CN110518604A CN201910795006.5A CN201910795006A CN110518604A CN 110518604 A CN110518604 A CN 110518604A CN 201910795006 A CN201910795006 A CN 201910795006A CN 110518604 A CN110518604 A CN 110518604A
Authority
CN
China
Prior art keywords
phase current
degree
balance
rack
deployed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910795006.5A
Other languages
Chinese (zh)
Inventor
杨洁
易南昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Tongji Science And Technology Co Ltd
Original Assignee
Shenzhen Tongji Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Tongji Science And Technology Co Ltd filed Critical Shenzhen Tongji Science And Technology Co Ltd
Priority to CN201910795006.5A priority Critical patent/CN110518604A/en
Publication of CN110518604A publication Critical patent/CN110518604A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/26Arrangements for eliminating or reducing asymmetry in polyphase networks
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/50Arrangements for eliminating or reducing asymmetry in polyphase networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of deployed with devices method, intelligent terminal and storage mediums based on degree of balance control, and wherein method is comprising steps of obtain three-phase current, three-phase current is respectively the first phase current, the second phase current and third phase current;The size for carrying out the first phase current, the second phase current and third phase current compares, using rack corresponding to wherein the smallest phase current as to restocking rack.Based on this, deployed with devices method provided by the present invention based on degree of balance control, the smallest rack restocking equipment of current load can be selected, improves the three-phrase burden balance degree of data center's electric system to a certain extent before equipment restocking by comparing phase current size.

Description

Deployed with devices method, intelligent terminal and storage medium based on degree of balance control
Technical field
The present invention relates to data center's technical fields, more particularly to a kind of deployed with devices side based on degree of balance control Method, intelligent terminal and storage medium.
Background technique
Data center is the core node of information system, comprising server, network, stores these computer systems and sets The site facilities such as standby, application software and the power supply and distribution, refrigeration, the security protection that support their safe and stable operations.
Internet+, Internet of Things, 5G, big data, cloud computing, AI, social informatization, intelligent Application etc. rapid development, The data center needed is more and more.Large-scale, ultra-large type data center scale of investment may be up to billions of members even over ten billion, The investment of middle electric system accounts for one third or more, is the infrastructure investment of lion's share.
If three-phase load current imbalance will result directly in data center's electric power, space, refrigeration design capacity cannot be sufficient Volume uses, and not only design objective can not achieve, but also also result in the huge wasting of resources;Biggish N line current can be also generated simultaneously And increase zero curve ground wire voltage, hidden danger is brought to IT system stable operation.
In general, people allow data center's Three-phase Power Systems load to balance as far as possible using the following method:
When first cabinet of each row distribution Deepen Design, as allow each every phase institute band IT rack number of first cabinet of each row in computer room roughly the same as possible, And serial number is arranged by cabinet, it is a, b, c three-phase successively alternate allocation cabinet;The power density difference of miscellaneous information technoloy equipment compared with Greatly, not can guarantee the equipment that each rack all installs Same Efficieney in practical restocking installation, the nominal power of each equipment because with reality Power difference is larger also cannot be taken as proof for operation, and needs to reserve some designated spaces in many cases in order to manage, so It cannot be guaranteed that the three-phase equilibrium of actual motion load.
Therefore, the prior art could be improved.
Summary of the invention
Based on this, it is necessary in view of the above technical problems, provide it is a kind of based on the degree of balance control deployed with devices method, intelligence Energy terminal and storage medium, it is intended to solve the problems, such as that the prior art cannot be guaranteed three-phrase burden balance.
Technical scheme is as follows:
A kind of deployed with devices method based on degree of balance control comprising:
Three-phase current is obtained, three-phase current is respectively the first phase current, the second phase current and third phase current;
The size for carrying out the first phase current, the second phase current and third phase current compares, will wherein the smallest phase current institute Corresponding rack is used as to restocking rack.
In further preferred embodiment, the step of the acquisition three-phase current before further include: preset for putting down The degree of balance threshold value of weighing apparatus degree early warning;After the step of degree of balance threshold value preset for degree of balance early warning further include:
Three-phrase burden balance degree is calculated in real time, and balance is issued when the three-phrase burden balance degree is less than degree of balance threshold value Spend early warning.
In further preferred embodiment, the calculation formula of the three-phrase burden balance degree are as follows: Lb=1-Max [Max (Idb, Idc), Ida]/2IA, wherein LbFor three-phrase burden balance degree, the IAFor three-phase current average value, the IdaFor the first phase current And the deviation of three-phase current average value, the IdbFor the deviation of the second phase current and three-phase current average value, the IdcFor third The deviation of phase current and three-phase current average value.
In further preferred embodiment, the degree of balance threshold value is 95%, when the three-phrase burden balance degree is 95% When, IAWith Ida、IdbAnd IdcRelationship it is as follows: IA=10*Max [Max (Idb, Idc), Ida]。
In further preferred embodiment, the size for carrying out the first phase current, the second phase current and third phase current Compare, specifically included using rack corresponding to wherein the smallest phase current as to the step of restocking rack:
Judge the first phase current whether less than the second phase current;
If then continuing to judge whether the first phase current is less than third phase current;
If then using rack corresponding to the first phase current as to restocking rack.
In further preferred embodiment, if described then continue to judge whether the first phase current is less than third phase current After step further include: if otherwise using rack corresponding to third phase current as to restocking rack.
It is described to judge to go back after the step of whether the first phase current is less than the second phase current in further preferred embodiment Include:
If otherwise judging whether the second phase current is less than third phase current;
If then using rack corresponding to the second phase current as to restocking rack.
In further preferred embodiment, if otherwise described judge the step of whether the second phase current is less than third phase current Later further include: if otherwise using rack corresponding to third phase current as to restocking rack.
A kind of intelligent terminal comprising have memory and one perhaps more than one program one of them or one A procedure above is stored in memory, and is configured to execute one or one by one or more than one processor A procedure above includes for executing method as described above.
A kind of storage medium, is stored thereon with computer program, wherein real when the computer program is executed by processor The step of described in any item deployed with devices methods based on degree of balance control now as above.
Compared with prior art, the deployed with devices method provided by the invention based on degree of balance control, comprising steps of obtaining Three-phase current, three-phase current are respectively the first phase current, the second phase current and third phase current;Carry out the first phase current, second The size of phase current and third phase current compares, using rack corresponding to wherein the smallest phase current as to restocking rack.Base In this, the deployed with devices method provided by the present invention based on degree of balance control can be before equipment restocking by comparing mutually electricity Size is flowed, the smallest rack restocking equipment of current load is selected, largely improves the three of data center's electric system The phase load degree of balance.
Detailed description of the invention
Fig. 1 is the flow chart of the deployed with devices method based on degree of balance control in the preferred embodiment of the present invention.
Fig. 2 is the functional schematic block diagram of intelligent terminal in the preferred embodiment of the present invention.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that specific embodiment described herein is only used to explain the present invention, not For limiting the present invention.
Since the type of information technoloy equipment is more, the operating load between equipment and equipment is also not quite similar, and therefore, successively replaces The degree of balance of load when the mode of restocking equipment does not ensure that actual motion.Such as: three equipment of N batch restocking, this three The operating load of platform equipment successively decreases, by restocking respectively to the first rack, the second rack and third rack;N+1 batch restocking three The operating load of platform equipment, three equipment successively decreases, still by restocking respectively to the first rack, the second rack and third rack; So result is exactly: although seeming this six equipment is mean allocation to three racks, the actually operation of third rack Load will be substantially less that the first rack.Obviously, this method of salary distribution is extremely unreasonable.If calculating can be passed through before restocking equipment Or the operating load of equipment opposite can then improve equipment restocking to the smallest rack of operating load in more each rack Three-phrase burden balance degree.
Based on above-mentioned thinking, the deployed with devices method provided by the present invention based on degree of balance control, as shown in Figure 1, institute State method comprising steps of
S100, three-phase current is obtained, three-phase current is respectively the first phase current, the second phase current and third phase current.
S200, carry out the first phase current, the size of the second phase current and third phase current compares, will wherein the smallest phase electricity The corresponding rack of stream is used as to restocking rack.
The prior art and the concept that three-phrase burden balance degree is not present, the present invention is defined it at this as follows: three Phase load tends to consistent quantitative expression, for measuring the degree of three-phase equilibrium.
Due to UPS (Uninterruptible Power System, i.e. uninterruptible power supply) output voltage be stablize it is constant , and information technoloy equipment input power module carries PFC (Power Factor Correction, PFC) function, power Factor is close to 1;Therefore, in the case where UPS load balancing, even if all the way using UPS power supply, all the way using mains-supplied, it is whole A IT power supply-distribution system load is also balanced, so being with UPS load power, load current or rate of load condensate the expression degree of balance Valence.It is the most convenient to obtain in view of three-phase current, and therefore, the present invention degree of being balanced will hereafter be calculated by taking three-phase current as an example, And the foundation as deployed with devices is compared using the size of three-phase current.
Why the present invention associates restocking equipment with three-phrase burden balance degree, is because undercarriage equipment is uncontrollable , it is needed depending on business, the operating status and administrative provisions of equipment itself, can not determine and the equipment one of undercarriage is needed to be scheduled on pair Increase in that advantageous phase equipment of the degree of balance, so undercarriage equipment can not be as the means for adjusting balancing the load degree;Only Equipment to restocking could be as unique succinct and effective means of adjustment degree.(restocking when including change when restocking Link) it is to increase load, newly-increased load is increased to the adjustable degree of balance in the smallest phase of load always.
As the preferred embodiment of the present invention, the S200 is specifically included:
Judge the first phase current whether less than the second phase current;
If then continuing to judge whether the first phase current is less than third phase current;When judging the first phase current less than the second phase When electric current, it is meant that the operating load of information technoloy equipment in rack corresponding to the second phase current is greater than rack corresponding to the first phase current Therefore the operating load of upper information technoloy equipment in next restocking information technoloy equipment, can't consider rack corresponding to the second phase current, This multilevel iudge will no longer pay close attention to the second phase current.
If then using rack corresponding to the first phase current as to restocking rack.When the first phase current is both less than the second phase Electric current, and when being less than third phase current, illustrate the operating load minimum of information technoloy equipment in rack corresponding to the first phase current, on next time The equipment of frame, can be by restocking thereon.
Based on same reason, when the first phase current is greater than third phase current, third phase current is both less than two phase electricity Stream, and less than the first phase current, illustrate that the operating load of information technoloy equipment in rack corresponding to third phase current is minimum, next restocking Equipment, can be by restocking thereon.
It is preferred that it is described judge the step of whether the first phase current is less than the second phase current after further include:
If otherwise judging whether the second phase current is less than third phase current;
If then using rack corresponding to the second phase current as to restocking rack, if otherwise will be corresponding to third phase current Rack be used as to restocking rack.
It is easily understood that the present invention only needs finally judge which phase current is minimum, three mutually electric The comparative sequence of stream will not influence the solution of the present invention realization, therefore, if first compare the first phase current and the second phase current Not within the scope of restriction of the invention, other comparative sequences such as first compare the second phase current and third phase current, Lesser one among the two is compared with the first phase current again;And first by the first phase current and third phase current into Row comparison, then lesser one among the two is compared with the second phase current, protection model of the invention all should belong to It encloses.
In addition, it should be noted that in addition to the conditions already mentioned, there are still the following situations: 1, two phases in three phase currents The value of electric current is equal and is less than another phase current, at this point, two equal phase currents are all minimum phase current, the two institute Corresponding rack all can be used as to restocking rack, can be all open by two racks when carrying out equipment restocking, can also appoint and select One opening is used for restocking equipment;2, three phase currents are all equal, at this point, three phase currents are all minimum phase current, three Corresponding rack all can be used as to restocking rack, can be all open by three racks when carrying out equipment restocking, can also appoint One or two is selected to open for restocking equipment.It will thus be appreciated that for realizing same when even three-phase current is equal in two-phase Protection scope of the present invention also should belong in the algorithm application of the multiple racks of Shi Kaifang (or any rack), because that can apply algorithm More, the present invention no longer repeats this one by one.
Above method step disclosed in this invention is generally managed in the capacity (resource) of data center's monitoring management system It is called automatically on a node (such as restocking preemption) in process, is the preposition algorithm application of rack position intelligent Matching in equipment, Its result is by the constraint condition as rack position intelligence Optimum Matching in equipment, for guaranteeing that data center's three-phase power load is flat Weighing apparatus, and then capacity utilization is improved, the wasting of resources is avoided, part-loading goods are reduced.
According to another aspect of the present invention, before the step of S100 further include: preset for degree of balance early warning Degree of balance threshold value;After the step of degree of balance threshold value preset for degree of balance early warning further include: calculate in real time Three-phrase burden balance degree, and degree of balance early warning is issued when the three-phrase burden balance degree is less than degree of balance threshold value.
The calculation formula of the three-phrase burden balance degree are as follows: Lb=1-Max [Max (Idb, Idc), Ida]/2IA, wherein LbFor Three-phrase burden balance degree, the IAFor three-phase current average value, the IdaFor the inclined of the first phase current and three-phase current average value Difference, the IdbFor the deviation of the second phase current and three-phase current average value, the IdcIt is average for third phase current and three-phase current The deviation of value.
If the first phase current is Ia, the second phase current is Ib, third phase current is Ic:
Then: IA=(Ia+Ib+Ic)/3;
Ida=| Ia-IA|;
Idb=| Ib-IA|;
Idc=| Ic-IA|;
Three-phase load unbalance degree Lub=Max [Max (Idb, Idc), Ida]/2IA
Why the present invention carries out three-phrase burden balance degree calculating, first is that because degree of balance data can verify that above equipment portion The validity of arranging method;Second is that because the degree of balance is one of the data that data center needs to monitor;Third is that because degree of balance data Can complex equilibrium degree threshold value, the data exception to be monitored provides judgment basis.
In addition, it is also noted that being outside one's consideration except can use three-phase current calculating three-phrase burden balance, UPS can also be utilized The power and load factor of output carry out three-phrase burden balance degree.
In addition, three-phrase burden balance degree calculation of the present invention is without paying close attention to whether voltage balances, it is only necessary to pay close attention to load Whether balance, compared with traditional degree of unbalancedness calculation, the degree of balance in the present invention can be expressed with the mode of percentage, and Traditional degree of unbalancedness when 1 phase is zero, in addition two-phase either what be worth, degree of unbalancedness all will be indicated as 1 even 2, such as 300,0,0 (degree of unbalancedness 2) and 150,150,0 (degree of unbalancedness 1), it is readable poor, with scheme provided by the present invention With essential distinction.
In the specific implementation, the degree of balance threshold value is 95%, when the three-phrase burden balance degree is 95%, IAWith Ida、IdbAnd IdcRelationship it is as follows: IA=10*Max [Max (Idb, Idc), Ida]。
As shown in Fig. 2, the present invention also provides a kind of intelligent terminals comprising have memory 10 and one or one A above program, perhaps more than one program is stored in memory 10 and is configured to by one or one for one of them It includes for executing as described above based on degree of balance control that a above processor 20, which executes the one or more programs, The deployed with devices method of system.
The present invention also provides a kind of storage mediums, are stored thereon with computer program, wherein the computer program quilt The step of deployed with devices method as described above based on degree of balance control is realized when processor executes.
Those of ordinary skill in the art will appreciate that realizing all or part of the process in above-described embodiment method, being can be with Relevant hardware is instructed to complete by computer program, the computer program can be stored in a non-volatile computer In read/write memory medium, the computer program is when being executed, it may include such as the process of the embodiment of above-mentioned each method.Wherein, To any reference of memory, storage, database or other media used in each embodiment provided by the present invention, Including non-volatile and/or volatile memory.Nonvolatile memory may include read-only memory (ROM), programming ROM (PROM), electrically programmable ROM (EPROM), electrically erasable ROM (EEPROM) or flash memory.Volatile memory may include Random access memory (RAM) or external cache.By way of illustration and not limitation, RAM is available in many forms, Such as static state RAM (SRAM), dynamic ram (DRAM), synchronous dram (SDRAM), double data rate sdram (DDRSDRAM), enhancing Type SDRAM (ESDRAM), synchronization link (SyNchliNk) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic ram (DRDRAM) and memory bus dynamic ram (RDRAM) etc..
Each technical characteristic of above embodiments can be combined arbitrarily, for simplicity of description, not to above-described embodiment In each technical characteristic it is all possible combination be all described, as long as however, the combination of these technical characteristics be not present lance Shield all should be considered as described in this specification.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection of the invention Range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (10)

1. a kind of deployed with devices method based on degree of balance control characterized by comprising
Three-phase current is obtained, three-phase current is respectively the first phase current, the second phase current and third phase current;
The size for carrying out the first phase current, the second phase current and third phase current compares, will be wherein corresponding to the smallest phase current Rack be used as to restocking rack.
2. the deployed with devices method according to claim 1 based on degree of balance control, which is characterized in that the acquisition three-phase Before the step of electric current further include: preset the degree of balance threshold value for degree of balance early warning;It is described to preset for balancing After the step of spending the degree of balance threshold value of early warning further include:
Three-phrase burden balance degree is calculated in real time, and the sending degree of balance is pre- when the three-phrase burden balance degree is less than degree of balance threshold value It is alert.
3. the deployed with devices method according to claim 2 based on degree of balance control, which is characterized in that the three-phase load The calculation formula of the degree of balance are as follows: Lb=1-Max [Max (Idb, Idc), Ida]/2IA, wherein LbIt is described for three-phrase burden balance degree IAFor three-phase current average value, the IdaFor the deviation of the first phase current and three-phase current average value, the IdbFor two phase electricity The deviation of stream and three-phase current average value, the IdcFor the deviation of third phase current and three-phase current average value.
4. the deployed with devices method according to claim 3 based on degree of balance control, which is characterized in that the degree of balance threshold Value is 95%, when the three-phrase burden balance degree is 95%, IAWith Ida、IdbAnd IdcRelationship it is as follows: IA=10*Max [Max (Idb, Idc), Ida]。
5. the deployed with devices method according to claim 1 based on degree of balance control, which is characterized in that described to carry out first The size of phase current, the second phase current and third phase current compares, using rack corresponding to wherein the smallest phase current as to The step of restocking rack, specifically includes:
Judge the first phase current whether less than the second phase current;
If then continuing to judge whether the first phase current is less than third phase current;
If then using rack corresponding to the first phase current as to restocking rack.
6. it is according to claim 5 based on the degree of balance control deployed with devices method, which is characterized in that if it is described then after Continue after judging the step of whether the first phase current is less than third phase current further include: if otherwise will be corresponding to third phase current Rack is used as to restocking rack.
7. the deployed with devices method according to claim 5 based on degree of balance control, which is characterized in that the judgement first After the step of whether phase current is less than the second phase current further include:
If otherwise judging whether the second phase current is less than third phase current;
If then using rack corresponding to the second phase current as to restocking rack.
8. the deployed with devices method according to claim 7 based on degree of balance control, which is characterized in that if otherwise described sentence After the step of whether disconnected second phase current is less than third phase current further include: if otherwise by rack corresponding to third phase current As to restocking rack.
9. a kind of intelligent terminal, which is characterized in that include memory and one or more than one program, wherein one A perhaps more than one program is stored in memory and is configured to execute described one by one or more than one processor A or more than one program includes for executing method as claimed in any of claims 1 to 8 in one of claims.
10. a kind of storage medium, is stored thereon with computer program, which is characterized in that the computer program is held by processor It is realized when row such as the step of the deployed with devices method described in any item of the claim 1 to 8 based on degree of balance control.
CN201910795006.5A 2019-08-27 2019-08-27 Deployed with devices method, intelligent terminal and storage medium based on degree of balance control Pending CN110518604A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910795006.5A CN110518604A (en) 2019-08-27 2019-08-27 Deployed with devices method, intelligent terminal and storage medium based on degree of balance control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910795006.5A CN110518604A (en) 2019-08-27 2019-08-27 Deployed with devices method, intelligent terminal and storage medium based on degree of balance control

Publications (1)

Publication Number Publication Date
CN110518604A true CN110518604A (en) 2019-11-29

Family

ID=68626234

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910795006.5A Pending CN110518604A (en) 2019-08-27 2019-08-27 Deployed with devices method, intelligent terminal and storage medium based on degree of balance control

Country Status (1)

Country Link
CN (1) CN110518604A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102055202A (en) * 2011-01-21 2011-05-11 浙江浙大网新能源技术有限公司 Three-phase balancing power-supply energy-saving control management system
CN102354999A (en) * 2011-10-13 2012-02-15 张颢 Balanced distribution method of single-phase load in low-voltage distribution network
CN102395938A (en) * 2009-02-13 2012-03-28 美国能量变换公司 Power supply and data center control
CN103545826A (en) * 2012-07-09 2014-01-29 江西龙跃电子科技有限公司 Intelligent low-voltage power load distribution system and method
CN109217341A (en) * 2018-10-09 2019-01-15 郑州云海信息技术有限公司 A kind of appraisal procedure and system of data center's tri-phase unbalance factor

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102395938A (en) * 2009-02-13 2012-03-28 美国能量变换公司 Power supply and data center control
CN102055202A (en) * 2011-01-21 2011-05-11 浙江浙大网新能源技术有限公司 Three-phase balancing power-supply energy-saving control management system
CN102354999A (en) * 2011-10-13 2012-02-15 张颢 Balanced distribution method of single-phase load in low-voltage distribution network
CN103545826A (en) * 2012-07-09 2014-01-29 江西龙跃电子科技有限公司 Intelligent low-voltage power load distribution system and method
CN109217341A (en) * 2018-10-09 2019-01-15 郑州云海信息技术有限公司 A kind of appraisal procedure and system of data center's tri-phase unbalance factor

Similar Documents

Publication Publication Date Title
Almabsout et al. A hybrid local search-genetic algorithm for simultaneous placement of DG units and shunt capacitors in radial distribution systems
Zhou et al. Distributed secondary control for islanded microgrids with mobile emergency resources
Xu et al. Extreme learning machine-based predictor for real-time frequency stability assessment of electric power systems
Naderi et al. Dynamic modeling, stability analysis and control of interconnected microgrids: A review
Castilla et al. Event-based state-space model predictive control of a renewable hydrogen-based microgrid for office power demand profiles
Li et al. Reduced-order modeling and comparative dynamic analysis of DC voltage control in DC microgrids under different droop methods
Mobashsher et al. Distributed optimal voltage control in islanded microgrids
Agnoletto et al. An optimal energy management technique using the $\epsilon $-constraint method for grid-tied and stand-alone battery-based microgrids
CN110994589B (en) Online evaluation method and system for frequency modulation capability of power electronic access power system
Mehmood et al. Distributed MPC for economic dispatch and intermittence control of renewable based autonomous microgrid
Vijayan et al. A blended approach to improve reliability and efficiency of active EDN via dynamic feeder reconfiguration, demand response, and VVO
CN110518604A (en) Deployed with devices method, intelligent terminal and storage medium based on degree of balance control
Li et al. Dynamic Equivalent Modeling for Black-Box Microgrids Under Multi-Operating-Point by Using LSTM
Yang et al. A novel partitioning method for the power grid restoration considering the support of multiple LCC-HVDC systems
CN113991760A (en) Direct-current locking multi-resource emergency control optimization method for alternating-current and direct-current series-parallel receiving-end power grid
Cai et al. Data-driven predictive based load frequency robust control of power system with renewables
Sheng et al. Framework and implementation of secondary voltage regulation strategy based on multi-agent technology
CN111935952A (en) Large machine room energy consumption regulation and control method and device
Fuchs et al. A security-constrained multi-period OPF for the locational allocation of automatic reserves
Birchfield et al. Security considerations in transmission planning for creating large synthetic power grids
Vaca et al. Secondary Voltage Control Areas Using Hybrid Methods for Systems with High Wind Penetration
CN112510685A (en) Urban power grid risk avoidance prediction control method and device
Xiao et al. Efficiency of linear supply function bidding in electricity markets
Parra et al. Reinforcement learning for service restoration algorithms in distribution networks
Li et al. Finite‐time consensus for frequency and voltage restoration in microgird under communication interruptions

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191129

RJ01 Rejection of invention patent application after publication