A (en) | Installation method for segmented pre-installation of anchor table, anchor mouth and hawse pipe | |
CN108773455B (en) | Bulb bow reform technology | |
CN105383642A (en) | Vertical guide rail mounting and welding method | |
CN102490864A (en) | Underwater folding method for half ships | |
CN110341878A (en) | A kind of installation method of stern transom plate hinge | |
CN104389268A (en) | Steel tower column with positioning structure and hoisting construction method thereof | |
CN107235117A (en) | A kind of fabrication and installation method of anchor recess | |
CN113148058A (en) | Process for installing and positioning double-rudder sleeve and tail casting in segmented construction stage | |
CN110789684A (en) | Method for assembling large deck machinery body base | |
CN110371240A (en) | A kind of ship porthole opens up method and ship | |
CN114379741A (en) | Full-width five-total-section zero-allowance carrying method for ship | |
CN105464049A (en) | Real-time testing-controlling acceptance system for deepwater dumping ship and construction method | |
CN102312436A (en) | Steel pipe pile sinking construction technology | |
CN111976916A (en) | Full-rotation telescopic push mounting process for engineering ship | |
CN204956849U (en) | A construction equipment for turning over dial structure 100MARK line | |
CN103482042B (en) | A kind of deep water comb shape slideway cross beam construction method of installation | |
CN112112186B (en) | Installation method of split jacket foundation on offshore converter station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191203 |